Loading...
HomeMy WebLinkAboutA4. Oak Street Project Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Bob Murray, Project Engineer Rick Hixson, City Engineer SUBJECT: Oak Street Improvements Project MEETING DATE: March 7th, 2016 AGENDA ITEM TYPE: Action RECOMMENDED MOTION: Having considered the information provided in written and presented materials, I move to approve the corridor improvement recommendations as follows: Completion of a 5 lane principal arterial section with a raised median from Cottonwood to North 27th, a 5 lane principal arterial section with a two way left turn lane from North 27th to North 5th, and a 3 lane urban section from North 5th to North Rouse. Intersection control shall include installation of a roundabout at Cottonwood; installation of signals at Ferguson, Davis, 27th, and11th; and modification of the signals and installation of additional turn lanes at 7th and 19th. BACKGROUND: Sanderson Stewart was hired to complete the design of Oak Street from Rouse to Cottonwood including the selected method of traffic control at the major intersections along the corridors. The first step in the process is the predesign effort which included the completion of a traffic engineering report. In this report, all of the major subdivisions, vacant land, and traffic growth projections were combined to complete a traffic study for the area. This was used to compare and contrast the installation of a signal versus a roundabout at the major intersections along the corridor. The analysis included preliminary layout and estimates for the options at each intersection. The full report is included for your review. The study concluded that at all of the intersections either a roundabout or signal will provide an adequate level of service for the projected future traffic loads. The advantages/disadvantages of each alternative can generally be described as follows: Signal Advantages: Higher driver familiarity, reduction in stop controlled crashes, minimal impact to adjoining properties, and lower capital costs. Signal Disadvantages: Induced delay during off peak hours, potential for increase in severe crashes, and potential for higher long term operation and maintenance costs. 326 Roundabout Advantages: Less overall delay and no induced delay during off-peak hours, available capacity for future demand, and improved safety. Roundabout Disadvantages: Greater right of way requirement, higher capital cost, and require pedestrian signals where there are multilane approach legs. After the study was completed, staff and the consultant met to review each intersection and come up with an overall recommendation for the each corridor. This is presented in Chapter 4 of the report, Recommended Improvements. The recommendation includes the installation of a 5 lane principal arterial section from Cottonwood to 5th and a 3 lane urban section from 5th to Rouse. For intersection control, a roundabout at Cottonwood and signals at Ferguson, Davis, 27th and 11th are being recommended. Finally, the study includes a recommendation for signal and geometric improvements to the 7th and 19th intersections for improved performance. A detailed cost estimate for the recommended corridor improvements is included in Appendix I, Opinions of Probable Costs. Overall, the estimate to complete the corridor with the recommended intersection control is $17.4 million. UNRESOLVED ISSUES: None ALTERNATIVES: As recommended by the Commission. FISCAL EFFECTS: The recommended improvements are estimated at $17.4 million. It is anticipated that this would be broken down into several projects over a number of years and would be financed though the arterial collector improvement district funds, impact fees, and developer contributions. Attachments: Pre-Design Report Report compiled on: 2/24/16 327 OAK STREET IMPROVEMENTS PRE-DESIGN REPORT FEBRUARY 2016 Oak Street Improvements Pre-Design Report i TABLE OF CONTENTS LIST OF FIGURES ................................................................................................................................................ ii LIST OF TABLES .................................................................................................................................................. iii APPENDIX .............................................................................................................................................................. iii INTRODUCTION ............................................................................................................................................................ 1 Project Corridor and Study Area Description ..................................................................................................... 1 Related Projects ............................................................................................................................................................ 3 EXISTING CONDITIONS ........................................................................................................................................... 5 Roadway & Intersection Characteristics .............................................................................................................. 5 Traffic Volumes.............................................................................................................................................................. 5 Crash History Analysis ................................................................................................................................................ 7 Existing Capacity Analysis ....................................................................................................................................... 10 Bike & Pedestrian Facilities .................................................................................................................................... 12 Lighting .......................................................................................................................................................................... 14 Stormwater Facilities ................................................................................................................................................. 15 CORRIDOR MODELING ........................................................................................................................................... 17 Traffic Volume Projections ...................................................................................................................................... 17 Methodology ............................................................................................................................................................. 17 Known Development Traffic ............................................................................................................................... 19 Potential Future Development............................................................................................................................ 19 Year 2035 Traffic Projections .............................................................................................................................. 20 Future Capacity Analysis .......................................................................................................................................... 22 Signal Warrants .......................................................................................................................................................... 24 RECOMMENDED IMPROVEMENTS .................................................................................................................... 25 Typical Section ............................................................................................................................................................. 25 Intersection Improvements ..................................................................................................................................... 27 Bike & Pedestrian Facilities .................................................................................................................................... 37 Lighting .......................................................................................................................................................................... 39 Stormwater ................................................................................................................................................................... 39 Wetland Delineation ................................................................................................................................................. 40 Geotechnical Analysis............................................................................................................................................... 42 Opinions of Probable Cost ...................................................................................................................................... 42 Oak Street Improvements Pre-Design Report ii LIST OF FIGURES FIGURE 1. STUDY AREA ........................................................................................................................ 2 FIGURE 2. EXISTING (2015) TRAFFIC VOLUMES .................................................................................. 6 FIGURE 3. CRASH DATA SUMMARY ..................................................................................................... 9 FIGURE 4. EXISTING BIKE & PEDESTRIAN FACILITIES ....................................................................... 13 FIGURE 5. PLANNED AND POTENTIAL FUTURE DEVELOPMENT ......................................................... 18 FIGURE 6. 2035 TRAFFIC VOLUME PROJECTIONS .............................................................................. 21 FIGURE 7. PROPOSED TYPICAL SECTIONS ......................................................................................... 26 FIGURE 8. COTTONWOOD ROAD INTERSECTION ALTERNATIVES ..................................................... 28 FIGURE 9. FERGUSON AVENUE INTERSECTION ALTERNATIVES ......................................................... 29 FIGURE 10. DAVIS LANE INTERSECTION ALTERNATIVES .................................................................... 30 FIGURE 11. NORTH 27TH AVENUE INTERSECTION ALTERNATIVES .................................................... 31 FIGURE 12. NORTH 19TH AVENUE INTERSECTION ALTERNATIVE ...................................................... 32 FIGURE 13. NORTH 11TH AVENUE INTERSECTION ALTERNATIVES .................................................... 33 FIGURE 14. NORTH 7TH AVENUE INTERSECTION ALTERNATIVE ........................................................ 34 FIGURE 15. NORTH ROUSE AVENUE INTERSECTION ALTERNATIVE ................................................... 35 FIGURE 16. FRONT STREET CONNECTOR PATHWAY CONCEPT ALIGNMENT ..................................... 38 Oak Street Improvements Pre-Design Report iii LIST OF TABLES TABLE 1. CORRIDOR CRASH DATA STATISTICS .................................................................................... 7 TABLE 2. INTERSECTION CRASH DATA STATISTICS ............................................................................... 7 TABLE 3. CRASH DATA SUMMARY ........................................................................................................ 8 TABLE 4. EXISTING CAPACITY CALCULATION RESULTS ...................................................................... 11 TABLE 5. EXISTING STREET LIGHTS ..................................................................................................... 14 TABLE 6. FUTURE TRIPS ON OAK STREET CORRIDOR – KNOWN DEVELOPMENTS ............................ 19 TABLE 7. FUTURE TRIPS ON OAK STREET CORRIDOR – POTENTIAL IN-FILL DEVELOPMENTS .......... 20 TABLE 8. AVERAGE WEEKDAY TRAFFIC ON OAK STREET CORRIDOR – 2035 PROJECTIONS ............. 22 TABLE 9. FUTURE (2035) CAPACITY CALCULATION RESULTS .............................................................. 23 TABLE 10. SIGNAL WARRANT SUMMARY ........................................................................................... 24 TABLE 11. INTERSECTION ALTERNATIVE SUMMARY – SIGNALS VS. ROUNDABOUTS ........................ 36 TABLE 12. WETLAND SUMMARY ......................................................................................................... 41 TABLE 13. OPINION OF PROBABLE COST SUMMARY ......................................................................... 42 APPENDIX Appendix A – Traffic Volume Data Appendix B – Existing Capacity Analysis Appendix C – Future Year Capacity Analysis Appendix D – Signal Warrant Analysis Appendix E – Lighting Calculations Appendix F – Stormwater Exhibits Appendix G – Wetland Delineation Report Appendix H – Geotechnical Memorandum Appendix I – Opinions of Probable Cost Oak Street Improvements Pre-Design Report 1 INTRODUCTION 1 This report provides a summary of the preliminary design tasks completed for the Oak Street Improvements project, including a review of existing traffic volumes, future design-year traffic volume projections, evaluation of design alternatives, and concept level designs for recommended improvements. It also summarizes the related stormwater analysis, wetland delineation and geotechnical analysis, as well as bike and pedestrian facility improvements. Project Corridor and Study Area Description Oak Street is one of the primary east-west routes in the Bozeman street network providing access from Rouse Avenue near Downtown out to the northwest side of town where much of the new residential development is taking place. The west end of Oak Street in particular has been constructed in a fragmentary fashion along with various private development projects, which has left several segments only partially built-out to the full five-lane typical section desired by the City of Bozeman. The purpose of this Oak Street Improvements project is to provide a design that will fill in those missing gaps and complete this key arterial route within the Bozeman transportation network. The extents of the Oak Street Improvements project begin at Cottonwood Road at the west end and continue east to the intersection of Rouse Avenue. The project consists of new road construction at the far west end, widening the remainder of the existing roadway, and installing traffic control improvements at several of the arterial intersections. The required level of roadway improvements vary by roadway segment and have generally been divided up as shown in Figure 1 on the following page. Cottonwood Road to Ferguson Avenue. There is an existing half-width segment of Oak Street approximately 650 feet in length that is constructed west of Cottonwood Road adjacent to Flanders Creek Subdivision. Other than that short segment, Oak Street has not yet been constructed from Cottonwood Road east to Ferguson Avenue. The future Oak Street alignment passes through two currently undeveloped parcels divided in a north-south direction by Flanders Mill Road. Right-of-way has been acquired along the eastern parcel from Flanders Mill Road to Ferguson Avenue, but it has not yet been acquired from Cottonwood Road to Flanders Mill Road. Oak Street Improvements Pre-Design Report 2 FIGURE 1. STUDY AREA Oak Street Improvements Pre-Design Report 3 3 Ferguson Avenue to Davis Lane. From Ferguson Avenue to Davis Lane, Oak Street currently consists of a single lane in each direction. The two lanes have been constructed within the south half of what will be the future five-lane cross-section from Ferguson Avenue to Meagher Avenue. Just east of Meagher Avenue, the two lanes shift to the north side of the future five-lane with a chicane of sorts and stay on that side through the Davis Lane intersection. Davis Lane to North 27th Avenue. At New Holland Drive, just east of Davis Lane, Oak Street opens up into an existing 5-lane cross-section with a 28-foot wide raised center median and two travel lanes in each direction. This segment also includes bike lanes and sidewalks on both sides of the roadway. This existing 5-lane cross-section runs from New Holland Drive to North 27th Avenue. North 27th Avenue to North 19th Avenue. At North 27th Avenue, Oak Street necks back down to a two-lane roadway for approximately 1500 feet before widening again into the turn lanes at the Oak Street and North 19th Avenue intersection. North 19th Avenue to North 7th Avenue. From North 19th Avenue to North 7th Avenue, Oak Street consists primarily of a five-lane typical section including two through lanes in each direction, a center two-way left-turn lane and bike lanes on both sides. From North 19th Avenue to North 15th Avenue however, there is only one eastbound through lane with no curb and gutter along the Covered Wagon trailer park, which has not yet been annexed into the City. There is another short segment from North 12th Avenue to North 11th Avenue that does not yet have curb and gutter, but the rest of the typical section is built out. The undeveloped private property adjacent to this stretch on the south side of Oak also has not yet been annexed. North 7th Avenue to North Rouse Avenue. East of North 7th Avenue, Oak Street includes one travel lane in each direction with dedicated turn bays and curb and gutter along the Walmart frontage. East of Walmart, it has a single travel lane in each direction with bike lanes and no curb and gutter all the way to Rouse Avenue. Related Projects Cottonwood Road Improvements. The City of Bozeman is currently in the preliminary design stages of improvements to Cottonwood Road from Babcock Street to Baxter Lane, consisting of a future five-lane typical section. The intersection of Cottonwood Road and Oak Street is a common intersection between this project and the Oak Street Improvements project. Therefore, traffic volume projections and recommended intersection improvements have been coordinated between the two projects. The timing of construction of the Cottonwood Road Improvements will depend on funding availability. Rouse Avenue Improvements. MDT has a project currently underway for reconstruction of approximately two miles of Rouse Avenue from Main Street to Story Mill Road, consisting of a future three-lane typical section with Oak Street Improvements Pre-Design Report 4 4 bike lanes, sidewalks, storm drain and intersection improvements. The intersection of Rouse Avenue and Oak Street is one of the intersections that will be improved with that project. The Oak Street project will begin just on the west side of the intersection. The improvements that will be constructed at this intersection are shown later in this report in Figure 15. MDT is currently working on right-of-way acquisition for the Rouse Avenue project and Phase I from Oak Street to Story Mill Road will be constructed in 2016. Phase II from Main Street to Oak Street (including the Oak Street intersection improvements) will be constructed in 2018. Gallatin County Fairgrounds Master Plan. The Gallatin County Fairgrounds has a master plan document that was approved by the Gallatin County Commission in December 2014. It shows a new east access drive to Oak Street adjacent to Heros Ball Park that was constructed in 2015, realignment of the existing central access point and relocation of the west access to line up with the Third Street alignment on the west boundary of the Fairgrounds property. The master plan also calls for a series of stormwater detention ponds along the north property line adjacent to Oak Street. Gallatin County Regional Park Master Plan. This master plan document, developed in August 2014, shows an expansion of the existing parking lot adjacent to Oak Street and the installation of a loop trail along the perimeter of the park, including along Oak Street. The existing parking lot access at the intersection of Oak Street and Yellowstone Avenue would remain, but two additional parking lot accesses are proposed to the east on Oak Street as well. Private Development. There are many private developments within the vicinity of the Oak Street corridor that are in various stages of planning and construction. These developments will be addressed in greater detail in the Corridor Modeling section of this report where future traffic volume projections are discussed. Some water and sewer services or extensions may need to be considered as part of the Oak Street Improvements project, but no new trunk mains would need to be installed. Oak Street Improvements Pre-Design Report 5 5 EXISTING CONDITIONS 2 A thorough evaluation of existing conditions was conducted to establish a baseline for this pre-design report. This effort included a topographic survey, collection of new peak hour turning movement counts at major intersections along the corridor, and review and analysis of crash data provided by MDT and the Bozeman Police Department. Roadway & Intersection Characteristics The Montana Department of Transportation (MDT) classifies Oak Street as an urban minor arterial (U-1202) from North 19th Avenue to North 7th Avenue, while the City of Bozeman classifies the entire length of the roadway as a principal arterial. In addition to through access from one side of town to the other, Oak Street also provides access to primarily residential development on the west side of North 19th Avenue and commercial development on the east side. The posted speed limit is 25 mph from Ferguson Avenue to Davis Lane, 35 mph from Davis Lane to North 19th Avenue, 45 mph from North 19th Avenue to North 11th Avenue and 35 mph from North 11th Avenue to Rouse Avenue. There are existing traffic signals at the intersections of Oak Street with North 19th Avenue, North 15th Avenue, North 7th Avenue and Rouse Avenue. The remaining intersections along Oak Street are two-way stop-controlled with stop signs located on the minor north and south approaches. Traffic Volumes Sanderson Stewart conducted AM and PM peak hour turning movement counts at the major intersections in May 2015, as well as 24-hour volume counts on many of the roadway segments in between. MDT seasonal adjustment factors were applied for the month of May to arrive at average annual daily traffic (AADT) volumes. The resulting AADT volumes and peak hour turning movement volumes at the key intersections are shown in Figure 2 on the following page. Detailed traffic count data is included in Appendix A. Oak Street Improvements Pre-Design Report 6 FIGURE 2. EXISTING (2015) TRAFFIC VOLUMES Oak Street Improvements Pre-Design Report 7 Crash History Analysis A crash history analysis was conducted for Oak Street from Ferguson Avenue to Rouse Avenue. Historical crash data was obtained from MDT for the five-year period from January 1, 2010 through December 31, 2014. During this time period, 183 crashes were reported including 0 fatal crashes, 58 injury crashes, and 125 property damage only crashes. Three crash rate statistics were calculated to analyze the crash history: crash rate, severity index, and severity rate. Crash rate is defined as the number of crashes per million vehicle miles. Severity index is defined as the weighted average by crash severity, including fatal, injury, and property damage only crashes. Severity rate is defined as the crash rate multiplied by the severity index. The crash rate statistics for Oak Street are calculated based on AADT volumes measured during the same time period. The crash rate for the 3.0-mile section of roadway was calculated at 2.56, the severity index at 1.69, and the severity rate at 4.33. As shown in Table 1, these numbers are compared to statewide average crash rates provided by MDT for the years 2008-2012 for Primary Urban Routes. The average rates are used by MDT to help gauge the need for safety improvements for a roadway. The calculated crash rate and severity rate for Oak Street are lower than the statewide average for non-interstate national highway system (NINHS) routes and state primary urban routes. Conversely, the severity index for the study corridor is slightly higher than the statewide average for the urban NINHS and state primary urban routes. Although Oak Street does not fall under this roadway classification, it is the only urban classification provided by MDT and can be used as a relative comparison. TABLE 1. CORRIDOR CRASH DATA STATISTICS Crash Rate Severity Index Severity Rate Oak Street 2.56 1.69 4.33 Statewide Average – NINHS & State Primary Urban Routes 4.51 1.66 7.48 As a general rule, intersections with a crash rate greater than 1.0 crashes per million-entering-vehicles should be monitored further to determine if an inherent safety concern exists. For this study, crash rates were calculated for the intersections with North 19th Avenue and North 7th Avenue, the two highest volume intersections along the corridor. These intersection crash data statistics are summarized in Table 2 below. These calculations show that both crash rates are below the 1.0 crashes per million-entering-vehicles that would trigger further monitoring by MDT. TABLE 2. INTERSECTION CRASH DATA STATISTICS Intersection Crash Rate Severity Index Severity Rate Oak Street & 19th Avenue 0.59 1.67 0.99 Oak Street & 7th Avenue 0.84 1.61 1.35 Table 3 on page 8 further summarizes all of the crash data for the corridor based on various characteristics and contributing factors such as location, weather and road conditions, crash type, and vehicle type. The majority of the crashes occurred at intersections along the corridor. The most prominent collision types (rear end, right angle and opposing-direction sideswipe) appear to be directly related to the high frequency of intersection and driveway crashes as opposed to crashes along areas with few access points. Figure 3 on page 9 provides a graphical representation of the same crash data by location along the corridor, again showing the spikes in number of crashes at the intersections. Oak Street Improvements Pre-Design Report 8 TABLE 3. CRASH DATA SUMMARY Month Crashes %Weather Crashes %Collision Type Crashes % January 22 12.0%Clear 89 48.6%Head On 1 0.5% February 14 7.7%Cloudy 61 33.3%Rear End 73 39.9% March 7 3.8%Snow 18 9.8%Right Angle 39 21.3% April 13 7.1%Sleet 3 1.6%Sideswipe SD 14 7.7% May 6 3.3%Rain 8 4.4%Sideswipe OD 1 0.5% June 18 9.8%Fog 0 0.0%Left Turn SD 4 2.2% July 14 7.7%Crosswinds 1 0.5%Left Turn OD 27 14.8% August 17 9.3%Blowing Snow 3 1.6%Fixed Object 14 7.7% September 14 7.7%Totals 183 100.0%Pedestrian 4 2.2% October 20 10.9%Wild Animal 1 0.5% November 20 10.9%Other 5 2.7% December 18 9.8%Road Conditions Crashes %Totals 183 100.0% Totals 183 100.0%Dry 119 65.0% Wet 28 15.3% Ice 20 10.9%Vehicle Type Vehicles % Day Crashes %Snow/Slush 16 8.7%Motorcycle 3 0.8% Sunday 10 5.5%Totals 183 100.0%Passenger Car 169 46.2% Monday 26 14.2%SUV 82 22.4% Tuesday 26 14.2%Van 13 3.6% Wednesday 33 18.0%Year Crashes %Pickup 84 23.0% Thursday 24 13.1%2010 40 21.9%Bus 2 0.5% Friday 40 21.9%2011 36 19.7%Truck/Tractor 9 2.5% Saturday 24 13.1%2012 41 22.4%Other 4 1.1% Totals 183 100.0%2013 39 21.3%Totals 366 100.0% 2014 27 14.8% Totals 183 100.0% Junc. Relation Crashes %Light Conditions Crashes % Intersection 131 71.6%Dawn 1 0.5% Driveway/Alley 20 10.9%Crash Severity Crashes %Daylight 133 72.7% Non-Junction 32 17.5%Fatal 0 0.0%Dusk 11 6.0% Totals 183 100.0%Injury Crash 58 31.7%Dark-Lighted 23 12.6% Prop. Damage Only 125 68.3%Dark-Not Lighted 15 8.2% Totals 183 100.0%Totals 183 100.0% Milepost Crashes % 0.0 - 0.3 6 3.3% 0.3 - 0.6 12 6.6%Note: Crash data summarized Time of Day Crashes % 0.6 - 0.9 2 1.1% from 1/1/10 through 12/31/14 Before 6:00 am 8 4.4% 0.9 - 1.2 11 6.0%6:00 am - 9:00 am 15 8.2% 1.2 - 1.5 7 3.8%9:00 am- 12:00 pm 22 12.0% 1.5 - 1.8 65 35.5%12:00 pm - 3:00 pm 46 25.1% 1.8 - 2.1 4 2.2%3:00 pm - 6:00 pm 51 27.9% 2.1 - 2.4 60 32.8%6:00 pm - 9:00 pm 24 13.1% 2.4 - 2.7 8 4.4%After 9:00 pm 17 9.3% 2.7 - 3.0 8 4.4%Totals 183 100.0% Totals 183 100.0% Oak Street Improvements Pre-Design Report 9 FIGURE 3. CRASH DATA SUMMARY Oak Street Improvements Pre-Design Report 10 The City of Bozeman Police Department also provided crash data for the same period from January 1, 2010 through December 31, 2014 that was available in their system. During this time period, 326 crashes were reported by the Bozeman Police Department, nearly twice the number provided by MDT. Because of the lack of information on crash type and contributing factors, crash severity and rates were unable to be calculated for this data set. Per MCA 61-7-108 and MCA 61-7- 109, local law enforcement are required to send their reported crashes to the Montana Highway Patrol (MDT crash database) for any crash involving an injury or more than $1000 in damage. Therefore, it is assumed the additional 143 crashes reported by the City of Bozeman Police Department are non-injury, property-damage-only crashes with the damage being less than $1000. Existing Capacity Analysis Capacity calculations were performed for existing conditions using Synchro 8, which is based on Highway Capacity Manual (HCM) methodologies. The HCM2010 defines level of service (LOS) as “a quality measure describing operational conditions within a traffic stream, generally in terms of such service measures as speed and travel time, freedom to maneuver, traffic interruptions, as well as comfort and convenience.” LOS is a qualitative measure of the performance of an intersection. LOS values range from LOS A, indicating good operation and low vehicle delays, to LOS F, which indicates congestion and longer vehicle delays. Both the City of Bozeman and MDT generally consider LOS C as the minimum standard for acceptable intersection operations. The existing capacity calculation results for this study show that all intersections and intersection approaches currently operate at an acceptable LOS for the AM peak hour, except for the west approach at North 19th Avenue and the north approach at Davis Lane. These two approaches currently operate at LOS D during the AM peak hour, but both intersections operate at LOS C or better overall. During the PM peak hour, the intersections of North 19th Avenue and North 7th Avenue fall to LOS E overall due to many of the individual approaches operating at unacceptable LOS values. Additionally, the north approaches at North 27th Avenue and North 11th Avenue fall to LOS D during the PM peak hour under existing conditions. A summary of existing capacity calculation results is provided in Table 4 on the following page. Detailed capacity calculation reports are provided in Appendix B. Oak Street Improvements Pre-Design Report 11 TABLE 4. EXISTING CAPACITY CALCULATION RESULTS Avg Delay (s/veh)LOS 95th % Queue (veh) Avg Delay (s/veh)LOS 95th % Queue (veh) WB 7.8 A 1 7.9 A 1 NB 9.7 A 2 0.0 A 0 Intersection ------------ EB 3.0 A 1 4.1 A 1 WB 0.0 A 0 0.0 A 0 SB 27.8 D 5 17.8 C 2 Intersection ------------ EB 0.8 A 1 0.7 A 1 WB 0.6 A 1 1.4 A 1 NB 21.5 C 2 21.2 C 2 SB 19.6 C 1 25.7 D 2 Intersection ------------ EB 37.4 D 22 54.4 D 24 WB 23.0 C 4 89.2 F 43 NB 23.0 C 8 35.3 D 22 SB 22.4 C 17 33.8 C 16 Intersection 25.0 C --56.9 E -- EB 6.2 A 5 9.3 A 7 WB 5.1 A 2 10.5 B 10 NB 14.2 B 2 14.8 B 7 SB 13.6 B 1 12.8 B 1 Intersection 7.1 A --10.9 B -- EB 0.1 A 0 0.3 A 1 WB 0.0 A 0 0.0 A 0 NB 0.0 A 0 10.5 B 1 SB 16.6 C 1 29.2 D 1 Intersection ------------ EB 22.0 C 12 42.8 D 16 WB 32.1 C 14 149.9 F 44 NB 25.8 C 10 37.1 D 22 SB 20.7 C 16 32.1 C 17 Intersection 23.1 C --57.6 E -- EB 27.3 C 7 27.2 C 7 WB 25.4 C 1 26.7 C 0 NB 5.6 A 3 5.5 A 6 SB 10.2 B 11 10.0 B 16 Intersection 13.7 B --11.4 B -- Davis Lane & Oak Street Intersection Control 15th Avenue & Oak Street PM Peak Existing (2015) One-way (NB) Stop Control Signalized Ferguson Avenue & Oak