Loading...
HomeMy WebLinkAbout13_Engineering Report Appendix DAppendix D – Norton Ranch Phase 3 and 5 Design Reports DESIGN REPORT STORMWATER MANAGEMENT NORTON RANCH SUBDIVISION, PHASE 5 Prepared for: Norton Properties, LLC 63020 NE Lower Meadow Road, Suite A, Bend, OR 97702 Prepared by: C&H Engineering and Surveying, Inc. 1091 Stoneridge Drive, Bozeman, MT 59718 (406) 587-1115 Project Number: 161141 September 2020 INTRODUCTION The proposed Norton Ranch Subdivision, Phase 5 is a 138-lot subdivision located on a 79.31-acre parcel in the East Half and the West Half of Section 9, Township 2 South, Range 5 East of P.M.M., Gallatin County, City of Bozeman. A combination of site grading, curb and gutter, storm inlets, and piping will be used to manage stormwater runoff on the site. Supporting stormwater calculations are attached to this report. A Drainage Area Map is included in Appendix A. Calculations for each individual drainage area (total area, weighted C factor, and time of concentration) are included in Appendix B. STORM SEWER FACILITIES DESIGN Storm sewer facilities were sized for the 25-yr storm using Manning’s Equation. For each inlet, the contributing area, weighted C factor, and time of concentration were calculated. These values were input into Manning’s Equation to check capacity and flow characteristics for inlets, storm drain pipes, and curb gutters. All curbs are designed to maintain 0.15’ freeboard per C.O.B. Design Manual Section IV.C.5. For the purposes of this report, each pipe section was named to match the associated upstream structure. Pipe sizing calculations are included in Appendix D. RETENTION/DETENTION POND DESIGN All ponds have been sized according to City of Bozeman Design Standards. Retention ponds are sized to capture the entire volume of the 10-year 2-hour storm event. They are designed with a maximum depth of 1.5 feet, and maximum side slope of 4:1. Detention Ponds are sized to limit discharge to pre-development rates for the 10-year storm event. Calculations used for sizing each pond can be found in Appendix C. GROUNDWATER The Geotechnical Investigation Report for Phase 5 encountered groundwater at depths varying from 3.5 to 5.5 feet below ground surface. The seasonally high groundwater was measured during the spring of 2018. Seasonally high groundwater levels were determined to be 0.5’ to 2’ below ground surface. Shallow groundwater elevations have been encountered throughout the Norton East Ranch Subdivision. The developer is aware of these elevations and all structures are constructed as slab-on-grade. The infrastructure plans for this development will account for the high groundwater condition on site. All streets will be constructed above existing grade to ensure all stormwater ponds are installed above the SHGWL. Dewatering for utility installations and foundation construction is expected and will be accounted for in any construction permits. Crawl space and basement foundations are not recommended within this subdivision – a note is included on the plat with this recommendation. Detention Pond #1 Detention Pond #1 is located in the northwest corner of the site within Park 5B. This detention pond will be replacing the temporary retention pond installed with Phase 3B that is located just north of Babcock Street. Detention Pond #1 receives runoff from Drainage Areas 1-8, 11-13, and the existing stormwater system from Norton East Ranch, Phase 3B (see Appendix F), totaling 63.43 acres. The pre-development time to concentration for the pond was calculated to be 50 minutes and the pre-development runoff rate for the 10-yr storm event was calculated to be 9.09 cfs. In order to limit discharge from the detention pond to pre-development runoff rates the proposed outlet structure for the pond will have a 17.8” weir installed. The outlet pipe (Pipe #Outlet Pipe) was sized for the 25-yr storm event using the maximum time of concentration of the contributing drainage areas (21.4 minutes for DA #3). The pipe will discharge into Aajker Creek. The required pond volume was calculated to be 37,018 cubic feet. The provided pond volume is 47,688 cubic feet at an effective water depth of 1.5’ above the seasonal high groundwater level. The groundwater elevation was found to be located at 4778.3’ in the vicinity of the detention pond and the bottom of the pond is set at 4778.8’. A profile showing the proposed detention pond, inlet pipe, outlet pipe, and groundwater levels can be found in Appendix E. In the case of a storm exceeding the 10-yr design storm, runoff will overflow the outlet structure top grate into the outlet pipe and flow into the Aajker Creek. Supporting calculations for the pond sizing can be found in Appendix C. Groundwater Influence within Detention Pond #1 It is known that there is currently groundwater influence within the Phase 3 stormwater system installed in 2017 contributing to the existing retention pond to be replaced with this development. Because of this, groundwater influence calculations have been included within the proposed detention pond. As a conservative measure, the groundwater infiltration rate was set at 300 