HomeMy WebLinkAboutPart 3 SWPPP 02-04-201 Flanders Mill Apartments NOI-SWPPP Section E - Construction Activity and BMP Schedule and Phasing Phase I: Site Stripping, Clearing and Grubbing Potential Pollutants:  Sediment laden stormwater;  Equipment petroleums from re-fueling, lubrication, leaks;  Vehicle tracking soils onto public streets from the site due to tires catching disturbed soils on-site;  Human generated garbage;  Wind Blown Dust from scarified soils;  Human sanitary waste. Construction Occurring in Phase:  Strip weeds;  Clear and grub top 9-inches of entire area of work; Site Best Management Practices:  Install gravel construction entrance pad per City Standards;  Store equipment and stockpile material in designated area;  Perform street sweeping after vehicle tracked sediment occurs on public streets;  Cover stockpiled material;  Perform any equipment maintenance or re-fueling in a protected lined area;  Immediately repair any leaks on equipment;  Have a watering truck available for wind blowing dust;  Provide a trash receptacle with scheduled pickup;  Install sanitary facility for workers, stake down (not near top of slope);  Earthwork Contractor shall perform biweekly inspections;  Maintain spill kit on site; Phase II: Utility Installation Potential Pollutants:  Sediment laden stormwater;  Equipment petroleums from re-fueling, lubrication, leaks;  Vehicle tracking soils onto public streets from the site due to tires catching disturbed soils on-site;  Human generated garbage;  Human sanitary waste. 2 Construction Occurring in Phase:  Installation of sanitary sewer main and services and related appurtenances;  Installation of water main and services and related appurtenances;  Installation of storm drain system and related appurtenances;  Installation of dry utilities conduit;  Sanitary Sewer and Water Main testing. Site Best Management Practices:  Install erosion control measures and BMP's in locations as noted on Phase II Site Plan;  Maintain gravel construction entrance pad;  Store equipment and stockpile material in designated area;  Store chemicals, petroleums, gasoline, fuel and other containered items in a locked trailer or shed.  Maintain sanitary facility for worker use;  Maintain trash receptacle for human generated trash;  Flush chlorinated water mains into an excavated hole and allow to infiltrate.  Sweep streets immediately to remove any sediment tracked from trucks exiting the site;  Utility Installer shall perform biweekly inspections;  Maintain spill kit on site;  Groundwater point wells to be installed for dewatering purposes. Clean water from the dewatering process to be piped to the nearest irrigation ditch. Phase III: Asphalt, Curbing, and Sidewalk Potential Pollutants:  Sediment laden stormwater;  Equipment petroleums from re-fueling, lubrication, leaks;  Vehicle tracking soils onto public streets from the site due to tires catching disturbed soils on-site;  Nuclear soil density gauge being struck;  Human generated garbage;  Human sanitary waste.  Concrete waste generated from trucks and testing; Construction Occurring in Phase:  Rough grading of entire site;  Excavation for placement of road subbase material  Installation of pitrun gravels;  Installation of roadmix gravel cushion;  Watering of gravels;  Pouring concrete for sidewalks;  Pouring concrete curb & gutter; 3  Placement of Asphalt Pavement;  Nuclear gauge testing of soils. Site Best Management Practices:  Install erosion control measures and BMP's in locations as noted on Phase III Site Plan.  Store equipment and stockpile material in designated area;  Store chemicals, petroleums, gasoline, fuel and other containered items in a locked trailer or shed;  Sweep streets immediately to remove any sediment tracked from trucks exiting the site;  Cover soil stockpiles if windy conditions occur;  Watering from watering trucks will immediately infiltrate into soils;  Utilize a water truck to dampen exposed soils and prevent windblown nuisance dust;  Maintain and clean sanitary facility for worker use;  Nuclear gauge will be performed by a certified nuclear gauge operator;  Nuclear gauge will never be left where there is a possibility of getting struck by equipment;  Nuclear gauge is regulated under US Nuclear Regulatory Commission guidelines and rules;  Roadway Contractor shall perform biweekly inspections;  Maintain spill kit on site.  Waste concrete from concrete trucks will always be washed into a poly lined containment area where it will be properly removed from the site and disposed of off-site at a concrete waste facility.  Waste asphalt pavement from asphalt trucks will always be dumped into a polylined containment area where it will be properly removed from the site and disposed of off- site at an asphalt waste facility.  Nuclear gauge is regulated under US Nuclear Regulatory Commission guidelines and rules; BMP SPECIFICATION SOURCE/REFERENCE SHEET Source: General Permit for Stormwater Discharges Associated with Construction Activity Permit Number MTR100000 Montana Department of Environmental Quality, effective January 1, 2018. Specific BMP's: Guide for filling out SWPPP application Source: Stormwater Discharges Associated with Construction Activity - Stormwater Pollution Prevention Plan Development Guidance Document Revised March 2014, Montana Department of Environmental Quality Specific BMP's: Guide for filling out SWPPP application Source: City of Bozeman Stormwater Department, Stormwater Erosion and Sediment Control Manual, May 2015 http://weblink.bozeman.net/WebLink8/0/doc/83010/Electronic.aspx Specific BMP's: Straw Wattles, Gravel Approach, Inlet Protection, and Concrete Washout. Source: United States Environmental Protection Agency, Water, Best Management Practices https://www.epa.gov/npdes/national-menu-best-management-practices-bmps-stormwater#edu Specific BMP's: Dust Control, Riprap, Seeding, Sodding, Soil Roughening, Construction Entrances, Fiber Rolls, Sediment Basins and Rock Check Dams, Straw or Haybales, Vegetated Buffers, Storm Drain Inlet Protection, Construction Site Operator BMP Inspection and Maintenance. Source: Colorado Urban Drainage and Flood Control District, Urban Storm Drainage Criteria Manual Volume 3, August 2013. http://www.udfcd.org/downloads/down_critmanual_volIII.htm Specific BMP's: Covering Outdoor Storage and Handling Areas, Good Housekeeping, Vehicle Maintenance, Fueling and Storage, Street Sweeping and Cleaning, Snow and Ice Management, Concrete Washout Area, Stockpile Management.