Street AM Peak Intersection Control Intersection Approach Intersection Control One-way (SB) Stop Control Intersection Control Two-way (NB & SB) Stop Control 27th Avenue & Oak Street Intersection Control Signalized 19th Avenue & Oak Street 7th Avenue & Oak Street Intersection Control Signalized Rouse Avenue & Oak Street/Birch Street Intersection Control Two-way (NB & SB) Stop Control 11th Avenue & Oak Street Intersection Control Signalized Oak Street Improvements Pre-Design Report 12 Bike & Pedestrian Facilities Existing bike and pedestrian facilities along Oak Street are shown in Figure 4 on the following page. They consist primarily of concrete sidewalk or asphalt path along the segments of Oak Street that have already been improved to the future five-lane section. Most of these segments also include striped bike lanes. There are various missing segments of sidewalk, path and bike lane that will need to be filled in with the Oak Street Improvements project. Bike and pedestrian volumes along the corridor generally consist of approximately 10 per peak hour on the lower volume intersections at the west end up to approximately 40 per peak hour at the higher volume intersections on the east end. There is an existing mid-block pedestrian crossing located approximately 700 feet east of Ferguson Avenue that connects an existing gravel trail south of Oak Street within Diamond Estates Subdivision with the existing gravel trails within the County Regional Park north of Oak Street. This crossing location is marked with a ladder-style crosswalk and pedestrian crossing signs as shown in the picture below. All other signed/marked crossing locations line up with existing intersections, many of which are signalized intersections. Existing mid-block crosswalk located east of Ferguson. Oak Street Improvements Pre-Design Report 13 FIGURE 4. EXISTING BIKE & PEDESTRIAN FACILITIES Oak Street Improvements Pre-Design Report 14 Lighting Marvin & Associates completed a visual inventory of existing street lights along the Oak Street corridor. As shown in Table 5 below, there are a total of 24 lights along the corridor with 10 of the lights being associated with signalized intersections. All but one of the 14 street lights are concentrated in the corridor area west of North 19th Avenue and 11 of those lights are located at intersections. There are three different types of existing lights: shoe-box, gull wing, and cobra head. It appears that all of the lights have High Pressure Sodium (HPS) lamps, although some of them could also be metal halide. It can be concluded that the existing corridor lighting does not exhibit a uniform appearance along the entire corridor, nor does the lighting meet AASHTO or ANSI-IES average illuminance or average/minimum uniformity ratios associated with principal arterial streets. Therefore, it has been assumed that the design of the new corridor lighting system would require replacement of existing lights with a single uniform style pole and luminaire with new LED lamps as required by City of Bozeman standards. TABLE 5. EXISTING STREET LIGHTS No.Height From To Lights Location Style (ft) Ferguson Avenue Davis Lane 6 South Side Shoe Box 35-45 HPS Intersections 0 Davis Lane N 27th Avenue 5 North Side Gull Wing 35-45 HPS Intersections NA N 27th Avenue Woodland Avenue 0 NA NA NA NA NA NA Woodland Avenue N 19th Avenue 2 North Side Cobra Head 35-45 HPS 200 ft 2 N 19th Avenue N 15th Avenue 0 NA NA NA NA NA 4 N 15th Avenue N 7th Avenue 0 NA NA NA NA NA 2 N 7th Avenue Rouse Avenue 1 South Side Cobra Head 35-45 HPS NA 2 14 10 Lamp Type Corridor Segment Total = Spacing Signal Luminaires Existing shoe-box lights located east of Ferguson. Existing shoe-box lights located east of Ferguson. Oak Street Improvements Pre-Design Report 15 Stormwater Facilities The natural stormwater runoff flow direction throughout the Oak Street corridor is generally south to north. Overland flows collect into multiple small waterways that ultimately flow north into the East Gallatin River. There is a wide range of land use along Oak Street which includes open farm fields, parks, commercial, industrial, and residential development. Some developed areas include stormwater detention ponds, pipe networks and culverts while other areas have no existing stormwater features. There is no continuous storm drain network within Oak Street itself and there is generally an absence of stormwater treatment. Many existing inlets empty to detention ponds, to the north or south of the street, before draining into the natural open channels. A series of culverts are currently used in Oak Street to convey the small waterways that run to the north. There are sections of Oak Street that do not have any existing curb and gutter and runoff from the roadway is allowed to flow off the shoulders to the north or south and is not controlled by additional stormwater features within the right-of-way. North Rouse Avenue to North 7th Avenue. Two inlets collect runoff at the intersection of Oak Street and North Rouse Avenue. The water is then conveyed to an outfall at Bozeman Creek to the east via an 18-inch storm drain pipe. These inlets also collect a portion of the runoff generated in Oak Street to the west. The County Fairgrounds, located to the south of Oak Street, currently do not have any stormwater features, resulting in runoff and debris collecting near the south boundary of the Oak Street right-of-way. A low point exists in Oak Street to the north of the fairgrounds that allows runoff to spill over the roadway to the open field to the north. There are no stormwater features or curb and gutter in Oak Street to the west until near the intersection with North 5th Avenue. At the intersection, a 30-inch pipe, that drains the commercial lots to the south via a detention pond, connects to a 42- inch pipe that runs south to north. This pipe connects to the drainage system for the Wal-Mart parking lot to the north which empties into a detention pond near Interstate 90. Three inlets at the intersection with North 7th Avenue collect into a single outfall pipe that empties into a ditch on the west side of North 7th Avenue to the north of the intersection. North 7th Avenue to North 19th Avenue. There are no existing stormwater features in the right-of-way between North 7th Avenue and the culvert crossing at Mandeville Creek. To the west of Mandeville Creek, near North 11th Avenue, a pair of inlets drain to the ditch on the south side of Oak Street. A small storm system, including one pond, transports runoff on the south side of Oak Street from a high point, between North 12th and North 14th Avenues, east to Mandeville Creek. West of that high point, another system collects runoff on the south side of Oak Street and transports it west to near North 17th Avenue before crossing under Oak Street where it outfalls into Farmer’s Canal to the north. Inlets at the intersection of North 19th Avenue connect to a 60-inch storm drain main. This main Oak Street Improvements Pre-Design Report 16 turns east on the north side of Oak Street and also outfalls to Farmer’s Canal. The majority of Oak Street through this section does not have curb and gutter. North 19th Avenue to Davis Lane. The only stormwater feature between North 19th Avenue and Woodland Drive is the culvert for Catron Creek to pass under Oak Street. Just west of Woodland Drive a pair of inlets connect to a 21-inch storm drain that empties to a large detention pond to the north of the street. This pond outfalls to the channel that crosses under Oak Street through culverts just to the west. Other inlets to the west empty north into the park area that extends to the intersection with North 27th Avenue. The only other storm system in this area is located between New Holland Drive and Buckrake Avenue and empties to the channel east of Hunters Way. Inlets on the south side of the street empty to three detention ponds south of the road while the inlets to the north drain to a single pond north of the street. Davis Lane to Cottonwood Road. Inlets just west of Davis Lane collect into an 18-inch storm drain that empties into the detention pond on the north side of Oak Street. Between Meagher Avenue and Ferguson Avenue, a series of inlets are used to collect runoff into a storm drain system (size 15-inch to 24-inch diameter) that empty to two stormwater detention ponds on the south side of Oak Street which outfall into a nearby open channel. The Oak Street corridor is currently undeveloped between Ferguson Avenue and Cottonwood Road. The new road will eventually be constructed, through the open fields that exist now. Inlets, pipe and detention ponds exist in the residential development west of Cottonwood Road. Existing storm drain pipes and detention ponds are shown on the Stormwater Exhibits shown in Appendix F. Existing low points and flow directions are also shown and drainage areas are delineated for the undeveloped areas south of Oak Street that drain to the right-of-way. Oak Street Improvements Pre-Design Report 17 CORRIDOR MODELING 3 Corridor traffic volumes were projected using a methodology based on existing traffic patterns at the primary corridor intersections, as described in greater detail in the following paragraphs. These volumes were then used to prepare a corridor model for the evaluation of traffic operations and ultimately, the evaluation of alternatives for improvement. Traffic Volume Projections Methodology Corridor traffic projection methodology was based primarily on existing traffic patterns at the ten key corridor intersections. Existing AM and PM traffic patterns at the key intersections were converted to percentage distribution values to determine relative travel demand from and to separate corridor links. Since the Oak Street corridor will be extended west to Cottonwood Road and Davis Lane will eventually be extended south to Fowler Avenue, a traffic redistribution routine was applied to existing AM and PM traffic volumes to determine patterns that would result if those roadway extensions existed today. The redistributed traffic patterns were then used to assign future development trips to the Oak Street corridor. Future trip assignments were based on the information contained within fourteen different traffic impact studies for known and proposed developments (orange properties in Figure 5 on the following page). The number of dwelling units contained within the known developments were compared to historic growth trends in the City of Bozeman and additional development within vacant properties along the corridor (blue properties in Figure 5) were included to introduce additional potential development that could occur in the next 20 years. Trip distribution that would use the Oak Street corridor and intersecting streets were introduced to the corridor at one or more of the key intersections. The new trips were then distributed along the corridor based upon traffic patterns developed in the traffic reassignment model. Four of the key intersections involve roadways that also serve regional through traffic. Those streets are Davis Lane, North 19th Avenue, North 7th Avenue, and Rouse Avenue. Additional through traffic was added to the cross street traffic based on an assumed annual growth rate of 2.5%. Thus, through traffic volumes on those streets were increased by approximately 60% to reflect 20 year design hour volumes. Oak Street Improvements Pre-Design Report 18 FIGURE 5. PLANNED AND POTENTIAL FUTURE DEVELOPMENT Oak Street Improvements Pre-Design Report 19 Known Development Traffic Table 6 indicates the number of trips that would be generated by known developments (orange properties in Figure 5) along with the relative percentage of trips that would be distributed to and from the Oak Street corridor. The distribution percentages were extracted from the TIS reports and in some cases modified to reflect the street extensions that would be involved with year 2035 street system changes. There would be a total of approximately 31,000 additional average weekday trips (AWT) generated by the known developments, with 2,400 in the AM peak hour and 3,100 in the PM peak hour. The number of trips actually impacting the Oak Street corridor would involve approximately 8,900 AWT with 700 AM peak hour trips and 890 PM peak hour trips. TABLE 6. FUTURE TRIPS ON OAK STREET CORRIDOR – KNOWN DEVELOPMENTS The known developments would contain approximately 3,150 dwelling units with an assumed occupation of 2.0 residents per unit resulting in a population increase of approximately 6,300. State statistics indicate that Bozeman has grown at an annual rate of approximately 2.5% in the past 10 years. If that rate were to continue over the next 20 years, the population of Bozeman would grow by approximately 25,600. Therefore, known developments in the area would represent approximately 25% of growth in Bozeman. Potential Future Development Since this area of Bozeman has seen tremendous development in the past three years, it has been assumed that at least one third of the growth in Bozeman will occur in this area. Thus, this area has potential to grow beyond the known developments within the next 20 years. Table 7 indicates trip generation created by development that could potentially occur within the Oak Street corridor’s area of influence (blue properties in Figure 5). These developments are large areas of unoccupied land that are adjacent to or surrounded by known development areas. It was assumed that future developments on these land areas would be similar in nature to those currently being developed. One large parcel has recently been identified as an area where a Resident Office Retail Resident Office/Ret Total % Trips on Connection Units Units Units AWT AWT AWT AM PM Oak Model AWT AM PM Location Boulder Creek/Westbrook 233 0 0 2230 0 2230 175 235 25%558 44 59 Laurel Parkway Flanders/Rosa 452 25.8 0 3253 284 3537 261 351 20%707 52 70 Cottonwood & East J&D/Norton East Ranch 40 4.7 90 234 3580 3814 283 341 5%191 14 17 Cottonwood The Lakes at Valley West 300 0 0 2310 0 2310 177 221 20%462 35 44 Laurel Parkway Norton Ranch 106 0 0 1014 0 1014 80 107 5%51 4 5 Cottonwood Oak Meadows 123 0 0 824 0 824 60 82 100%824 60 82 14th Avenue N Sundance (Baxter Meadows 2)554 40 0 3684 654 4338 344 418 27%1171 93 113 Davis/Ferguson Traditions 98 0 0 938 0 938 74 99 20%188 15 20 East of Cottonwood West Winds 210 0 0 1232 0 1232 93 123 30%370 28 37 Davis/N 27th Baxter Meadows 3 112 0 0 1218 0 1218 98 126 35%426 34 44 Flanders Mill Road Baxter Meadows 4 112 0 0 1099 0 1099 88 130 32%352 28 42 Davis Lane Four Points Sub 414 0 0 2753 0 2753 221 256 35%964 77 90 Ferguson/Davis Flanders Mill Sub 396 0 0 3545 0 3545 269 348 35%1241 94 122 Ferguson/Flanders Mill Cannery Development 0 109 28 0 2344 2344 205 237 57%1336 117 135 Rouse & West Sports Complex 0 0 80 0 0 152 15 30 30%46 5 9 Cottonwood/Flanders Mill Totals =3150 179.5 198 24334 6862 31348 2443 3104 8887 700 889 Demographics:New Residents at 2.0 per Unit =6300 Bozeman Annual Growth Rate =2.5% 20 Year Growth Factor =1.64 Current Population = 40000 Net Increase by 2035 =25600 Growth within Oak Corridor Area (% of Total)=25% Traffic On Oak CorridorTrips Development Oak Street Improvements Pre-Design Report 20 new high school may be located in the future. Table 7 indicates the level of trip generation and trip distribution that would be directed to and from the Oak Street corridor, similar to Table 6. TABLE 7. FUTURE TRIPS ON OAK STREET CORRIDOR – POTENTIAL IN-FILL DEVELOPMENTS There would be a total of approximately 17,700 additional average weekday trips (AWT) generated by the potential developments, with 1,900 in the AM peak hour and 1,800 in the PM peak hour. The number of trips actually impacting the Oak Street corridor would involve approximately 6,500 AWT with 640 AM peak hour trips and 640 PM peak hour trips. When combined with the known developments, traffic impacts on the Oak Street corridor would result in an additional 15,400 AWT with 1,340 AM peak hour trips and 1,530 PM peak hour trips. Using the same assumptions for 20 year growth in Bozeman, it can be seen that growth in the Oak Street corridor area would amount to approximately 31% of the total 20 year growth in Bozeman, which is within the rational limits that were assumed. Year 2035 Traffic Projections The trip generation numbers at corridor entry points identified in Tables 6 and 7 were input into the existing traffic redistribution model. The model was modified somewhat to account for special trip generation conditions and distribution patterns influenced by new development attractions and productions. The model was designed to balance directional traffic flows wherever possible to check for anomalies and ensure that traffic inputs were equated with resultant departures at each intersection. Four system routes (Davis Lane, North 19th Avenue, North 7th Avenue, and Rouse Avenue) accommodate through traffic with no origins or destinations within the development areas. Since through traffic on those routes impact traffic operations at their intersections with Oak Street, 20 year traffic projections were applied to existing through traffic volumes and were added to the model at those intersections. It was assumed that the growth rate on the four routes would increase proportionately with growth in Bozeman, at 2.5% annually. This resulted in approximately 60% more through traffic than currently exists. Figure 6 on the following page presents the resulting year 2035 AM and PM peak hour traffic projections used in the operations analysis for the Oak Street corridor, along with the 2035 projected daily traffic volumes on the roadway segments between major intersections. Resident Office Retail Resident Office/Ret Total % Trips on Connection Units Units Units AWT AWT AWT AM PM Oak Model AWT AM PM Location 1 Northwest of Cottonwood/Oak 230 0 0 2300 0 2300 173 230 50%1150 86 115 Cottonwood/Oak 2 East of Lakes at Valley West 70 0 0 700 0 700 53 70 20%140 11 14 Laurel Parkway 3 East of Flanders/Rosa **0 0 0 0 1500 1500 644 195 25%375 161 49 Cottonwood/Oak 4 NW of Ferguson Durston 30 0 0 300 0 300 23 30 30%90 7 9 Ferguson 5 NE of Ferguson/Oak 40 0 0 400 0 400 30 40 60%240 18 24 Ferguson 6 NE of Davis/Oak 30 0 0 300 0 300 23 30 60%180 14 18 Davis/Oak 7 NE of Baxter/Davis 180 0 0 1440 0 1440 114 137 30%432 34 41 Davis/N 27th 8 NE of Baxter/27th Ave 70 25 80 560 3500 4060 320 386 20%812 64 77 N 27th 9 NE of N 27th/Oak 105 0 15 840 600 1440 114 137 35%504 40 48 N 27th 10 W of N 11th Ave N of Oak 50 40 40 400 2050 2450 193 233 30%735 58 70 N15th/N 11th 11 NW of N 7th Ave/Durston 70 0 0 700 0 700 53 70 20%140 11 14 N 11th 12 S of Oak E of N 7th 0 20 10 0 800 800 63 76 50%400 32 38 Oak 13 West of Cannery District 0 25 25 0 1300 1300 103 124 100%1300 103 124 Oak Totals =875 110 170 7940 9750 17690 1902 1757 6498 636 641 * It is assummed that only 30% of potential developments would occur in the next 20 years. ** New High School/Middle School (1500 Students assummed) New Residents at 2.0 per Unit =8050 Bozeman Annual Growth Rate =2.5% 20 Year Growth Factor =1.64 Current Population = 40000 Net Increase by 2035 =25600 Growth in Oak Corridor Area (% of Total)=31% Trips Traffic On Oak Corridor Demographics Including Known Developments: Development* Oak Street Improvements Pre-Design Report 21 FIGURE 6. 2035 TRAFFIC VOLUME PROJECTIONS Oak Street Improvements Pre-Design Report 22 Average weekday traffic (AWT) volumes along the corridor were calculated based on hourly variation factors applied to the AM and PM peak hour traffic projections. Table 8 presents the design AWT volumes along with percentages of heavy truck traffic, based on existing traffic data. TABLE 8. AVERAGE WEEKDAY TRAFFIC ON OAK STREET CORRIDOR – 2035 PROJECTIONS Future Capacity Analysis Peak hour capacity calculations were performed for the future (2035) traffic volume scenario using the same methodology outlined for the analysis of existing conditions. For a baseline comparison of future conditions, these calculations were first completed using the full future five-lane typical section on Oak Street without any improvements to existing intersection traffic control. The results of these calculations are presented in Table 9 on the following page. With this scenario, many of the arterial intersections along the corridor would operate at less than desirable levels of service. The intersections of Oak Street with Ferguson Avenue, Davis Lane, 27th Avenue, 19th Avenue, 11th Avenue, and 7th Avenue are all expected to experience less than desirable LOS for individual approaches or the intersection as a whole for the future (2035) traffic volume scenario. The existing signalized intersections of Oak Street with North 19th Avenue and North 7th Avenue are anticipated to operate at LOS D during the PM peak hour for the future (2035) traffic volume scenario with implementation of the proposed design typical sections. These anticipated improvements include an additional through lane and right-turn lane for eastbound traffic at North 19th Avenue and an additional through lane and right-turn lane for westbound traffic at North 7th Avenue. These additional lanes would result in significant operational improvements at both intersections over existing conditions. A sensitivity analysis was conducted for the two intersections and found that LOS D would not be reached until future years 2033 and 2030 for the 7th Avenue and 19th Avenue intersections, respectively. Due to the favorable results of this analysis and the cost associated with complete reconstruction, a roundabout alternative was not evaluated for either of these two intersections. Preliminary discussions with the City of Bozeman indicated agreement with this approach. The remaining four intersections with less than desirable LOS, along with the Cottonwood Road intersection, were evaluated for both signal and roundabout intersection control alternatives. For all five intersections evaluated, both the signal and roundabout intersection control alternatives are anticipated to handle the future (2035) traffic volumes within an acceptable LOS range as shown in Table 9. Future year capacity calculation worksheets can be found in Appendix C. AM PM Highest Design Calculation Calculation AM - PM AWT East of Cottonwood Road 5885 4869 5885 6,000 1% East of Flanders Mill Road 6306 5486 6306 6,500 1% East of Ferguson Avenue 14424 14158 14424 14,500 1% East of Davis Lane 11739 12348 12348 12,500 2% East of N 27th Avenue 11403 13501 13501 13,500 3% East of N 19th Avenue 20119 20740 20740 20,800 3% East of N 15th Avenue 19075 19579 19579 19,600 3% East of N 11th Avenue 19587 19470 19470 19,500 3% East of N 7th Avenue 17405 18280 18280 18,300 3% West of Rouse Avenue 13053 10056 13053 13,100 3% Corridor Link % Trucks Oak Street Improvements Pre-Design Report 23 23 TABLE 9. FUTURE (2035) CAPACITY CALCULATION RESULTS Avg Delay (s/veh)LOS 95th % Queue (veh) Avg Delay (s/veh)LOS 95th % Queue (veh) Avg Delay (s/veh)LOS 95th % Queue (veh) Avg Delay (s/veh)LOS 95th % Queue (veh) Avg Delay (s/veh)LOS 95th % Queue (veh) Avg Delay (s/veh)LOS 95th % Queue (veh) EB 0.6 A 0 1.0 A 0 7.6 A 1 6.6 A 1 3.9 A 1 3.6 A 1 WB 1.5 A 1 2.6 A 1 7.5 A 1 7.2 A 2 3.7 A 1 4.2 A 1 NB 12.0 B 1 14.3 B 1 6.7 A 1 7.3 A 2 2.8 A 1 3.1 A 1 SB 13.5 B 1 16.7 C 1 7.0 A 2 7.4 A 1 3.5 A 1 3.3 A 1 Intersection ------------7.2 A --7.2 A --3.5 A --3.6 A -- EB 0.2 A 0 0.4 A 0 WB 0.5 A 0 0.9 A 1 NB 11.9 B 1 14.4 B 1 SB 13.6 B 1 15.6 C 1 Intersection ------------ EB 0.1 A 0 0.2 A 0 9.8 A 3 7.8 A 2 5.1 A 2 4.8 A 1 WB 6.5 A 2 5.6 A 2 24.6 C 5 21.4 C 10 5.1 A 3 8.6 A 7 NB 18.8 D 3 --F 3 16.7 B 2 16.1 B 2 2.7 A 2 2.9 A 2 SB 692.5 F 15 --F --10.3 B 3 10.6 B 3 4.0 A 1 4.5 A 1 Intersection ------------17.7 B --17.3 B --4.0 A --5.7 A -- EB 2.1 A 1 4.9 A 2 11.8 B 4 9.9 A 5 15.4 C 13 7.2 A 4 WB 0.1 A 0 0.0 A 0 9.7 A 3 8.3 A 5 4.6 A 3 15.1 C 16 NB --F 9 9.4 A --9.9 A 2 15.0 B 5 7.2 A 2 7.8 A 4 SB --F 33 116.0 F 10 12.0 B 3 15.5 B 3 9.5 A 9 7.2 A 4 Intersection ------------11.2 B --11.6 B --9.9 A --10.2 B -- EB 1.1 A 1 1.2 A 1 8.5 A 6 6.2 A 3 2.6 A 2 2.3 A 1 WB 0.5 A 1 1.0 A 1 7.0 A 3 7.2 A 5 2.2 A 1 2.8 A 2 NB 278.4 F 12 236.4 F 10 10.5 B 3 10.5 B 3 4.7 A 1 4.2 A 1 SB 398.5 F 14 --F 1 10.6 B 3 11.2 B 3 4.1 A 1 5.2 A 2 Intersection ------------8.6 A --7.8 A --2.9 A --3.1 A -- EB 54.9 D 17 55.9 E 18 WB 41.9 D 8 61.0 E 22 NB 24.4 C 13 37.2 D 38 SB 28.9 C 30 33.8 C 26 Intersection 34.6 C --44.6 D -- EB 7.7 A 7 12.6 B 10 WB 6.3 A 3 14.7 B 14 NB 18.6 B 3 20.7 C 9 SB 17.8 B 2 17.1 B 3 Intersection 9.3 A --15.2 B -- EB 0.2 A 1 0.4 A 1 5.8 A 5 5.2 A 5 2.4 A 2 2.5 A 2 WB 0.2 A 0 0.3 A 1 4.8 A 3 5.8 A 6 2.0 A 1 2.7 A 3 NB 37.1 E 2 44.6 E 2 12.3 B 2 12.8 B 1 4.4 A 1 4.2 A 1 SB 32.5 D 2 90.3 F 4 11.6 B 2 13.1 B 2 3.8 A 1 5.1 A 1 Intersection ------------6.1 A --6.1 A --2.4 A --2.8 A -- EB 38.5 D 21 52.0 D 24 WB 42.8 D 7 50.1 D 14 NB 28.5 C 15 35.0 C 33 SB 25.4 C 21 30.0 C 24 Intersection 31.3 C --38.9 D -- EB 27.9 C 13 27.4 C 12 WB 24.3 C 1 25.4 C 0 NB 11.2 B 14 10.5 B 13 SB 17.7 B 21 16.7 B 28 Intersection 18.5 B --16.7 B -- Cottonwood Road & Oak Street Intersection Approach New Typical Section & Ex. Intersection Control AM Peak PM Peak 15th Avenue & Oak Street Intersection Control Two-way (NB & SB) Stop Control 27th Avenue & Oak Street Intersection Control Signalized 19th Avenue & Oak Street Intersection Control Signalized Intersection Control Signalized Rouse Avenue & Oak Street 11th Avenue & Oak Street Intersection Control Signalized 7th Avenue & Oak Street Two-way (NB & SB) Stop Control Davis Lane & Oak Street Intersection Control Two-way (NB & SB) Stop Control Signal Alternative AM Peak PM Peak Intersection Control Two-way (NB & SB) Stop Control Flanders Mill Road & Oak Street Intersection Control Two-way (NB & SB) Stop Control Ferguson Avenue & Oak Street Intersection Control Intersection Control Two-way (NB & SB) Stop Control Roundabout Alternative AM Peak PM Peak Roundabout Semi-Actuated Signal Roundabout Roundabout Roundabout Roundabout Semi-Actuated Signal Semi-Actuated Signal Semi-Actuated Signal Semi-Actuated Signal Oak Street Improvements Pre-Design Report 24 24 Signal Warrants Traffic signal warrant evaluations, based on the Manual on Uniform Traffic Control Devices (MUTCD) methodologies, were performed for the five major intersections that are not currently signalized. These calculations were completed for weekday peak hour scenarios for both the existing year (2015) and future year (2035) volumes. Oak Street intersections evaluated include Cottonwood Road, Ferguson Avenue, Davis Lane, North 27th Avenue, and North 11th Avenue. A comprehensive evaluation of all nine warrants could not be completed with the data available, so only the volume warrants were considered in this analysis. For existing year volumes, the Peak Hour warrant was evaluated for all intersections except Cottonwood Road and the Eight-Hour Vehicular Volume and Four-Hour Vehicular Volume warrants were evaluated for the Davis Lane and North 27th Avenue intersections. For the future year volumes, the Peak Hour warrant was evaluated for all five project intersections. None of the traffic volume signal warrants were met for the existing year (2015) volume scenario. The Peak Hour Volume warrant was met for all the project intersections, except Cottonwood Road, for the future year (2035) volume scenario. Table 10 below summarizes the signal warrants and complete worksheets can be found in Appendix D. TABLE 10. SIGNAL WARRANT SUMMARY Although signal warrants would not be met for the projected 20-year volumes at the intersection of Oak Street and Cottonwood Road, the future build-out of this intersection was still considered to be a signalized (or roundabout) intersection of two five-lane arterial roadways. Warrants will be met at some point in the future so it is important for the City of Bozeman to be able to plan for this ultimate level of improvement. Oak &Oak &Oak &Oak &Oak &Oak &Oak &Oak &Oak &Oak & Cottonwood Ferguson Davis 27th 11th Cottonwood Ferguson Davis 27th 11th ----x x ------------ ----x x ------------ --x x x x x  -------------------- -------------------- -------------------- -------------------- -------------------- -------------------- Yes  No x x x x x x TRAFFIC SIGNAL WARRANTS 8. Roadway Network Signals Warranted 1. Eight-Hour Vehicular Volume 2. Four-Hour Vehicular Volume 3. Peak Hour 4. Pedestrian Volume 5. School Crossing 6. Coordinated Signal System 7. Crash History 9. Intersection Near a Grade Crossing Existing Volumes (2015)Future Volumes (2035) Oak Street Improvements Pre-Design Report 25 RECOMMENDED IMPROVEMENTS 4 The preceding evaluation of existing conditions, analysis of projected future traffic operations and other study considerations resulted in many recommended improvements for the future build-out of the Oak Street corridor. In general, all design elements for this project should be implemented with the ultimate goal of constructing a cohesive corridor that operates safely and efficiently for all modes of traffic. The recommended improvements should ultimately be designed to City of Bozeman, MDT, MUTCD, and other standards as appropriate. Typical Section Figure 7 on the following page shows the proposed typical sections for the Oak Street Corridor. These typical sections are based on the standard typical sections included in the Greater Bozeman Area Transportation Plan (2007 Update) with various adjustments made to match existing conditions. The proposed five-lane typical section for the segment that runs from Cottonwood Road to North 27th Avenue matches the existing section from New Holland Drive to North 27th Avenue. This section generally consists of a 28-foot wide raised median, two travel lanes in each direction, striped bike lanes, landscaped boulevards and 5 to 6-foot wide sidewalks. New sidewalks should be constructed at 6 feet wide wherever possible, but some may be constructed at 5-feet wide to match existing conditions. The wide median through this segment may include bioswales for stormwater treatment. East of North 27th Avenue, the proposed typical section matches the existing 5-lane section between North 19th Avenue and North 7th Avenue. It generally consists of a center two-way left-turn lane, two travel lanes in each direction, striped bike lanes, landscaped boulevard and either a 10-foot wide multi-use path or 5 to 6-foot wide sidewalks. Existing sidewalks should be replaced as needed for the roadway widening west of North 19th Avenue. Missing gaps in the existing multi-use path east of North 19th Avenue should be filled in to provide a continuous bike/pedestrian route. A three-lane typical section will be adequate for the traffic volumes projected east of North 7th Avenue. The proposed typical section for this segment is similar to the 3-lane collector option in the Greater Bozeman Area Transportation Plan (2007 Update). It includes a center two-way left-turn lane, one travel lane in each direction, striped bike lanes, landscaped boulevards, and either a 10-foot wide multi-use path (to match the existing path on the south side) or 5 to 6-foot wide sidewalks to match existing on the west end of this segment. Oak Street Improvements Pre-Design Report 26 FIGURE 7. PROPOSED TYPICAL SECTIONS Oak Street Improvements Pre-Design Report 27 Intersection Improvements As discussed previously in the evaluation of future traffic conditions, both signals and roundabouts were considered as potential traffic control at the major arterial intersections along the corridor. Because North 19th Avenue, North 15th Avenue and North 7th Avenue are already signalized, and the signals will operate well with fairly minor improvements, it was assumed that it would be cost prohibitive to go back and