gal/ac/day. • Groundwater Infiltration Rate = 300 gal/ac/day • 1 Gallon = 0.13368 ft3 • Groundwater Infiltration Rate = 0.02785 ft3/ac/min As an additional conservative measure, this infiltration rate was applied to not only the entirety of the Phase 3 development that will contribute to the proposed detention pond, but also over the entire Phase 5 development contributing to the detention pond for a total of 63.37 acres. This results in a groundwater infiltration rate of 1.765 ft3/min. This infiltration rate was added to the runoff volume calculations within the proposed detention pond as the detention pond calculations are on a per minute basis. The groundwater was found to have minimal impact on the proposed detention pond due to the high time of concentration and the presence of an outlet structure. The outlet structure will help mitigate the groundwater influence as it will provide a hydraulic conduit for the groundwater to continue into Aajker Creek rather than accumulate and occupy pond capacity as it currently does within the existing temporary retention pond that is being replaced with this detention pond. Additionally, all storm manholes and inlets within the Phase 3 development will be inspected for any leakage and/or standing groundwater during the first phase of development for Norton Phase 5. If any leakage is found, the pipe between the two suspect inlets/MH will be TV inspected and any cracks will be fixed. Retention Pond #2 Retention Pond #2 is located just east of the terminus of Laurel Parkway, directly south of the existing lift station. It receives runoff from Drainage Areas 9 and 10, totaling 5.55 acres. Runoff from Drainage Areas 9 and 10 is conveyed via surface flow and gutters to proposed inlets located within the proposed curb. The groundwater elevation was found to be located at 4782.1’ in the vicinity of this retention pond and the bottom of the pond is set at 4782.7’. The required pond volume was calculated to be 7,891 cubic feet. The proposed pond is designed to store 8,021 cubic feet of water. This pond may be temporary and incorporated into the future development plans for Lot R1A once that development layout is decided upon. Supporting calculations for the required pond volume can be found in Appendix C. Drainage/Retention Swale #3 The drainage/retention swale #3 is located along the northern boundary of the proposed subdivision. It receives runoff from Drainage Areas 14 and 15, totaling 3.15 acres. Runoff from Drainage Areas 14 and 15 is conveyed via surface flow and gutters to proposed inlets which discharge into the proposed swale. The swale has a shallow slope of 0.8% to the west and will ultimately discharge into Aajker Creek. The shallow slope was utilized so that the drainage swale can act as a retention pond with a bottom width of 2’, water depth of 1.5’, and 4:1 side slopes. This cross-sectional area in conjunction with the length of the swale was used to determine its retention volume. Due to the shallow slope, stormwater will have ample time to be treated and settle prior to discharging into Aajker Creek. The required swale volume was calculated to be 2,572 cubic feet. The proposed swale is designed to store 9,000 cubic feet of water. The proposed swale will have an overtopping berm installed on the far west side to ensure that during storm events exceeding the design storm, the runoff will not flow north into the Lakes property or flood the proposed houses. Supporting calculations for the required retention swale volume can be found in Appendix C. A detailed exhibit showing proposed elevations of the swale is included in Appendix E. APPENDIX A DRAINAGE AREA MAP APPENDIX B DRAINAGE AREA CALCULATIONS DRAINAGE AREA #1 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 26475 19525 Hardscape 0.95 0 0 OS 0.2 43799 8760 Low-Med Residential 0.35 0 0 Dense Residential 0.5 0 0 Total 70274 28285 A = Area (acres) 1.6133 C = Weighted C Factor 0.40 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 76 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)11.6 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.84% L = length of gutter (ft) 845 V = mean velocity (ft/s) 2.75 Tc Gutter Flow (minutes) =5.1 Tc Total = 16.7 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.40 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.77 (25-yr storm) A = area (acres) 1.61 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 1.15 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.84% Q = PROVIDED GUTTER CAPACITY (cfs) 3.42 DRAINAGE AREA #2 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 10505 7747 Hardscape 0.95 0 0 OS 0.2 0 0 Low-Med Residential 0.35 29555 10344 Dense Residential 0.5 0 0 Total 40060 18091 A = Area (acres) 0.9196 C = Weighted C Factor 0.45 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 130 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)15.2 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.86% L = length of gutter (ft) 224 V = mean velocity (ft/s) 2.78 Tc Gutter Flow (minutes) =1.3 Tc Total = 16.6 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.45 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.78 (25-yr storm) A = area (acres) 0.92 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 0.74 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.86% Q = PROVIDED GUTTER CAPACITY (cfs) 3.44 DRAINAGE AREA #3 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 74335 54822 Hardscape 0.95 0 0 OS 0.2 3251 650 Low-Med Residential 0.35 148300 51905 Dense Residential 0.5 0 0 Total 225887 107378 A = Area (acres) 5.1857 C = Weighted C Factor 0.48 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 136 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)15.6 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 1.01% L = length of gutter (ft) 1058 V = mean velocity (ft/s) 3.01 Tc Gutter Flow (minutes) =5.8 Tc Total = 21.4 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.48 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.51 (25-yr storm) A = area (acres) 5.19 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 3.71 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 1.01% Q = PROVIDED GUTTER CAPACITY (cfs) 3.74 DRAINAGE AREA #4 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 36002 26552 Hardscape 0.95 0 0 OS 0.2 350 70 Low-Med Residential 0.35 92427 32349 Dense Residential 0.5 0 0 Total 128779 58971 A = Area (acres) 2.9564 C = Weighted C Factor 0.46 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 116 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)14.4 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.89% L = length of gutter (ft) 914 V = mean velocity (ft/s) 2.83 Tc Gutter Flow (minutes) =5.4 Tc Total = 19.8 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.46 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.59 (25-yr storm) A = area (acres) 2.96 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 2.15 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.89% Q = PROVIDED GUTTER CAPACITY (cfs) 3.51 DRAINAGE AREA #5 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 32466 23944 Hardscape 0.95 0 0 OS 0.2 65 13 Low-Med Residential 0.35 78948 27632 Dense Residential 0.5 0 0 Total 111479 51589 A = Area (acres) 2.5592 C = Weighted C Factor 0.46 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 131 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)15.3 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.97% L = length of gutter (ft) 870 V = mean velocity (ft/s) 2.95 Tc Gutter Flow (minutes) =4.9 Tc Total = 20.2 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.46 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.56 (25-yr storm) A = area (acres) 2.56 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 1.85 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.97% Q = PROVIDED GUTTER CAPACITY (cfs) 3.65 DRAINAGE AREA #6 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 35341 26064 Hardscape 0.95 0 0 OS 0.2 51 10 Low-Med Residential 0.35 86872 30405 Dense Residential 0.5 0 0 Total 122263 56479 A = Area (acres) 2.8068 C = Weighted C Factor 0.46 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 138 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)15.7 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.96% L = length of gutter (ft) 863 V = mean velocity (ft/s) 2.94 Tc Gutter Flow (minutes) =4.9 Tc Total = 20.6 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.46 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.55 (25-yr storm) A = area (acres) 2.81 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 2.01 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.96% Q = PROVIDED GUTTER CAPACITY (cfs) 3.65 DRAINAGE AREA #7 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 32740 24146 Hardscape 0.95 0 0 OS 0.2 0 0 Low-Med Residential 0.35 83718 29301 Dense Residential 0.5 0 0 Total 116458 53447 A = Area (acres) 2.6735 C = Weighted C Factor 0.46 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 142 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)15.9 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 1.13% L = length of gutter (ft) 851 V = mean velocity (ft/s) 3.18 Tc Gutter Flow (minutes) =4.5 Tc Total = 20.4 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.46 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.56 (25-yr storm) A = area (acres) 2.67 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 1.91 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 1.13% Q = PROVIDED GUTTER CAPACITY (cfs) 3.95 DRAINAGE AREA #8 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 49511 36514 Hardscape 0.95 0 0 OS 0.2 33642 6728 Low-Med Residential 0.35 105497 36924 Dense Residential 0.5 0 0 Total 188651 80167 A = Area (acres) 4.3308 C = Weighted C Factor 0.42 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 124 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)14.9 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 1.12% L = length of gutter (ft) 948 V = mean velocity (ft/s) 3.17 Tc Gutter Flow (minutes) =5.0 Tc Total = 19.9 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.42 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.58 (25-yr storm) A = area (acres) 4.33 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 2.91 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 