replace those intersections with roundabouts. In addition, the North Rouse Avenue intersection is already signalized and will be further improved as a signalized intersection with MDT’s Rouse Avenue reconstruction project. Therefore, the comprehensive review of signals vs. roundabouts was conducted at the following intersections:  Cottonwood Road  Ferguson Avenue  Davis Lane  North 27th Avenue  North 11th Avenue Capacity calculation results for both alternatives at these five intersections are presented in Table 9 on page 23. Figures 8-15 on the following pages show the concept level design improvements for each alternative, and Table 11 on page 36 presents a matrix of the pros and cons of signals vs. roundabouts for these five intersections. The existing power poles that run down the centerline of Oak Street from North 27th Avenue to the west present a significant design challenge, especially for the signalized alternatives. In many cases, auxiliary left-turn bays cannot be installed at the intersections unless power poles were relocated. The power line is a major 161 KV transmission line with a heavy distribution feeder line attached. For the purposes of this evaluation, it was assumed that they would only be moved if they are located near the center of the intersection (specifically for the signalized alternatives at Ferguson Avenue and Davis Lane) and left-turn bays would only be installed where they would fit within the existing power pole spacing. Cost estimates were provided by NorthWestern Energy for the relocation of power poles at Ferguson Avenue and Davis Lane. Although the preferred design for Oak Street on the west end consists of two travel lanes in each direction, the traffic volumes projected for the 20-year design life do not dictate the need for two full circulating lanes for the roundabout alternatives. Therefore, it is being proposed that the roundabouts generally be constructed with one through lane and one right-turn lane in each direction, as shown in the design concepts. It is worth noting that in most cases, raised median (aka sausage median) is recommended between the two entering lanes to better control speeds of entering vehicles and channelize them into the correct lanes. It also mimics the benefits, to a large degree, of a single-lane roundabout by limiting motorist decisions, reducing speeds, and limiting vehicle-vehicle conflicts. The right turns are recommended to be either free-right or yield depending on the receiving lane configuration. This configuration does require motorists to make appropriate lane choices prior to arriving at the roundabout, so adequate signing and striping will be important. With only minor modifications (removing sausage medians, pulling back the splitter islands, moving crosswalks back, minor curb modifications, and adjusting signing and striping), the roundabouts could be converted to provide two lanes through the roundabout when volumes warrant it in the future. At 11th Avenue, due to the high through-traffic volumes, providing two eastbound and westbound lanes through the roundabout is recommended since there is a potential for delays and queuing before the design year is reached. Existing power poles along center median. Oak Street Improvements Pre-Design Report 28 FIGURE 8. COTTONWOOD ROAD INTERSECTION ALTERNATIVES Oak Street Improvements Pre-Design Report 29 FIGURE 9. FERGUSON AVENUE INTERSECTION ALTERNATIVES Oak Street Improvements Pre-Design Report 30 FIGURE 10. DAVIS LANE INTERSECTION ALTERNATIVES Oak Street Improvements Pre-Design Report 31 FIGURE 11. NORTH 27TH AVENUE INTERSECTION ALTERNATIVES Oak Street Improvements Pre-Design Report 32 FIGURE 12. NORTH 19TH AVENUE INTERSECTION ALTERNATIVE Oak Street Improvements Pre-Design Report 33 FIGURE 13. NORTH 11TH AVENUE INTERSECTION ALTERNATIVES Oak Street Improvements Pre-Design Report 34 FIGURE 14. NORTH 7TH AVENUE INTERSECTION ALTERNATIVE Oak Street Improvements Pre-Design Report 35 FIGURE 15. NORTH ROUSE AVENUE INTERSECTION ALTERNATIVE Oak Street Improvements Pre-Design Report 36 TABLE 11. INTERSECTION ALTERNATIVE SUMMARY – SIGNALS VS. ROUNDABOUTS Pro Con Pro Con Pro Con Pro Con Pro Con Pro Con Pro Con Pro Con Pro Con Pro Con Safety Performance Higher driver familiarity. Anticipated reduction in stop-controlled intersection-related crashes. Higher speed collisions are more likely w/ signal than roundabout, right- angle collisions still a possibility. Low speeds, reduction in conflict points compared to signal. Anticipated reduction in intersection-related crashes and crash severity compared to signal alternative. Lower driver familiarity. Higher driver familiarity. Anticipated reduction in stop-controlled intersection-related crashes. Higher speed collisions are more likely w/ signal than roundabout, right- angle collisions still a possibility. Low speeds, reduction in conflict points compared to signal. Anticipated reduction in intersection-related crashes and crash severity compared to signal alternative. Lower driver familiarity. Higher driver familiarity. Anticipated reduction in stop-controlled intersection-related crashes. Higher speed collisions are more likely w/ signal than roundabout, right- angle collisions still a possibility. Low speeds, reduction in conflict points compared to signal. Anticipated reduction in intersection-related crashes and crash severity compared to signal alternative. Lower driver familiarity. Higher driver familiarity. Anticipated reduction in stop-controlled intersection-related crashes. Higher speed collisions are more likely w/ signal than roundabout, right- angle collisions still a possibility. Low speeds, reduction in conflict points compared to signal. Anticipated reduction in intersection-related crashes and crash severity compared to signal alternative. Lower driver familiarity. Higher driver familiarity. Anticipated reduction in stop-controlled intersection-related crashes. Higher speed collisions are more likely w/ signal than roundabout, right- angle collisions still a possibility. Low speeds, reduction in conflict points compared to signal. Anticipated reduction in intersection-related crashes and crash severity compared to signal alternative. High-speed facility and drivers are not familiar or anticipating change in traffic control. Capacity & Operations Acceptable LOS and delay for future traffic volume scenario. Higher delay during off-peak periods. No left-turn bays due to power poles. Slightly better LOS and delay values than signal alternative. Continuous flow = little to no delay during off-peak periods. Expandable design for future capacity. Acceptable LOS and delay for future traffic volume scenario. Higher delay during off-peak periods. No left-turn bays due to power poles. Better LOS and delay values than signal alternative. Continuous flow = little to no delay during off-peak periods. Expandable design for future capacity. Acceptable LOS and delay for future traffic volume scenario. Higher delay during off-peak periods. No WB left-turn bay due to relocated power pole. Acceptable LOS and delay values for future traffic volume scenario. Continuous flow = little to no delay during off-peak periods. Expandable design for future capacity. Westbound left-turn lane would increase capacity. Higher delay during off-peak periods. Location of power pole in west median would restrict the design of an eastbound left-turn lane. Slightly better LOS and delay values than signal alternative. Continuous flow = little to no delay during off-peak periods. Expandable design for future capacity. Acceptable LOS and delay for future traffic volume scenario. Higher delay during off-peak periods. Slightly better LOS and delay values than signal alternative. Continuous flow = little to no delay during off-peak periods. Expandable design for future capacity. Addition of raised median and removal of turn-lane on Oak Street. Aesthetics Opportunity for landscaping in medians on all four approaches. Larger pavement area, signal equipment less aesthetically pleasing. Views already impeded by power poles further impeded by signal equipment. Additional opportunity for landscaping in central island and stamped concrete on truck apron allow for better overall aesthetic. Opportunity for landscaping in medians on two approaches. Larger pavement area, signal equipment less aesthetically pleasing. Views already impeded by power poles further impeded by signal equipment. Additional opportunity for landscaping in central island and stamped concrete on truck apron allow for better overall aesthetic. Larger footprint overall. Opportunity for landscaping in medians on all four approaches. Relocation of power pole may provide better aesthetic. Larger pavement area at center of intersection, signal equipment less aesthetically pleasing. Would require more piping of canal. Better opportunity to preserve open canal because no left-turn bays NB/SB. Landscaping options in medians and central island, stamped concrete. Alternative would perpetuate power pole in middle of central island. Larger footprint overall. Opportunity for landscaping in medians on three approaches. Larger pavement area, signal equipment less aesthetically pleasing. Views already impeded by power poles further impeded by signal equipment. Additional opportunity for landscaping in central island and stamped concrete on truck apron allow for better overall aesthetic. Alternative would perpetuate power pole in west median. Larger footprint overall. No major changes to roadway cross-section on Oak Street, no added oppportunity for landscaping. Larger pavement area at center of intersection, signal equipment less aesthetically pleasing, impedes view. Additional opportunity for landscaping in central island and stamped concrete on truck apron allow for better overall aesthetic. Larger footprint overall. Initial Construction Cost Because only the SW quadrant of the intersection exists today, overall construction cost is comparable to roundabout Because only the SW quadrant of the intersection exists today, overall construction cost is comparable to signal. Because only the south half of the intersection exists today, overall construction cost is comparable, but signal is less expensive. Because only the south half of the intersection exists today, overall construction cost is comparable. More expensive than signal. Because only the north half of the intersection exists today, overall construction cost is comparable, but signal is less expensive. Cost associated with relocation of existing power pole at center of intersection, but signal still less expensive. Because only the north half of the intersection exists today, overall construction cost is comparable, but signal is less expensive. More expensive than signal. Allows for reuse of existing lane configurations. Cost limited to signal hardware. Would require complete reconstruction of existing intersection. Allows for reuse of existing lane configurations. Cost limited to signal hardware. Would require complete reconstruction of existing intersection. Long-term Cost of Operations & Maintenance Minimal landscaping maintenance would be required. Signal equipment depreciates in value and will need continued maintenance, power and signal timing updates. Hawk signals would require less maintenance than signal alternative. Required maintenance would be needed to ensure landscaping is kept up. Snow removal more challenging. Minimal landscaping maintenance would be required. Signal equipment depreciates in value and will need continued maintenance, power and signal timing updates. Hawk signals would require less maintenance than signal alternative. Required maintenance would be needed to ensure landscaping is kept up. Snow removal more challenging . Minimal landscaping maintenance would be required. Signal equipment depreciates in value and will need continued maintenance, power and signal timing updates. Hawk signals would require less maintenance than signal alternative. Required maintenance would be needed to ensure landscaping is kept up. Snow removal more challenging . Minimal landscaping maintenance would be required. Signal equipment depreciates in value and will need continued maintenance, power and signal timing updates. Hawk signals would require less maintenance than signal alternative. Required maintenance would be needed to ensure landscaping is kept up. Snow removal more challenging . Minimal landscaping maintenance would be required. Signal equipment depreciates in value and will need continued maintenance, power and signal timing updates. Hawk signals would require less maintenance than signal alternative. Required maintenance would be needed to ensure landscaping is kept up. Snow removal more challenging. Right-of-Way & Utility Impacts Slightly smaller footprint, less R/W needed on corners of intersection. Existing power poles don't allow adequate space for left turn bays. No conflict with existing power poles. Slightly larger footprint will require more R/W on corners (10-20 ft beyond signal alternatve). Smaller footprint, less R/W needed on corners of intersection. Existing power poles don't allow adequate space for left turn bays. No power pole will need to be relocated. No conflict with existing power poles, center of roundabout can be shifted to avoid power pole near center of intersection. Much larger footprint in this location. 30 to 40 additional feet of R/W needed on each corner. Smaller footprint, less R/W needed on corners of intersection. Relocation of power pole in center of the intersection would be required, resulting in three new poles. Existing power pole in center of intersection can remain in place. Larger footprint requires slightly more R/W. 20 to 30 ft of R/W needed on each corner. Existing power poles can remain in place. Existing power pole on west approach doesn't allow for left- turn bay. Existing power poles can remain in place. Much larger footprint in this location. 20 to 30 additional feet fo R/W needed on each corner. Much greater impact to existing homes on south side. Existing utilies can remain in place. Oak Street right-of- way can remain as existing. Additional right-of- way needed on north and south approaches to change roadway geometry. Multi-Modal Signalized intersection design would include crosswalks and bike lanes on all four approaches with pedestrian walk indication from signal. Longer pedestrian crossing distances without refuge. Hawk signals protect pedestrian crossings. Bicyclists could navigate the roundabout in the traffic lanes or use the escape ramp to access the path/sidewalk. Multi-lane roundabouts generally considered less bike/ped friendly. Signalized intersection design would include crosswalks and bike lanes on all four approaches with pedestrian walk indication from signal. Longer pedestrian crossing distances without refuge. Hawk signals protect pedestrian crossings. Bicyclists could navigate the roundabout in the traffic lanes or use the escape ramp to access the path/sidewalk. Multi-lane roundabouts generally considered less bike/ped friendly. Signalized intersection design would include crosswalks and bike lanes on all four approaches with pedestrian walk indication from signal. Longer pedestrian crossing distances without refuge. Hawk signals protect pedestrian crossings. Bicyclists could navigate the roundabout in the traffic lanes or use the escape ramp to access the path/sidewalk. Multi-lane roundabouts generally considered less bike/ped friendly. Signalized intersection design would include crosswalks and bike lanes on all four approaches with pedestrian walk indication from signal. Longer pedestrian crossing distances without refuge. Hawk signals protect pedestrian crossings. Bicyclists could navigate the roundabout in the traffic lanes or use the escape ramp to access the path/sidewalk. Multi-lane roundabouts generally considered less bike/ped friendly. Signalized intersection design would include crosswalks and bike lanes on all four approaches with pedestrian walk indication from signal. Longer pedestrian crossing distances without refuge. Hawk signals protect pedestrian crossings. Bicyclists could navigate the roundabout in the traffic lanes or use the escape ramp to access the path/sidewalk. Multi-lane roundabouts generally considered less bike/ped friendly. Recommendation Roundabout Signal Signal Signal Signal Roundabout Alternative Signal Alternative Roundabout Alternative Criteria Ferguson Avenue & Oak Street Davis Lane & Oak Street 27th Avenue & Oak Street 11th Avenue & Oak StreetCottonwood Road & Oak Street Signal Alternative Roundabout Alternative Roundabout AlternativeSignal Alternative Signal Alternative Roundabout Alternative Signal Alternative Oak Street Improvements Pre-Design Report 37 For the roundabout alternatives, Pedestrian Hybrid Beacons (also referred to as High Intensity Activated crossWalk or HAWK signals) are recommended at the pedestrian crossings with multiple entering lanes, which is consistent with recommendations from the US Access Board and the draft Public Rights-of-Way Accessibility Guidelines (PROWAG) requirements. The pieces of sausage median also provide an interim refuge area between the multiple lanes for pedestrians. It was initially thought that roundabouts would be more feasible on the west end where the existing intersections are only partially constructed and they can also be aligned better to avoid the existing power poles. However, the additional right-of- way needed for the roundabout alternatives will be a challenge to obtain in many locations. Roundabouts are less feasible for the intersections on the east end where a complete reconstruction would be required. Both alternatives would operate well from a capacity standpoint in all locations, but roundabouts would provide slightly more reserve capacity for future growth beyond the 20-year design life because of the option to convert them to two-lane configurations at a relatively low cost. When all of these factors are considered, as shown in Table 11, the roundabout appears to be the preferred alternative at Cottonwood Road, while the signal appears to be the preferred alternative at the other four major intersections. This information will be presented to the Bozeman City Commission and they will make the final decision on which alternative is selected for each location. Bike & Pedestrian Facilities As discussed previously, the recommended typical sections for full build-out of the Oak Street corridor include striped bike lanes and 10-foot wide multi-use paths or 5 to 6-wide sidewalks, varying by segment and by existing conditions. Once all the missing segments are filled in, these improvements should provide for a safe and continuous route for bikes and pedestrians along the Oak Street corridor. Safe access for pedestrians and bicyclists across the Oak Street corridor is also an important consideration. Pedestrian crossings have been considered in all of the intersection concepts for both signalized and roundabout alternatives. The signalized alternatives include striped crosswalks and pedestrian signal indications for all intersection approaches. Minimum green times will be set according to pedestrian clearance intervals. Bicycle accommodations at several of the existing signalized intersections have been improved by striping a bicycle lane between the outside through lane and dedicated right-turn lane so that bicyclists wishing to travel through the intersection can get to the inside of right-turning vehicles in advance of the intersection. For the roundabout alternatives, access for pedestrians will be provided by striped crosswalks and Pedestrian Hybrid Beacons (HAWK Signals) for all multi-lane approaches to the roundabouts. Bicycles will be given the option to either circulate with vehicle traffic or use the escape ramp to merge onto the sidewalk/path and negotiate the roundabout with pedestrians using the HAWK Signals. Multi-lane roundabouts are generally considered less friendly to bikes and pedestrians, but the splitter islands are wide enough to provide pedestrian refuge so they can focus on crossing one direction of travel at a time. The HAWK Signals also greatly improve the safety of crossings for pedestrians with disabilities. Enhancements to the existing mid-block crossing on the east side of Ferguson should be considered in the final design of Oak Street from Ferguson Avenue to Davis Lane. At a minimum, the existing signage and striping should be replicated with pedestrian refuge in the newly constructed center median. Rectangular Rapid Flash Beacons or HAWK Signals could also be considered as additional enhancements in this location. Also included as part of the scope of the Oak Street Improvements project were concept alignments for the proposed Front Street Connector Pathway. After the completion of much background work by the Gallatin Valley Land Trust (GVLT) and the City Parks Department, the Front Street Pathway project was recently selected by the City Commission for funding through the City of Bozeman Trails, Open Space and Parks (TOP) Program. The path will provide a key connection between the existing pathway along the south side of Oak Street and the existing Story Mill Spur Trail. Sanderson Stewart worked with GVLT and the Parks Department to develop the concept alignment illustrated in Figure 16 on the following page. Oak Street Improvements Pre-Design Report 38 FIGURE 16. FRONT STREET CONNECTOR PATHWAY CONCEPT ALIGNMENT Response to RFP for the 2014 Sidewalks II to RFP for the 2014 Sidewalks II – Oak Street Improvements Pre-Design Report 39 Lighting Marvin & Associates conducted an analysis of additional lighting needs for the recommended Oak Street improvements. One LED light that would provide the necessary illuminance level was selected to determine the relative light spacing that would be required along the planned corridor. The AutoBahn LED by American Electric utilizes 60 LEDs which provides approximately 16,400 Lumens. The Visual Roadway Lighting software was used to determine optimum spacing. ANSI-IES guidelines indicate that the average illumination levels should be 0.9 HFC with a maximum uniformity ratio of 3:1. Oak Street is a principal arterial street and the assumed roadside environment is residential along most of its length. After a number of computational iterations, it was discovered that a Type II light distribution would result in the optimum spacing. There are three typical sections within the corridor, which resulted in three different spacing lengths as noted below (and as shown in Appendix E):  Segment 1 – 92-ft Street with 28-ft Median – 142 ft Staggered  Segment 2 – 75-ft Street with No Median – 170 ft Staggered  Segment 3 – 51-ft Street with No Median – 208 ft Staggered Light locations were fit along the corridor using the above noted spacing and lights that would already be covered by signalized intersection lights were eliminated. Street light location analysis indicated that there would be approximately 103 new street lights along the entire corridor. If some of the intersections are ultimately designed as roundabouts, there would probably be an additional 8 lights per roundabout intersection. Final design will determine whether a lesser illuminance level, a higher uniformity ratio, other lamp types, higher luminaire mounting heights, or a combination thereof would allow longer light spacing and fewer lights. Stormwater In general, runoff generated north of Oak Street flows north and will not enter the right-of-way. Runoff generated to the south of Oak Street will need to be considered during the design process as it flows towards the right-of-way. Curb and gutter are planned throughout the new corridor. New on-grade and sag inlets should be utilized along the areas of the corridor that are to be newly constructed or widened. New or existing detention ponds located in or near the right-of-way will collect and store water conveyed from the inlets through new storm drain pipes. Culverts may also be used to help control and convey any water that would otherwise be trapped in the right-of-way due to the construction of the Oak Street improvements. There is also potential to integrate new stormwater features, including treatment facilities, into the existing storm drain systems in the area of Oak Street, though this is not possible in all situations. The Stormwater Exhibits provided in Appendix F show the areas of the project that will be newly constructed and/or widened. Potential locations of new detention ponds are also shown. The City will need to acquire easements or right-of-way for new or expanding existing detention ponds. These areas could be incorporated into park areas for future developments along Oak Street. North Rouse Avenue to North 7th Avenue. The County Fairgrounds, located on the south side of Oak Street between North Rouse Avenue and North 7th Avenue, currently have little to no stormwater features, resulting in runoff and debris collecting near the south boundary of the Oak Street right-of-way. The improvements made in this project should consider the master plan that has already been approved for the Fairgrounds and potentially work in connection with them, specifically for future detention ponds and conveyance pipes to outfall structures. An overflow outfall to the north through the Westlake property could potentially be used. This would be dependent upon acquiring an easement from Westlake and approval by MDT of the additional flow to their right-of-way after the completion of a detailed hydraulic study. Oak Street will be widened Response to RFP for the 2014 Sidewalks II to RFP for the 2014 Sidewalks II – Oak Street Improvements Pre-Design Report 40 from North Rouse Avenue to near North 5th Avenue. Most of this area will also have curb and gutter added, as none currently exists. Inlets and piping will be used to catch runoff that would otherwise be trapped in the roadway with these improvements. The vacant lot to the east of North 5th Avenue will require a detention pond in the future to prevent additional runoff to Oak Street. North 7th Avenue to North 19th Avenue. Curb and gutter will be added along the south side of Oak Street in the areas where there is currently none. These areas are North 11th Avenue to North 12th Avenue and North 15th Avenue to North 19th Avenue. Inlets and piping will be needed to capture runoff that currently drains into the ditch on the south side of Oak Street. Where an additional lane will be added between North 15th Avenue to North 19th Avenue, it is likely that a detention pond with treatment will be required prior to discharging into Farmer’s Canal. North 19th Avenue to Davis Lane. Oak Street is to be widened between North 19th Avenue and North 27th Avenue. Current inlet locations will need to be adjusted to match the new curb line. Additional inlets and piping will be required to convey the design storm. Existing detention ponds will be utilized and upsized where feasible to account for the increase in impervious surface. A new detention pond with treatment may be required north of the intersection of Oak Street and North 25th Avenue in Rose Park. Davis Lane to Cottonwood Road. The area between Ferguson Avenue and Cottonwood Road is currently undeveloped and will be fully constructed with the planned five lane street improvements. The new stormwater system in this area will include curb and gutter, inlets, piping, detention areas and outfall structures to open channels that pass through the right-of-way. There is potential to utilize or expand the existing detention and outfall structures that exist near both Ferguson Avenue and Cottonwood Road. Refer to the attached Stormwater Exhibits in Appendix F showing existing and proposed detention areas. Wetland Delineation A wetland delineation and waters of the U.S. evaluation was conducted by Sanderson Stewart for the proposed improvements to Oak Street. The assessment was performed as part of the initial site evaluation at the request of the City of Bozeman. Site visits conducted in September of 2015 identified ten drainageways that cross the Oak Street corridor within the scope of work of this project. At each crossing, wetlands were delineated and an evaluation of likely connections to waters of the US was conducted. It should be noted that the area of the proposed Oak Street alignment between Ferguson Avenue and Flanders Mill Road was not within the scope of work because that parcel is being evaluated independently as part of a private development project. The scope of the wetland evaluation included assessment of ten drainageways that cross Oak Street within the proposed project area. The drainageways include stormwater drainage ditches, irrigation ditches and streams, or a combination of those Response to RFP for the 2014 Sidewalks II to RFP for the 2014 Sidewalks II – Oak Street Improvements Pre-Design Report 41 features. Regional drainage in the vicinity of Oak Street is to the north to the East Gallatin River, with local small-scale variations. Oak Street is oriented perpendicular to regional slope, so the flows within each drainageway are approximately right angles to the street. There is a strong influence of land use on the vegetation, and therefore, Cowardin wetland classification. Several of the wetlands associated with a single source of hydrology have distinctly different vegetation across different property boundaries and on opposite sides of the street. Table 12 below identifies the drainageway, wetland, Cowardin classification of any wetland, area of wetland delineated, and the anticipated jurisdictional status. TABLE 12. WETLAND SUMMARY Drainageway Wetland Wetland Classification (Cowardin) Area (acres) Anticipated Jurisdictional Status 1 Ephemeral stormwater ditch Not likely WOUS 2 Mandeville Creek 2 N: emergent S: scrub-shrub 0.027 Likely 3 Ephemeral stormwater ditch; Farmers Canal 3 Scrub-shrub 0.019 Not likely 4 East Fork of East Catron Creek 4 Emergent 0.028 Likely 5 Un-named tributary to East Catron Creek 5 N: emergent S: scrub-shrub 0.017 Likely Stormwater detention pond 5a Emergent 0.023 Not likely 6 Abandoned channel Cattail Creek 6 Emergent 0.018 Not likely 7 Cattail Creek 7 Scrub-shrub 0.002 Likely Stormwater detention pond 7a Scrub-shrub 0.008 Not likely 8 Section Line Ditch 8 Scrub-shrub 0.011 Likely 9 Tributary of Baxter Creek 9 Emergent 0.046 Likely Stormwater detention pond 9a Emergent 0.057 Likely Stormwater detention pond 9b Emergent 0.107 Not likely 10 Maynard Border Ditch Overflow 10 Emergent 0.016 Likely Notes to table: Drainageway names are primarily based upon City of Bozeman waterways GIS layer labels. N: North side of Oak Street S: South side of Oak Street WOUS: Waters of the U.S. A more detailed discussion of the characteristics of each of the drainageways and associated wetlands are presented in the Wetland Delineation Report in Appendix G. This report also includes representative site photos of drainageways and wetlands, field delineation data sheets and various maps and figures illustrating the wetland areas. The anticipated jurisdictional status of the wetlands is listed in Table 12. Irrigation ditches can be considered connected to waters of the US if the headwaters and return waters are both tied to a water of the US. City stormwater drainage system components may be considered jurisdictional if there is a surface channel connection to waters of the US as of the date of this delineation. At the time of this delineation, the COE is responsible for final decisions on jurisdictional determinations. Any waters or wetlands that are considered waters of the U.S. as defined by Section 404 of the Clean Water Response to RFP for the 2014 Sidewalks II to RFP for the 2014 Sidewalks II – Oak Street Improvements Pre-Design Report    42 Act (Appendix G) fall under the jurisdiction of the COE and may need Section 404 permitting through the COE if impacts (fill) occur. It is important to note that the COE makes the final determination regarding the status of waters of the U.S., jurisdictional wetlands and mitigation requirements. Geotechnical Analysis   Terracon Consultants, Inc. conducted a preliminary pavement design evaluation using anticipated traffic loading associated with the 2035 traffic volume projections and a California Bearing Ratio (CBR) of 3.0 psi. No soil borings or cores of existing asphalt pavement were completed for this pre-design phase of the Oak Street Improvements project. Preliminary pavement section thickness recommendations generally consist of 4 inches of asphalt over 12-17 inches of crushed base course varying by segment and associated traffic loading. Recommended pavement sections will require that the upper six inches of the in- place subgrade soils be scarified in place and compacted to 95% of the maximum dry density. Some of the subgrades will likely require geotextile fabric to be placed between the subgrade and crushed base course. Terracon’s complete report can be found in Appendix H. Opinions of Probable Cost Concept-level cost estimates were prepared for each of the recommended improvements along the Oak Street corridor, including both signal and roundabout alternatives. A summary of these opinions of probable cost is provided in Table 13 and detailed estimates are included in Appendix I.   TABLE 13. OPINION OF PROBABLE COST SUMMARY  Intersection Baseline Cost Design & CA Services (15%) Construction Contingency (15%) Total Cost Oak Street Corridor - Traffic Signal Alternative $13,171,043.61 $1,975,656.54 $1,975,656.54 $17,122,356.69 Oak Street Corridor - Roundabout Alternative $15,410,903.34 $2,311,635.50 $2,311,635.50 $20,034,174.34 Cost Difference $2,239,859.72 $335,978.96 $335,978.96 $2,911,817.64 APPENDIX A: TRAFFIC VOLUME DATA Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 0.98 0.98 0.98 0.98 0 1.00 1.00 1.00 1.00 0 7:45 AM 56 214 59 11 340 12 103 11 0 126 30 61 84 0 175 21 27 6 0 54 695 8:00 AM 47 152 43 3 245 12 73 19 0 104 29 60 62 0 151 17 37 8 0 62 562 8:15 AM 44 145 54 1 244 10 93 14 0 117 29 47 55 0 131 25 43 11 0 79 571 8:30 AM 57 140 51 0 248 17 90 19 1 127 25 56 51 0 132 26 35 12 0 73 580 Grand Total 204 651 207 15 1077 51 359 63 1 474 113 224 252 0 589 89 142 37 0 268 2408 Medium Truck % 2.9 2.2 3.9 0.0 2.6 3.9 4.2 3.2 0.0 4.0 3.5 4.0 1.6 0.0 2.9 6.7 7.0 8.1 0.0 7.1 Heavy Truck % 2.5 0.2 0.5 0.0 0.6 0.0 1.4 0.0 0.0 1.1 0.0 0.9 0.4 0.0 0.5 1.1 1.4 0.0 0.0 1.1 Total Truck % 5.4 2.3 4.3 0.0 3.2 3.9 5.6 3.2 0.0 5.1 3.5 4.9 2.0 0.0 3.4 7.9 8.5 8.1 0.0 8.2 Total % 8.5 27.0 8.6 0.6 44.7 2.1 14.9 2.6 0.0 19.7 4.7 9.3 10.5 0.0 24.5 3.7 5.9 1.5 0.0 11.1 100.0 PHF 0.79 0.79 0.79 0.93 0.93 0.93 0.84 0.84 0.84 0.85 0.85 0.85 0.87 RT TH LT U 204 651 207 15 89RT142TH37LT0UU0LT252TH224RT1131 63 359 51 U LT TH RT Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: 7th Avenue AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound 7th Avenue Northbound Oak Street Eastbound East/West Street: INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & 7th AvenueCounted By:Oak StreetOak Street589City of Bozeman / MDTThursday, March 26, 2015Date Performed: Count Time Period: Oak Street Improvements 7th Avenue Oak Street Oak Street Vehicle Volumes and Adjustments 7th Avenue 1077 In Out 715 7th Avenue 474 InOut 802In409 In268Out482Total Entering 2408Out NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 0.98 0.98 0.98 0.98 0 1.00 1.00 1.00 1.00 0 4:45 PM 59 126 32 6 223 36 191 50 0 277 40 66 61 0 167 51 82 34 0 167 834 5:00 PM 112 175 55 5 347 30 212 51 0 293 37 54 42 0 133 52 80 21 0 153 926 5:15 PM 101 154 46 7 308 42 207 47 0 296 41 68 74 0 183 50 94 47 0 191 978 5:30 PM 79 166 51 8 304 24 155 38 0 217 38 39 55 0 132 44 65 24 0 133 786 Grand Total 351 621 184 26 1182 132 765 186 0 1083 156 227 232 0 615 197 321 126 0 644 3524 Medium Truck % 0.0 1.4 1.1 0.0 0.9 2.3 0.8 0.0 0.0 0.8 0.6 2.6 0.9 0.0 1.5 0.5 1.9 0.0 0.0 1.1 Heavy Truck % 0.0 0.3 1.6 0.0 0.4 0.8 0.1 0.5 0.0 0.3 0.0 0.4 0.4 0.0 0.3 1.0 0.0 0.8 0.0 0.5 Total Truck % 0.0 1.8 2.7 0.0 1.4 3.0 0.9 0.5 0.0 1.1 0.6 3.1 1.3 0.0 1.8 1.5 1.9 0.8 0.0 1.6 Total % 10.0 17.6 5.2 0.7 33.5 3.7 21.7 5.3 0.0 30.7 4.4 6.4 6.6 0.0 17.5 5.6 9.1 3.6 0.0 18.3 100.0 PHF 0.85 0.85 0.85 0.91 0.91 0.91 0.84 0.84 0.84 0.84 0.84 0.84 0.90 RT TH LT U 351 621 184 26 197RT321TH126LT0UU0LT232TH227RT1560 186 765 132 U LT TH RT Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & 7th Avenue North/South Street: 7th Avenue Oak Street Date Performed: Thursday, March 26, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street:Oak StreetOut858Vehicle Volumes and Adjustments 7th Avenue 7th Avenue Oak Street Oak Street Southbound Northbound Eastbound Westbound In615543Out7th Avenue In Out 1182 1220 7th Avenue 644InOak StreetTotal Entering 3524 903 1083 Out In NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.98 0.98 0.98 0.98 0 0.98 0.98 0.98 0.98 0 7:45 AM 2 0 8 0 10 0 0 0 0 0 0 183 0 0 183 3 88 0 0 91 284 8:00 AM 3 0 6 0 9 0 0 0 0 0 0 136 4 0 140 4 82 0 0 86 235 8:15 AM 3 0 5 0 8 0 0 0 0 0 0 146 2 0 148 3 84 0 0 87 243 8:30 AM 1 2 4 0 7 0 0 0 0 0 0 121 5 0 126 3 90 0 0 93 226 Grand Total 9 2 23 0 34 0 0 0 0 0 0 586 11 0 597 13 344 0 0 357 988 Medium Truck % 11.1 0.0 4.3 0.0 5.9 0.0 0.0 0.0 0.0 0.0 0.0 1.9 0.0 0.0 1.8 30.8 5.2 0.0 0.0 6.2 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.0 0.0 0.2 7.7 0.0 0.0 0.0 0.3 Total Truck % 11.1 0.0 4.3 0.0 5.9 0.0 0.0 0.0 0.0 0.0 0.0 2.0 0.0 0.0 2.0 38.5 5.2 0.0 0.0 6.4 Total % 0.9 0.2 2.3 0.0 3.4 0.0 0.0 0.0 0.0 0.0 0.0 59.3 1.1 0.0 60.4 1.3 34.8 0.0 0.0 36.1 100.0 PHF 0.85 0.85 0.85 0.00 0.00 0.00 0.82 0.82 0.82 0.96 0.96 0.96 0.87 RT TH LT U 9 2 23 0 13RT344TH0LT0UU0LT11TH586RT00 0 0 0 U LT TH RT Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: 11th Avenue AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound 11th Avenue Northbound Oak Street Eastbound East/West Street: INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & 11th AvenueCounted By:Oak StreetOak Street597City of Bozeman / MDTWednesday, March 25, 2015Date Performed: Count Time Period: Oak Street Improvements 11th Avenue Oak Street Oak Street Vehicle Volumes and Adjustments 11th Avenue 34 In Out 24 11th Avenue 0 InOut 2In353 In357Out609Total Entering 988Out NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.98 0.98 0.98 0.98 0 0.98 0.98 0.98 0.98 0 4:45 PM 4 1 7 0 12 1 0 0 0 1 0 161 9 0 170 5 153 1 0 159 342 5:00 PM 11 0 3 0 14 3 0 0 0 3 2 149 3 0 154 2 238 0 0 240 411 5:15 PM 3 1 4 0 8 0 0 0 0 0 1 150 3 0 154 1 215 2 0 218 380 5:30 PM 7 0 5 0 12 0 0 0 0 0 1 142 5 0 148 2 191 0 0 193 353 Grand Total 25 2 19 0 46 4 0 0 0 4 4 602 20 0 626 10 797 3 0 810 1486 Medium Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.8 10.0 0.0 2.1 0.0 1.1 0.0 0.0 1.1 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 1.8 10.0 0.0 2.1 0.0 1.1 0.0 0.0 1.1 Total % 1.7 0.1 1.3 0.0 3.1 0.3 0.0 0.0 0.0 0.3 0.3 40.5 1.3 0.0 42.1 0.7 53.6 0.2 0.0 54.5 100.0 PHF 0.82 0.82 0.82 0.33 0.33 0.33 0.92 0.92 0.92 0.84 0.84 0.84 0.90 RT TH LT U 25 2 19 0 10RT797TH3LT0UU0LT20TH602RT40 0 0 4 U LT TH RT Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & 11th Avenue North/South Street: 11th Avenue Oak Street Date Performed: Wednesday, March 25, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street:Oak StreetOut822Vehicle Volumes and Adjustments 11th Avenue 11th Avenue Oak Street Oak Street Southbound Northbound Eastbound Westbound In626625Out11th Avenue In Out 46 30 11th Avenue 810InOak StreetTotal Entering 1486 9 4 Out In NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.98 0.98 0.98 0.98 0 0.98 0.98 0.98 0.98 0 7:45 AM 2 0 0 0 2 11 0 12 0 23 39 187 3 0 229 0 71 8 0 79 333 8:00 AM 2 5 0 0 7 13 0 13 0 26 55 135 2 0 192 1 64 11 0 76 301 8:15 AM 2 1 4 0 7 22 3 15 0 40 30 130 3 0 163 0 70 10 0 80 290 8:30 AM 9 5 4 0 18 11 1 12 0 24 21 109 1 0 131 1 79 5 0 85 258 Grand Total 15 11 8 0 34 57 4 52 0 113 145 561 9 0 715 2 284 34 0 320 1182 Medium Truck % 6.7 0.0 0.0 0.0 2.9 3.5 0.0 1.9 0.0 2.7 2.8 1.2 0.0 0.0 1.5 0.0 5.6 2.9 0.0 5.3 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.0 0.0 0.1 0.0 0.0 0.0 0.0 0.0 Total Truck % 6.7 0.0 0.0 0.0 2.9 3.5 0.0 1.9 0.0 2.7 2.8 1.4 0.0 0.0 1.7 0.0 5.6 2.9 0.0 5.3 Total % 1.3 0.9 0.7 0.0 2.9 4.8 0.3 4.4 0.0 9.6 12.3 47.5 0.8 0.0 60.5 0.2 24.0 2.9 0.0 27.1 100.0 PHF 0.47 0.47 0.47 0.71 0.71 0.71 0.78 0.78 0.78 0.94 0.94 0.94 0.89 RT TH LT U 15 11 8 0 2RT284TH34LT0UU0LT9TH561RT1450 52 4 57 U LT TH RT Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: 15th Avenue AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound 15th Avenue Northbound Oak Street Eastbound East/West Street: INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & 15th AvenueCounted By:Oak StreetOak Street715City of Bozeman / MDTWednesday, March 25, 2015Date Performed: Count Time Period: Oak Street Improvements 15th Avenue Oak Street Oak Street Vehicle Volumes and Adjustments 15th Avenue 34 In Out 15 15th Avenue 113 InOut 190In351 In320Out626Total Entering 1182Out NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.98 0.98 0.98 0.98 0 0.98 0.98 0.98 0.98 0 4:45 PM 4 2 2 0 8 23 3 39 0 65 25 135 3 0 163 1 142 9 0 152 388 5:00 PM 3 4 3 0 10 27 1 63 0 91 22 123 3 0 148 2 227 15 0 244 493 5:15 PM 4 0 2 0 6 22 4 55 0 81 17 134 2 0 153 2 208 10 0 220 460 5:30 PM 0 2 2 0 4 13 3 40 0 56 12 135 0 0 147 0 191 17 0 208 415 Grand Total 11 8 9 0 28 85 11 197 0 293 76 527 8 0 611 5 768 51 0 824 1756 Medium Truck % 0.0 0.0 11.1 0.0 3.6 2.4 0.0 1.0 0.0 1.4 0.0 1.9 0.0 0.0 1.6 20.0 1.2 0.0 0.0 1.2 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.0 0.0 0.2 0.0 0.1 0.0 0.0 0.1 Total Truck % 0.0 0.0 11.1 0.0 3.6 2.4 0.0 1.0 0.0 1.4 0.0 2.1 0.0 0.0 1.8 20.0 1.3 0.0 0.0 1.3 Total % 0.6 0.5 0.5 0.0 1.6 4.8 0.6 11.2 0.0 16.7 4.3 30.0 0.5 0.0 34.8 0.3 43.7 2.9 0.0 46.9 100.0 PHF 0.70 0.70 0.70 0.80 0.80 0.80 0.94 0.94 0.94 0.84 0.84 0.84 0.89 RT TH LT U 11 8 9 0 5RT768TH51LT0UU0LT8TH527RT760 197 11 85 U LT TH RT Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & 15th Avenue North/South Street: 15th Avenue Oak Street Date Performed: Wednesday, March 25, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street:Oak StreetOut976Vehicle Volumes and Adjustments 15th Avenue 15th Avenue Oak Street Oak Street Southbound Northbound Eastbound Westbound In611621Out15th Avenue In Out 28 24 15th Avenue 824InOak StreetTotal Entering 1756 135 293 Out In NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.00 1.00 1.00 1.00 0 0.98 0.98 0.98 0.98 0 7:45 AM 23 236 69 0 328 61 81 15 0 157 5 96 13 0 114 14 41 25 0 80 679 8:00 AM 22 191 58 0 271 39 69 15 0 123 13 81 16 0 110 18 48 27 0 93 597 8:15 AM 14 198 60 0 272 35 106 11 0 152 8 80 14 0 102 19 44 21 0 84 610 8:30 AM 11 125 32 0 168 42 86 16 0 144 14 68 16 0 98 33 41 33 0 107 517 Grand Total 70 750 219 0 1039 177 342 57 0 576 40 325 59 0 424 84 174 106 0 364 2403 Medium Truck % 0.0 1.7 1.4 0.0 1.5 1.7 5.0 8.8 0.0 4.3 0.0 1.5 0.0 0.0 1.2 1.2 5.7 4.7 0.0 4.4 Heavy Truck % 0.0 0.8 0.5 0.0 0.7 1.7 2.0 0.0 0.0 1.7 0.0 0.0 0.0 0.0 0.0 1.2 1.1 0.0 0.0 0.8 Total Truck % 0.0 2.5 1.8 0.0 2.2 3.4 7.0 8.8 0.0 6.1 0.0 1.5 0.0 0.0 1.2 2.4 6.9 4.7 0.0 5.2 Total % 2.9 31.2 9.1 0.0 43.2 7.4 14.2 2.4 0.0 24.0 1.7 13.5 2.5 0.0 17.6 3.5 7.2 4.4 0.0 15.1 100.0 PHF 0.79 0.79 0.79 0.92 0.92 0.92 0.93 0.93 0.93 0.85 0.85 0.85 0.88 RT TH LT U 70 750 219 0 84RT174TH106LT0UU0LT59TH325RT400 57 342 177 U LT TH RTIn301 In364Out721Total Entering 2403Out 19th Avenue 576 InOut 896 19th Avenue 1039 In Out 485 Oak StreetOak Street424City of Bozeman / MDTTuesday, March 24, 2015Date Performed: Count Time Period: Oak Street Improvements 19th Avenue Oak Street Oak Street Vehicle Volumes and Adjustments INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & 19th AvenueCounted By: Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: 19th Avenue AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound 19th Avenue Northbound Oak Street Eastbound East/West Street: NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.00 1.00 1.00 1.00 0 0.98 0.98 0.98 0.98 0 4:45 PM 27 140 52 0 219 63 200 24 0 287 22 71 39 0 132 50 75 56 0 181 819 5:00 PM 28 149 35 0 212 58 198 28 0 284 7 67 56 0 130 50 121 74 0 245 871 5:15 PM 18 166 36 0 220 52 193 27 0 272 10 57 37 0 104 74 127 71 0 272 868 5:30 PM 19 141 26 0 186 49 207 37 0 293 17 54 39 0 110 48 107 42 0 197 786 Grand Total 92 596 149 0 837 222 798 116 0 1136 56 249 171 0 476 222 430 243 0 895 3344 Medium Truck % 1.1 0.8 2.7 0.0 1.2 0.9 1.4 0.0 0.0 1.1 0.0 0.4 1.2 0.0 0.6 0.9 0.2 0.8 0.0 0.6 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.4 0.0 0.0 0.2 0.0 0.0 0.0 0.0 0.0 Total Truck % 1.1 0.8 2.7 0.0 1.2 0.9 1.4 0.0 0.0 1.1 0.0 0.8 1.2 0.0 0.8 0.9 0.2 0.8 0.0 0.6 Total % 2.8 17.8 4.5 0.0 25.0 6.6 23.9 3.5 0.0 34.0 1.7 7.4 5.1 0.0 14.2 6.6 12.9 7.3 0.0 26.8 100.0 PHF 0.95 0.95 0.95 0.97 0.97 0.97 0.90 0.90 0.90 0.82 0.82 0.82 0.96 RT TH LT U 92 596 149 0 222RT430TH243LT0UU0LT171TH249RT560 116 798 222 U LT TH RT 19th Avenue 895InOak StreetTotal Entering 3344 895 1136 Out In 19th Avenue In Out 837 1191 Oak StreetOut638Vehicle Volumes and Adjustments 19th Avenue 19th Avenue Oak Street Oak Street Southbound Northbound Eastbound Westbound In476620OutNorth/South Street: 19th Avenue Oak Street Date Performed: Tuesday, March 24, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street: Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & 19th Avenue NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0 1.00 1.00 1.00 1.00 0 7:45 AM 9 13 3 0 25 12 20 3 0 35 3 106 14 0 123 2 52 2 0 56 239 8:00 AM 9 9 9 0 27 12 11 5 0 28 9 93 11 0 113 7 63 6 0 76 244 8:15 AM 5 15 8 0 28 15 15 5 0 35 11 82 9 0 102 14 53 3 0 70 235 8:30 AM 6 9 3 0 18 12 8 5 0 25 6 77 6 1 90 5 50 4 1 60 193 Grand Total 29 46 23 0 98 51 54 18 0 123 29 358 40 1 428 28 218 15 1 262 911 Medium Truck % 0.0 0.0 0.0 0.0 0.0 2.0 1.9 11.1 0.0 3.3 0.0 1.4 0.0 0.0 1.2 3.6 6.9 6.7 0.0 6.5 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.5 0.0 0.0 0.4 Total Truck % 0.0 0.0 0.0 0.0 0.0 2.0 1.9 11.1 0.0 3.3 0.0 1.4 0.0 0.0 1.2 3.6 7.3 6.7 0.0 6.9 Total % 3.2 5.0 2.5 0.0 10.8 5.6 5.9 2.0 0.0 13.5 3.2 39.3 4.4 0.1 47.0 3.1 23.9 1.6 0.1 28.8 100.0 PHF 0.88 0.88 0.88 0.88 0.88 0.88 0.87 0.87 0.87 0.86 0.86 0.86 0.93 RT TH LT U 29 46 23 0 28RT218TH15LT1UU1LT40TH358RT290 18 54 51 U LT TH RT Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: 27th Avenue AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound 27th Avenue Northbound Oak Street Eastbound East/West Street: INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & 27th AvenueCounted By:Oak StreetOak Street428City of Bozeman / MDTTuesday, March 24, 2015Date Performed: Count Time Period: Oak Street Improvements 27th Avenue Oak Street Oak Street Vehicle Volumes and Adjustments 27th Avenue 98 In Out 122 27th Avenue 123 InOut 90In266 In262Out433Total Entering 911Out NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0 1.00 1.00 1.00 1.00 0 4:45 PM 13 11 9 0 33 10 7 1 0 18 2 68 8 0 78 13 79 14 0 106 235 5:00 PM 19 16 3 0 38 10 8 0 0 18 5 44 3 0 52 15 118 25 0 158 266 5:15 PM 8 14 3 0 25 12 9 1 0 22 7 54 7 0 68 16 122 16 0 154 269 5:30 PM 12 10 0 0 22 6 10 1 0 17 2 71 6 0 79 11 93 24 0 128 246 Grand Total 52 51 15 0 118 38 34 3 0 75 16 237 24 0 277 55 412 79 0 546 1016 Medium Truck % 0.0 0.0 0.0 0.0 0.0 0.0 2.9 0.0 0.0 1.3 0.0 0.4 0.0 0.0 0.4 0.0 0.0 1.3 0.0 0.2 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.4 0.0 0.0 0.4 0.0 0.0 0.0 0.0 0.0 Total Truck % 0.0 0.0 0.0 0.0 0.0 0.0 2.9 0.0 0.0 1.3 0.0 0.8 0.0 0.0 0.7 0.0 0.0 1.3 0.0 0.2 Total % 5.1 5.0 1.5 0.0 11.6 3.7 3.3 0.3 0.0 7.4 1.6 23.3 2.4 0.0 27.3 5.4 40.6 7.8 0.0 53.7 100.0 PHF 0.78 0.78 0.78 0.85 0.85 0.85 0.88 0.88 0.88 0.86 0.86 0.86 0.94 RT TH LT U 52 51 15 0 55RT412TH79LT0UU0LT24TH237RT160 3 34 38 U LT TH RT Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & 27th Avenue North/South Street: 27th Avenue Oak Street Date Performed: Tuesday, March 24, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street:Oak StreetOut467Vehicle Volumes and Adjustments 27th Avenue 27th Avenue Oak Street Oak Street Southbound Northbound Eastbound Westbound In277290Out27th Avenue In Out 118 113 27th Avenue 546InOak StreetTotal Entering 1016 146 75 Out In NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 0.00 0.00 0.00 0.00 1.00 1.00 1.00 1.00 0 1.00 1.00 1.00 1.00 0 7:45 AM 40 0 35 0 75 0 0 0 0 0 0 79 34 0 113 32 38 0 0 70 258 8:00 AM 45 0 44 0 89 0 0 0 0 0 0 66 47 0 113 42 51 0 0 93 295 8:15 AM 37 0 47 0 84 0 0 0 0 0 0 53 23 0 76 23 50 0 0 73 233 8:30 AM 34 0 24 0 58 0 0 0 0 0 0 60 32 0 92 25 33 0 0 58 208 Grand Total 156 0 150 0 306 0 0 0 0 0 0 258 136 0 394 122 172 0 0 294 994 Medium Truck % 3.8 0.0 1.3 0.0 2.6 0.0 0.0 0.0 0.0 0.0 0.0 2.3 5.9 0.0 3.6 5.7 5.2 0.0 0.0 5.4 Heavy Truck % 0.6 0.0 0.0 0.0 0.3 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.7 0.0 0.3 0.0 0.6 0.0 0.0 0.3 Total Truck % 4.5 0.0 1.3 0.0 2.9 0.0 0.0 0.0 0.0 0.0 0.0 2.3 6.6 0.0 3.8 5.7 5.8 0.0 0.0 5.8 Total % 15.7 0.0 15.1 0.0 30.8 0.0 0.0 0.0 0.0 0.0 0.0 26.0 13.7 0.0 39.6 12.3 17.3 0.0 0.0 29.6 100.0 PHF 0.86 0.86 0.86 0.00 0.00 0.00 0.87 0.87 0.87 0.79 0.79 0.79 0.84 RT LT U 156 150 0 122RT172TH0UU0LT136TH258Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: Davis Lane AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound Northbound Oak Street Eastbound East/West Street: INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & Davis LaneCounted By:Oak StreetOak Street394City of Bozeman / MDTTuesday, March 24, 2015Date Performed: Count Time Period: Oak Street Improvements Davis Lane Oak Street Oak Street Vehicle Volumes and Adjustments Davis Lane 306 In Out 258 In328In294Out408Total Entering 994Out NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 1.00 1.00 1.00 1.00 0.00 0.00 0.00 0.00 1.00 1.00 1.00 1.00 0 1.00 1.00 1.00 1.00 0 4:45 PM 43 0 19 0 62 0 0 0 0 0 0 64 34 0 98 23 58 0 0 81 241 5:00 PM 45 0 17 0 62 0 0 0 0 0 0 38 42 0 80 35 84 0 0 119 261 5:15 PM 45 0 19 0 64 0 0 0 0 0 0 47 39 0 86 21 98 0 0 119 269 5:30 PM 45 0 19 0 64 0 0 0 0 0 0 44 47 0 91 18 72 0 0 90 245 Grand Total 178 0 74 0 252 0 0 0 0 0 0 193 162 0 355 97 312 0 0 409 1016 Medium Truck % 0.6 0.0 0.0 0.0 0.4 0.0 0.0 0.0 0.0 0.0 0.0 0.5 3.7 0.0 2.0 0.0 0.3 0.0 0.0 0.2 Heavy Truck % 0.6 0.0 0.0 0.0 0.4 0.0 0.0 0.0 0.0 0.0 0.0 0.5 1.2 0.0 0.8 0.0 0.0 0.0 0.0 0.0 Total Truck % 1.1 0.0 0.0 0.0 0.8 0.0 0.0 0.0 0.0 0.0 0.0 1.0 4.9 0.0 2.8 0.0 0.3 0.0 0.0 0.2 Total % 17.5 0.0 7.3 0.0 24.8 0.0 0.0 0.0 0.0 0.0 0.0 19.0 15.9 0.0 34.9 9.5 30.7 0.0 0.0 40.3 100.0 PHF 0.98 0.98 0.98 0.00 0.00 0.00 0.91 0.91 0.91 0.86 0.86 0.86 0.94 RT LT U 178 74 0 97RT312TH0UU0LT162TH193Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & Davis Lane North/South Street: Davis Lane Oak Street Date Performed: Tuesday, March 24, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street:Oak StreetOut490Vehicle Volumes and Adjustments Davis Lane Oak Street Oak Street Southbound Northbound Eastbound Westbound In355267OutDavis Lane In Out 252 259 409InOak StreetTotal Entering 1016 NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 0.00 0.00 0.00 0.00 1.00 1.00 1.00 1.00 0.00 0.00 0.00 0.00 0 1.00 1.00 1.00 1.00 0 7:45 AM 0 0 0 0 0 67 0 0 0 67 0 0 0 0 0 0 0 77 0 77 144 8:00 AM 0 0 0 0 0 64 0 0 0 64 0 0 0 0 0 0 0 61 0 61 125 8:15 AM 0 0 0 0 0 65 0 0 0 65 0 0 0 0 0 0 0 68 0 68 133 8:30 AM 0 0 0 0 0 78 0 0 0 78 0 0 0 0 0 0 0 64 0 64 142 Grand Total 0 0 0 0 0 274 0 0 0 274 0 0 0 0 0 0 0 270 0 270 544 Medium Truck % 0.0 0.0 0.0 0.0 0.0 1.8 0.0 0.0 0.0 1.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 2.6 0.0 2.6 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.7 0.0 0.0 0.0 0.7 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.7 0.0 0.7 Total Truck % 0.0 0.0 0.0 0.0 0.0 2.6 0.0 0.0 0.0 2.6 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.3 0.0 3.3 Total % 0.0 0.0 0.0 0.0 0.0 50.4 0.0 0.0 0.0 50.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 49.6 0.0 49.6 100.0 PHF 0.00 0.00 0.00 0.88 0.88 0.88 0.00 0.00 0.00 0.88 0.88 0.88 0.94 270LT0U0 274 U RT Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: Ferguson Avenue AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound Ferguson Avenue Northbound Eastbound East/West Street: INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & Ferguson AvenueCounted By:Oak StreetCity of Bozeman / MDTThursday, March 26, 2015Date Performed: Count Time Period: Oak Street Improvements Oak Street Oak Street Vehicle Volumes and Adjustments Ferguson Avenue 274 InOut 270 In270Out274Total Entering 544 NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 0.00 0.00 0.00 0.00 1.00 1.00 1.00 1.00 0.00 0.00 0.00 0.00 0 1.00 1.00 1.00 1.00 0 4:45 PM 0 0 0 0 0 73 0 0 0 73 0 0 0 0 0 0 0 64 0 64 137 5:00 PM 0 0 0 0 0 72 0 0 0 72 0 0 0 0 0 0 0 89 0 89 161 5:15 PM 0 0 0 0 0 71 0 0 0 71 0 0 0 0 0 0 0 98 0 98 169 5:30 PM 0 0 0 0 0 68 0 0 0 68 0 0 0 0 0 0 0 85 0 85 153 Grand Total 0 0 0 0 0 284 0 0 0 284 0 0 0 0 0 0 0 336 0 336 620 Medium Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 1.4 0.0 0.0 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.6 Total Truck % 0.0 0.0 0.0 0.0 0.0 1.4 0.0 0.0 0.0 1.4 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.6 0.0 0.6 Total % 0.0 0.0 0.0 0.0 0.0 45.8 0.0 0.0 0.0 45.8 0.0 0.0 0.0 0.0 0.0 0.0 0.0 54.2 0.0 54.2 100.0 PHF 0.00 0.00 0.00 0.97 0.97 0.97 0.00 0.00 0.00 0.86 0.86 0.86 0.92 336LT0U0 284 U RT Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & Ferguson Avenue North/South Street: Ferguson Avenue Oak Street Date Performed: Thursday, March 26, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street: Vehicle Volumes and Adjustments Ferguson Avenue Oak Street Southbound Northbound Eastbound Westbound 284OutFerguson Avenue 336InOak StreetTotal Entering 620 336 284 Out In NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 1.00 1.00 1.00 1.00 0 1.00 1.00 1.00 1.00 0 7:45 AM 26 76 0 0 102 0 73 23 0 96 56 4 42 0 102 0 0 1 0 1 301 8:00 AM 24 78 0 0 102 0 70 30 0 100 52 0 24 0 76 0 0 0 0 0 278 8:15 AM 25 95 0 0 120 0 83 35 0 118 42 0 35 0 77 0 0 0 0 0 315 8:30 AM 19 68 0 0 87 0 89 31 0 120 44 0 38 0 82 0 1 1 0 2 291 Grand Total 94 317 0 0 411 0 315 119 0 434 194 4 139 0 337 0 1 2 0 3 1185 Medium Truck % 3.2 3.8 0.0 0.0 3.6 0.0 3.2 6.7 0.0 4.1 2.6 0.0 2.2 0.0 2.4 0.0 0.0 0.0 0.0 0.0 Heavy Truck % 2.1 0.6 0.0 0.0 1.0 0.0 0.0 3.4 0.0 0.9 1.0 0.0 0.0 0.0 0.6 0.0 0.0 0.0 0.0 0.0 Total Truck % 5.3 4.4 0.0 0.0 4.6 0.0 3.2 10.1 0.0 5.1 3.6 0.0 2.2 0.0 3.0 0.0 0.0 0.0 0.0 0.0 Total % 7.9 26.8 0.0 0.0 34.7 0.0 26.6 10.0 0.0 36.6 16.4 0.3 11.7 0.0 28.4 0.0 0.1 0.2 0.0 0.3 100.0 PHF 0.86 0.86 0.86 0.90 0.90 0.90 0.83 0.83 0.83 0.38 0.38 0.38 0.94 RT TH LT U 94 317 0 0 0RT1TH2LT0UU0LT139TH4RT1940 119 315 0 U LT TH RT Westbound Agency/Company: T. Mosdal Sanderson Stewart North/South Street: Rouse Avenue AM Peak Hour (7:45 - 8:45 AM) 15022Project Number: Southbound Rouse Avenue Northbound Oak Street Eastbound East/West Street: INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Oak Street & Rouse AvenueCounted By:Oak StreetBirch Street337City of Bozeman / MDTThursday, March 26, 2015Date Performed: Count Time Period: Oak Street Improvements Rouse Avenue Birch Street Oak Street/Birch Street Vehicle Volumes and Adjustments Rouse Avenue 411 In Out 454 Rouse Avenue 434 InOut 513In214 In3Out4Total Entering 1185Out NNNNN Intersection: Jurisdiction: Project Description: Int. Start Time Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Right Thru Left U-turn Total Total Factor 0.98 0.98 0.98 0.98 0.98 0.98 0.98 0.98 1.00 1.00 1.00 1.00 0 1.00 1.00 1.00 1.00 0 4:45 PM 45 109 0 0 154 0 71 52 0 123 48 0 28 0 76 1 0 0 0 1 354 5:00 PM 58 111 0 0 169 0 106 72 0 178 40 0 31 0 71 0 0 0 0 0 418 5:15 PM 37 97 0 0 134 0 93 45 0 138 42 0 37 0 79 0 0 0 0 0 351 5:30 PM 31 101 1 0 133 0 71 49 0 120 29 0 21 0 50 0 0 0 0 0 303 Grand Total 171 418 1 0 590 0 341 218 0 559 159 0 117 0 276 1 0 0 0 1 1426 Medium Truck % 0.0 1.2 0.0 0.0 0.8 0.0 1.2 0.5 0.0 0.9 3.1 0.0 0.9 0.0 2.2 0.0 0.0 0.0 0.0 0.0 Heavy Truck % 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 3.1 0.0 0.9 0.0 2.2 0.0 0.0 0.0 0.0 0.0 Total Truck % 0.0 1.2 0.0 0.0 0.8 0.0 1.2 0.5 0.0 0.9 6.3 0.0 1.7 0.0 4.3 0.0 0.0 0.0 0.0 0.0 Total % 12.0 29.3 0.1 0.0 41.4 0.0 23.9 15.3 0.0 39.2 11.2 0.0 8.2 0.0 19.4 0.1 0.0 0.0 0.0 0.1 100.0 PHF 0.87 0.87 0.87 0.79 0.79 0.79 0.87 0.87 0.87 0.25 0.25 0.25 0.85 RT TH LT U 171 418 1 0 1RT0TH0LT0UU0LT117TH0RT1590 218 341 0 U LT TH RT Agency/Company: Sanderson Stewart INTERSECTION TURNING MOVEMENT COUNT SUMMARY General Information Counted By: T. Mosdal Oak Street & Rouse Avenue North/South Street: Rouse Avenue Oak Street/Birch Street Date Performed: Thursday, March 26, 2015 City of Bozeman / MDT Count Time Period: PM Peak Hour (4:45 - 5:45 PM) Project Number: 15022 Oak Street Improvements East/West Street:Oak StreetOut389Vehicle Volumes and Adjustments Rouse Avenue Rouse Avenue Oak Street Birch Street Southbound Northbound Eastbound Westbound In2761OutRouse Avenue In Out 590 459 Rouse Avenue 1InBirch StreetTotal Entering 1426 577 559 Out In NNNNN APPENDIX B: EXISTING CAPACITY ANALYSIS Queues 1: 19th Avenue & Oak Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Lane Group EBL EBT WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 63 392 125 205 99 62 372 192 277 949 89 v/c Ratio 0.13 0.76 0.40 0.20 0.11 0.28 0.39 0.27 0.53 0.72 0.10 Control Delay 19.0 46.6 22.6 29.0 3.0 19.5 33.5 5.2 21.2 33.7 1.6 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 19.0 46.6 22.6 29.0 3.0 19.5 33.5 5.2 21.2 33.7 1.6 Queue Length 50th (ft) 24 243 50 54 0 22 108 9 112 298 0 Queue Length 95th (ft) 53 #423 88 85 22 48 166 53 154 338 7 Internal Link Dist (ft) 1120 1040 615 420 Turn Bay Length (ft) 200 250 250 425 425 285 285 Base Capacity (vph) 638 517 555 1263 923 535 1421 1023 563 1311 1045 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.10 0.76 0.23 0.16 0.11 0.12 0.26 0.19 0.49 0.72 0.09 Intersection Summary # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 2: 7th Avenue & Oak Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 2 Lane Group EBL EBT EBR WBL WBT NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 300 267 135 44 272 69 386 55 281 824 258 v/c Ratio 0.60 0.40 0.21 0.12 0.75 0.24 0.45 0.13 0.55 0.67 0.27 Control Delay 24.3 28.5 5.7 18.7 49.0 18.7 34.9 5.6 21.7 32.8 4.6 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 24.3 28.5 5.7 18.7 49.0 18.7 34.9 5.6 21.7 32.8 4.6 Queue Length 50th (ft) 116 129 0 14 149 24 111 0 110 243 19 Queue Length 95th (ft) 212 232 36 40 262 56 184 23 172 315 50 Internal Link Dist (ft) 1263 2871 420 420 Turn Bay Length (ft) 175 300 175 175 125 125 Base Capacity (vph) 525 705 679 588 608 492 1587 742 567 1649 1014 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.57 0.38 0.20 0.07 0.45 0.14 0.24 0.07 0.50 0.50 0.25 Intersection Summary Queues 16: Rouse Avenue & Oak Street/Birch Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 4 Lane Group EBT EBR WBT NBL NBT SBT SBR Lane Group Flow (vph) 172 234 8 132 350 369 109 v/c Ratio 0.67 0.32 0.03 0.22 0.28 0.40 0.14 Control Delay 43.7 3.5 26.3 6.1 6.6 15.8 6.4 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 43.7 3.5 26.3 6.1 6.6 15.8 6.4 Queue Length 50th (ft) 80 0 3 19 60 109 9 Queue Length 95th (ft) 137 30 6 49 127 210 40 Internal Link Dist (ft) 839 303 425 421 Turn Bay Length (ft) 225 240 100 Base Capacity (vph) 590 987 700 786 1606 913 788 Starvation Cap Reductn 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 Reduced v/c Ratio 0.29 0.24 0.01 0.17 0.22 0.40 0.14 Intersection Summary Queues 20: 15th Avenue & Oak Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Lane Group EBL EBT WBL WBT NBL NBT SBL SBT Lane Group Flow (vph) 12 905 36 304 73 86 17 55 v/c Ratio 0.02 0.46 0.11 0.16 0.21 0.19 0.05 0.12 Control Delay 5.8 7.1 7.1 5.9 14.5 5.9 13.0 8.7 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 5.8 7.1 7.1 5.9 14.5 5.9 13.0 8.7 Queue Length 50th (ft) 1 54 4 15 11 1 2 3 Queue Length 95th (ft) 6 85 16 35 31 16 7 9 Internal Link Dist (ft) 230 1310 357 332 Turn Bay Length (ft) 125 125 125 125 Base Capacity (vph) 1041 3348 541 3315 1142 1335 1133 1413 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.01 0.27 0.07 0.09 0.06 0.06 0.02 0.04 Intersection Summary HCM 2010 Signalized Intersection Summary 1: 19th Avenue & Oak Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 59 325 40 106 174 84 57 342 177 219 750 70 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 0.98 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1867 1900 1810 1776 1863 1743 1776 1845 1863 1845 1900 Adj Flow Rate, veh/h 63 349 43 125 205 99 62 372 192 277 949 89 Adj No. of Lanes 1 1 0 1 2 1 1 2 1 1 2 1 Peak Hour Factor 0.93 0.93 0.93 0.85 0.85 0.85 0.92 0.92 0.92 0.79 0.79 0.79 Percent Heavy Veh, % 0 2 2 5 7 2 9 7 3 2 3 0 Cap, veh/h 422 421 52 259 971 656 236 1044 590 494 1380 706 Arrive On Green 0.04 0.26 0.26 0.07 0.29 0.29 0.04 0.31 0.31 0.13 0.39 0.39 Sat Flow, veh/h 1810 1630 201 1723 3374 1578 1660 3374 1533 1774 3505 1614 Grp Volume(v), veh/h 63 0 392 125 205 99 62 372 192 277 949 89 Grp Sat Flow(s),veh/h/ln 1810 0 1830 1723 1687 1578 1660 1687 1533 1774 1752 1614 Q Serve(g_s), s 2.3 0.0 18.4 4.7 4.2 3.6 2.3 7.8 8.1 9.1 20.5 3.0 Cycle Q Clear(g_c), s 2.3 0.0 18.4 4.7 4.2 3.6 2.3 7.8 8.1 9.1 20.5 3.0 Prop In Lane 1.00 0.11 1.00 1.00 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 422 0 472 259 971 656 236 1044 590 494 1380 706 V/C Ratio(X) 0.15 0.00 0.83 0.48 0.21 0.15 0.26 0.36 0.33 0.56 0.69 0.13 Avail Cap(c_a), veh/h 739 0 602 699 1479 894 710 1664 871 656 1380 706 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 23.1 0.0 32.0 23.8 24.6 16.6 20.9 24.4 19.9 16.6 23.0 15.3 Incr Delay (d2), s/veh 0.2 0.0 7.7 1.4 0.1 0.1 0.6 0.2 0.3 1.0 1.4 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 1.2 0.0 10.4 2.3 2.0 1.6 1.1 3.6 3.4 4.5 10.2 1.3 LnGrp Delay(d),s/veh 23.2 0.0 39.6 25.2 24.7 16.7 21.5 24.7 20.2 17.6 24.4 15.4 LnGrp LOS C D C C B C C C B C B Approach Vol, veh/h 455 429 626 1315 Approach Delay, s/veh 37.4 23.0 23.0 22.4 Approach LOS D C C C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 15.6 34.4 10.7 30.4 8.0 42.1 8.0 33.2 Change Period (Y+Rc), s 4.0 * 6.2 4.0 6.9 4.0 * 6.2 4.0 6.9 Max Green Setting (Gmax), s 20.0 * 45 30.0 30.0 30.0 * 35 20.0 40.0 Max Q Clear Time (g_c+I1), s 11.1 10.1 6.7 20.4 4.3 22.5 4.3 6.2 Green Ext Time (p_c), s 0.5 10.8 0.3 2.7 0.1 7.4 0.1 4.3 Intersection Summary HCM 2010 Ctrl Delay 25.0 HCM 2010 LOS C Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 2: 7th Avenue & Oak Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 252 224 113 37 142 89 64 359 51 222 651 204 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 0.98 1.00 0.99 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1863 1810 1827 1759 1749 1900 1845 1792 1827 1827 1863 1810 Adj Flow Rate, veh/h 300 267 135 44 167 105 69 386 55 281 824 258 Adj No. of Lanes 1 1 1 1 1 0 1 2 1 1 2 1 Peak Hour Factor 0.84 0.84 0.84 0.85 0.85 0.85 0.93 0.93 0.93 0.79 0.79 0.79 Percent Heavy Veh, % 2 5 4 8 9 9 3 6 4 4 2 5 Cap, veh/h 432 614 526 357 226 142 248 881 398 481 1246 773 Arrive On Green 0.15 0.34 0.34 0.04 0.23 0.23 0.05 0.26 0.26 0.14 0.35 0.35 Sat Flow, veh/h 1774 1810 1550 1675 999 628 1757 3406 1541 1740 3539 1533 Grp Volume(v), veh/h 300 267 135 44 0 272 69 386 55 281 824 258 Grp Sat Flow(s),veh/h/ln 1774 1810 1550 1675 0 1627 1757 1703 1541 1740 1770 1533 Q Serve(g_s), s 10.3 9.7 5.3 1.7 0.0 13.2 2.4 8.0 2.3 9.4 16.7 8.5 Cycle Q Clear(g_c), s 10.3 9.7 5.3 1.7 0.0 13.2 2.4 8.0 2.3 9.4 16.7 8.5 Prop In Lane 1.00 1.00 1.00 0.39 