1.12% Q = PROVIDED GUTTER CAPACITY (cfs) 3.93 DRAINAGE AREA #9 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 66028 48696 Hardscape 0.95 0 0 OS 0.2 93614 18723 Low-Med Residential 0.35 22024 7708 Dense Residential 0.5 0 0 Total 181666 75127 A = Area (acres) 4.1705 C = Weighted C Factor 0.41 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 70 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)11.2 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.88% L = length of gutter (ft) 1295 V = mean velocity (ft/s) 2.81 Tc Gutter Flow (minutes) =7.7 Tc Total = 18.9 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.41 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.64 (25-yr storm) A = area (acres) 4.17 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 2.82 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.88% Q = PROVIDED GUTTER CAPACITY (cfs) 3.49 DRAINAGE AREA #10 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 60307 44477 Hardscape 0.95 0 0 OS 0.2 0 0 Low-Med Residential 0.35 0 0 Dense Residential 0.5 0 0 Total 60307 44477 A = Area (acres) 1.3845 C = Weighted C Factor 0.74 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 100 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)13.4 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.88% L = length of gutter (ft) 1340 V = mean velocity (ft/s) 2.81 Tc Gutter Flow (minutes) =7.9 Tc Total = 21.3 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.74 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.51 (25-yr storm) A = area (acres) 1.38 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 1.54 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.88% Q = PROVIDED GUTTER CAPACITY (cfs) 3.49 DRAINAGE AREA #11 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 0 0 Hardscape 0.95 0 0 OS 0.2 94835 18967 Low-Med Residential 0.35 15528 5435 Dense Residential 0.5 0 0 Total 110363 24402 A = Area (acres) 2.5336 C = Weighted C Factor 0.22 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 219 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)19.8 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 1.16% L = length of gutter (ft) 0 V = mean velocity (ft/s) 3.23 Tc Gutter Flow (minutes) =0.0 Tc Total = 19.8 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.22 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.59 (25-yr storm) A = area (acres) 2.53 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs)N/A (assuming no carry flow) DRAINAGE AREA #12 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 7030 5184 Hardscape 0.95 0 0 OS 0.2 0 0 Low-Med Residential 0.35 3065 1073 Dense Residential 0.5 0 0 Total 10095 6257 A = Area (acres) 0.2317 C = Weighted C Factor 0.62 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 73 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)11.4 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.89% L = length of gutter (ft) 136 V = mean velocity (ft/s) 2.82 Tc Gutter Flow (minutes) =0.8 Tc Total = 12.2 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.62 (calculated above) I = 0.78 Tc-0.64 (in/hr)2.16 (25-yr storm) A = area (acres) 0.23 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 0.31 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.89% Q = PROVIDED GUTTER CAPACITY (cfs) 3.50 DRAINAGE AREA #13 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 54530 40216 Hardscape 0.95 0 0 OS 0.2 30338 6068 Low-Med Residential 0.35 76817 26886 Dense Residential 0.5 0 0 Total 161685 73169 A = Area (acres) 3.7118 C = Weighted C Factor 0.45 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.20% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 127 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)14.2 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.80% L = length of gutter (ft) 630 V = mean velocity (ft/s) 2.68 Tc Gutter Flow (minutes) =3.9 Tc Total = 18.1 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.45 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.68 (25-yr storm) A = area (acres) 3.71 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 2.82 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.80% Q = PROVIDED GUTTER CAPACITY (cfs) 3.33 DRAINAGE AREA #14 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 7089 5228 Hardscape 0.95 0 0 OS 0.2 4849 970 Low-Med Residential 0.35 12800 4480 Dense Residential 0.5 0 0 Total 24739 10678 A = Area (acres) 0.5679 C = Weighted C Factor 0.43 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 219 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)19.8 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.83% L = length of gutter (ft) 408 V = mean velocity (ft/s) 2.73 Tc Gutter Flow (minutes) =2.5 Tc Total = 22.3 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.43 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.47 (25-yr storm) A = area (acres) 0.57 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 0.36 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.83% Q = PROVIDED GUTTER CAPACITY (cfs) 3.39 DRAINAGE AREA #15 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2)C * Area Composite ROW 0.74 7600 5605 Hardscape 