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 432 614 526 357 0 367 248 881 398 481 1246 773 V/C Ratio(X) 0.69 0.43 0.26 0.12 0.00 0.74 0.28 0.44 0.14 0.58 0.66 0.33 Avail Cap(c_a), veh/h 581 747 640 688 0 672 579 1808 818 647 1879 1047 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 20.2 21.7 20.3 23.6 0.0 30.5 21.8 26.3 24.2 17.7 23.2 12.5 Incr Delay (d2), s/veh 2.3 0.5 0.3 0.2 0.0 2.9 0.6 0.3 0.2 1.1 0.6 0.3 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 5.2 4.9 2.3 0.8 0.0 6.2 1.2 3.8 1.0 4.6 8.2 3.6 LnGrp Delay(d),s/veh 22.4 22.2 20.5 23.7 0.0 33.5 22.4 26.6 24.3 18.8 23.8 12.8 LnGrp LOS C C C C C C C C B C B Approach Vol, veh/h 702 316 510 1363 Approach Delay, s/veh 22.0 32.1 25.8 20.7 Approach LOS C C C C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 14.9 28.7 6.2 34.9 7.0 36.6 15.9 25.2 Change Period (Y+Rc), s 3.0 * 6.8 3.0 6.1 3.0 * 6.8 3.0 6.1 Max Green Setting (Gmax), s 20.0 * 45 20.0 35.0 20.0 * 45 20.0 35.0 Max Q Clear Time (g_c+I1), s 11.4 10.0 3.7 11.7 4.4 18.7 12.3 15.2 Green Ext Time (p_c), s 0.5 11.9 0.1 3.7 0.1 10.7 0.5 3.6 Intersection Summary HCM 2010 Ctrl Delay 23.1 HCM 2010 LOS C Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 16: Rouse Avenue & Oak Street/Birch Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 139 4 194 2 1 0 119 315 0 0 317 94 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 0.99 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1864 1827 1900 1900 1900 1727 1845 1900 1900 1827 1810 Adj Flow Rate, veh/h 167 5 234 5 3 0 132 350 0 0 369 109 Adj No. of Lanes 0 1 1 0 1 0 1 1 0 1 1 1 Peak Hour Factor 0.83 0.83 0.83 0.38 0.38 0.38 0.90 0.90 0.90 0.86 0.86 0.86 Percent Heavy Veh, % 0 0 4 0 0 0 10 3 3 0 4 5 Cap, veh/h 334 7 406 129 61 0 569 1233 0 96 972 817 Arrive On Green 0.19 0.19 0.19 0.19 0.19 0.00 0.07 0.67 0.00 0.00 0.53 0.53 Sat Flow, veh/h 1272 38 1545 270 323 0 1645 1845 0 1047 1827 1535 Grp Volume(v), veh/h 172 0 234 8 0 0 132 350 0 0 369 109 Grp Sat Flow(s),veh/h/ln 1310 0 1545 593 0 0 1645 1845 0 1047 1827 1535 Q Serve(g_s), s 0.0 0.0 9.9 0.1 0.0 0.0 2.4 5.8 0.0 0.0 8.9 2.7 Cycle Q Clear(g_c), s 9.6 0.0 9.9 9.7 0.0 0.0 2.4 5.8 0.0 0.0 8.9 2.7 Prop In Lane 0.97 1.00 0.62 0.00 1.00 0.00 1.00 1.00 Lane Grp Cap(c), veh/h 341 0 406 189 0 0 569 1233 0 96 972 817 V/C Ratio(X) 0.50 0.00 0.58 0.04 0.00 0.00 0.23 0.28 0.00 0.00 0.38 0.13 Avail Cap(c_a), veh/h 734 0 836 566 0 0 993 1709 0 96 972 817 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 0.00 1.00 1.00 0.00 0.00 1.00 1.00 Uniform Delay (d), s/veh 28.7 0.0 24.1 25.4 0.0 0.0 6.4 5.1 0.0 0.0 10.3 8.8 Incr Delay (d2), s/veh 1.2 0.0 1.3 0.1 0.0 0.0 0.2 0.1 0.0 0.0 0.2 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 3.5 0.0 4.3 0.1 0.0 0.0 1.1 3.0 0.0 0.0 4.5 1.1 LnGrp Delay(d),s/veh 29.8 0.0 25.4 25.4 0.0 0.0 6.6 5.2 0.0 0.0 10.5 8.9 LnGrp LOS C C C A A B A Approach Vol, veh/h 406 8 482 478 Approach Delay, s/veh 27.3 25.4 5.6 10.2 Approach LOS C C A B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 5 6 8 Phs Duration (G+Y+Rc), s 55.6 19.5 10.2 45.4 19.5 Change Period (Y+Rc), s 5.4 5.4 * 4.6 5.4 5.4 Max Green Setting (Gmax), s 69.6 35.0 * 25 40.0 35.0 Max Q Clear Time (g_c+I1), s 7.8 11.9 4.4 10.9 11.7 Green Ext Time (p_c), s 5.7 1.8 0.3 5.3 1.8 Intersection Summary HCM 2010 Ctrl Delay 13.7 HCM 2010 LOS B Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 20: 15th Avenue & Oak Street 10/30/2015 Existing (2015) AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 7 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 9 561 145 34 284 2 52 4 57 8 11 15 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 0.97 1.00 0.99 1.00 0.98 1.00 0.98 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1874 1900 1845 1793 1900 1863 1832 1900 1900 1826 1900 Adj Flow Rate, veh/h 12 719 186 36 302 2 73 6 80 17 23 32 Adj No. of Lanes 1 2 0 1 2 0 1 1 0 1 1 0 Peak Hour Factor 0.78 0.78 0.78 0.94 0.94 0.94 0.71 0.71 0.71 0.47 0.47 0.47 Percent Heavy Veh, % 0 1 1 3 6 6 2 0 0 0 0 0 Cap, veh/h 708 1427 369 409 1778 12 381 18 235 353 112 156 Arrive On Green 0.51 0.51 0.51 0.51 0.51 0.51 0.16 0.16 0.16 0.16 0.16 0.16 Sat Flow, veh/h 1088 2784 720 607 3469 23 1339 108 1440 1329 685 953 Grp Volume(v), veh/h 12 460 445 36 148 156 73 0 86 17 0 55 Grp Sat Flow(s),veh/h/ln 1088 1780 1724 607 1703 1789 1339 0 1548 1329 0 1638 Q Serve(g_s), s 0.2 6.1 6.1 1.5 1.7 1.7 1.8 0.0 1.8 0.4 0.0 1.0 Cycle Q Clear(g_c), s 1.9 6.1 6.1 7.6 1.7 1.7 2.8 0.0 1.8 2.2 0.0 1.0 Prop In Lane 1.00 0.42 1.00 0.01 1.00 0.93 1.00 0.58 Lane Grp Cap(c), veh/h 708 912 883 409 873 917 381 0 253 353 0 267 V/C Ratio(X) 0.02 0.50 0.50 0.09 0.17 0.17 0.19 0.00 0.34 0.05 0.00 0.21 Avail Cap(c_a), veh/h 1367 1990 1927 776 1904 2000 1285 0 1298 1250 0 1373 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 5.2 5.7 5.7 8.2 4.7 4.7 14.2 0.0 13.3 14.2 0.0 13.0 Incr Delay (d2), s/veh 0.0 0.4 0.4 0.1 0.1 0.1 0.2 0.0 0.8 0.1 0.0 0.4 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.1 3.0 3.0 0.3 0.8 0.8 0.7 0.0 0.8 0.2 0.0 0.5 LnGrp Delay(d),s/veh 5.2 6.2 6.2 8.3 4.7 4.7 14.4 0.0 14.1 14.3 0.0 13.3 LnGrp LOS A A A A A A B B B B Approach Vol, veh/h 917 340 159 72 Approach Delay, s/veh 6.2 5.1 14.2 13.6 Approach LOS A A B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 11.8 23.9 11.8 23.9 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 30.0 40.0 30.0 40.0 Max Q Clear Time (g_c+I1), s 4.8 8.1 4.2 9.6 Green Ext Time (p_c), s 1.1 8.7 1.1 8.6 Intersection Summary HCM 2010 Ctrl Delay 7.1 HCM 2010 LOS A HCM 2010 TWSC 5: 27th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Intersection Int Delay, s/veh 87.4 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 64 566 51 19 304 39 24 85 59 40 77 70 Conflicting Peds, #/hr 0 0 3 3 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - 200 - - - - 300 - - 300 Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 2 2 2 3 3 3 2 2 3 3 2 2 Mvmt Flow 80 708 64 24 380 49 30 106 74 50 96 88 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 429 0 0 771 0 0 1185 1375 389 1019 1383 217 Stage 1 - - - - - - 899 899 - 452 452 - Stage 2 - - - - - - 286 476 - 567 931 - Critical Hdwy 4.14 - - 4.16 - - 7.54 6.54 6.96 7.56 6.54 6.94 Critical Hdwy Stg 1 - - - - - - 6.54 5.54 - 6.56 5.54 - Critical Hdwy Stg 2 - - - - - - 6.54 5.54 - 6.56 5.54 - Follow-up Hdwy 2.22 - - 2.23 - - 3.52 4.02 3.33 3.53 4.02 3.32 Pot Cap-1 Maneuver 1127 - - 833 - - 144 144 607 190 143 787 Stage 1 - - - - - - 300 356 - 554 569 - Stage 2 - - - - - - 697 555 - 473 344 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1124 - - 831 - - 39 122 605 ~ 39 121 785 Mov Cap-2 Maneuver - - - - - - 39 122 - ~ 39 121 - Stage 1 - - - - - - 262 311 - 484 553 - Stage 2 - - - - - - 496 539 - 238 301 - Approach EB WB NB SB HCM Control Delay, s 1.1 0.5 278.4 $ 398.5 HCM LOS F F Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 83 605 1124 - - 831 - - 70 785 HCM Lane V/C Ratio 1.642 0.122 0.071 - - 0.029 - - 2.089 0.111 HCM Control Delay (s) $ 422.7 11.8 8.4 0.4 - 9.5 - -$ 630.8 10.2 HCM Lane LOS F B A A - A - - F B HCM 95th %tile Q(veh) 11.2 0.4 0.2 - - 0.1 - - 13.6 0.4 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 11: Davis Lane & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Intersection Int Delay, s/veh 0.7 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 167 449 44 6 254 124 28 224 11 213 352 161 Conflicting Peds, #/hr 3 0 0 0 0 0 0 0 0 0 0 4 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - - - 200 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 2 2 2 1 1 2 2 1 1 Mvmt Flow 209 561 55 8 318 155 35 280 14 266 440 201 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 322 0 0 616 0 0 1404 1343 308 1175 1371 166 Stage 1 - - - - - - 1006 1006 - 337 337 - Stage 2 - - - - - - 398 337 - 838 1034 - Critical Hdwy 4.12 - - 4.14 - - 7.52 6.52 6.94 7.54 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.54 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.54 5.52 - Follow-up Hdwy 2.21 - - 2.22 - - 3.51 4.01 3.32 3.52 4.01 3.31 Pot Cap-1 Maneuver 1242 - - 960 - - 100 ~ 152 688 ~ 147 ~ 146 852 Stage 1 - - - - - - 260 319 - 651 642 - Stage 2 - - - - - - 602 642 - 327 ~ 310 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1239 - - 960 - - - ~ 124 688 - ~ 120 847 Mov Cap-2 Maneuver - - - - - - - ~ 124 - - ~ 120 - Stage 1 - - - - - - 216 ~ 265 - 539 632 - Stage 2 - - - - - - 137 632 - - ~ 258 - Approach EB WB NB SB HCM Control Delay, s 2.1 0.1 HCM LOS - - Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) - 124 134 1239 - - 960 - - - 120 203 HCM Lane V/C Ratio - 1.129 1.147 0.168 - - 0.008 - - - 1.833 2.075 HCM Control Delay (s) - 187.9 187.4 8.5 - - 8.8 0 - -$ 467.3$ 538.6 HCM Lane LOS - F F A - - A A - - F F HCM 95th %tile Q(veh) - 8.3 8.9 0.6 - - 0 - - - 17.3 32.2 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 13: Ferguson Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Intersection Int Delay, s/veh 76.3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 5 254 9 332 130 17 1 30 308 41 67 11 Conflicting Peds, #/hr 0 0 0 0 0 0 1 0 0 0 0 1 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - 200 - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 6 318 11 415 162 21 1 38 385 51 84 14 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 185 0 0 330 0 0 1291 1352 165 1195 1346 93 Stage 1 - - - - - - 337 337 - 1004 1004 - Stage 2 - - - - - - 954 1015 - 191 342 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1394 - - 1234 - - 122 150 854 143 151 949 Stage 1 - - - - - - 654 642 - 261 320 - Stage 2 - - - - - - 280 316 - 795 639 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1394 - - 1234 - - 21 93 853 ~ 39 94 948 Mov Cap-2 Maneuver - - - - - - 21 93 - ~ 39 94 - Stage 1 - - - - - - 650 638 - 259 200 - Stage 2 - - - - - - 100 197 - 408 635 - Approach EB WB NB SB HCM Control Delay, s 0.1 6.6 18.8 $ 692.5 HCM LOS C F Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) 84 853 1394 - - 1234 - - 67 HCM Lane V/C Ratio 0.461 0.451 0.004 - - 0.336 - - 2.22 HCM Control Delay (s) 80.2 12.6 7.6 0 - 9.4 0.3 -$ 692.5 HCM Lane LOS F B A A - A A - F HCM 95th %tile Q(veh) 1.9 2.4 0 - - 1.5 - - 14.2 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 23: 11th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Intersection Int Delay, s/veh 3.4 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 16 767 9 9 406 17 27 1 26 48 2 23 Conflicting Peds, #/hr 5 0 0 0 0 5 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - 500 - - - - - - - 100 Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 3 3 3 3 3 3 3 3 3 3 3 3 Mvmt Flow 20 959 11 11 508 21 34 1 32 60 2 29 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 529 0 0 970 0 0 1282 1555 490 1061 1551 269 Stage 1 - - - - - - 1004 1004 - 541 541 - Stage 2 - - - - - - 278 551 - 520 1010 - Critical Hdwy 4.16 - - 4.16 - - 7.56 6.56 6.96 7.56 6.56 6.96 Critical Hdwy Stg 1 - - - - - - 6.56 5.56 - 6.56 5.56 - Critical Hdwy Stg 2 - - - - - - 6.56 5.56 - 6.56 5.56 - Follow-up Hdwy 2.23 - - 2.23 - - 3.53 4.03 3.33 3.53 4.03 3.33 Pot Cap-1 Maneuver 1027 - - 700 - - 121 111 521 177 112 726 Stage 1 - - - - - - 257 316 - 490 516 - Stage 2 - - - - - - 702 511 - 505 313 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1023 - - 697 - - 111 107 519 159 108 723 Mov Cap-2 Maneuver - - - - - - 111 107 - 159 108 - Stage 1 - - - - - - 252 310 - 480 508 - Stage 2 - - - - - - 657 503 - 460 307 - Approach EB WB NB SB HCM Control Delay, s 0.2 0.2 37.1 32.5 HCM LOS E D Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 178 1023 - - 697 - - 156 723 HCM Lane V/C Ratio 0.379 0.02 - - 0.016 - - 0.401 0.04 HCM Control Delay (s) 37.1 8.6 - - 10.2 - - 42.7 10.2 HCM Lane LOS E A - - B - - E B HCM 95th %tile Q(veh) 1.6 0.1 - - 0 - - 1.7 0.1 HCM 2010 TWSC 26: Flanders Mill Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Intersection Int Delay, s/veh 3.4 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 7 229 9 9 129 8 3 26 26 10 51 10 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - - - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 9 286 11 11 161 10 4 32 32 12 64 12 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 171 0 0 298 0 0 444 503 149 366 504 86 Stage 1 - - - - - - 309 309 - 189 189 - Stage 2 - - - - - - 135 194 - 177 315 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1411 - - 1267 - - 500 472 874 568 471 959 Stage 1 - - - - - - 679 661 - 798 745 - Stage 2 - - - - - - 857 741 - 810 657 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1411 - - 1267 - - 435 464 874 511 463 959 Mov Cap-2 Maneuver - - - - - - 435 464 - 511 463 - Stage 1 - - - - - - 674 656 - 792 738 - Stage 2 - - - - - - 765 734 - 735 652 - Approach EB WB NB SB HCM Control Delay, s 0.2 0.5 11.9 13.6 HCM LOS B B Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) 593 1411 - - 1267 - - 507 HCM Lane V/C Ratio 0.116 0.006 - - 0.009 - - 0.175 HCM Control Delay (s) 11.9 7.6 0 - 7.9 0 - 13.6 HCM Lane LOS B A A - A A - B HCM 95th %tile Q(veh) 0.4 0 - - 0 - - 0.6 HCM 2010 TWSC 38: Cottonwood Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 11 Intersection Int Delay, s/veh 6.8 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 16 115 60 26 32 79 24 75 55 76 79 6 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 20 144 75 32 40 99 30 94 69 95 99 8 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 139 0 0 219 0 0 355 425 109 313 413 69 Stage 1 - - - - - - 221 221 - 154 154 - Stage 2 - - - - - - 134 204 - 159 259 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1450 - - 1355 - - 578 522 927 619 530 983 Stage 1 - - - - - - 764 722 - 836 771 - Stage 2 - - - - - - 858 734 - 830 695 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1450 - - 1355 - - 472 500 927 475 507 983 Mov Cap-2 Maneuver - - - - - - 472 500 - 475 507 - Stage 1 - - - - - - 752 710 - 823 750 - Stage 2 - - - - - - 719 714 - 656 684 - Approach EB WB NB SB HCM Control Delay, s 0.6 1.5 12 13.5 HCM LOS B B Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) 472 500 689 1450 - - 1355 - - 475 507 542 HCM Lane V/C Ratio 0.064 0.094 0.168 0.014 - - 0.024 - - 0.2 0.097 0.105 HCM Control Delay (s) 13.1 12.9 11.3 7.5 0 - 7.7 0 - 14.5 12.9 12.4 HCM Lane LOS B B B A A - A A - B B B HCM 95th %tile Q(veh) 0.2 0.3 0.6 0 - - 0.1 - - 0.7 0.3 0.4 Queues 1: 19th Avenue & Oak Street 11/1/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Lane Group EBL EBT WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 190 339 662 524 271 120 823 229 157 627 97 v/c Ratio 0.49 0.87 1.30 0.43 0.34 0.38 0.79 0.23 0.63 0.57 0.13 Control Delay 26.0 71.3 176.8 36.3 10.6 25.6 48.6 2.2 34.2 40.1 2.0 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 26.0 71.3 176.8 36.3 10.6 25.6 48.6 2.2 34.2 40.1 2.0 Queue Length 50th (ft) 88 272 ~646 178 54 62 343 0 83 238 0 Queue Length 95th (ft) 158 #475 #856 246 109 101 438 37 129 310 19 Internal Link Dist (ft) 1120 1040 615 420 Turn Bay Length (ft) 200 250 250 425 425 285 285 Base Capacity (vph) 479 434 511 1223 890 532 1255 1012 341 1124 832 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.40 0.78 1.30 0.43 0.30 0.23 0.66 0.23 0.46 0.56 0.12 Intersection Summary ~ Volume exceeds capacity, queue is theoretically infinite. Queue shown is maximum after two cycles. # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 2: 7th Avenue & Oak Street 11/1/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 2 Lane Group EBL EBT EBR WBL WBT NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 276 270 186 150 617 204 841 145 247 731 413 v/c Ratio 0.82 0.43 0.28 0.30 1.23 0.61 0.81 0.30 0.83 0.68 0.47 Control Delay 52.1 38.2 6.2 23.0 158.0 28.1 48.5 13.8 49.5 41.9 10.6 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 52.1 38.2 6.2 23.0 158.0 28.1 48.5 13.8 49.5 41.9 10.6 Queue Length 50th (ft) 166 174 0 70 ~632 98 339 27 129 276 91 Queue Length 95th (ft) #304 277 45 121 #864 148 431 82 211 334 157 Internal Link Dist (ft) 1263 2871 420 420 Turn Bay Length (ft) 175 300 175 175 125 125 Base Capacity (vph) 348 624 661 611 502 411 1282 581 351 1284 915 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.79 0.43 0.28 0.25 1.23 0.50 0.66 0.25 0.70 0.57 0.45 Intersection Summary ~ Volume exceeds capacity, queue is theoretically infinite. Queue shown is maximum after two cycles. # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 16: Rouse Avenue & Oak Street/Birch Street 11/1/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 4 Lane Group EBT EBR WBT NBL NBT SBL SBT SBR Lane Group Flow (vph) 134 183 4 276 432 1 480 197 v/c Ratio 0.60 0.26 0.01 0.43 0.32 0.00 0.52 0.24 Control Delay 45.1 3.6 0.0 6.5 5.7 15.0 19.0 8.5 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 45.1 3.6 0.0 6.5 5.7 15.0 19.0 8.5 Queue Length 50th (ft) 64 2 0 39 69 0 160 26 Queue Length 95th (ft) 127 33 0 71 117 4 315 79 Internal Link Dist (ft) 839 303 425 421 Turn Bay Length (ft) 225 240 100 100 Base Capacity (vph) 600 889 950 803 1598 474 918 838 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.22 0.21 0.00 0.34 0.27 0.00 0.52 0.24 Intersection Summary Queues 20: 15th Avenue & Oak Street 11/1/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Lane Group EBL EBT WBL WBT NBL NBT SBL SBT Lane Group Flow (vph) 9 642 61 920 246 120 13 27 v/c Ratio 0.04 0.43 0.19 0.60 0.57 0.21 0.04 0.05 Control Delay 10.6 10.8 11.9 13.1 20.9 5.4 13.4 9.2 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 10.6 10.8 11.9 13.1 20.9 5.4 13.4 9.2 Queue Length 50th (ft) 1 53 9 87 52 2 2 2 Queue Length 95th (ft) 11 135 37 192 121 26 11 12 Internal Link Dist (ft) 230 1310 357 332 Turn Bay Length (ft) 125 125 125 125 Base Capacity (vph) 389 2878 620 2960 916 1097 772 1142 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.02 0.22 0.10 0.31 0.27 0.11 0.02 0.02 Intersection Summary HCM 2010 Signalized Intersection Summary 1: 19th Avenue & Oak Street 10/30/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 171 249 56 543 430 222 116 798 222 149 596 92 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1881 1885 1900 1881 1900 1881 1900 1881 1881 1845 1881 1881 Adj Flow Rate, veh/h 190 277 62 662 524 271 120 823 229 157 627 97 Adj No. of Lanes 1 1 0 1 2 1 1 2 1 1 2 1 Peak Hour Factor 0.90 0.90 0.90 0.82 0.82 0.82 0.97 0.97 0.97 0.95 0.95 0.95 Percent Heavy Veh, % 1 1 1 1 0 1 0 1 1 3 1 1 Cap, veh/h 381 307 69 527 1270 689 295 1051 863 243 1110 657 Arrive On Green 0.10 0.21 0.21 0.25 0.35 0.35 0.06 0.29 0.29 0.08 0.31 0.31 Sat Flow, veh/h 1792 1490 334 1792 3610 1595 1810 3574 1594 1757 3574 1596 Grp Volume(v), veh/h 190 0 339 662 524 271 120 823 229 157 627 97 Grp Sat Flow(s),veh/h/ln 1792 0 1824 1792 1805 1595 1810 1787 1594 1757 1787 1596 Q Serve(g_s), s 10.0 0.0 22.0 30.0 13.4 14.1 5.6 25.7 9.4 7.5 17.8 4.6 Cycle Q Clear(g_c), s 10.0 0.0 22.0 30.0 13.4 14.1 5.6 25.7 9.4 7.5 17.8 4.6 Prop In Lane 1.00 0.18 1.00 1.00 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 381 0 376 527 1270 689 295 1051 863 243 1110 657 V/C Ratio(X) 0.50 0.00 0.90 1.26 0.41 0.39 0.41 0.78 0.27 0.65 0.57 0.15 Avail Cap(c_a), veh/h 495 0 450 527 1270 689 627 1323 984 392 1110 657 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 32.7 0.0 47.1 32.9 29.9 23.7 28.1 39.4 15.0 30.0 35.1 22.4 Incr Delay (d2), s/veh 1.0 0.0 18.9 129.9 0.2 0.4 0.9 2.5 0.2 2.9 0.7 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 5.0 0.0 13.1 36.6 6.7 6.3 2.8 13.0 4.2 3.8 8.9 2.1 LnGrp Delay(d),s/veh 33.7 0.0 66.0 162.8 30.1 24.0 29.0 41.8 15.1 32.9 35.7 22.5 LnGrp LOS C E F C C C D B C D C Approach Vol, veh/h 529 1457 1172 881 Approach Delay, s/veh 54.4 89.2 35.3 33.8 Approach LOS D F D C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 13.7 41.9 34.0 32.0 11.7 43.9 16.3 49.7 Change Period (Y+Rc), s 4.0 * 6.2 4.0 6.9 4.0 * 6.2 4.0 6.9 Max Green Setting (Gmax), s 20.0 * 45 30.0 30.0 30.0 * 35 20.0 40.0 Max Q Clear Time (g_c+I1), s 9.5 27.7 32.0 24.0 7.6 19.8 12.0 16.1 Green Ext Time (p_c), s 0.3 8.1 0.0 0.9 0.3 9.1 0.3 6.6 Intersection Summary HCM 2010 Ctrl Delay 56.9 HCM 2010 LOS E Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 2: 7th Avenue & Oak Street 10/30/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 232 227 156 126 321 197 186 765 132 210 621 351 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 0.98 1.00 0.97 1.00 0.98 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1881 1845 1900 1881 1863 1900 1881 1881 1845 1845 1863 1900 Adj Flow Rate, veh/h 276 270 186 150 382 235 204 841 145 247 731 413 Adj No. of Lanes 1 1 1 1 1 0 1 2 1 1 2 1 Peak Hour Factor 0.84 0.84 0.84 0.84 0.84 0.84 0.91 0.91 0.91 0.85 0.85 0.85 Percent Heavy Veh, % 1 3 0 1 2 2 1 1 3 3 2 0 Cap, veh/h 304 631 551 410 302 186 307 1138 483 314 1186 753 Arrive On Green 0.14 0.34 0.34 0.08 0.28 0.28 0.09 0.32 0.32 0.11 0.34 0.34 Sat Flow, veh/h 1792 1845 1609 1792 1073 660 1792 3574 1519 1757 3539 1586 Grp Volume(v), veh/h 276 270 186 150 0 617 204 841 145 247 731 413 Grp Sat Flow(s),veh/h/ln 1792 1845 1609 1792 0 1733 1792 1787 1519 1757 1770 1586 Q Serve(g_s), s 14.8 14.0 10.7 7.3 0.0 35.0 9.4 26.1 8.9 11.4 21.5 23.1 Cycle Q Clear(g_c), s 14.8 14.0 10.7 7.3 0.0 35.0 9.4 26.1 8.9 11.4 21.5 23.1 Prop In Lane 1.00 1.00 1.00 0.38 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 304 631 551 410 0 488 307 1138 483 314 1186 753 V/C Ratio(X) 0.91 0.43 0.34 0.37 0.00 1.26 0.66 0.74 0.30 0.79 0.62 0.55 Avail Cap(c_a), veh/h 346 631 551 561 0 488 426 1294 550 402 1281 795 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 36.4 31.5 30.4 28.2 0.0 44.7 26.8 37.8 31.9 27.8 34.6 23.4 Incr Delay (d2), s/veh 25.1 0.5 0.4 0.5 0.0 134.7 2.5 2.0 0.3 7.7 0.8 0.7 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 11.4 7.2 4.8 3.6 0.0 34.9 4.8 13.2 3.8 6.2 10.6 10.2 LnGrp Delay(d),s/veh 61.5 32.0 30.8 28.7 0.0 179.4 29.3 39.8 32.3 35.5 35.4 24.1 LnGrp LOS E C C C F C D C D D C Approach Vol, veh/h 732 767 1190 1391 Approach Delay, s/veh 42.8 149.9 37.1 32.1 Approach LOS D F D C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 16.8 46.4 12.5 48.6 14.7 48.5 20.0 41.1 Change Period (Y+Rc), s 3.0 * 6.8 3.0 6.1 3.0 * 6.8 3.0 6.1 Max Green Setting (Gmax), s 20.0 * 45 20.0 35.0 20.0 * 45 20.0 35.0 Max Q Clear Time (g_c+I1), s 13.4 28.1 9.3 16.0 11.4 25.1 16.8 37.0 Green Ext Time (p_c), s 0.4 11.5 0.3 6.4 0.3 12.9 0.3 0.0 Intersection Summary HCM 2010 Ctrl Delay 57.6 HCM 2010 LOS E Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 16: Rouse Avenue & Oak Street/Birch Street 10/30/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 117 0 159 0 0 1 218 341 0 1 418 171 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1863 1792 1900 1900 1900 1881 1881 1900 1900 1881 1900 Adj Flow Rate, veh/h 134 0 183 0 0 4 276 432 0 1 480 197 Adj No. of Lanes 0 1 1 0 1 0 1 1 0 1 1 1 Peak Hour Factor 0.87 0.87 0.87 0.25 0.25 0.25 0.79 0.79 0.79 0.87 0.87 0.87 Percent Heavy Veh, % 0 0 6 0 0 0 1 1 1 0 1 0 Cap, veh/h 304 0 374 0 0 239 571 1326 0 627 1025 880 Arrive On Green 0.15 0.00 0.15 0.00 0.00 0.15 0.10 0.70 0.00 0.54 0.54 0.54 Sat Flow, veh/h 1387 0 1524 0 0 1615 1792 1881 0 971 1881 1615 Grp Volume(v), veh/h 134 0 183 0 0 4 276 432 0 1 480 197 Grp Sat Flow(s),veh/h/ln 1387 0 1524 0 0 1615 1792 1881 0 971 1881 1615 Q Serve(g_s), s 6.6 0.0 7.6 0.0 0.0 0.2 4.4 6.5 0.0 0.0 11.5 4.6 Cycle Q Clear(g_c), s 6.8 0.0 7.6 0.0 0.0 0.2 4.4 6.5 0.0 0.0 11.5 4.6 Prop In Lane 1.00 1.00 0.00 1.00 1.00 0.00 1.00 1.00 Lane Grp Cap(c), veh/h 304 0 374 0 0 239 571 1326 0 627 1025 880 V/C Ratio(X) 0.44 0.00 0.49 0.00 0.00 0.02 0.48 0.33 0.00 0.00 0.47 0.22 Avail Cap(c_a), veh/h 766 0 874 0 0 770 1006 1783 0 627 1025 880 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 0.00 0.00 1.00 1.00 1.00 0.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 29.6 0.0 23.7 0.0 0.0 26.7 6.7 4.2 0.0 7.6 10.2 8.7 Incr Delay (d2), s/veh 1.0 0.0 1.0 0.0 0.0 0.0 0.6 0.1 0.0 0.0 0.3 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 2.7 0.0 3.3 0.0 0.0 0.1 2.2 3.3 0.0 0.0 6.0 2.1 LnGrp Delay(d),s/veh 30.6 0.0 24.7 0.0 0.0 26.7 7.3 4.3 0.0 7.6 10.6 8.8 LnGrp LOS C C C A A A B A Approach Vol, veh/h 317 4 708 678 Approach Delay, s/veh 27.2 26.7 5.5 10.0 Approach LOS C C A B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 5 6 8 Phs Duration (G+Y+Rc), s 57.1 16.3 11.7 45.4 16.3 Change Period (Y+Rc), s 5.4 5.4 * 4.6 5.4 5.4 Max Green Setting (Gmax), s 69.6 35.0 * 25 40.0 35.0 Max Q Clear Time (g_c+I1), s 8.5 9.6 6.4 13.5 2.2 Green Ext Time (p_c), s 8.2 1.3 0.8 7.3 1.4 Intersection Summary HCM 2010 Ctrl Delay 11.4 HCM 2010 LOS B Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 20: 15th Avenue & Oak Street 10/30/2015 Existing (2015) PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 7 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 8 527 76 51 768 5 197 11 85 9 8 11 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 0.99 1.00 0.99 0.98 0.98 0.99 0.98 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1867 1900 1900 1879 1900 1881 1867 1900 1712 1900 1900 Adj Flow Rate, veh/h 9 561 81 61 914 6 246 14 106 13 11 16 Adj No. of Lanes 1 2 0 1 2 0 1 1 0 1 1 0 Peak Hour Factor 0.94 0.94 0.94 0.84 0.84 0.84 0.80 0.80 0.80 0.70 0.70 0.70 Percent Heavy Veh, % 0 2 2 0 1 1 1 0 0 11 0 0 Cap, veh/h 314 1425 205 414 1667 11 553 58 436 435 215 313 Arrive On Green 0.46 0.46 0.46 0.46 0.46 0.46 0.31 0.31 0.31 0.31 0.31 0.31 Sat Flow, veh/h 616 3109 448 797 3635 24 1370 186 1406 1149 693 1009 Grp Volume(v), veh/h 9 319 323 61 449 471 246 0 120 13 0 27 Grp Sat Flow(s),veh/h/ln 616 1774 1783 797 1785 1874 1370 0 1591 1149 0 1702 Q Serve(g_s), s 0.5 6.0 6.0 2.7 9.1 9.1 7.7 0.0 2.8 0.4 0.0 0.6 Cycle Q Clear(g_c), s 9.7 6.0 6.0 8.8 9.1 9.1 8.3 0.0 2.8 3.3 0.0 0.6 Prop In Lane 1.00 0.25 1.00 0.01 1.00 0.88 1.00 0.59 Lane Grp Cap(c), veh/h 314 813 817 414 818 859 553 0 494 435 0 528 V/C Ratio(X) 0.03 0.39 0.39 0.15 0.55 0.55 0.44 0.00 0.24 0.03 0.00 0.05 Avail Cap(c_a), veh/h 522 1415 1421 684 1423 1495 947 0 952 766 0 1018 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 13.3 9.0 9.0 11.9 9.8 9.8 15.0 0.0 12.9 14.1 0.0 12.1 Incr Delay (d2), s/veh 0.0 0.3 0.3 0.2 0.6 0.5 0.6 0.0 0.3 0.0 0.0 0.0 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.1 2.9 2.9 0.6 4.5 4.7 3.0 0.0 1.3 0.1 0.0 0.3 LnGrp Delay(d),s/veh 13.4 9.3 9.3 12.0 10.4 10.4 15.6 0.0 13.2 14.1 0.0 12.2 LnGrp LOS B A A B B B B B B B Approach Vol, veh/h 651 981 366 40 Approach Delay, s/veh 9.3 10.5 14.8 12.8 Approach LOS A B B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 21.6 28.6 21.6 28.6 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 30.0 40.0 30.0 40.0 Max Q Clear Time (g_c+I1), s 10.3 11.7 5.3 11.1 Green Ext Time (p_c), s 1.7 11.3 1.8 11.4 Intersection Summary HCM 2010 Ctrl Delay 10.9 HCM 2010 LOS B HCM 2010 TWSC 5: 27th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Intersection Int Delay, s/veh 24.6 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 46 380 29 85 597 79 15 99 46 25 72 117 Conflicting Peds, #/hr 0 0 3 3 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - 200 - - - - 300 - - 300 Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 2 2 2 3 3 3 2 2 3 3 2 2 Mvmt Flow 51 422 32 94 663 88 17 110 51 28 80 130 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 751 0 0 454 0 0 1102 1481 230 1264 1453 379 Stage 1 - - - - - - 541 541 - 896 896 - Stage 2 - - - - - - 561 940 - 368 557 - Critical Hdwy 4.14 - - 4.16 - - 7.54 6.54 6.96 7.56 6.54 6.94 Critical Hdwy Stg 1 - - - - - - 6.54 5.54 - 6.56 5.54 - Critical Hdwy Stg 2 - - - - - - 6.54 5.54 - 6.56 5.54 - Follow-up Hdwy 2.22 - - 2.23 - - 3.52 4.02 3.33 3.53 4.02 3.32 Pot Cap-1 Maneuver 854 - - 1096 - - 166 124 769 125 129 619 Stage 1 - - - - - - 493 519 - 299 357 - Stage 2 - - - - - - 480 340 - 621 510 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 852 - - 1093 - - 46 ~ 104 767 - 108 617 Mov Cap-2 Maneuver - - - - - - 46 ~ 104 - - 108 - Stage 1 - - - - - - 454 477 - 275 326 - Stage 2 - - - - - - 261 311 - 409 469 - Approach EB WB NB SB HCM Control Delay, s 1.2 1 236.4 HCM LOS F - Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 89 767 852 - - 1093 - - - 617 HCM Lane V/C Ratio 1.423 0.067 0.06 - - 0.086 - - - 0.211 HCM Control Delay (s) $ 327.7 10 9.5 0.3 - 8.6 - - - 12.4 HCM Lane LOS F B A A - A - - - B HCM 95th %tile Q(veh) 9.6 0.2 0.2 - - 0.3 - - - 0.8 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 11: Davis Lane & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Intersection Int Delay, s/veh 29.7 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 303 349 0 0 524 176 0 0 3 98 0 331 Conflicting Peds, #/hr 3 0 0 0 0 0 0 0 0 0 0 4 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - - - 200 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 1 1 1 2 2 2 1 1 2 2 1 1 Mvmt Flow 337 388 0 0 582 196 0 0 3 109 0 368 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 586 0 0 388 0 0 1356 1647 194 1453 1647 298 Stage 1 - - - - - - 1061 1061 - 586 586 - Stage 2 - - - - - - 295 586 - 867 1061 - Critical Hdwy 4.12 - - 4.14 - - 7.52 6.52 6.94 7.54 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.54 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.54 5.52 - Follow-up Hdwy 2.21 - - 2.22 - - 3.51 4.01 3.32 3.52 4.01 3.31 Pot Cap-1 Maneuver 992 - - 1167 - - 109 99 815 ~ 91 99 701 Stage 1 - - - - - - 241 301 - 463 498 - Stage 2 - - - - - - 692 498 - 314 301 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 990 - - 1167 - - 38 65 815 ~ 66 65 697 Mov Cap-2 Maneuver - - - - - - 38 65 - ~ 66 65 - Stage 1 - - - - - - 159 199 - 304 496 - Stage 2 - - - - - - 326 496 - 206 199 - Approach EB WB NB SB HCM Control Delay, s 4.9 0 9.4 116 HCM LOS A F Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) - - 815 990 - - 1167 - - 66 - 697 HCM Lane V/C Ratio - - 0.004 0.34 - - - - - 1.65 - 0.528 HCM Control Delay (s) 0 0 9.4 10.5 - - 0 - -$ 454.5 0 15.8 HCM Lane LOS A A A B - - A - - F A C HCM 95th %tile Q(veh) - - 0 1.5 - - 0 - - 9.6 - 3.1 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 13: Ferguson Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Intersection Int Delay, s/veh 2.9 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 5 194 5 429 285 44 1 79 323 42 64 20 Conflicting Peds, #/hr 0 0 0 0 0 0 1 0 0 0 0 1 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - 200 - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 6 242 6 536 356 55 1 99 404 52 80 25 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 412 0 0 250 0 0 1551 1744 125 1641 1719 207 Stage 1 - - - - - - 259 259 - 1457 1457 - Stage 2 - - - - - - 1292 1485 - 184 262 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1151 - - 1320 - - 78 ~ 86 905 67 90 802 Stage 1 - - - - - - 726 695 - 137 194 - Stage 2 - - - - - - 174 188 - 803 693 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1151 - - 1320 - - - ~ 40 904 - ~ 42 801 Mov Cap-2 Maneuver - - - - - - - ~ 40 - - ~ 42 - Stage 1 - - - - - - 721 690 - 136 91 - Stage 2 - - - - - - 10 ~ 88 - 378 688 - Approach EB WB NB SB HCM Control Delay, s 0.2 5.6 HCM LOS - - Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) - 904 1151 - - 1320 - - - HCM Lane V/C Ratio - 0.447 0.005 - - 0.406 - - - HCM Control Delay (s) - 12.2 8.1 0 - 9.6 0.6 - - HCM Lane LOS - B A A - A A - - HCM 95th %tile Q(veh) - 2.3 0 - - 2 - - - Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 23: 11th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Intersection Int Delay, s/veh 6.1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 28 726 36 34 912 15 17 0 20 48 2 53 Conflicting Peds, #/hr 5 0 0 0 0 5 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - 500 - - - - - - - 100 Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 3 3 3 3 3 3 3 3 3 3 3 3 Mvmt Flow 31 807 40 38 1013 17 19 0 22 53 2 59 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 1030 0 0 847 0 0 1472 1995 428 1563 2006 520 Stage 1 - - - - - - 889 889 - 1097 1097 - Stage 2 - - - - - - 583 1106 - 466 909 - Critical Hdwy 4.16 - - 4.16 - - 7.56 6.56 6.96 7.56 6.56 6.96 Critical Hdwy Stg 1 - - - - - - 6.56 5.56 - 6.56 5.56 - Critical Hdwy Stg 2 - - - - - - 6.56 5.56 - 6.56 5.56 - Follow-up Hdwy 2.23 - - 2.23 - - 3.53 4.03 3.33 3.53 4.03 3.33 Pot Cap-1 Maneuver 664 - - 780 - - 88 59 572 75 58 498 Stage 1 - - - - - - 302 357 - 226 285 - Stage 2 - - - - - - 463 282 - 543 350 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 661 - - 777 - - 69 53 570 67 53 496 Mov Cap-2 Maneuver - - - - - - 69 53 - 67 53 - Stage 1 - - - - - - 288 340 - 215 271 - Stage 2 - - - - - - 383 268 - 495 334 - Approach EB WB NB SB HCM Control Delay, s 0.4 0.3 44.6 90.3 HCM LOS E F Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 131 661 - - 777 - - 66 496 HCM Lane V/C Ratio 0.314 0.047 - - 0.049 - - 0.842 0.119 HCM Control Delay (s) 44.6 10.7 - - 9.9 - - 172 13.2 HCM Lane LOS E B - - A - - F B HCM 95th %tile Q(veh) 1.2 0.1 - - 0.2 - - 4 0.4 HCM 2010 TWSC 26: Flanders Mill Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Intersection Int Delay, s/veh 4.1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 10 176 4 34 253 16 5 51 18 13 55 9 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - - - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 11 196 4 38 281 18 6 57 20 14 61 10 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 299 0 0 200 0 0 467 594 100 514 588 149 Stage 1 - - - - - - 220 220 - 366 366 - Stage 2 - - - - - - 247 374 - 148 222 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1266 - - 1377 - - 481 419 939 446 422 874 Stage 1 - - - - - - 765 722 - 628 624 - Stage 2 - - - - - - 738 619 - 842 721 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1266 - - 1377 - - 407 401 939 377 404 874 Mov Cap-2 Maneuver - - - - - - 407 401 - 377 404 - Stage 1 - - - - - - 757 715 - 622 603 - Stage 2 - - - - - - 634 599 - 751 714 - Approach EB WB NB SB HCM Control Delay, s 0.4 0.9 14.4 15.6 HCM LOS B C Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) 466 1266 - - 1377 - - 426 HCM Lane V/C Ratio 0.176 0.009 - - 0.027 - - 0.201 HCM Control Delay (s) 14.4 7.9 0 - 7.7 0.1 - 15.6 HCM Lane LOS B A A - A A - C HCM 95th %tile Q(veh) 0.6 0 - - 0.1 - - 0.7 HCM 2010 TWSC 38: Cottonwood Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 11 Intersection Int Delay, s/veh 8.3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 15 85 15 89 91 85 72 122 39 63 38 13 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 17 94 17 99 101 94 80 136 43 70 42 14 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 196 0 0 111 0 0 405 529 56 494 490 98 Stage 1 - - - - - - 136 136 - 346 346 - Stage 2 - - - - - - 269 393 - 148 144 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1382 - - 1484 - - 533 456 1002 461 480 942 Stage 1 - - - - - - 856 785 - 646 636 - Stage 2 - - - - - - 716 607 - 842 779 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1382 - - 1484 - - 454 416 1002 309 438 942 Mov Cap-2 Maneuver - - - - - - 454 416 - 309 438 - Stage 1 - - - - - - 845 775 - 638 588 - Stage 2 - - - - - - 605 561 - 656 769 - Approach EB WB NB SB HCM Control Delay, s 1 2.6 14.3 16.7 HCM LOS B C Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) 454 416 539 1382 - - 1484 - - 309 438 560 HCM Lane V/C Ratio 0.176 0.163 0.206 0.012 - - 0.067 - - 0.227 0.048 0.063 HCM Control Delay (s) 14.6 15.3 13.4 7.6 0 - 7.6 0.1 - 20 13.6 11.9 HCM Lane LOS B C B A A - A A - C B B HCM 95th %tile Q(veh) 0.6 0.6 0.8 0 - - 0.2 - - 0.9 0.2 0.2 APPENDIX C: FUTURE YEAR CAPACITY ANALYSIS Queues 1: 19th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 109 634 74 161 318 128 82 684 234 285 1500 101 v/c Ratio 0.34 0.85 0.14 0.75 0.36 0.17 0.59 0.46 0.27 0.63 0.87 0.10 Control Delay 36.9 62.2 2.2 55.0 43.2 4.4 37.5 29.3 9.5 20.1 35.7 2.6 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 36.9 62.2 2.2 55.0 43.2 4.4 37.5 29.3 9.5 20.1 35.7 2.6 Queue Length 50th (ft) 68 288 0 104 123 0 30 229 54 121 606 1 Queue Length 95th (ft) 106 328 1 #159 156 26 60 257 87 151 582 18 Internal Link Dist (ft) 2554 1350 615 420 Turn Bay Length (ft) 200 200 250 250 425 425 285 285 Base Capacity (vph) 324 868 518 220 1003 780 139 1680 900 494 2053 1032 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.34 0.73 0.14 0.73 0.32 0.16 0.59 0.41 0.26 0.58 0.73 0.10 Intersection Summary # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 2: 7th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 2 Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 399 449 179 61 254 148 85 674 94 299 1221 266 v/c Ratio 0.77 0.83 0.28 0.28 0.51 0.27 0.46 0.56 0.13 0.67 0.82 0.24 Control Delay 39.2 53.0 14.6 29.0 51.4 10.9 25.1 34.9 5.1 23.7 35.4 3.0 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 39.2 53.0 14.6 29.0 51.4 10.9 25.1 34.9 5.1 23.7 35.4 3.0 Queue Length 50th (ft) 236 321 48 29 97 24 29 215 0 119 418 17 Queue Length 95th (ft) 313 410 88 55 131 54 58 294 25 183 494 43 Internal Link Dist (ft) 1263 708 420 420 Turn Bay Length (ft) 175 300 300 175 175 125 125 Base Capacity (vph) 544 771 642 219 842 659 186 1355 711 531 1863 1148 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.73 0.58 0.28 0.28 0.30 0.22 0.46 0.50 0.13 0.56 0.66 0.23 Intersection Summary Queues 5: 27th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Lane Group EBT WBL WBT NBT NBR SBT SBR Lane Group Flow (vph) 852 24 429 136 74 146 88 v/c Ratio 0.52 0.08 0.23 0.29 0.15 0.33 0.17 Control Delay 9.3 8.1 6.7 12.8 4.4 13.5 4.3 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 9.3 8.1 6.7 12.8 4.4 13.5 4.3 Queue Length 50th (ft) 58 3 23 22 0 24 0 Queue Length 95th (ft) 106 12 45 45 15 48 16 Internal Link Dist (ft) 2533 2554 420 420 Turn Bay Length (ft) 200 300 300 Base Capacity (vph) 1672 324 1909 903 895 849 898 Starvation Cap Reductn 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 Reduced v/c Ratio 0.51 0.07 0.22 0.15 0.08 0.17 0.10 Intersection Summary Queues 11: Davis Lane & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Lane Group EBL EBT WBT WBR NBL NBT SBL SBT Lane Group Flow (vph) 209 616 326 155 35 294 266 641 v/c Ratio 0.59 0.51 0.29 0.24 0.13 0.23 0.71 0.49 Control Delay 19.0 11.6 10.4 3.4 10.7 9.4 25.2 8.4 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 19.0 11.6 10.4 3.4 10.7 9.4 25.2 8.4 Queue Length 50th (ft) 39 55 28 0 6 24 53 40 Queue Length 95th (ft) 76 76 44 19 17 38 #107 60 Internal Link Dist (ft) 2585 2533 510 433 Turn Bay Length (ft) 500 200 200 200 Base Capacity (vph) 441 1510 1401 760 325 1511 451 1548 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.47 0.41 0.23 0.20 0.11 0.19 0.59 0.41 Intersection Summary # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 13: Ferguson Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Lane Group EBT WBT NBT NBR SBT Lane Group Flow (vph) 335 598 39 385 149 v/c Ratio 0.29 1.15dl 0.05 0.47 0.23 Control Delay 10.4 19.0 9.3 4.2 10.0 Queue Delay 0.0 0.0 0.0 0.0 0.0 Total Delay 10.4 19.0 9.3 4.2 10.0 Queue Length 50th (ft) 28 62 6 5 22 Queue Length 95th (ft) 44 90 17 32 44 Internal Link Dist (ft) 1220 2585 420 262 Turn Bay Length (ft) 200 Base Capacity (vph) 1280 889 711 821 638 Starvation Cap Reductn 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 Reduced v/c Ratio 0.26 0.67 0.05 0.47 0.23 Intersection Summary dl Defacto Left Lane. Recode with 1 though lane as a left lane. Queues 16: Rouse Avenue & Oak Street/Birch Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 7 Lane Group EBT EBR WBT NBL NBT SBT SBR Lane Group Flow (vph) 287 380 3 181 591 595 129 v/c Ratio 0.83 0.48 0.01 0.44 0.51 0.70 0.17 Control Delay 54.2 11.1 27.5 11.5 12.6 27.4 9.8 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 54.2 11.1 27.5 11.5 12.6 27.4 9.8 Queue Length 50th (ft) 154 65 1 39 175 275 21 Queue Length 95th (ft) 249 128 8 76 276 405 52 Internal Link Dist (ft) 835 303 425 421 Turn Bay Length (ft) 225 240 100 Base Capacity (vph) 503 824 601 451 1393 1035 889 Starvation Cap Reductn 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 Reduced v/c Ratio 0.57 0.46 0.00 0.40 0.42 0.57 0.15 Intersection Summary Queues 20: 15th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 8 Lane Group EBL EBT WBL WBT NBL NBT SBL SBT Lane Group Flow (vph) 24 1125 52 471 82 163 38 99 v/c Ratio 0.04 0.54 0.21 0.22 0.28 0.36 0.14 0.23 Control Delay 5.8 7.7 9.0 5.8 18.6 11.6 16.9 11.0 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 5.8 7.7 9.0 5.8 18.6 11.6 16.9 11.0 Queue Length 50th (ft) 2 81 6 27 16 15 7 9 Queue Length 95th (ft) 10 128 22 50 47 53 26 38 Internal Link Dist (ft) 1350 1310 357 332 Turn Bay Length (ft) 125 125 125 125 Base Capacity (vph) 801 3072 358 3160 974 1303 920 1306 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.03 0.37 0.15 0.15 0.08 0.13 0.04 0.08 Intersection Summary Queues 23: 11th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Lane Group EBL EBT WBL WBT NBT SBL SBT Lane Group Flow (vph) 20 970 11 529 67 60 31 v/c Ratio 0.04 0.41 0.03 0.23 0.16 0.11 0.07 Control Delay 6.1 6.4 6.2 5.2 8.4 11.2 6.0 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 6.1 6.4 6.2 5.2 8.4 11.2 6.0 Queue Length 50th (ft) 2 61 1 27 5 9 0 Queue Length 95th (ft) 8 94 6 47 21 24 10 Internal Link Dist (ft) 1310 1263 471 383 Turn Bay Length (ft) 500 500 100 Base Capacity (vph) 561 2343 353 2334 964 1236 1072 Starvation Cap Reductn 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 Reduced v/c Ratio 0.04 0.41 0.03 0.23 0.07 0.05 0.03 Intersection Summary Queues 38: Cottonwood Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Lane Group EBT WBT NBL NBT SBL SBT Lane Group Flow (vph) 239 171 30 163 95 107 v/c Ratio 0.25 0.20 0.07 0.15 0.23 0.10 Control Delay 6.3 4.7 7.4 4.8 8.9 6.7 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 6.3 4.7 7.4 4.8 8.9 6.7 Queue Length 50th (ft) 8 3 3 4 9 4 Queue Length 95th (ft) 19 12 10 12 23 11 Internal Link Dist (ft) 418 1316 424 422 Turn Bay Length (ft) 200 200 Base Capacity (vph) 2595 2331 1289 3327 1289 3511 Starvation Cap Reductn 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 Reduced v/c Ratio 0.09 0.07 0.02 0.05 0.07 0.03 Intersection Summary HCM 2010 Signalized Intersection Summary 1: 19th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 87 507 59 129 254 102 66 547 187 228 1200 81 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 0.99 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 Adj Flow Rate, veh/h 109 634 74 161 318 128 82 684 234 285 1500 101 Adj No. of Lanes 1 2 1 1 2 1 1 2 1 1 2 1 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 293 749 393 224 878 551 166 1572 820 421 1796 872 Arrive On Green 0.04 0.21 0.21 0.08 0.25 0.25 0.04 0.45 0.45 0.10 0.51 0.51 Sat Flow, veh/h 1757 3505 1561 1757 3505 1562 1757 3505 1547 1757 3505 1567 Grp Volume(v), veh/h 109 634 74 161 318 128 82 684 234 285 1500 101 Grp Sat Flow(s),veh/h/ln 1757 1752 1561 1757 1752 1562 1757 1752 1547 1757 1752 1567 Q Serve(g_s), s 6.0 23.6 5.1 9.5 10.2 7.9 3.4 18.2 11.4 11.5 49.7 4.2 Cycle Q Clear(g_c), s 6.0 23.6 5.1 9.5 10.2 7.9 3.4 18.2 11.4 11.5 49.7 4.2 Prop In Lane 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 293 749 393 224 878 551 166 1572 820 421 1796 872 V/C Ratio(X) 0.37 0.85 0.19 0.72 0.36 0.23 0.49 0.44 0.29 0.68 0.84 0.12 Avail Cap(c_a), veh/h 293 826 428 224 955 586 177 1593 830 500 1953 942 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 40.6 51.4 40.0 38.8 42.1 31.1 27.2 25.7 17.8 18.2 28.3 14.3 Incr Delay (d2), s/veh 0.8 7.6 0.2 10.6 0.3 0.2 2.3 0.2 0.2 2.9 3.1 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.6 12.2 2.2 5.2 5.0 3.4 1.7 8.9 4.9 5.8 24.7 1.8 LnGrp Delay(d),s/veh 41.4 59.0 40.2 49.4 42.3 31.3 29.4 25.9 18.0 21.1 31.4 14.4 LnGrp LOS D E D D D C C C B C C B Approach Vol, veh/h 817 607 1000 1886 Approach Delay, s/veh 54.9 41.9 24.4 28.9 Approach LOS D D C C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 17.9 67.3 15.0 36.0 9.2 76.0 10.0 41.0 Change Period (Y+Rc), s 4.0 * 6.2 4.0 6.9 4.0 * 6.2 4.0 6.9 Max Green Setting (Gmax), s 20.0 * 62 11.0 32.1 6.0 * 76 6.0 37.1 Max Q Clear Time (g_c+I1), s 13.5 20.2 11.5 25.6 5.4 51.7 8.0 12.2 Green Ext Time (p_c), s 0.5 26.5 0.0 3.5 0.0 18.1 0.0 7.4 Intersection Summary HCM 2010 Ctrl Delay 34.6 HCM 2010 LOS C Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 2: 7th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 319 359 143 49 203 118 68 539 75 239 977 213 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 0.98 1.00 0.99 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 Adj Flow Rate, veh/h 399 449 179 61 254 148 85 674 94 299 1221 266 Adj No. of Lanes 1 1 1 1 2 1 1 2 1 1 2 1 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 497 570 553 200 503 415 191 1286 635 427 1564 1020 Arrive On Green 0.21 0.31 0.31 0.04 0.14 0.14 0.04 0.37 0.37 0.12 0.45 0.45 Sat Flow, veh/h 1757 1845 1565 1757 3505 1540 1757 3505 1559 1757 3505 1564 Grp Volume(v), veh/h 399 449 179 61 254 148 85 674 94 299 1221 266 Grp Sat Flow(s),veh/h/ln 1757 1845 1565 1757 1752 1540 1757 1752 1559 1757 1752 1564 Q Serve(g_s), s 21.9 26.2 9.8 3.5 7.9 9.2 3.5 17.8 4.5 11.9 34.9 8.4 Cycle Q Clear(g_c), s 21.9 26.2 9.8 3.5 7.9 9.2 3.5 17.8 4.5 11.9 34.9 8.4 Prop In Lane 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 497 570 553 200 503 415 191 1286 635 427 1564 1020 V/C Ratio(X) 0.80 0.79 0.32 0.31 0.50 0.36 0.44 0.52 0.15 0.70 0.78 0.26 Avail Cap(c_a), veh/h 523 737 695 219 806 548 218 1286 635 568 1781 1117 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 31.3 37.2 27.8 40.9 46.6 35.0 25.1 29.2 22.1 20.2 27.7 8.6 Incr Delay (d2), s/veh 8.5 4.3 0.3 0.9 0.8 0.5 1.6 0.4 0.1 2.5 2.0 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 11.7 14.0 4.3 1.7 3.9 4.0 1.8 8.7 1.9 6.0 17.2 3.7 LnGrp Delay(d),s/veh 39.8 41.5 28.2 41.7 47.4 35.5 26.8 29.6 22.2 22.6 29.8 8.7 LnGrp LOS D D C D D D C C C C C A Approach Vol, veh/h 1027 463 853 1786 Approach Delay, s/veh 38.5 42.8 28.5 25.4 Approach LOS D D C C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 17.5 50.0 7.7 42.5 8.2 59.4 27.2 23.0 Change Period (Y+Rc), s 3.0 * 6.8 3.0 6.1 3.0 * 6.8 3.0 6.1 Max Green Setting (Gmax), s 24.0 * 43 6.0 47.1 7.0 * 60 26.0 27.1 Max Q Clear Time (g_c+I1), s 13.9 19.8 5.5 28.2 5.5 36.9 23.9 11.2 Green Ext Time (p_c), s 0.6 15.9 0.0 5.4 0.0 15.7 0.3 5.0 Intersection Summary HCM 2010 Ctrl Delay 31.3 HCM 2010 LOS C Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 5: 27th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 64 566 51 19 304 39 24 85 59 40 77 70 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.99 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1863 1900 1845 1845 1900 1900 1863 1845 1900 1857 1863 Adj Flow Rate, veh/h 80 708 64 24 380 49 30 106 74 50 96 88 Adj No. of Lanes 0 2 0 1 2 0 0 1 1 0 1 1 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 2 2 2 3 3 3 2 2 3 2 2 2 Cap, veh/h 206 1178 104 362 1275 163 170 336 379 201 264 378 Arrive On Green 0.41 0.41 0.41 0.41 0.41 0.41 0.24 0.24 0.24 0.24 0.24 0.24 Sat Flow, veh/h 190 2886 255 687 3125 400 154 1389 1568 227 1093 1563 Grp Volume(v), veh/h 438 0 414 24 212 217 136 0 74 146 0 88 Grp Sat Flow(s),veh/h/ln 1681 0 1649 687 1752 1772 1543 0 1568 1320 0 1563 Q Serve(g_s), s 1.7 0.0 6.6 0.9 2.7 2.7 0.1 0.0 1.2 0.2 0.0 1.5 Cycle Q Clear(g_c), s 6.3 0.0 6.6 7.5 2.7 2.7 4.7 0.0 1.2 4.8 0.0 1.5 Prop In Lane 0.18 0.15 1.00 0.23 0.22 1.00 0.34 1.00 Lane Grp Cap(c), veh/h 815 0 673 362 715 723 506 0 379 465 0 378 V/C Ratio(X) 0.54 0.00 0.62 0.07 0.30 0.30 0.27 0.00 0.20 0.31 0.00 0.23 Avail Cap(c_a), veh/h 933 0 796 414 846 856 906 0 757 841 0 755 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 1.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 7.6 0.0 7.8 10.7 6.6 6.6 10.3 0.0 10.0 10.4 0.0 10.1 Incr Delay (d2), s/veh 0.6 0.0 1.1 0.1 0.2 0.2 0.3 0.0 0.2 0.4 0.0 0.3 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 3.2 0.0 3.1 0.2 1.3 1.4 1.1 0.0 0.6 1.1 0.0 0.7 LnGrp Delay(d),s/veh 8.2 0.0 8.8 10.8 6.8 6.8 10.6 0.0 10.2 10.8 0.0 10.4 LnGrp LOS A A B A A B B B B Approach Vol, veh/h 852 453 210 234 Approach Delay, s/veh 8.5 7.0 10.5 10.6 Approach LOS A A B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 14.1 19.1 14.1 19.1 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 16.0 16.0 16.0 16.0 Max Q Clear Time (g_c+I1), s 6.7 8.6 6.8 9.5 Green Ext Time (p_c), s 1.6 4.4 1.6 4.0 Intersection Summary HCM 2010 Ctrl Delay 8.6 HCM 2010 LOS A HCM 2010 Signalized Intersection Summary 11: Davis Lane & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 7 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 167 449 44 6 254 124 28 224 11 213 352 161 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1881 1881 1900 1900 1863 1863 1881 1880 1900 1863 1881 1900 Adj Flow Rate, veh/h 209 561 55 8 318 155 35 280 14 266 440 201 Adj No. of Lanes 1 2 0 0 2 1 1 2 0 1 2 0 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 1 1 1 2 2 2 1 1 1 2 1 1 Cap, veh/h 444 1186 116 98 1234 571 344 1259 63 503 869 393 Arrive On Green 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 0.36 Sat Flow, veh/h 926 3289 322 23 3421 1583 792 3464 172 1081 2391 1082 Grp Volume(v), veh/h 209 304 312 174 152 155 35 144 150 266 328 313 Grp Sat Flow(s),veh/h/ln 926 1787 1823 1833 1610 1583 792 1786 1850 1081 1787 1686 Q Serve(g_s), s 8.7 5.5 5.5 0.0 2.8 2.9 1.5 2.3 2.4 9.5 6.0 6.1 Cycle Q Clear(g_c), s 11.4 5.5 5.5 2.8 2.8 2.9 7.6 2.3 2.4 11.9 6.0 6.1 Prop In Lane 1.00 0.18 0.05 1.00 1.00 0.09 1.00 0.64 Lane Grp Cap(c), veh/h 444 644 658 750 581 571 344 649 673 503 650 613 V/C Ratio(X) 0.47 0.47 0.47 0.23 0.26 0.27 0.10 0.22 0.22 0.53 0.50 0.51 Avail Cap(c_a), veh/h 462 680 694 785 613 602 358 680 704 522 680 641 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 13.5 10.4 10.4 9.5 9.5 9.5 13.4 9.3 9.3 13.4 10.4 10.5 Incr Delay (d2), s/veh 0.8 0.5 0.5 0.2 0.2 0.3 0.1 0.2 0.2 0.9 0.6 0.7 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 2.3 2.8 2.9 1.4 1.3 1.3 0.3 1.2 1.2 2.9 3.0 2.9 LnGrp Delay(d),s/veh 14.3 10.9 10.9 9.6 9.7 9.8 13.6 9.4 9.4 14.3 11.0 11.1 LnGrp LOS B B B A A A B A A B B B Approach Vol, veh/h 825 481 329 907 Approach Delay, s/veh 11.8 9.7 9.9 12.0 Approach LOS B A A B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 21.3 20.8 21.3 20.8 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 16.0 16.0 16.0 16.0 Max Q Clear Time (g_c+I1), s 9.6 13.4 13.9 4.9 Green Ext Time (p_c), s 3.6 1.7 1.4 5.5 Intersection Summary HCM 2010 Ctrl Delay 11.2 HCM 2010 LOS B HCM 2010 Signalized Intersection Summary 13: Ferguson Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 8 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 5 254 9 332 130 17 1 30 308 41 67 11 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 0.99 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1881 1900 1900 1881 1900 1900 1881 1881 1900 1881 1900 Adj Flow Rate, veh/h 6 318 11 415 162 21 1 38 385 51 84 14 Adj No. of Lanes 0 2 0 0 2 0 0 1 1 0 1 0 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 1 1 1 1 1 1 1 1 1 1 1 1 Cap, veh/h 91 1259 43 484 545 71 88 686 579 246 366 52 Arrive On Green 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 Sat Flow, veh/h 16 3431 117 868 1485 193 8 1870 1578 369 997 142 Grp Volume(v), veh/h 176 0 159 415 0 183 39 0 385 149 0 0 Grp Sat Flow(s),veh/h/ln 1872 0 1691 868 0 1678 1878 0 1578 1508 0 0 Q Serve(g_s), s 0.0 0.0 2.9 13.1 0.0 3.4 0.0 0.0 8.9 0.0 0.0 0.0 Cycle Q Clear(g_c), s 2.9 0.0 2.9 16.0 0.0 3.4 0.6 0.0 8.9 2.4 0.0 0.0 Prop In Lane 0.03 0.07 1.00 0.11 0.03 1.00 0.34 0.09 Lane Grp Cap(c), veh/h 772 0 621 484 0 616 774 0 579 664 0 0 V/C Ratio(X) 0.23 0.00 0.26 0.86 0.00 0.30 0.05 0.00 0.67 0.22 0.00 0.00 Avail Cap(c_a), veh/h 772 0 621 484 0 616 774 0 579 664 0 0 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 0.00 Uniform Delay (d), s/veh 9.6 0.0 9.6 16.8 0.0 9.8 8.9 0.0 11.6 9.5 0.0 0.0 Incr Delay (d2), s/veh 0.1 0.0 0.2 14.3 0.0 0.3 0.1 0.0 5.9 0.8 0.0 0.0 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 1.5 0.0 1.4 6.8 0.0 1.6 0.3 0.0 4.8 1.3 0.0 0.0 LnGrp Delay(d),s/veh 9.8 0.0 9.9 31.0 0.0 10.1 9.0 0.0 17.5 10.3 0.0 0.0 LnGrp LOS A A C B A B B Approach Vol, veh/h 335 598 424 149 Approach Delay, s/veh 9.8 24.6 16.7 10.3 Approach LOS A C B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 22.0 21.6 22.0 21.6 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 16.0 16.0 16.0 16.0 Max Q Clear Time (g_c+I1), s 10.9 4.9 4.4 18.0 Green Ext Time (p_c), s 1.3 4.9 2.1 0.0 Intersection Summary HCM 2010 Ctrl Delay 17.7 HCM 2010 LOS B HCM 2010 Signalized Intersection Summary 16: Rouse Avenue & Oak Street/Birch Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 218 12 304 2 1 0 145 473 0 0 476 103 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1845 1845 1900 1845 1845 1845 1845 1900 1845 1845 1845 Adj Flow Rate, veh/h 272 15 380 2 1 0 181 591 0 0 595 129 Adj No. of Lanes 0 1 1 0 1 1 1 1 0 1 1 1 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 415 18 544 114 44 427 374 1107 0 85 869 737 Arrive On Green 0.27 0.27 0.27 0.27 0.27 0.00 0.08 0.60 0.00 0.00 0.47 0.47 Sat Flow, veh/h 1219 67 1562 160 160 1568 1757 1845 0 814 1845 1565 Grp Volume(v), veh/h 287 0 380 3 0 0 181 591 0 0 595 129 Grp Sat Flow(s),veh/h/ln 1286 0 1562 320 0 1568 1757 1845 0 814 1845 1565 Q Serve(g_s), s 0.0 0.0 17.8 0.0 0.0 0.0 4.2 16.0 0.0 0.0 21.4 4.0 Cycle Q Clear(g_c), s 18.3 0.0 17.8 18.4 0.0 0.0 4.2 16.0 0.0 0.0 21.4 4.0 Prop In Lane 0.95 1.00 0.67 1.00 1.00 0.00 1.00 1.00 Lane Grp Cap(c), veh/h 433 0 544 158 0 427 374 1107 0 85 869 737 V/C Ratio(X) 0.66 0.00 0.70 0.02 0.00 0.00 0.48 0.53 0.00 0.00 0.68 0.18 Avail Cap(c_a), veh/h 623 0 754 314 0 639 520 1520 0 200 1129 958 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 0.00 1.00 1.00 0.00 0.00 1.00 1.00 Uniform Delay (d), s/veh 29.1 0.0 23.9 24.3 0.0 0.0 13.1 10.0 0.0 0.0 17.5 13.0 Incr Delay (d2), s/veh 1.7 0.0 1.7 0.0 0.0 0.0 1.0 0.4 0.0 0.0 1.2 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 6.5 0.0 7.9 0.1 0.0 0.0 2.1 8.2 0.0 0.0 11.0 1.7 LnGrp Delay(d),s/veh 30.9 0.0 25.6 24.3 0.0 0.0 14.0 10.4 0.0 0.0 18.7 13.1 LnGrp LOS C C C B B B B Approach Vol, veh/h 667 3 772 724 Approach Delay, s/veh 27.9 24.3 11.2 17.7 Approach LOS C C B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 5 6 8 Phs Duration (G+Y+Rc), s 56.4 28.6 11.0 45.4 28.6 Change Period (Y+Rc), s 5.4 5.4 * 4.6 5.4 5.4 Max Green Setting (Gmax), s 70.0 34.6 * 13 52.0 34.6 Max Q Clear Time (g_c+I1), s 18.0 20.3 6.2 23.4 20.4 Green Ext Time (p_c), s 11.7 2.7 0.3 10.1 2.7 Intersection Summary HCM 2010 Ctrl Delay 18.5 HCM 2010 LOS B Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 20: 15th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 19 721 179 42 368 9 66 60 70 30 40 39 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 0.97 1.00 0.99 1.00 0.98 1.00 0.98 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1900 1845 1845 1900 1845 1845 1900 1845 1845 1900 Adj Flow Rate, veh/h 24 901 224 52 460 11 82 75 88 38 50 49 Adj No. of Lanes 1 2 0 1 2 0 1 1 0 1 1 0 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 592 1548 384 316 1957 47 345 159 186 290 175 172 Arrive On Green 0.56 0.56 0.56 0.56 0.56 0.56 0.21 0.21 0.21 0.21 0.21 0.21 Sat Flow, veh/h 908 2767 687 493 3498 84 1275 768 901 1204 849 832 Grp Volume(v), veh/h 24 570 555 52 230 241 82 0 163 38 0 99 Grp Sat Flow(s),veh/h/ln 908 1752 1702 493 1752 1829 1275 0 1669 1204 0 1682 Q Serve(g_s), s 0.7 10.5 10.6 3.8 3.3 3.3 2.9 0.0 4.3 1.4 0.0 2.5 Cycle Q Clear(g_c), s 4.0 10.5 10.6 14.4 3.3 3.3 5.3 0.0 4.3 5.7 0.0 2.5 Prop In Lane 1.00 0.40 1.00 0.05 1.00 0.54 1.00 0.49 Lane Grp Cap(c), veh/h 592 980 952 316 980 1023 345 0 345 290 0 347 V/C Ratio(X) 0.04 0.58 0.58 0.16 0.23 0.24 0.24 0.00 0.47 0.13 0.00 0.29 Avail Cap(c_a), veh/h 806 1394 1353 433 1394 1455 870 0 1031 785 0 1039 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 6.6 7.1 7.1 11.8 5.5 5.5 18.8 0.0 17.3 19.8 0.0 16.6 Incr Delay (d2), s/veh 0.0 0.5 0.6 0.2 0.1 0.1 0.4 0.0 1.0 0.2 0.0 0.4 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.2 5.1 5.1 0.5 1.6 1.7 1.0 0.0 2.0 0.5 0.0 1.2 LnGrp Delay(d),s/veh 6.6 7.7 7.7 12.1 5.7 5.7 19.2 0.0 18.3 20.0 0.0 17.0 LnGrp LOS A A A B A A B B B B Approach Vol, veh/h 1149 523 245 137 Approach Delay, s/veh 7.7 6.3 18.6 17.8 Approach LOS A A B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 16.2 33.3 16.2 33.3 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 30.6 39.4 30.6 39.4 Max Q Clear Time (g_c+I1), s 7.3 12.6 7.7 16.4 Green Ext Time (p_c), s 2.1 12.2 2.1 11.3 Intersection Summary HCM 2010 Ctrl Delay 9.3 HCM 2010 LOS A HCM 2010 Signalized Intersection Summary 23: 11th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 11 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 16 767 9 9 406 17 27 1 26 48 2 23 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 0.97 1.00 0.97 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1900 1845 1845 1900 1900 1845 1900 1845 1845 1900 Adj Flow Rate, veh/h 20 959 11 11 508 21 34 1 32 60 2 29 Adj No. of Lanes 1 2 0 1 2 0 0 1 0 1 1 0 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 589 1680 19 420 1623 67 262 3 63 429 11 158 Arrive On Green 0.47 0.47 0.47 0.47 0.47 0.47 0.11 0.11 0.11 0.11 0.11 0.11 Sat Flow, veh/h 860 3548 41 571 3426 141 616 28 589 1357 102 1481 Grp Volume(v), veh/h 20 474 496 11 259 270 67 0 0 60 0 31 Grp Sat Flow(s),veh/h/ln 860 1752 1836 571 1752 1815 1232 0 0 1357 0 1583 Q Serve(g_s), s 0.4 5.4 5.4 0.4 2.5 2.5 1.2 0.0 0.0 0.0 0.0 0.5 Cycle Q Clear(g_c), s 2.9 5.4 5.4 5.8 2.5 2.5 1.7 0.0 0.0 0.9 0.0 0.5 Prop In Lane 1.00 0.02 1.00 0.08 0.51 0.48 1.00 0.94 Lane Grp Cap(c), veh/h 589 830 870 420 830 860 328 0 0 429 0 169 V/C Ratio(X) 0.03 0.57 0.57 0.03 0.31 0.31 0.20 0.00 0.00 0.14 0.00 0.18 Avail Cap(c_a), veh/h 680 1015 1064 480 1015 1051 1017 0 0 1071 0 917 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 0.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 5.4 5.2 5.2 7.3 4.5 4.5 12.0 0.0 0.0 11.4 0.0 11.2 Incr Delay (d2), s/veh 0.0 0.6 0.6 0.0 0.2 0.2 0.3 0.0 0.0 0.1 0.0 0.5 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.1 2.6 2.8 0.1 1.2 1.2 0.5 0.0 0.0 0.4 0.0 0.2 LnGrp Delay(d),s/veh 5.4 5.9 5.8 7.4 4.7 4.7 12.3 0.0 0.0 11.6 0.0 11.8 LnGrp LOS A A A A A A B B B Approach Vol, veh/h 990 540 67 91 Approach Delay, s/veh 5.8 4.8 12.3 11.6 Approach LOS A A B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 8.9 18.7 8.9 18.7 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 16.0 16.0 16.0 16.0 Max Q Clear Time (g_c+I1), s 3.7 7.4 2.9 7.8 Green Ext Time (p_c), s 0.5 5.4 0.5 5.2 Intersection Summary HCM 2010 Ctrl Delay 6.1 HCM 2010 LOS A HCM 2010 Signalized Intersection Summary 38: Cottonwood Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 12 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 16 115 60 26 32 79 24 75 55 76 79 6 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1881 1900 1900 1881 1900 1881 1881 1900 1881 1881 1900 Adj Flow Rate, veh/h 20 144 75 32 40 99 30 94 69 95 99 8 Adj No. of Lanes 0 2 0 0 2 0 1 2 0 1 2 0 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 1 1 1 1 1 1 1 1 1 1 1 1 Cap, veh/h 217 487 243 323 279 334 624 532 360 589 873 70 Arrive On Green 0.23 0.23 0.23 0.23 0.23 0.23 0.26 0.26 0.26 0.26 0.26 0.26 Sat Flow, veh/h 151 2123 1058 413 1217 1455 1294 2043 1382 1230 3353 268 Grp Volume(v), veh/h 131 0 108 72 0 99 30 81 82 95 52 55 Grp Sat Flow(s),veh/h/ln 1806 0 1525 1630 0 1455 1294 1787 1637 1230 1787 1834 Q Serve(g_s), s 0.0 0.0 1.3 0.0 0.0 1.3 0.4 0.8 0.9 1.5 0.5 0.5 Cycle Q Clear(g_c), s 1.3 0.0 1.3 0.7 0.0 1.3 0.9 0.8 0.9 2.4 0.5 0.5 Prop In Lane 0.15 0.69 0.44 1.00 1.00 0.84 1.00 0.15 Lane Grp Cap(c), veh/h 597 0 350 603 0 334 624 465 426 589 465 478 V/C Ratio(X) 0.22 0.00 0.31 0.12 0.00 0.30 0.05 0.17 0.19 0.16 0.11 0.11 Avail Cap(c_a), veh/h 1810 0 1408 1630 0 1344 1937 2279 2088 1837 2279 2338 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 7.3 0.0 7.3 7.0 0.0 7.2 6.8 6.5 6.5 7.5 6.4 6.4 Incr Delay (d2), s/veh 0.2 0.0 0.5 0.1 0.0 0.5 0.0 0.2 0.2 0.1 0.1 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.7 0.0 0.6 0.4 0.0 0.5 0.1 0.4 0.4 0.5 0.3 0.3 LnGrp Delay(d),s/veh 7.4 0.0 7.8 7.1 0.0 7.7 6.8 6.7 6.8 7.6 6.5 6.5 LnGrp LOS A A A A A A A A A A Approach Vol, veh/h 239 171 193 202 Approach Delay, s/veh 7.6 7.5 6.7 7.0 Approach LOS A A A A Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 11.9 10.8 11.9 10.8 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 29.0 21.0 29.0 21.0 Max Q Clear Time (g_c+I1), s 2.9 3.3 4.4 3.3 Green Ext Time (p_c), s 2.1 2.3 2.1 2.3 Intersection Summary HCM 2010 Ctrl Delay 7.2 HCM 2010 LOS A HCM 2010 TWSC 5: 27th Avenue & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Intersection Int Delay, s/veh 37.6 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 64 566 51 19 304 39 24 85 59 40 77 70 Conflicting Peds, #/hr 0 0 3 3 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - 200 - - 300 - - 300 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 2 2 2 3 3 3 2 2 3 3 2 2 Mvmt Flow 80 708 64 24 380 49 30 106 74 50 96 88 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 429 0 0 771 0 0 1185 1375 389 1019 1383 217 Stage 1 - - - - - - 899 899 - 452 452 - Stage 2 - - - - - - 286 476 - 567 931 - Critical Hdwy 4.14 - - 4.16 - - 7.54 6.54 6.96 7.56 6.54 6.94 Critical Hdwy Stg 1 - - - - - - 6.54 5.54 - 6.56 5.54 - Critical Hdwy Stg 2 - - - - - - 6.54 5.54 - 6.56 5.54 - Follow-up Hdwy 2.22 - - 2.23 - - 3.52 4.02 3.33 3.53 4.02 3.32 Pot Cap-1 Maneuver 1127 - - 833 - - 144 144 607 190 143 787 Stage 1 - - - - - - 300 356 - 554 569 - Stage 2 - - - - - - 697 555 - 473 344 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1124 - - 831 - - 39 122 605 ~ 39 121 785 Mov Cap-2 Maneuver - - - - - - 39 122 - ~ 39 121 - Stage 1 - - - - - - 262 311 - 484 553 - Stage 2 - - - - - - 496 539 - 238 301 - Approach EB WB NB SB HCM Control Delay, s 1.1 0.5 134.2 155.5 HCM LOS F F Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 39 181 1124 - - 831 - - 39 203 HCM Lane V/C Ratio 0.769 0.994 0.071 - - 0.029 - - 1.282 0.905 HCM Control Delay (s) 231.5 118 8.4 0.4 - 9.5 - -$ 400.1 89 HCM Lane LOS F F A A - A - - F F HCM 95th %tile Q(veh) 2.8 8.2 0.2 - - 0.1 - - 5.1 7.2 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 11: Davis Lane & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Intersection Int Delay, s/veh 0.8 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 167 449 44 6 254 124 28 224 11 213 352 161 Conflicting Peds, #/hr 3 0 0 0 0 0 0 0 0 0 0 4 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - - - - 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 2 2 2 1 1 2 2 1 1 Mvmt Flow 209 561 55 8 318 155 35 280 14 266 440 201 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 477 0 0 616 0 0 1404 1498 308 1252 1448 243 Stage 1 - - - - - - 1006 1006 - 414 414 - Stage 2 - - - - - - 398 492 - 838 1034 - Critical Hdwy 4.12 - - 4.14 - - 7.52 6.52 6.94 7.54 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.54 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.54 5.52 - Follow-up Hdwy 2.21 - - 2.22 - - 3.51 4.01 3.32 3.52 4.01 3.31 Pot Cap-1 Maneuver 1089 - - 960 - - 100 ~ 122 688 ~ 129 ~ 131 761 Stage 1 - - - - - - 260 319 - 586 594 - Stage 2 - - - - - - 602 548 - 327 ~ 310 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1086 - - 960 - - - ~ 97 688 - ~ 104 757 Mov Cap-2 Maneuver - - - - - - - ~ 97 - - ~ 104 - Stage 1 - - - - - - 210 ~ 258 - 472 585 - Stage 2 - - - - - - 108 540 - - ~ 250 - Approach EB WB NB SB HCM Control Delay, s 2.3 0.2 HCM LOS - - Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) - 97 105 1086 - - 960 - - - 104 177 HCM Lane V/C Ratio - 1.443 1.464 0.192 - - 0.008 - - - 2.115 2.38 HCM Control Delay (s) -$ 326.4$ 326.8 9.1 - - 8.8 0.1 - -$ 600.3$ 679.6 HCM Lane LOS - F F A - - A A - - F F HCM 95th %tile Q(veh) - 10.4 11.2 0.7 - - 0 - - - 18.9 35 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 13: Ferguson Avenue & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Intersection Int Delay, s/veh 76.3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 5 254 9 332 130 17 1 30 308 41 67 11 Conflicting