0.95 0 0 OS 0.2 97533 19507 Low-Med Residential 0.35 7249 2537 Dense Residential 0.5 0 0 Total 112382 27649 A = Area (acres) 2.5799 C = Weighted C Factor 0.25 3. Calculate Tc (Time to Concentration) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.00% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.35 2 to 10 1 Cf = Frequency Adjustment Factor 1.1 11 to 25 1.1 D = Length of Basin (ft) 219 26 to 50 1.2 51 to 100 1.25 Tc Overland Flow (minutes)19.8 Tc Gutter Flow Tc = L/V/60 V = (1.486/n)R2/3 S1/2 n = Mannings Coefficient 0.013 R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.83% L = length of gutter (ft) 408 V = mean velocity (ft/s) 2.73 Tc Gutter Flow (minutes) =2.5 Tc Total = 22.3 (5 minute minimum) 4. Calculate Flow (Rational Formula) Q = CIA C = Weighted C Factor 0.25 (calculated above) I = 0.78 Tc-0.64 (in/hr)1.47 (25-yr storm) A = area (acres) 2.58 (calculated above) Q = REQUIRED GUTTER CAPACITY (cfs) 0.93 (assuming no carry flow) PROVIDED GUTTER CAPACITY 1. Calculate Gutter Capacity @ 0.15' Below Top of Curb Q = (1.486/n)AR2/3 S1/2 n = Mannings Coefficient 0.013 A = Area (ft2)1.24 (0.15' below top of curb) P = Wetted perimeter (ft) 9.23 (0.15' below top of curb) R = Hydraulic Radius A/P (ft) 0.13 (0.15' below top of curb) S = slope (%) 0.83% Q = PROVIDED GUTTER CAPACITY (cfs) 3.39 APPENDIX C POND SIZING CALCULATIONS DETENTION POND #1 REQUIRED VOLUME 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 2. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 358934 264714 Hardscape 0.95 0 0 OS 0.2 206332 41266 Low-Med Residential 0.35 720728 252255 Dense Residential 0.5 0 0 Norton Phase 3 0.49 1474393 722453 *From existing Norton Ranch Ph 3 Total 2760387 1280688 (see Appendix F) A = Area (acres) 63.3698 C = Weighted C Factor 0.46 3. Calculate Tc (Pre-Development) Tc Overland Flow Tc = 1.87 (1.1-CCf)D1/2/S1/3 Storm S = Slope of Basin (%) 1.49% Return (yrs)Cf C = Rational Method Runoff Coefficient 0.2 2 to 10 1 Cf = Frequency Adjustment Factor 1 11 to 25 1.1 D = Length of Basin (ft) 1168 26 to 50 1.2 51 to 100 1.25 Tc (Pre-Development) (minutes) 50 4. Calculate Rainfall Intensity (Duration = Pre-Development Tc) i = 0.64x-0.65 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.84 (Tc Pre-Development) i = rainfall intensity (in./hr.) 0.72 5. Calculate Runoff Rate (Pre-Development) Q = CiA C = Rational Method Runoff Coefficient 0.2 (open land) i = rainfall intensity (in./hr.) 0.72 (calculated above) A = Area (acres) 63.37 (calculated above) Q = Runoff Rate (Pre-Development) (cfs) 9.09 6. Calculate Required Pond Volume Total Area (acres) = 63.37 acres Weighted C = 0.46 Discharge Rate (cfs) = 9.09 cfs (Equal to Pre-Development Runoff Rate) Duration(min) Duration(hrs) Intensity (in/hr)Qin (cfs)Runoff Volume* Release Volume Required Storage (ft3) 31 0.52 0.98 28.90 53762 16906 36856 32 0.53 0.96 28.31 54363 17452 36911 33 0.55 0.94 27.75 54951 17997 36954 34 0.57 0.93 27.22 55529 18543 36986 35 0.58 0.91 26.71 56095 19088 37007 36 0.60 0.89 26.23 56651 19633 37017 37 0.62 0.88 25.76 57196 20179 37018 38 0.63 0.86 25.32 57733 20724 37009 39 0.65 0.85 24.90 58260 21269 36991 40 0.67 0.83 24.49 58779 21815 36964 *An additional 1.765 ft3/min is added to account for groundwater influence. See the stormwater design report for more information. OUTLET STRUCTURE SLOT Q=CLH3/2 Q = Discharge (cfs) 9.09 (calculated above) C = Weir Coefficient 3.33 (per COB Design Standards) H = Head (ft) 1.5 L = Horizontal Length (ft) 1.49 L = Slot Width (inches) 17.8 RETENTION POND #2 REQUIRED VOLUME 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 41 0.95 ROW Landscape 19 0.2 Weighted C Factor = 0.71 1. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2 )C * Area Composite ROW 0.71 126335 90014 Hardscape 0.95 0 0 OS 0.2 93614 18723 Low-Med Residential 0.35 22024 7708 Dense Residential 0.5 0 0 Total 241973 116445 C=Weighted C Factor 0.48 2. Calculate Required Volume Q = CIA V=7200Q C = Weighted C Factor 0.48 I = intensity (in/hr) 0.41 (10 yr, 2hr storm) A = Area (acres) 5.55 Q = runoff (cfs) 1.10 V = REQUIRED VOL (ft3)7891 DRAINAGE/RETENTION SWALE REQUIRED VOLUME 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 41 0.95 ROW Landscape 19 0.2 Weighted C Factor = 0.71 1. Calculate Area and Weighted C Factor Contributing Area C Area (ft 2 )C * Area Composite ROW 0.71 14690 10466 Hardscape 0.95 0 0 OS 0.2 102382 20476 Low-Med Residential 0.35 20049 7017 Dense Residential 0.5 0 0 Total 137121 37960 C=Weighted C Factor 0.28 2. Calculate Required Volume Q = CIA V=7200Q C = Weighted C Factor 0.28 I = intensity (in/hr) 0.41 (10 yr, 2hr storm) A = Area (acres) 3.15 Q = runoff (cfs) 0.36 V = REQUIRED VOL (ft3)2572 PROVIDED VOLUME 1. Calculate Provided Volume A = [(a+b)/2]*h V = L*A L = Length of Swale (ft) 750 a = bottom width (ft) 2.0 b = top width (ft) 14.0 h = depth of swale (ft) 1.5 A = area of swale (ft2)12.00 V = PROVIDED VOL (ft3)9000 APPENDIX D PIPE SIZING CALCULATIONS PIPE #5A 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 36979 27272 Hardscape 0.95 0 0 OS 0.2 43799 8760 Low-Med Residential 0.35 29555 10344 Dense Residential 0.5 0 0 Norton Phase 3 0.49 1474393 722453 *From existing Norton Ranch Ph 3 Total 1584727 768829 A = Area (acres) 36.3803 C = Weighted C Factor 0.49 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.28 (DA #1) i = rainfall intensity (in./hr.) 1.77 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.49 i = rainfall intensity (in./hr.) 1.77 A = Area (acres) 36.38 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 31.16 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5A Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 30 inches d= 28.14 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.04 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 4.78 6.60 0.73 18.45 88.24 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5B 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 10505 7747 Hardscape 0.95 0 0 OS 0.2 0 0 Low-Med Residential 0.35 29555 10344 Dense Residential 0.5 0 0 Norton Phase 3 0.49 1474393 722453 *From existing Norton Ranch Ph 3 Total 1514453 740544 A = Area (acres) 34.7670 C = Weighted C Factor 0.49 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.28 (DA #2) i = rainfall intensity (in./hr.) 1.78 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.49 i = rainfall intensity (in./hr.) 1.78 A = Area (acres) 34.77 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 30.19 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5B Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 30 inches d= 28.14 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.04 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 4.78 6.60 0.73 18.45 88.24 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5C 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 260396 192042 Hardscape 0.95 0 0 OS 0.2 37360 7472 Low-Med Residential 0.35 595762 208517 Dense Residential 0.5 0 0 Norton Phase 3 0.49 1474393 722453 *From existing Norton Ranch Ph 3 Total 2367910 1130483 A = Area (acres) 54.3597 C = Weighted C Factor 0.48 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.36 (DA #3) i = rainfall intensity (in./hr.) 1.51 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.48 i = rainfall intensity (in./hr.) 1.51 A = Area (acres) 54.36 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 39.11 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5C Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 30 inches d= 28.14 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.04 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 4.78 6.60 0.73 18.45 88.24 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5D 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 186061 137220 Hardscape 0.95 0 0 OS 0.2 34108 6822 Low-Med Residential 0.35 447462 156612 Dense Residential 0.5 0 0 Total 667630 300653 A = Area (acres) 15.3267 C = Weighted C Factor 0.45 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.34 (DA #6) i = rainfall intensity (in./hr.) 1.55 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.45 i = rainfall intensity (in./hr.) 1.55 A = Area (acres) 15.33 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 10.67 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5D Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 21 inches d= 19.70 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 2.34 4.62 0.51 5.39 12.63 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5E 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 150058 110668 Hardscape 0.95 0 0 OS 0.2 33758 6752 Low-Med Residential 0.35 355035 124262 Dense Residential 0.5 0 0 Total 538851 241682 A = Area (acres) 12.3703 C = Weighted C Factor 0.45 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.34 (DA #6) i = rainfall intensity (in./hr.) 1.55 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.45 i = rainfall intensity (in./hr.) 1.55 A = Area (acres) 12.37 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 8.58 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5E Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 18 inches d= 16.88 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.006 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 1.72 3.96 0.44 5.29 9.10 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5F 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 117592 86724 Hardscape 0.95 0 0 OS 0.2 33693 6739 Low-Med Residential 0.35 276087 96630 Dense Residential 0.5 0 0 Total 427372 190093 A = Area (acres) 9.8111 C = Weighted C Factor 0.44 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.34 (DA #6) i = rainfall intensity (in./hr.) 1.55 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.44 i = rainfall intensity (in./hr.) 1.55 A = Area (acres) 9.81 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 6.75 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5F Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 18 inches d= 16.88 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 1.72 3.96 0.44 4.64 7.99 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5G 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 82252 60661 Hardscape 0.95 0 0 OS 0.2 33642 6728 Low-Med Residential 0.35 189215 66225 Dense Residential 0.5 0 0 Total 305109 133614 A = Area (acres) 7.0043 C = Weighted C Factor 