Peds, #/hr 0 0 0 0 0 0 1 0 0 0 0 1 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - 200 - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 6 318 11 415 162 21 1 38 385 51 84 14 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 185 0 0 330 0 0 1291 1352 165 1195 1346 93 Stage 1 - - - - - - 337 337 - 1004 1004 - Stage 2 - - - - - - 954 1015 - 191 342 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1394 - - 1234 - - 122 150 854 143 151 949 Stage 1 - - - - - - 654 642 - 261 320 - Stage 2 - - - - - - 280 316 - 795 639 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1394 - - 1234 - - 21 93 853 ~ 39 94 948 Mov Cap-2 Maneuver - - - - - - 21 93 - ~ 39 94 - Stage 1 - - - - - - 650 638 - 259 200 - Stage 2 - - - - - - 100 197 - 408 635 - Approach EB WB NB SB HCM Control Delay, s 0.1 6.6 18.8 $ 692.5 HCM LOS C F Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) 84 853 1394 - - 1234 - - 67 HCM Lane V/C Ratio 0.461 0.451 0.004 - - 0.336 - - 2.22 HCM Control Delay (s) 80.2 12.6 7.6 0 - 9.4 0.3 -$ 692.5 HCM Lane LOS F B A A - A A - F HCM 95th %tile Q(veh) 1.9 2.4 0 - - 1.5 - - 14.2 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 23: 11th Avenue & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Intersection Int Delay, s/veh 3.4 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 16 767 9 9 406 17 27 1 26 48 2 23 Conflicting Peds, #/hr 5 0 0 0 0 5 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - 500 - - - - - - - 100 Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 3 3 3 3 3 3 3 3 3 3 3 3 Mvmt Flow 20 959 11 11 508 21 34 1 32 60 2 29 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 529 0 0 970 0 0 1282 1555 490 1061 1551 269 Stage 1 - - - - - - 1004 1004 - 541 541 - Stage 2 - - - - - - 278 551 - 520 1010 - Critical Hdwy 4.16 - - 4.16 - - 7.56 6.56 6.96 7.56 6.56 6.96 Critical Hdwy Stg 1 - - - - - - 6.56 5.56 - 6.56 5.56 - Critical Hdwy Stg 2 - - - - - - 6.56 5.56 - 6.56 5.56 - Follow-up Hdwy 2.23 - - 2.23 - - 3.53 4.03 3.33 3.53 4.03 3.33 Pot Cap-1 Maneuver 1027 - - 700 - - 121 111 521 177 112 726 Stage 1 - - - - - - 257 316 - 490 516 - Stage 2 - - - - - - 702 511 - 505 313 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1023 - - 697 - - 111 107 519 159 108 723 Mov Cap-2 Maneuver - - - - - - 111 107 - 159 108 - Stage 1 - - - - - - 252 310 - 480 508 - Stage 2 - - - - - - 657 503 - 460 307 - Approach EB WB NB SB HCM Control Delay, s 0.2 0.2 37.1 32.5 HCM LOS E D Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 178 1023 - - 697 - - 156 723 HCM Lane V/C Ratio 0.379 0.02 - - 0.016 - - 0.401 0.04 HCM Control Delay (s) 37.1 8.6 - - 10.2 - - 42.7 10.2 HCM Lane LOS E A - - B - - E B HCM 95th %tile Q(veh) 1.6 0.1 - - 0 - - 1.7 0.1 HCM 2010 TWSC 26: Flanders Mill Road & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Intersection Int Delay, s/veh 3.4 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 7 229 9 9 129 8 3 26 26 10 51 10 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - - - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 9 286 11 11 161 10 4 32 32 12 64 12 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 171 0 0 298 0 0 444 503 149 366 504 86 Stage 1 - - - - - - 309 309 - 189 189 - Stage 2 - - - - - - 135 194 - 177 315 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1411 - - 1267 - - 500 472 874 568 471 959 Stage 1 - - - - - - 679 661 - 798 745 - Stage 2 - - - - - - 857 741 - 810 657 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1411 - - 1267 - - 435 464 874 511 463 959 Mov Cap-2 Maneuver - - - - - - 435 464 - 511 463 - Stage 1 - - - - - - 674 656 - 792 738 - Stage 2 - - - - - - 765 734 - 735 652 - Approach EB WB NB SB HCM Control Delay, s 0.2 0.5 11.9 13.6 HCM LOS B B Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) 593 1411 - - 1267 - - 507 HCM Lane V/C Ratio 0.116 0.006 - - 0.009 - - 0.175 HCM Control Delay (s) 11.9 7.6 0 - 7.9 0 - 13.6 HCM Lane LOS B A A - A A - B HCM 95th %tile Q(veh) 0.4 0 - - 0 - - 0.6 HCM 2010 TWSC 38: Cottonwood Road & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane AM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 11 Intersection Int Delay, s/veh 6.8 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 16 115 60 26 32 79 24 75 55 76 79 6 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 20 144 75 32 40 99 30 94 69 95 99 8 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 139 0 0 219 0 0 355 425 109 313 413 69 Stage 1 - - - - - - 221 221 - 154 154 - Stage 2 - - - - - - 134 204 - 159 259 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1450 - - 1355 - - 578 522 927 619 530 983 Stage 1 - - - - - - 764 722 - 836 771 - Stage 2 - - - - - - 858 734 - 830 695 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1450 - - 1355 - - 472 500 927 475 507 983 Mov Cap-2 Maneuver - - - - - - 472 500 - 475 507 - Stage 1 - - - - - - 752 710 - 823 750 - Stage 2 - - - - - - 719 714 - 656 684 - Approach EB WB NB SB HCM Control Delay, s 0.6 1.5 12 13.5 HCM LOS B B Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) 472 500 689 1450 - - 1355 - - 475 507 542 HCM Lane V/C Ratio 0.064 0.094 0.168 0.014 - - 0.024 - - 0.2 0.097 0.105 HCM Control Delay (s) 13.1 12.9 11.3 7.5 0 - 7.7 0 - 14.5 12.9 12.4 HCM Lane LOS B B B A A - A A - B B B HCM 95th %tile Q(veh) 0.2 0.3 0.6 0 - - 0.1 - - 0.7 0.3 0.4 Queues 1: 19th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 237 388 78 298 672 272 159 1419 263 180 1060 131 v/c Ratio 0.93 0.52 0.15 0.81 0.91 0.48 0.60 0.90 0.28 0.95 0.68 0.13 Control Delay 78.8 53.0 10.1 54.8 71.9 33.2 24.5 45.4 8.8 89.9 34.2 4.6 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 78.8 53.0 10.1 54.8 71.9 33.2 24.5 45.4 8.8 89.9 34.2 4.6 Queue Length 50th (ft) 169 173 8 215 331 164 68 638 65 118 409 14 Queue Length 95th (ft) #344 228 44 #347 #439 255 106 747 113 #282 503 44 Internal Link Dist (ft) 2554 1350 615 420 Turn Bay Length (ft) 200 200 250 250 425 425 285 285 Base Capacity (vph) 254 771 566 366 771 565 297 1658 950 190 1607 982 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.93 0.50 0.14 0.81 0.87 0.48 0.54 0.86 0.28 0.95 0.66 0.13 Intersection Summary # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 2: 7th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 2 Lane Group EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Group Flow (vph) 291 379 196 172 484 270 222 1276 178 246 1036 418 v/c Ratio 0.90 0.85 0.32 0.77 0.77 0.47 0.71 0.89 0.21 0.86 0.68 0.43 Control Delay 64.2 65.5 20.3 57.1 59.8 25.6 27.6 45.0 7.2 60.7 32.7 10.7 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 64.2 65.5 20.3 57.1 59.8 25.6 27.6 45.0 7.2 60.7 32.7 10.7 Queue Length 50th (ft) 200 323 83 109 216 128 86 540 28 156 371 121 Queue Length 95th (ft) #348 #475 138 #167 280 210 149 654 68 #310 479 209 Internal Link Dist (ft) 1263 708 420 420 Turn Bay Length (ft) 250 300 300 175 175 125 125 Base Capacity (vph) 325 512 657 223 752 588 365 1590 834 306 1639 983 Starvation Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.90 0.74 0.30 0.77 0.64 0.46 0.61 0.80 0.21 0.80 0.63 0.43 Intersection Summary # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 5: 27th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Lane Group EBT WBL WBT NBT NBR SBT SBR Lane Group Flow (vph) 487 94 770 128 51 108 141 v/c Ratio 0.32 0.20 0.42 0.26 0.10 0.23 0.27 Control Delay 7.3 8.5 7.6 12.4 3.8 12.3 6.8 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 7.3 8.5 7.6 12.4 3.8 12.3 6.8 Queue Length 50th (ft) 27 10 45 19 0 16 7 Queue Length 95th (ft) 60 35 93 49 13 43 35 Internal Link Dist (ft) 2533 2554 420 420 Turn Bay Length (ft) 200 300 300 Base Capacity (vph) 1654 502 1993 993 928 928 936 Starvation Cap Reductn 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 Reduced v/c Ratio 0.29 0.19 0.39 0.13 0.05 0.12 0.15 Intersection Summary Queues 11: Davis Lane & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Lane Group EBL EBT WBT WBR NBL NBT SBL SBT Lane Group Flow (vph) 189 369 582 190 71 383 100 413 v/c Ratio 0.58 0.26 0.46 0.25 0.27 0.39 0.37 0.39 Control Delay 17.6 7.7 9.7 2.6 15.9 13.2 17.7 8.2 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 17.6 7.7 9.7 2.6 15.9 13.2 17.7 8.2 Queue Length 50th (ft) 27 22 40 0 11 30 16 17 Queue Length 95th (ft) 92 54 94 26 46 82 62 60 Internal Link Dist (ft) 2585 2533 510 433 Turn Bay Length (ft) 500 200 200 200 Base Capacity (vph) 628 2729 2459 1265 531 1966 542 1916 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.30 0.14 0.24 0.15 0.13 0.19 0.18 0.22 Intersection Summary Queues 13: Ferguson Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Lane Group EBT WBT NBT NBR SBT Lane Group Flow (vph) 236 934 100 386 154 v/c Ratio 0.16 1.04dl 0.22 0.57 0.38 Control Delay 7.5 21.4 11.7 5.3 12.4 Queue Delay 0.0 0.0 0.0 0.0 0.0 Total Delay 7.5 21.4 11.7 5.3 12.4 Queue Length 50th (ft) 12 72 16 0 21 Queue Length 95th (ft) 32 #188 33 26 44 Internal Link Dist (ft) 1220 2585 420 333 Turn Bay Length (ft) 200 Base Capacity (vph) 1448 1107 820 908 702 Starvation Cap Reductn 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 Reduced v/c Ratio 0.16 0.84 0.12 0.43 0.22 Intersection Summary # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. dl Defacto Left Lane. Recode with 1 though lane as a left lane. Queues 16: Rouse Avenue & Oak Street/Birch Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 7 Lane Group EBT EBR WBR NBL NBT SBL SBT SBR Lane Group Flow (vph) 213 290 1 289 569 1 693 213 v/c Ratio 0.77 0.39 0.00 0.67 0.45 0.00 0.78 0.27 Control Delay 57.2 10.1 0.0 18.0 8.7 15.0 29.5 10.2 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 57.2 10.1 0.0 18.0 8.7 15.0 29.5 10.2 Queue Length 50th (ft) 117 42 0 57 140 0 352 41 Queue Length 95th (ft) #238 122 0 161 243 3 575 97 Internal Link Dist (ft) 835 425 421 Turn Bay Length (ft) 225 50 240 100 100 Base Capacity (vph) 380 801 687 495 1545 497 1105 955 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.56 0.36 0.00 0.58 0.37 0.00 0.63 0.22 Intersection Summary # 95th percentile volume exceeds capacity, queue may be longer. Queue shown is maximum after two cycles. Queues 20: 15th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 8 Lane Group EBL EBT WBL WBT NBL NBT SBL SBT Lane Group Flow (vph) 24 900 71 1159 301 205 48 108 v/c Ratio 0.19 0.57 0.34 0.73 0.70 0.32 0.12 0.18 Control Delay 16.9 14.3 18.4 17.5 28.1 9.6 15.9 11.6 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 16.9 14.3 18.4 17.5 28.1 9.6 15.9 11.6 Queue Length 50th (ft) 5 116 16 170 94 24 12 18 Queue Length 95th (ft) 21 186 48 263 170 60 32 46 Internal Link Dist (ft) 1350 1310 357 332 Turn Bay Length (ft) 125 125 125 125 Base Capacity (vph) 179 2267 300 2299 724 994 664 979 Starvation Cap Reductn 0 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 0 Reduced v/c Ratio 0.13 0.40 0.24 0.50 0.42 0.21 0.07 0.11 Intersection Summary Queues 23: 11th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Lane Group EBL EBT WBL WBT NBT SBL SBT Lane Group Flow (vph) 31 840 38 1034 41 53 63 v/c Ratio 0.09 0.36 0.09 0.44 0.10 0.11 0.14 Control Delay 6.9 5.8 6.6 6.5 3.2 11.4 9.0 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 6.9 5.8 6.6 6.5 3.2 11.4 9.0 Queue Length 50th (ft) 3 48 3 65 0 8 6 Queue Length 95th (ft) 14 91 15 120 10 25 24 Internal Link Dist (ft) 1310 1263 471 383 Turn Bay Length (ft) 500 500 100 Base Capacity (vph) 327 2277 405 2286 941 1206 1039 Starvation Cap Reductn 0 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 0 Reduced v/c Ratio 0.09 0.37 0.09 0.45 0.04 0.04 0.06 Intersection Summary Queues 38: Cottonwood Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Lane Group EBT WBT NBL NBT SBL SBT Lane Group Flow (vph) 121 293 80 179 63 56 v/c Ratio 0.12 0.30 0.19 0.16 0.15 0.05 Control Delay 6.9 6.2 8.8 6.2 8.4 6.1 Queue Delay 0.0 0.0 0.0 0.0 0.0 0.0 Total Delay 6.9 6.2 8.8 6.2 8.4 6.1 Queue Length 50th (ft) 4 10 8 6 6 2 Queue Length 95th (ft) 15 27 24 18 20 8 Internal Link Dist (ft) 418 1316 424 422 Turn Bay Length (ft) 200 200 Base Capacity (vph) 2859 2678 1368 3446 1368 3438 Starvation Cap Reductn 0 0 0 0 0 0 Spillback Cap Reductn 0 0 0 0 0 0 Storage Cap Reductn 0 0 0 0 0 0 Reduced v/c Ratio 0.04 0.11 0.06 0.05 0.05 0.02 Intersection Summary HCM 2010 Signalized Intersection Summary 1: 19th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 213 349 70 268 605 245 143 1277 237 162 954 118 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 0.99 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 Adj Flow Rate, veh/h 237 388 78 298 672 272 159 1419 263 180 1060 131 Adj No. of Lanes 1 2 1 1 2 1 1 2 1 1 2 1 Peak Hour Factor 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 264 747 432 354 747 448 268 1586 877 202 1621 901 Arrive On Green 0.11 0.21 0.21 0.11 0.21 0.21 0.06 0.45 0.45 0.07 0.46 0.46 Sat Flow, veh/h 1757 3505 1561 1757 3505 1561 1757 3505 1547 1757 3505 1567 Grp Volume(v), veh/h 237 388 78 298 672 272 159 1419 263 180 1060 131 Grp Sat Flow(s),veh/h/ln 1757 1752 1561 1757 1752 1561 1757 1752 1547 1757 1752 1567 Q Serve(g_s), s 14.9 13.9 5.4 16.0 26.5 21.4 6.8 52.9 12.7 8.4 33.1 5.5 Cycle Q Clear(g_c), s 14.9 13.9 5.4 16.0 26.5 21.4 6.8 52.9 12.7 8.4 33.1 5.5 Prop In Lane 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 264 747 432 354 747 448 268 1586 877 202 1621 901 V/C Ratio(X) 0.90 0.52 0.18 0.84 0.90 0.61 0.59 0.89 0.30 0.89 0.65 0.15 Avail Cap(c_a), veh/h 264 767 441 354 767 456 330 1649 905 210 1621 901 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 40.5 49.5 39.2 42.8 54.4 43.8 23.7 35.8 16.2 34.8 29.4 14.0 Incr Delay (d2), s/veh 30.3 0.6 0.2 16.6 13.4 2.3 2.1 6.6 0.2 33.3 1.0 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 9.4 6.8 2.4 5.4 14.3 9.5 3.4 27.1 5.4 8.9 16.3 2.4 LnGrp Delay(d),s/veh 70.8 50.1 39.4 59.4 67.8 46.1 25.8 42.4 16.4 68.1 30.4 14.1 LnGrp LOS E D D E E D C D B E C B Approach Vol, veh/h 703 1242 1841 1371 Approach Delay, s/veh 55.9 61.0 37.2 33.8 Approach LOS E E D C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 14.4 70.5 20.0 37.2 13.0 71.9 20.0 37.2 Change Period (Y+Rc), s 4.0 * 6.2 4.0 6.9 4.0 * 6.2 4.0 6.9 Max Green Setting (Gmax), s 11.0 * 67 16.0 31.1 14.0 * 64 16.0 31.1 Max Q Clear Time (g_c+I1), s 10.4 54.9 18.0 15.9 8.8 35.1 16.9 28.5 Green Ext Time (p_c), s 0.0 9.4 0.0 7.0 0.2 22.8 0.0 1.8 Intersection Summary HCM 2010 Ctrl Delay 44.6 HCM 2010 LOS D Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 2: 7th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 262 341 176 155 436 243 200 1148 160 221 932 376 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 0.98 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 1845 Adj Flow Rate, veh/h 291 379 196 172 484 270 222 1276 178 246 1036 418 Adj No. of Lanes 1 1 1 1 2 1 1 2 1 1 2 1 Peak Hour Factor 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 328 467 533 226 672 456 285 1509 780 273 1562 901 Arrive On Green 0.13 0.25 0.25 0.07 0.19 0.19 0.09 0.43 0.43 0.10 0.45 0.45 Sat Flow, veh/h 1757 1845 1564 1757 3505 1543 1757 3505 1561 1757 3505 1564 Grp Volume(v), veh/h 291 379 196 172 484 270 222 1276 178 246 1036 418 Grp Sat Flow(s),veh/h/ln 1757 1845 1564 1757 1752 1543 1757 1752 1561 1757 1752 1564 Q Serve(g_s), s 17.0 25.2 12.3 9.0 16.9 19.5 9.1 42.5 8.4 11.0 30.4 20.2 Cycle Q Clear(g_c), s 17.0 25.2 12.3 9.0 16.9 19.5 9.1 42.5 8.4 11.0 30.4 20.2 Prop In Lane 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Lane Grp Cap(c), veh/h 328 467 533 226 672 456 285 1509 780 273 1562 901 V/C Ratio(X) 0.89 0.81 0.37 0.76 0.72 0.59 0.78 0.85 0.23 0.90 0.66 0.46 Avail Cap(c_a), veh/h 328 499 560 226 733 483 361 1550 798 335 1577 908 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 36.7 45.8 32.4 43.3 49.4 39.4 24.6 33.3 18.4 31.7 28.5 16.0 Incr Delay (d2), s/veh 24.2 9.3 0.4 14.0 3.1 1.7 8.1 4.4 0.1 23.2 1.0 0.4 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 10.4 14.1 5.4 2.7 8.5 8.6 5.0 21.5 3.7 10.5 14.9 8.7 LnGrp Delay(d),s/veh 60.9 55.1 32.9 57.3 52.6 41.1 32.7 37.7 18.6 54.9 29.5 16.4 LnGrp LOS E E C E D D C D B D C B Approach Vol, veh/h 866 926 1676 1700 Approach Delay, s/veh 52.0 50.1 35.0 30.0 Approach LOS D D C C Timer 1 2 3 4 5 6 7 8 Assigned Phs 1 2 3 4 5 6 7 8 Phs Duration (G+Y+Rc), s 16.4 63.0 12.0 39.1 14.4 64.9 20.0 31.1 Change Period (Y+Rc), s 3.0 * 6.8 3.0 6.1 3.0 * 6.8 3.0 6.1 Max Green Setting (Gmax), s 18.0 * 58 9.0 35.3 17.0 * 59 17.0 27.3 Max Q Clear Time (g_c+I1), s 13.0 44.5 11.0 27.2 11.1 32.4 19.0 21.5 Green Ext Time (p_c), s 0.3 11.7 0.0 4.3 0.3 21.3 0.0 3.3 Intersection Summary HCM 2010 Ctrl Delay 38.9 HCM 2010 LOS D Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 5: 27th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 46 366 26 85 614 79 16 99 46 25 72 127 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.99 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1863 1900 1845 1845 1900 1900 1863 1845 1900 1858 1863 Adj Flow Rate, veh/h 51 407 29 94 682 88 18 110 51 28 80 141 Adj No. of Lanes 0 2 0 1 2 0 0 1 1 0 1 1 Peak Hour Factor 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 Percent Heavy Veh, % 2 2 2 3 3 3 2 2 3 2 2 2 Cap, veh/h 209 1210 84 539 1299 167 163 323 307 202 286 306 Arrive On Green 0.42 0.42 0.42 0.42 0.42 0.42 0.20 0.20 0.20 0.20 0.20 0.20 Sat Flow, veh/h 154 2909 201 938 3122 402 131 1651 1568 258 1464 1563 Grp Volume(v), veh/h 248 0 239 94 383 387 128 0 51 108 0 141 Grp Sat Flow(s),veh/h/ln 1605 0 1659 938 1752 1772 1782 0 1568 1722 0 1563 Q Serve(g_s), s 0.0 0.0 2.9 2.3 4.9 4.9 0.0 0.0 0.8 0.0 0.0 2.4 Cycle Q Clear(g_c), s 2.7 0.0 2.9 5.2 4.9 4.9 1.8 0.0 0.8 1.5 0.0 2.4 Prop In Lane 0.21 0.12 1.00 0.23 0.14 1.00 0.26 1.00 Lane Grp Cap(c), veh/h 813 0 690 539 729 737 486 0 307 489 0 306 V/C Ratio(X) 0.30 0.00 0.35 0.17 0.52 0.53 0.26 0.00 0.17 0.22 0.00 0.46 Avail Cap(c_a), veh/h 978 0 888 651 938 949 1069 0 840 1044 0 837 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 1.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 5.9 0.0 6.0 7.7 6.5 6.5 10.4 0.0 10.0 10.3 0.0 10.6 Incr Delay (d2), s/veh 0.2 0.0 0.3 0.2 0.6 0.6 0.3 0.0 0.3 0.2 0.0 1.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 1.4 0.0 1.4 0.6 2.5 2.5 0.9 0.0 0.4 0.8 0.0 1.1 LnGrp Delay(d),s/veh 6.1 0.0 6.2 7.9 7.1 7.1 10.7 0.0 10.2 10.5 0.0 11.7 LnGrp LOS A A A A A B B B B Approach Vol, veh/h 487 864 179 249 Approach Delay, s/veh 6.2 7.2 10.5 11.2 Approach LOS A A B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 11.8 18.0 11.8 18.0 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 16.0 16.0 16.0 16.0 Max Q Clear Time (g_c+I1), s 3.8 4.9 4.4 7.2 Green Ext Time (p_c), s 1.7 6.0 1.6 5.1 Intersection Summary HCM 2010 Ctrl Delay 7.8 HCM 2010 LOS A HCM 2010 Signalized Intersection Summary 11: Davis Lane & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 7 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 170 304 28 40 484 171 64 321 23 90 203 168 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1881 1881 1900 1900 1863 1863 1881 1880 1900 1863 1881 1900 Adj Flow Rate, veh/h 189 338 31 44 538 190 71 357 26 100 226 187 Adj No. of Lanes 1 2 0 0 2 1 1 2 0 1 2 0 Peak Hour Factor 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 Percent Heavy Veh, % 1 1 1 2 2 2 1 1 1 2 1 1 Cap, veh/h 413 1579 144 149 1534 755 330 982 71 350 552 436 Arrive On Green 0.48 0.48 0.48 0.48 0.48 0.48 0.29 0.29 0.29 0.29 0.29 0.29 Sat Flow, veh/h 731 3312 302 139 3217 1583 977 3378 245 996 1897 1499 Grp Volume(v), veh/h 189 181 188 305 277 190 71 188 195 100 212 201 Grp Sat Flow(s),veh/h/ln 731 1787 1827 1745 1610 1583 977 1786 1837 996 1787 1609 Q Serve(g_s), s 11.0 3.0 3.0 0.0 5.4 3.6 3.2 4.2 4.2 4.4 4.8 5.0 Cycle Q Clear(g_c), s 16.4 3.0 3.0 5.1 5.4 3.6 8.2 4.2 4.2 8.6 4.8 5.0 Prop In Lane 1.00 0.17 0.14 1.00 1.00 0.13 1.00 0.93 Lane Grp Cap(c), veh/h 413 852 871 915 768 755 330 519 534 350 520 468 V/C Ratio(X) 0.46 0.21 0.22 0.33 0.36 0.25 0.22 0.36 0.37 0.29 0.41 0.43 Avail Cap(c_a), veh/h 481 1017 1040 1068 916 901 437 716 736 459 716 645 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 13.4 7.6 7.6 8.2 8.3 7.8 17.7 14.0 14.0 17.5 14.2 14.3 Incr Delay (d2), s/veh 0.8 0.1 0.1 0.2 0.3 0.2 0.3 0.4 0.4 0.4 0.5 0.6 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 2.3 1.5 1.5 2.7 2.4 1.6 0.9 2.1 2.2 1.3 2.4 2.3 LnGrp Delay(d),s/veh 14.2 7.7 7.7 8.4 8.5 7.9 18.0 14.5 14.5 17.9 14.8 15.0 LnGrp LOS B A A A A A B B B B B B Approach Vol, veh/h 558 772 454 513 Approach Delay, s/veh 9.9 8.3 15.0 15.5 Approach LOS A A B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 20.5 29.4 20.5 29.4 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 20.0 28.4 20.0 28.4 Max Q Clear Time (g_c+I1), s 10.2 18.4 10.6 7.4 Green Ext Time (p_c), s 4.0 5.4 3.9 8.2 Intersection Summary HCM 2010 Ctrl Delay 11.6 HCM 2010 LOS B HCM 2010 Signalized Intersection Summary 13: Ferguson Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 8 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 5 179 5 420 283 44 1 79 309 39 64 20 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 0.99 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1881 1900 1900 1881 1900 1900 1881 1881 1900 1881 1900 Adj Flow Rate, veh/h 6 224 6 525 354 55 1 99 386 49 80 25 Adj No. of Lanes 0 2 0 0 2 0 0 1 1 0 1 0 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 1 1 1 1 1 1 1 1 1 1 1 1 Cap, veh/h 103 1377 36 593 578 90 92 583 490 212 302 77 Arrive On Green 0.40 0.40 0.40 0.40 0.40 0.40 0.31 0.31 0.31 0.31 0.31 0.31 Sat Flow, veh/h 21 3446 91 1034 1447 225 4 1876 1577 302 971 247 Grp Volume(v), veh/h 124 0 112 525 0 409 100 0 386 154 0 0 Grp Sat Flow(s),veh/h/ln 1862 0 1696 1034 0 1672 1880 0 1577 1519 0 0 Q Serve(g_s), s 0.0 0.0 1.7 14.3 0.0 7.8 0.0 0.0 8.9 0.0 0.0 0.0 Cycle Q Clear(g_c), s 1.7 0.0 1.7 16.0 0.0 7.8 1.5 0.0 8.9 2.5 0.0 0.0 Prop In Lane 0.05 0.05 1.00 0.13 0.01 1.00 0.32 0.16 Lane Grp Cap(c), veh/h 838 0 678 593 0 668 675 0 490 591 0 0 V/C Ratio(X) 0.15 0.00 0.17 0.89 0.00 0.61 0.15 0.00 0.79 0.26 0.00 0.00 Avail Cap(c_a), veh/h 838 0 678 593 0 668 841 0 630 713 0 0 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 1.00 0.00 0.00 Uniform Delay (d), s/veh 7.7 0.0 7.7 14.4 0.0 9.6 10.0 0.0 12.6 10.4 0.0 0.0 Incr Delay (d2), s/veh 0.1 0.0 0.1 14.9 0.0 1.7 0.1 0.0 5.1 0.2 0.0 0.0 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.9 0.0 0.8 8.1 0.0 3.8 0.8 0.0 4.6 1.3 0.0 0.0 LnGrp Delay(d),s/veh 7.8 0.0 7.8 29.3 0.0 11.2 10.1 0.0 17.7 10.6 0.0 0.0 LnGrp LOS A A C B B B B Approach Vol, veh/h 236 934 486 154 Approach Delay, s/veh 7.8 21.4 16.1 10.6 Approach LOS A C B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 18.4 21.6 18.4 21.6 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 16.0 16.0 16.0 16.0 Max Q Clear Time (g_c+I1), s 10.9 3.7 4.5 18.0 Green Ext Time (p_c), s 1.5 6.5 2.5 0.0 Intersection Summary HCM 2010 Ctrl Delay 17.3 HCM 2010 LOS B HCM 2010 Signalized Intersection Summary 16: Rouse Avenue & Oak Street/Birch Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 192 0 261 0 0 1 260 512 0 1 624 192 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1845 1845 1900 1845 1845 1845 1845 1900 1845 1845 1845 Adj Flow Rate, veh/h 213 0 290 0 0 1 289 569 0 1 693 213 Adj No. of Lanes 0 1 1 0 1 1 1 1 0 1 1 1 Peak Hour Factor 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 377 0 490 0 383 324 392 1215 0 501 914 776 Arrive On Green 0.21 0.00 0.21 0.00 0.00 0.21 0.11 0.66 0.00 0.50 0.50 0.50 Sat Flow, veh/h 1390 0 1560 0 1845 1560 1757 1845 0 830 1845 1565 Grp Volume(v), veh/h 213 0 290 0 0 1 289 569 0 1 693 213 Grp Sat Flow(s),veh/h/ln 1390 0 1560 0 1845 1560 1757 1845 0 830 1845 1565 Q Serve(g_s), s 11.6 0.0 12.6 0.0 0.0 0.0 5.9 12.3 0.0 0.0 24.5 6.4 Cycle Q Clear(g_c), s 11.6 0.0 12.6 0.0 0.0 0.0 5.9 12.3 0.0 0.0 24.5 6.4 Prop In Lane 1.00 1.00 0.00 1.00 1.00 0.00 1.00 1.00 Lane Grp Cap(c), veh/h 377 0 490 0 383 324 392 1215 0 501 914 776 V/C Ratio(X) 0.56 0.00 0.59 0.00 0.00 0.00 0.74 0.47 0.00 0.00 0.76 0.27 Avail Cap(c_a), veh/h 530 0 661 0 585 495 607 1806 0 665 1280 1086 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 0.00 0.00 1.00 1.00 1.00 0.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 29.9 0.0 23.4 0.0 0.0 25.4 14.5 6.8 0.0 10.3 16.4 11.9 Incr Delay (d2), s/veh 1.3 0.0 1.1 0.0 0.0 0.0 2.7 0.3 0.0 0.0 1.7 0.2 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 4.6 0.0 5.6 0.0 0.0 0.0 3.7 6.3 0.0 0.0 12.8 2.8 LnGrp Delay(d),s/veh 31.3 0.0 24.5 0.0 0.0 25.4 17.2 7.1 0.0 10.3 18.1 12.1 LnGrp LOS C C C B A B B B Approach Vol, veh/h 503 1 858 907 Approach Delay, s/veh 27.4 25.4 10.5 16.7 Approach LOS C C B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 5 6 8 Phs Duration (G+Y+Rc), s 58.6 22.1 13.2 45.4 22.1 Change Period (Y+Rc), s 5.4 5.4 * 4.6 5.4 5.4 Max Green Setting (Gmax), s 79.0 25.6 * 18 56.0 25.6 Max Q Clear Time (g_c+I1), s 14.3 14.6 7.9 26.5 2.0 Green Ext Time (p_c), s 14.1 1.7 0.6 11.7 2.2 Intersection Summary HCM 2010 Ctrl Delay 16.7 HCM 2010 LOS B Notes * HCM 2010 computational engine requires equal clearance times for the phases crossing the barrier. HCM 2010 Signalized Intersection Summary 20: 15th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 19 637 83 57 913 14 241 60 104 38 40 46 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 0.97 1.00 0.99 1.00 0.99 1.00 0.99 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1900 1845 1845 1900 1845 1845 1900 1845 1845 1900 Adj Flow Rate, veh/h 24 796 104 71 1141 18 301 75 130 48 50 58 Adj No. of Lanes 1 2 0 1 2 0 1 1 0 1 1 0 Peak Hour Factor 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 0.80 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 223 1511 197 296 1718 27 481 205 355 393 263 306 Arrive On Green 0.49 0.49 0.49 0.49 0.49 0.49 0.34 0.34 0.34 0.34 0.34 0.34 Sat Flow, veh/h 478 3107 406 610 3531 56 1266 601 1042 1160 774 897 Grp Volume(v), veh/h 24 449 451 71 566 593 301 0 205 48 0 108 Grp Sat Flow(s),veh/h/ln 478 1752 1760 610 1752 1834 1266 0 1643 1160 0 1671 Q Serve(g_s), s 2.7 11.9 11.9 6.1 16.4 16.4 14.7 0.0 6.3 2.2 0.0 3.1 Cycle Q Clear(g_c), s 19.1 11.9 11.9 18.0 16.4 16.4 17.8 0.0 6.3 8.5 0.0 3.1 Prop In Lane 1.00 0.23 1.00 0.03 1.00 0.63 1.00 0.54 Lane Grp Cap(c), veh/h 223 852 856 296 852 892 481 0 559 393 0 569 V/C Ratio(X) 0.11 0.53 0.53 0.24 0.66 0.66 0.63 0.00 0.37 0.12 0.00 0.19 Avail Cap(c_a), veh/h 257 978 982 340 978 1023 665 0 799 562 0 813 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 1.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 20.3 11.9 11.9 18.1 13.1 13.1 21.9 0.0 16.7 19.9 0.0 15.6 Incr Delay (d2), s/veh 0.2 0.5 0.5 0.4 1.4 1.3 1.3 0.0 0.4 0.1 0.0 0.2 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.4 5.9 5.9 1.1 8.2 8.6 5.3 0.0 2.9 0.7 0.0 1.4 LnGrp Delay(d),s/veh 20.5 12.4 12.4 18.5 14.5 14.4 23.2 0.0 17.1 20.0 0.0 15.7 LnGrp LOS C B B B B B C B B B Approach Vol, veh/h 924 1230 506 156 Approach Delay, s/veh 12.6 14.7 20.7 17.1 Approach LOS B B C B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 28.8 38.2 28.8 38.2 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 32.6 37.4 32.6 37.4 Max Q Clear Time (g_c+I1), s 19.8 21.1 10.5 20.0 Green Ext Time (p_c), s 2.8 11.5 3.4 12.1 Intersection Summary HCM 2010 Ctrl Delay 15.2 HCM 2010 LOS B HCM 2010 Signalized Intersection Summary 23: 11th Avenue & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 11 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 28 720 36 34 915 15 17 0 20 48 2 55 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 0.97 1.00 0.97 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1845 1845 1900 1845 1845 1900 1900 1845 1900 1845 1845 1900 Adj Flow Rate, veh/h 31 800 40 38 1017 17 19 0 22 53 2 61 Adj No. of Lanes 1 2 0 1 2 0 0 1 0 1 1 0 Peak Hour Factor 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 Percent Heavy Veh, % 3 3 3 3 3 3 3 3 3 3 3 3 Cap, veh/h 407 1697 85 470 1764 29 224 7 58 407 5 155 Arrive On Green 0.50 0.50 0.50 0.50 0.50 0.50 0.10 0.00 0.10 0.10 0.10 0.10 Sat Flow, veh/h 538 3392 170 645 3526 59 422 70 570 1371 50 1525 Grp Volume(v), veh/h 31 413 427 38 505 529 41 0 0 53 0 63 Grp Sat Flow(s),veh/h/ln 538 1752 1809 645 1752 1832 1062 0 0 1371 0 1575 Q Serve(g_s), s 1.3 4.5 4.5 1.2 5.9 5.9 0.5 0.0 0.0 0.0 0.0 1.1 Cycle Q Clear(g_c), s 7.2 4.5 4.5 5.7 5.9 5.9 1.6 0.0 0.0 0.8 0.0 1.1 Prop In Lane 1.00 0.09 1.00 0.03 0.46 0.54 1.00 0.97 Lane Grp Cap(c), veh/h 407 877 905 470 877 917 289 0 0 407 0 160 V/C Ratio(X) 0.08 0.47 0.47 0.08 0.58 0.58 0.14 0.00 0.00 0.13 0.00 0.39 Avail Cap(c_a), veh/h 434 963 994 502 963 1007 935 0 0 1021 0 866 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 0.00 0.00 1.00 0.00 1.00 Uniform Delay (d), s/veh 7.6 4.8 4.8 6.6 5.1 5.1 12.5 0.0 0.0 12.1 0.0 12.2 Incr Delay (d2), s/veh 0.1 0.4 0.4 0.1 0.7 0.7 0.2 0.0 0.0 0.1 0.0 1.6 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.2 2.2 2.2 0.2 3.0 3.1 0.3 0.0 0.0 0.4 0.0 0.5 LnGrp Delay(d),s/veh 7.7 5.2 5.1 6.7 5.8 5.8 12.8 0.0 0.0 12.3 0.0 13.8 LnGrp LOS A A A A A A B B B Approach Vol, veh/h 871 1072 41 116 Approach Delay, s/veh 5.2 5.8 12.8 13.1 Approach LOS A A B B Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 9.0 20.2 9.0 20.2 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 16.0 16.0 16.0 16.0 Max Q Clear Time (g_c+I1), s 3.6 9.2 3.1 7.9 Green Ext Time (p_c), s 0.5 5.4 0.6 6.2 Intersection Summary HCM 2010 Ctrl Delay 6.1 HCM 2010 LOS A HCM 2010 Signalized Intersection Summary 38: Cottonwood Road & Oak Street 11/2/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 12 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Lane Configurations Volume (veh/h) 15 78 15 89 91 84 72 122 39 57 38 13 Number 7 4 14 3 8 18 5 2 12 1 6 16 Initial Q (Qb), veh 0 0 0 0 0 0 0 0 0 0 0 0 Ped-Bike Adj(A_pbT) 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Parking Bus, Adj 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Adj Sat Flow, veh/h/ln 1900 1881 1900 1900 1881 1900 1881 1881 1900 1881 1881 1900 Adj Flow Rate, veh/h 17 87 17 99 101 93 80 136 43 63 42 14 Adj No. of Lanes 0 2 0 0 2 0 1 2 0 1 2 0 Peak Hour Factor 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 0.90 Percent Heavy Veh, % 1 1 1 1 1 1 1 1 1 1 1 1 Cap, veh/h 252 687 130 428 315 297 616 635 194 549 628 200 Arrive On Green 0.26 0.26 0.26 0.26 0.26 0.26 0.24 0.24 0.24 0.24 0.24 0.24 Sat Flow, veh/h 212 2667 504 697 1225 1154 1355 2699 824 1212 2671 848 Grp Volume(v), veh/h 66 0 55 171 0 122 80 88 91 63 27 29 Grp Sat Flow(s),veh/h/ln 1760 0 1623 1568 0 1508 1355 1787 1736 1212 1787 1732 Q Serve(g_s), s 0.0 0.0 0.6 0.7 0.0 1.5 1.1 0.9 1.0 1.0 0.3 0.3 Cycle Q Clear(g_c), s 0.6 0.0 0.6 1.9 0.0 1.5 1.4 0.9 1.0 2.0 0.3 0.3 Prop In Lane 0.26 0.31 0.58 0.77 1.00 0.47 1.00 0.49 Lane Grp Cap(c), veh/h 651 0 418 652 0 388 616 420 408 549 420 407 V/C Ratio(X) 0.10 0.00 0.13 0.26 0.00 0.31 0.13 0.21 0.22 0.11 0.07 0.07 Avail Cap(c_a), veh/h 2050 0 1802 1926 0 1675 2253 2579 2504 2013 2579 2498 HCM Platoon Ratio 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Upstream Filter(I) 1.00 0.00 1.00 1.00 0.