0.44 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.34 (DA #7) i = rainfall intensity (in./hr.) 1.56 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.44 i = rainfall intensity (in./hr.) 1.56 A = Area (acres) 7.00 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 4.77 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5G Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 15 inches d= 14.07 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 1.20 3.30 0.36 4.11 4.91 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5H 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 49511 36514 Hardscape 0.95 0 0 OS 0.2 33642 6728 Low-Med Residential 0.35 105497 36924 Dense Residential 0.5 0 0 Total 188651 80167 A = Area (acres) 4.3308 C = Weighted C Factor 0.42 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.33 (DA #8) i = rainfall intensity (in./hr.) 1.58 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.42 i = rainfall intensity (in./hr.) 1.58 A = Area (acres) 4.33 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 2.91 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5H Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 15 inches d= 14.07 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 1.20 3.30 0.36 4.11 4.91 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5I 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 321955 237442 Hardscape 0.95 0 0 OS 0.2 67697 13539 Low-Med Residential 0.35 675644 236476 Dense Residential 0.5 0 0 Total 1065297 487457 A = Area (acres) 24.4559 C = Weighted C Factor 0.46 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.36 (DA #3) i = rainfall intensity (in./hr.) 1.51 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.46 i = rainfall intensity (in./hr.) 1.51 A = Area (acres) 24.46 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 16.86 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5I Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 24 inches d= 22.51 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 3.06 5.28 0.58 5.62 17.21 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5J 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 54530 40216 Hardscape 0.95 0 0 OS 0.2 30338 6068 Low-Med Residential 0.35 76817 26886 Dense Residential 0.5 0 0 Total 161685 73169 A = Area (acres) 3.7118 C = Weighted C Factor 0.45 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.30 (DA #13) i = rainfall intensity (in./hr.) 1.68 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.45 i = rainfall intensity (in./hr.) 1.68 A = Area (acres) 3.71 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 2.82 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5J Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 12 inches d= 11.26 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 0.77 2.64 0.29 3.71 2.84 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5K 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 36979 27272 Hardscape 0.95 0 0 OS 0.2 43799 8760 Low-Med Residential 0.35 29555 10344 Dense Residential 0.5 0 0 Norton Phase 3 0.49 1474393 722453 *From existing Norton Ranch Ph 3 Total 1584727 768829 A = Area (acres) 36.3803 C = Weighted C Factor 0.49 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.28 (DA #1) i = rainfall intensity (in./hr.) 1.77 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.49 i = rainfall intensity (in./hr.) 1.77 A = Area (acres) 36.38 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 31.16 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5K Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 30 inches d= 28.14 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.025 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 4.78 6.60 0.73 14.59 69.76 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5L 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 36979 27272 Hardscape 0.95 0 0 OS 0.2 43799 8760 Low-Med Residential 0.35 29555 10344 Dense Residential 0.5 0 0 Norton Phase 3 0.49 1474393 722453 *From existing Norton Ranch Ph 3 Total 1584727 768829 A = Area (acres) 36.3803 C = Weighted C Factor 0.49 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.28 (DA #1) i = rainfall intensity (in./hr.) 1.77 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.49 i = rainfall intensity (in./hr.) 1.77 A = Area (acres) 36.38 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 31.16 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5L Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 30 inches d= 28.14 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.01 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 4.78 6.60 0.73 9.23 44.12 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5M 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 7089 5228 Hardscape 0.95 0 0 OS 0.2 4849 970 Low-Med Residential 0.35 12800 4480 Dense Residential 0.5 0 0 Total 24739 10678 A = Area (acres) 0.5679 C = Weighted C Factor 0.43 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.37 (DA #14) i = rainfall intensity (in./hr.) 1.47 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.43 i = rainfall intensity (in./hr.) 1.47 A = Area (acres) 0.57 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 0.36 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5M Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 12 inches d= 11.26 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 0.77 2.64 0.29 3.71 2.84 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5N 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 7089 5228 Hardscape 0.95 0 0 OS 0.2 4849 970 Low-Med Residential 0.35 12800 4480 Dense Residential 0.5 0 0 Total 24739 10678 A = Area (acres) 0.5679 C = Weighted C Factor 0.43 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.37 (DA #14) i = rainfall intensity (in./hr.) 1.47 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.43 i = rainfall intensity (in./hr.) 1.47 A = Area (acres) 0.57 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 0.36 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5N Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 12 inches d= 11.26 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 0.77 2.64 0.29 3.71 2.84 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5O 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 7600 5605 Hardscape 0.95 0 0 OS 0.2 97533 19507 Low-Med Residential 0.35 7249 2537 Dense Residential 0.5 0 0 Total 112382 27649 A = Area (acres) 2.5799 C = Weighted C Factor 0.25 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.37 (DA #15) i = rainfall intensity (in./hr.) 1.47 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.25 i = rainfall intensity (in./hr.) 1.47 A = Area (acres) 2.58 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 0.93 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5O Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 12 inches d= 11.26 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 0.77 2.64 0.29 3.71 2.84 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5P 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 7600 5605 Hardscape 0.95 0 0 OS 0.2 97533 19507 Low-Med Residential 0.35 7249 2537 Dense Residential 0.5 0 0 Total 112382 27649 A = Area (acres) 2.5799 C = Weighted C Factor 0.25 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.37 (DA #15) i = rainfall intensity (in./hr.) 1.47 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.25 i = rainfall intensity (in./hr.) 1.47 A = Area (acres) 2.58 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 0.93 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5P Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 12 inches d= 11.26 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 0.77 2.64 0.29 3.71 2.84 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5Q 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 66028 48696 Hardscape 0.95 0 0 OS 0.2 93614 18723 Low-Med Residential 0.35 22024 7708 Dense Residential 0.5 0 0 Total 181666 75127 A = Area (acres) 4.1705 C = Weighted C Factor 0.41 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.31 (DA #13) i = rainfall intensity (in./hr.) 1.64 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.41 i = rainfall intensity (in./hr.) 1.64 A = Area (acres) 4.17 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 2.82 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5Q Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 12 inches d= 11.26 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.006 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 0.77 2.64 0.29 4.03 3.09 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D PIPE #5R 25-YR OUTFLOW RATE REQUIRED CAPACITY 1. Calculate Weighted C Factor for Right-of-Way Component Width C ROW Hardscape 43 0.95 ROW Landscape 17 0.2 Weighted C Factor = 0.74 1. Calculate Area and Weighted C Factor (Post-Development) Contributing Area C Area (ft 2 )C * Area Composite ROW 0.74 126335 93172 Hardscape 0.95 0 0 OS 0.2 93614 18723 Low-Med Residential 0.35 22024 7708 Dense Residential 0.5 0 0 Total 241973 119603 A = Area (acres) 5.5549 C = Weighted C Factor 0.49 2. Calculate Rainfall Intensity (Duration = Max Tc from Contributing Drainage Areas) i = 0.78x-0.64 (10-yr Storm, Fig. I-3, COB Design Standards) x = storm duration (hrs) 0.36 (DA #10) i = rainfall intensity (in./hr.) 1.51 3. Calculate 25-yr Pond Outflow Rate Q = CiA C = Rational Method Runoff Coefficient 0.49 i = rainfall intensity (in./hr.) 1.51 A = Area (acres) 5.55 (calculated above) (calculated above) Q = 25-yr Pond Outflow Rate (cfs) 4.15 (calculated above) MANNING'S EQUATION FOR PIPE FLOW Pipe: Pipe 5R Project: Norton East Ranch Subdivision, Phase 5 INPUT D= 15 inches d= 14.07 inches Mannings Formula n= 0.013 mannings 57.7 degrees Q=(1.486/n)ARh2/3S1/2 S= 0.005 slope in/in R=A/P A=cross sectional area P=wetted perimeter S=slope of channel V=(1.49/n)Rh2/3S1/2 n=Manning's roughness coefficient Q=V x A Solution to Mannings Equation Area,ft2 Wetted Perimeter, ft Hydraulic Radius, ft velocity ft/s flow, cfs PVC 0.013 1.20 3.30 0.36 4.31 5.15 PE (<9"dia) 0.015 PE (>12"dia) 0.02 PE(9-12"dia) 0.017 CMP 0.025 ADS N12 0.012 HCMP 0.023 Conc 0.013 Manning's n-values d  D APPENDIX E DETENTION POND #1 PROFILE & DRAINAGE SWALE EXHIBIT APPENDIX F NORTON RANCH PHASE 3 STORMWATER DESIGN REPORT