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 Uniform Delay (d), s/veh 6.5 0.0 6.5 7.0 0.0 6.9 7.3 7.0 7.1 7.9 6.8 6.8 Incr Delay (d2), s/veh 0.1 0.0 0.1 0.2 0.0 0.5 0.1 0.2 0.3 0.1 0.1 0.1 Initial Q Delay(d3),s/veh 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 %ile BackOfQ(50%),veh/ln 0.3 0.0 0.3 0.9 0.0 0.7 0.4 0.5 0.5 0.3 0.1 0.1 LnGrp Delay(d),s/veh 6.6 0.0 6.7 7.2 0.0 7.3 7.4 7.3 7.3 7.9 6.9 6.9 LnGrp LOS A A A A A A A A A A Approach Vol, veh/h 121 293 259 119 Approach Delay, s/veh 6.6 7.2 7.3 7.4 Approach LOS A A A A Timer 1 2 3 4 5 6 7 8 Assigned Phs 2 4 6 8 Phs Duration (G+Y+Rc), s 11.4 11.5 11.4 11.5 Change Period (Y+Rc), s 6.0 5.6 6.0 5.6 Max Green Setting (Gmax), s 33.0 25.4 33.0 25.4 Max Q Clear Time (g_c+I1), s 3.4 2.6 4.0 3.9 Green Ext Time (p_c), s 1.9 2.5 1.9 2.5 Intersection Summary HCM 2010 Ctrl Delay 7.2 HCM 2010 LOS A HCM 2010 TWSC 5: 27th Avenue & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 3 Intersection Int Delay, s/veh 18 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 46 380 29 85 597 79 15 99 46 25 72 117 Conflicting Peds, #/hr 0 0 3 3 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - 200 - - 300 - - 300 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 2 2 2 3 3 3 2 2 3 3 2 2 Mvmt Flow 51 422 32 94 663 88 17 110 51 28 80 130 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 751 0 0 454 0 0 1102 1481 230 1264 1453 379 Stage 1 - - - - - - 541 541 - 896 896 - Stage 2 - - - - - - 561 940 - 368 557 - Critical Hdwy 4.14 - - 4.16 - - 7.54 6.54 6.96 7.56 6.54 6.94 Critical Hdwy Stg 1 - - - - - - 6.54 5.54 - 6.56 5.54 - Critical Hdwy Stg 2 - - - - - - 6.54 5.54 - 6.56 5.54 - Follow-up Hdwy 2.22 - - 2.23 - - 3.52 4.02 3.33 3.53 4.02 3.32 Pot Cap-1 Maneuver 854 - - 1096 - - 166 124 769 125 129 619 Stage 1 - - - - - - 493 519 - 299 357 - Stage 2 - - - - - - 480 340 - 621 510 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 852 - - 1093 - - 46 ~ 104 767 - 108 617 Mov Cap-2 Maneuver - - - - - - 46 ~ 104 - - 108 - Stage 1 - - - - - - 454 477 - 275 326 - Stage 2 - - - - - - 261 311 - 409 469 - Approach EB WB NB SB HCM Control Delay, s 1.2 1 170.3 HCM LOS F - Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 46 143 852 - - 1093 - - - 221 HCM Lane V/C Ratio 0.362 1.127 0.06 - - 0.086 - - - 0.95 HCM Control Delay (s) 122.4 175.2 9.5 0.3 - 8.6 - - - 94.3 HCM Lane LOS F F A A - A - - - F HCM 95th %tile Q(veh) 1.3 9 0.2 - - 0.3 - - - 8.2 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 11: Davis Lane & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 5 Intersection Int Delay, s/veh 42.9 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 303 349 0 0 524 176 0 0 3 98 0 331 Conflicting Peds, #/hr 3 0 0 0 0 0 0 0 0 0 0 4 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - - - - 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 1 1 1 2 2 2 1 1 2 2 1 1 Mvmt Flow 337 388 0 0 582 196 0 0 3 109 0 368 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 782 0 0 388 0 0 1356 1843 194 1551 1745 396 Stage 1 - - - - - - 1061 1061 - 684 684 - Stage 2 - - - - - - 295 782 - 867 1061 - Critical Hdwy 4.12 - - 4.14 - - 7.52 6.52 6.94 7.54 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.54 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.54 5.52 - Follow-up Hdwy 2.21 - - 2.22 - - 3.51 4.01 3.32 3.52 4.01 3.31 Pot Cap-1 Maneuver 838 - - 1167 - - 109 75 815 ~ 77 86 606 Stage 1 - - - - - - 241 301 - 405 449 - Stage 2 - - - - - - 692 405 - 314 301 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 836 - - 1167 - - 29 45 815 ~ 52 51 602 Mov Cap-2 Maneuver - - - - - - 29 45 - ~ 52 51 - Stage 1 - - - - - - 144 180 - 241 448 - Stage 2 - - - - - - 269 404 - 187 180 - Approach EB WB NB SB HCM Control Delay, s 5.7 0 9.4 169.6 HCM LOS A F Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) - - 815 836 - - 1167 - - 52 - 602 HCM Lane V/C Ratio - - 0.004 0.403 - - - - - 2.094 - 0.611 HCM Control Delay (s) 0 0 9.4 12.2 - - 0 - -$ 675.1 0 19.9 HCM Lane LOS A A A B - - A - - F A C HCM 95th %tile Q(veh) - - 0 2 - - 0 - - 10.9 - 4.1 Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 13: Ferguson Avenue & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 6 Intersection Int Delay, s/veh 2.9 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 5 194 5 429 285 44 1 79 323 42 64 20 Conflicting Peds, #/hr 0 0 0 0 0 0 1 0 0 0 0 1 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - 200 - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 80 80 80 80 80 80 80 80 80 80 80 80 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 6 242 6 536 356 55 1 99 404 52 80 25 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 412 0 0 250 0 0 1551 1744 125 1641 1719 207 Stage 1 - - - - - - 259 259 - 1457 1457 - Stage 2 - - - - - - 1292 1485 - 184 262 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1151 - - 1320 - - 78 ~ 86 905 67 90 802 Stage 1 - - - - - - 726 695 - 137 194 - Stage 2 - - - - - - 174 188 - 803 693 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1151 - - 1320 - - - ~ 40 904 - ~ 42 801 Mov Cap-2 Maneuver - - - - - - - ~ 40 - - ~ 42 - Stage 1 - - - - - - 721 690 - 136 91 - Stage 2 - - - - - - 10 ~ 88 - 378 688 - Approach EB WB NB SB HCM Control Delay, s 0.2 5.6 HCM LOS - - Minor Lane/Major Mvmt NBLn1NBLn2 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) - 904 1151 - - 1320 - - - HCM Lane V/C Ratio - 0.447 0.005 - - 0.406 - - - HCM Control Delay (s) - 12.2 8.1 0 - 9.6 0.6 - - HCM Lane LOS - B A A - A A - - HCM 95th %tile Q(veh) - 2.3 0 - - 2 - - - Notes ~: Volume exceeds capacity $: Delay exceeds 300s +: Computation Not Defined *: All major volume in platoon HCM 2010 TWSC 23: 11th Avenue & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 9 Intersection Int Delay, s/veh 6.1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 28 726 36 34 912 15 17 0 20 48 2 53 Conflicting Peds, #/hr 5 0 0 0 0 5 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length 500 - - 500 - - - - - - - 100 Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 3 3 3 3 3 3 3 3 3 3 3 3 Mvmt Flow 31 807 40 38 1013 17 19 0 22 53 2 59 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 1030 0 0 847 0 0 1472 1995 428 1563 2006 520 Stage 1 - - - - - - 889 889 - 1097 1097 - Stage 2 - - - - - - 583 1106 - 466 909 - Critical Hdwy 4.16 - - 4.16 - - 7.56 6.56 6.96 7.56 6.56 6.96 Critical Hdwy Stg 1 - - - - - - 6.56 5.56 - 6.56 5.56 - Critical Hdwy Stg 2 - - - - - - 6.56 5.56 - 6.56 5.56 - Follow-up Hdwy 2.23 - - 2.23 - - 3.53 4.03 3.33 3.53 4.03 3.33 Pot Cap-1 Maneuver 664 - - 780 - - 88 59 572 75 58 498 Stage 1 - - - - - - 302 357 - 226 285 - Stage 2 - - - - - - 463 282 - 543 350 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 661 - - 777 - - 69 53 570 67 53 496 Mov Cap-2 Maneuver - - - - - - 69 53 - 67 53 - Stage 1 - - - - - - 288 340 - 215 271 - Stage 2 - - - - - - 383 268 - 495 334 - Approach EB WB NB SB HCM Control Delay, s 0.4 0.3 44.6 90.3 HCM LOS E F Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 Capacity (veh/h) 131 661 - - 777 - - 66 496 HCM Lane V/C Ratio 0.314 0.047 - - 0.049 - - 0.842 0.119 HCM Control Delay (s) 44.6 10.7 - - 9.9 - - 172 13.2 HCM Lane LOS E B - - A - - F B HCM 95th %tile Q(veh) 1.2 0.1 - - 0.2 - - 4 0.4 HCM 2010 TWSC 26: Flanders Mill Road & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 10 Intersection Int Delay, s/veh 4.1 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 10 176 4 34 253 16 5 51 18 13 55 9 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - - - - - - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 11 196 4 38 281 18 6 57 20 14 61 10 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 299 0 0 200 0 0 467 594 100 514 588 149 Stage 1 - - - - - - 220 220 - 366 366 - Stage 2 - - - - - - 247 374 - 148 222 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1266 - - 1377 - - 481 419 939 446 422 874 Stage 1 - - - - - - 765 722 - 628 624 - Stage 2 - - - - - - 738 619 - 842 721 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1266 - - 1377 - - 407 401 939 377 404 874 Mov Cap-2 Maneuver - - - - - - 407 401 - 377 404 - Stage 1 - - - - - - 757 715 - 622 603 - Stage 2 - - - - - - 634 599 - 751 714 - Approach EB WB NB SB HCM Control Delay, s 0.4 0.9 14.4 15.6 HCM LOS B C Minor Lane/Major Mvmt NBLn1 EBL EBT EBR WBL WBT WBRSBLn1 Capacity (veh/h) 466 1266 - - 1377 - - 426 HCM Lane V/C Ratio 0.176 0.009 - - 0.027 - - 0.201 HCM Control Delay (s) 14.4 7.9 0 - 7.7 0.1 - 15.6 HCM Lane LOS B A A - A A - C HCM 95th %tile Q(veh) 0.6 0 - - 0.1 - - 0.7 HCM 2010 TWSC 38: Cottonwood Road & Oak Street 10/30/2015 Future (2035) Existing Intersection 5 lane PM Peak Hour 6/17/2015 Baseline Synchro 8 Report Page 11 Intersection Int Delay, s/veh 8.3 Movement EBL EBT EBR WBL WBT WBR NBL NBT NBR SBL SBT SBR Vol, veh/h 15 85 15 89 91 85 72 122 39 63 38 13 Conflicting Peds, #/hr 0 0 0 0 0 0 0 0 0 0 0 0 Sign Control Free Free Free Free Free Free Stop Stop Stop Stop Stop Stop RT Channelized - - None - - None - - None - - None Storage Length - - - - - - 200 - - 200 - - Veh in Median Storage, # - 0 - - 0 - - 0 - - 0 - Grade, % - 0 - - 0 - - 0 - - 0 - Peak Hour Factor 90 90 90 90 90 90 90 90 90 90 90 90 Heavy Vehicles, % 1 1 1 1 1 1 1 1 1 1 1 1 Mvmt Flow 17 94 17 99 101 94 80 136 43 70 42 14 Major/Minor Major1 Major2 Minor1 Minor2 Conflicting Flow All 196 0 0 111 0 0 405 529 56 494 490 98 Stage 1 - - - - - - 136 136 - 346 346 - Stage 2 - - - - - - 269 393 - 148 144 - Critical Hdwy 4.12 - - 4.12 - - 7.52 6.52 6.92 7.52 6.52 6.92 Critical Hdwy Stg 1 - - - - - - 6.52 5.52 - 6.52 5.52 - Critical Hdwy Stg 2 - - - - - - 6.52 5.52 - 6.52 5.52 - Follow-up Hdwy 2.21 - - 2.21 - - 3.51 4.01 3.31 3.51 4.01 3.31 Pot Cap-1 Maneuver 1382 - - 1484 - - 533 456 1002 461 480 942 Stage 1 - - - - - - 856 785 - 646 636 - Stage 2 - - - - - - 716 607 - 842 779 - Platoon blocked, % - - - - Mov Cap-1 Maneuver 1382 - - 1484 - - 454 416 1002 309 438 942 Mov Cap-2 Maneuver - - - - - - 454 416 - 309 438 - Stage 1 - - - - - - 845 775 - 638 588 - Stage 2 - - - - - - 605 561 - 656 769 - Approach EB WB NB SB HCM Control Delay, s 1 2.6 14.3 16.7 HCM LOS B C Minor Lane/Major Mvmt NBLn1NBLn2NBLn3 EBL EBT EBR WBL WBT WBRSBLn1 SBLn2 SBLn3 Capacity (veh/h) 454 416 539 1382 - - 1484 - - 309 438 560 HCM Lane V/C Ratio 0.176 0.163 0.206 0.012 - - 0.067 - - 0.227 0.048 0.063 HCM Control Delay (s) 14.6 15.3 13.4 7.6 0 - 7.6 0.1 - 20 13.6 11.9 HCM Lane LOS B C B A A - A A - C B B HCM 95th %tile Q(veh) 0.6 0.6 0.8 0 - - 0.2 - - 0.9 0.2 0.2 APPENDIX D: SIGNAL WARRANT ANALYSIS Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (3 lanes) 11th Avenue (1 lanes) Analysis Year/Case: Existing Weekday (2015) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?No (.37) High minor approach volume > 100 for peak hour?No (46) Total entering volume > 800 for peak hour?Yes (1486) Category A warrant satisfied?No Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?No Warrant 3 Satisfied?No PM Peak Hour 954 4:45-5:45 PM 7:45-8:45 AM 1486 Agency/Company: High Minor Total Stopped Time Delay (hrs) High Minor Approach Volume (vehs) Total Entering Volume (vehs) Total Volume of Major Approaches (vehs) 1436 Project Description: 0.37 General Information 46 High Minor Approach Volume (vehs) Total Entering Volume (vehs) 34 988 Total Volume of Major Approaches (vehs) Minor Street (Approach Lanes): AM Peak Hour 0.16 Warrant 3: Peak Hour Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Date: High Minor Total Stopped Time Delay (hrs) Project Number: X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (3 lanes) 11th Avenue (1 lanes) Analysis Year/Case: Future Weekday (2035) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?No (2.38) High minor approach volume > 100 for peak hour?Yes (105) Total entering volume > 800 for peak hour?Yes (1748) Category A warrant satisfied?No Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?No Warrant 3 Satisfied?No Total Volume of Major Approaches (vehs) 1748 High Minor Approach Volume (vehs) 105 Total Entering Volume (vehs) 1890 Total Entering Volume (vehs) 1351 PM Peak Hour 4:45-5:45 PM High Minor Total Stopped Time Delay (hrs) 2.38 7:45-8:45 AM High Minor Total Stopped Time Delay (hrs) 0.63 Total Volume of Major Approaches (vehs) 1224 High Minor Approach Volume (vehs) 73 Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): AM Peak Hour Warrant 3: Peak Hour General Information Agency/Company: Date: Project Number: Project Description: X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (2 lanes) 27th Avenue (2 lanes) Analysis Year/Case: Existing Weekday (2015) Hour Begin NB SB EB WB 0:00 6 3 9 21 30 6 1:00 1 2 2 11 13 2 2:00 1 1 2 4 6 1 3:00 4 0 3 1 4 4 4:00 5 2 14 10 24 5 5:00 11 10 57 21 78 11 6:00 30 24 108 41 149 30 7:00 86 65 334 155 489 86 8:00 105 103 392 250 642 105 9:00 64 79 229 185 414 79 10:00 39 65 222 215 437 65 11:00 60 74 246 288 534 74 12:00 70 101 263 349 612 101 13:00 61 83 276 327 603 83 14:00 47 76 232 295 527 76 15:00 71 112 276 369 645 112 16:00 74 89 275 435 710 89 17:00 82 117 260 590 850 117 18:00 65 96 239 376 615 96 19:00 48 65 161 251 412 65 20:00 27 51 112 199 311 51 21:00 28 47 59 132 191 47 22:00 11 18 21 76 97 18 23:00 5 6 18 60 78 6 TOTAL 1001 1289 3810 4661 8471 1329 Condition A - Minimum Vehicular Volume (100% Columns): Major Street Total > 500 and Higher Minor Street Total > 200 for 8 hours?No (0 hrs) Condition B - Interruption of Continuous Traffic (100% Columns): Major Street Total >750 and Higher Minor Street Total > 100 for 8 hours?No (1 hr) Combination of Conditions A & B (80% Columns): Major Street Total > 400 and Higher Minor Street Total > 160 for 8 hours?No (0 hrs) Major Street Total > 600 and Higher Minor Street Total > 80 for 8 hours?No (6 hrs) Warrant 1 Satisfied?No Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): Date: Agency/Company: Project Number: Warrant 1: Eight-Hour Vehicular Volume Project Description: Avg. Entering Volume Major Street Total (Both Approaches) General Information Higher Volume Minor Approach Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (2 lanes) 27th Avenue (2 lanes) Analysis Year/Case: Existing Weekday (2015) Hour Begin NB SB EB WB 0:00 6 3 9 21 30 6 1:00 1 2 2 11 13 2 2:00 1 1 2 4 6 1 3:00 4 0 3 1 4 4 4:00 5 2 14 10 24 5 5:00 11 10 57 21 78 11 6:00 30 24 108 41 149 30 7:00 86 65 334 155 489 86 8:00 105 103 392 250 642 105 9:00 64 79 229 185 414 79 10:00 39 65 222 215 437 65 11:00 60 74 246 288 534 74 12:00 70 101 263 349 612 101 13:00 61 83 276 327 603 83 14:00 47 76 232 295 527 76 15:00 71 112 276 369 645 112 16:00 74 89 275 435 710 89 17:00 82 117 260 590 850 117 18:00 65 96 239 376 615 96 19:00 48 65 161 251 412 65 20:00 27 51 112 199 311 51 21:00 28 47 59 132 191 47 22:00 11 18 21 76 97 18 23:00 5 6 18 60 78 6 TOTAL 1001 1289 3810 4661 8471 1329 Meets warrant criteria on graph for minimum of 4 hours (100% thresholds)?No (0 hrs) Warrant 2 Satisfied?No Project Number: Project Description: Avg. Entering Volume Warrant 2: Four-Hour Vehicular Volume General Information Date: Agency/Company: Major Street Total (Both Approaches) Higher Volume Minor Approach Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (2 lanes) 27th Avenue (2 lanes) Analysis Year/Case: Existing Weekday (2015) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?No (0.84) High minor approach volume > 100 for peak hour?Yes (118) Total entering volume > 800 for peak hour?Yes (1016) Category A warrant satisfied?No Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?No Warrant 3 Satisfied?No 0.73 Warrant 3: Peak Hour Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Date: High Minor Total Stopped Time Delay (hrs) Project Number: Project Description: Minor Street (Approach Lanes): General Information 118 High Minor Approach Volume (vehs) Total Entering Volume (vehs) 123 911 Total Volume of Major Approaches (vehs) 690 AM Peak Hour 7:45-8:45 AM 1016 Agency/Company: High Minor Total Stopped Time Delay (hrs) High Minor Approach Volume (vehs) Total Entering Volume (vehs) Total Volume of Major Approaches (vehs) 823 PM Peak Hour 0.84 4:45-5:45 PM X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (2 lanes) 27th Avenue (2 lanes) Analysis Year/Case: Future Weekday (2035) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?Yes High minor approach volume > 100 for peak hour?Yes (224) Total entering volume > 800 for peak hour?Yes (1601) Category A warrant satisfied?Yes Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?Yes Warrant 3 Satisfied?Yes Warrant 3: Peak Hour General Information Agency/Company: Date: Project Number: Project Description: Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): AM Peak Hour 7:45-8:45 AM High Minor Total Stopped Time Delay (hrs) 8.38 Total Volume of Major Approaches (vehs) 1043 High Minor Approach Volume (vehs) 187 Total Entering Volume (vehs) 1398 PM Peak Hour 4:45-5:45 PM High Minor Total Stopped Time Delay (hrs) -- Total Volume of Major Approaches (vehs) 1216 High Minor Approach Volume (vehs) 224 Total Entering Volume (vehs) 1601 X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (3 lanes) Cottonwood Road(3 lanes) Analysis Year/Case: Future Weekday (2035) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?No (0.91) High minor approach volume > 100 for peak hour?Yes (233) Total entering volume > 800 for peak hour?No (713) Category A warrant satisfied?No Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?No Warrant 3 Satisfied?No Total Volume of Major Approaches (vehs) 372 High Minor Approach Volume (vehs) 233 Total Entering Volume (vehs) 713 Total Entering Volume (vehs) 644 PM Peak Hour 4:45-5:45 PM High Minor Total Stopped Time Delay (hrs) 0.91 7:45-8:45 AM High Minor Total Stopped Time Delay (hrs) 0.60 Total Volume of Major Approaches (vehs) 329 High Minor Approach Volume (vehs) 161 Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): AM Peak Hour Warrant 3: Peak Hour General Information Agency/Company: Date: Project Number: Project Description: X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (1 lanes) Davis Lane (2 lanes) Analysis Year/Case: Existing Weekday (2015) Hour Begin NB SB EB WB 0:00 0 28 14 16 30 28 1:00 0 3 4 5 9 3 2:00 0 5 2 4 6 5 3:00 0 2 1 4 5 2 4:00 0 3 17 12 29 3 5:00 0 27 51 24 75 27 6:00 0 41 105 54 159 41 7:00 0 219 292 174 466 219 8:00 0 288 372 262 634 288 9:00 0 147 227 185 412 147 10:00 0 116 239 199 438 116 11:00 0 171 260 234 494 171 12:00 0 181 285 266 551 181 13:00 0 149 295 270 565 149 14:00 0 153 236 263 499 153 15:00 0 277 291 331 622 277 16:00 0 210 339 347 686 210 17:00 0 232 347 427 774 232 18:00 0 173 299 309 608 173 19:00 0 132 200 206 406 132 20:00 0 132 121 138 259 132 21:00 0 67 83 100 183 67 22:00 0 19 37 61 98 19 23:00 0 30 16 44 60 30 TOTAL 0 2805 4133 3935 8068 2805 Condition A - Minimum Vehicular Volume (100% Columns): Major Street Total > 500 and Higher Minor Street Total > 200 for 8 hours?No (4 hrs) Condition B - Interruption of Continuous Traffic (100% Columns): Major Street Total >750 and Higher Minor Street Total > 100 for 8 hours?No (1 hr) Combination of Conditions A & B (80% Columns): Major Street Total > 400 and Higher Minor Street Total > 160 for 8 hours?Yes (8 hrs) Major Street Total > 600 and Higher Minor Street Total > 80 for 8 hours?No (5 hrs) Warrant 1 Satisfied?No Date: Agency/Company: Project Number: Warrant 1: Eight-Hour Vehicular Volume Project Description: Avg. Entering Volume Major Street Total (Both Approaches) General Information Higher Volume Minor Approach Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (1 lanes) Davis Lane (2 lanes) Analysis Year/Case: Existing Weekday (2015) Hour Begin NB SB EB WB 0:00 0 28 14 16 30 28 1:00 0 3 4 5 9 3 2:00 0 5 2 4 6 5 3:00 0 2 1 4 5 2 4:00 0 3 17 12 29 3 5:00 0 27 51 24 75 27 6:00 0 41 105 54 159 41 7:00 0 219 292 174 466 219 8:00 0 288 372 262 634 288 9:00 0 147 227 185 412 147 10:00 0 116 239 199 438 116 11:00 0 171 260 234 494 171 12:00 0 181 285 266 551 181 13:00 0 149 295 270 565 149 14:00 0 153 236 263 499 153 15:00 0 277 291 331 622 277 16:00 0 210 339 347 686 210 17:00 0 232 347 427 774 232 18:00 0 173 299 309 608 173 19:00 0 132 200 206 406 132 20:00 0 132 121 138 259 132 21:00 0 67 83 100 183 67 22:00 0 19 37 61 98 19 23:00 0 30 16 44 60 30 TOTAL 0 2805 4133 3935 8068 2805 Meets warrant criteria on graph for minimum of 4 hours (100% thresholds)?No (2 hrs) Warrant 2 Satisfied?No Avg. Entering Volume Warrant 2: Four-Hour Vehicular Volume General Information Date: Agency/Company: Major Street Total (Both Approaches) Higher Volume Minor Approach Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): Project Number: Project Description: Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (1 lanes) Davis Lane (2 lanes) Analysis Year/Case: Existing Weekday (2015) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?No (1.25 hrs) High minor approach volume > 100 for peak hour?Yes (252) Total entering volume > 800 for peak hour?Yes (1016) Category A warrant satisfied?No Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?No Warrant 3 Satisfied?No 1016 Agency/Company: High Minor Total Stopped Time Delay (hrs) High Minor Approach Volume (vehs) Total Entering Volume (vehs) Total Volume of Major Approaches (vehs) 764 PM Peak Hour 1.25 4:45-5:45 PM 252 High Minor Approach Volume (vehs) Total Entering Volume (vehs) 306 994 Warrant 3: Peak Hour Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Date: High Minor Total Stopped Time Delay (hrs) Project Number: Project Description: Minor Street (Approach Lanes): General Information Total Volume of Major Approaches (vehs) 688 AM Peak Hour 7:45-8:45 AM 2.36 X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (3 lanes) Davis Lane (3 lanes) Analysis Year/Case: Future Weekday (2035) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?-- High minor approach volume > 100 for peak hour?Yes (461) Total entering volume > 800 for peak hour?Yes (2066) Category A warrant satisfied?Yes Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?Yes Warrant 3 Satisfied?Yes Total Volume of Major Approaches (vehs) 1197 High Minor Approach Volume (vehs) 461 Total Entering Volume (vehs) 2066 Total Entering Volume (vehs) 2033 PM Peak Hour 4:45-5:45 PM High Minor Total Stopped Time Delay (hrs) -- 7:45-8:45 AM High Minor Total Stopped Time Delay (hrs) -- Total Volume of Major Approaches (vehs) 1044 High Minor Approach Volume (vehs) 726 Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): AM Peak Hour Warrant 3: Peak Hour General Information Agency/Company: Date: Project Number: Project Description: X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (1 lane) Ferguson Avenue (1 lane) Analysis Year/Case: Existing Weekday (2015) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?No (0.74 hrs) High minor approach volume > 100 for peak hour?Yes (284) Total entering volume > 800 for peak hour?No (620) Category A warrant satisfied?No Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?No Warrant 3 Satisfied?No 4:45-5:45 PM 7:45-8:45 AM 620 Agency/Company: High Minor Total Stopped Time Delay (hrs) High Minor Approach Volume (vehs) Total Entering Volume (vehs) Total Volume of Major Approaches (vehs) 336 PM Peak Hour 0.74 General Information 284 High Minor Approach Volume (vehs) Total Entering Volume (vehs) 274 544 Total Volume of Major Approaches (vehs) 270 AM Peak Hour 0.59 Warrant 3: Peak Hour Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Date: High Minor Total Stopped Time Delay (hrs) Project Number: Project Description: Minor Street (Approach Lanes): X Sanderson Stewart 10/23/2015 15022 Oak Street Corridor City of Bozeman/MDT 35 mph Oak Street (1 lane) Ferguson Avenue (1 lane) Analysis Year/Case: Future Weekday (2035) Category A:Peak Period: PM Total stopped time delay for minor approach > 4 veh-hrs?Yes High minor approach volume > 100 for peak hour?Yes (389) Total entering volume > 800 for peak hour?Yes (1448) Category A warrant satisfied?Yes Category B: Meets warrant criteria on graph for minimum of one hour (100% thresholds)?Yes Warrant 3 Satisfied?Yes Total Volume of Major Approaches (vehs) 936 High Minor Approach Volume (vehs) 389 Total Entering Volume (vehs) 1448 Total Entering Volume (vehs) 1205 PM Peak Hour 4:45-5:45 PM High Minor Total Stopped Time Delay (hrs) -- 7:45-8:45 AM High Minor Total Stopped Time Delay (hrs) 3.59 Total Volume of Major Approaches (vehs) 747 High Minor Approach Volume (vehs) 339 Jurisdiction: Major Street Speed Limit: Major Street (Approach Lanes): Minor Street (Approach Lanes): AM Peak Hour Warrant 3: Peak Hour General Information Agency/Company: Date: Project Number: Project Description: X APPENDIX E: LIGHTING CALCULATIONS Visual Roadway Lighting Tool - Oak Street 92' - 30' Median 10/29/2015 283 ft Design Information Project Number Name Company Project Title Project Number Your Name Your Company Roadway Information Number Left Lanes Left Lane Width Median Width Number Right Lanes Right Lane Width Calculation Method Pavement Reflectance Roadway Classification Pedestrian Conflict 2 15.5 ft 30 ft 2 15.5 ft IES RP8-2000 Asphalt - R3 Major Low Luminaire Information Left Side Label LED Type II Catalog Number ATB2 60BLEDE85 XXXXX R2 Photometric File 62563.ies Lamp Lumens Absolute Light Loss Factor 0.90 Input Power 178 W Tilt 0° Arm Length 10 ft Mounting Height 40 ft Setback 3 ft Quantity 4 Right Side Label LED Type II Catalog Number ATB2 60BLEDE85 XXXXX R2 Photometric File 62563.ies Lamp Lumens Absolute Light Loss Factor 0.90 Input Power 178 W Tilt 0° Arm Length 10 ft Mounting Height 40 ft Setback 3 ft Quantity 4 Calculation Results - Right Side Luminance Average Max Min Max/Min Avg/Min 0.9 cd/m² 1.6 cd/m² 0.4 cd/m² 4.0 2.2 Illuminance Average Max Min Max/Min Avg/Min 0.9 fc 2.0 fc 0.3 fc 6.7 3.0 Lv Ratio STV Spacing Length Quantity 0.3 3.4 283 ft 1000 ft 8 Calculations are based on procedures established by the governing standards body or standard industry practice. Visual computes output performance basedon input data as provided by, and which is the sole responsibility of, the user. Acuity Brands Lighting, Inc. cannot be held responsible for the variations in actualsituations which can effect calculated output. www.VisualLightingSoftware.com 92 ft Street 30' Median Type II LED.RWT Visual Roadway Lighting Tool - Oak Street 92' - 30' Median 10/29/2015 Luminance vs Spacing 507090110130150170190210230250270290310330Spacing (ft) 0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 Luminance (cd/m²)0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 Uniformity RatioMin Avg Avg/Min IES Avg IES Avg/Min Calculations are based on procedures established by the governing standards body or standard industry practice. Visual computes output performance basedon input data as provided by, and which is the sole responsibility of, the user. Acuity Brands Lighting, Inc. cannot be held responsible for the variations in actualsituations which can effect calculated output. www.VisualLightingSoftware.com 92 ft Street 30' Median Type II LED.RWT Visual Roadway Lighting Tool - Oak Street 75' Street No Median 10/29/2015 340 ft Design Information Project Number Name Company Project Title Project Number Your Name Your Company Roadway Information Number Left Lanes Left Lane Width Median Width Number Right Lanes Right Lane Width Calculation Method Pavement Reflectance Roadway Classification Pedestrian Conflict 2 18.7 ft 0 ft 2 18.7 ft IES RP8-2000 Asphalt - R3 Major Low Luminaire Information Left Side Label LED Type II Catalog Number ATB2 60BLEDE85 XXXXX R2 Photometric File 62563.ies Lamp Lumens Absolute Light Loss Factor 0.90 Input Power 178 W Tilt 0° Arm Length 10 ft Mounting Height 40 ft Setback 3 ft Quantity 3 Right Side Label LED Type II Catalog Number ATB2 60BLEDE85 XXXXX R2 Photometric File 62563.ies Lamp Lumens Absolute Light Loss Factor 0.90 Input Power 178 W Tilt 0° Arm Length 10 ft Mounting Height 40 ft Setback 3 ft Quantity 3 Calculation Results - Left Side Luminance Average Max Min Max/Min Avg/Min 0.8 cd/m² 1.5 cd/m² 0.3 cd/m² 5.0 2.7 Illuminance Average Max Min Max/Min Avg/Min 0.9 fc 2.0 fc 0.3 fc 6.7 3.0 Lv Ratio STV Spacing Length Quantity 0.3 2.9 340 ft 1000 ft 6 Calculations are based on procedures established by the governing standards body or standard industry practice. Visual computes output performance basedon input data as provided by, and which is the sole responsibility of, the user. Acuity Brands Lighting, Inc. cannot be held responsible for the variations in actualsituations which can effect calculated output. www.VisualLightingSoftware.com 75 ft Street No Median Type II LED.RWT Visual Roadway Lighting Tool - Oak Street 75' Street No Median 10/29/2015 Luminance vs Spacing 507090110130150170190210230250270290310330Spacing (ft) 0 1 2 3 4 5 6 7 8 9 10 Luminance (cd/m²)0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 Uniformity RatioMin Avg Avg/Min IES Avg IES Avg/Min Calculations are based on procedures established by the governing standards body or standard industry practice. Visual computes output performance basedon input data as provided by, and which is the sole responsibility of, the user. Acuity Brands Lighting, Inc. cannot be held responsible for the variations in actualsituations which can effect calculated output. www.VisualLightingSoftware.com 75 ft Street No Median Type II LED.RWT Visual Roadway Lighting Tool - Oak Street 3 Lane Section 10/29/2015 415 ft Design Information Project Number Name Company Project Title Project Number Your Name Your Company Roadway Information Number Left Lanes Left Lane Width Median Width Number Right Lanes Right Lane Width Calculation Method Pavement Reflectance Roadway Classification Pedestrian Conflict 2 12.75 ft 0 ft 2 12.75 ft IES RP8-2000 Asphalt - R3 Major Low Luminaire Information Left Side Label LED Type II Catalog Number ATB2 60BLEDE85 XXXXX R2 Photometric File 62563.ies Lamp Lumens Absolute Light Loss Factor 0.90 Input Power 178 W Tilt 0° Arm Length 10 ft Mounting Height 40 ft Setback 3 ft Quantity 3 Right Side Label LED Type II Catalog Number ATB2 60BLEDE85 XXXXX R2 Photometric File 62563.ies Lamp Lumens Absolute Light Loss Factor 0.90 Input Power 178 W Tilt 0° Arm Length 10 ft Mounting Height 40 ft Setback 3 ft Quantity 2 Calculation Results - Left Side Luminance Average Max Min Max/Min Avg/Min 0.8 cd/m² 1.6 cd/m² 0.3 cd/m² 5.3 2.7 Illuminance Average Max Min Max/Min Avg/Min 0.9 fc 1.9 fc 0.4 fc 4.8 2.2 Lv Ratio STV Spacing Length Quantity 0.3 2.1 415 ft 1000 ft 5 Calculations are based on procedures established by the governing standards body or standard industry practice. Visual computes output performance basedon input data as provided by, and which is the sole responsibility of, the user. Acuity Brands Lighting, Inc. cannot be held responsible for the variations in actualsituations which can effect calculated output. www.VisualLightingSoftware.com 3 Lane 51 ft Street No Median Type II LED.RWT Visual Roadway Lighting Tool - Oak Street 3 Lane Section 10/29/2015 Luminance vs Spacing 507090110130150170190210230250270290310330Spacing (ft) 0 1 2 3 4 5 6 7 8 9 10 Luminance (cd/m²)0 0.5 1 1.5 2 2.5 3 3.5 4 4.5 5 Uniformity RatioMin Avg Avg/Min IES Avg IES Avg/Min Calculations are based on procedures established by the governing standards body or standard industry practice. Visual computes output performance basedon input data as provided by, and which is the sole responsibility of, the user. Acuity Brands Lighting, Inc. cannot be held responsible for the variations in actualsituations which can effect calculated output. www.VisualLightingSoftware.com 3 Lane 51 ft Street No Median Type II LED.RWT APPENDIX F: STORMWATER EXHIBITS NORTH 0 200 SCALE: 1" = 200' NOTE: -EXISTING UNDERGROUND INSTALLATIONS & PRIVATE UTILITIES SHOWN ARE INDICATED ACCORDING TO THE BEST INFORMATION AVAILABLE TO THE ENGINEER. THE ENGINEER DOES NOT GUARANTEE THE ACCURACY OF SUCH INFORMATION. SERVICE LINES (WATER, POWER, GAS, STORM, SEWER, TELEPHONE & TELEVISION) MAY NOT BE STRAIGHT LINES OR AS INDICATED ON THE PLANS. STATE LAW REQUIRES CONTRACTOR TO CALL ALL UTILITY COMPANIES BEFORE EXCAVATION FOR EXACT LOCATIONS. -ALL IMPROVEMENTS SHALL BE PERFORMED IN ACCORDANCE WITH MONTANA PUBLIC WORKS STANDARD SPECIFICATIONS 6TH EDITION, APRIL, 2010, INCLUDING ALL ADDENDA, AND THE CITY OF BOZEMAN MODIFICATIONS TO MONTANA PUBLIC WORKS STANDARD SPECIFICATIONS SIXTH EDITION, APPROVED MARCH 31, 2011 AND ANY ADDENDA THERETO. -UNLESS OTHERWISE SPECIFIED, ALL CONSTRUCTION LAYOUT AND STAKING SHALL BE PERFORMED UNDER THE RESPONSIBLE CHARGE OF A LAND SURVEYOR LICENSED IN THE STATE OF MONTANA AND BY A PARTY CHIEF OR ENGINEERING TECHNICIAN EXPERIENCED IN CONSTRUCTION LAYOUT AND STAKING TECHNIQUES AS ARE REQUIRED BY THE SPECIFIC TYPE OF WORK BEING PERFORMED. C2.0STREET IMPROVEMENTS FROM NORTH ROUSEOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSBOZEMAN, MONTANASTORMWATER EXHIBIT - NORTH 7TH AVENUE TO NORTH 19TH AVENUEC 2015 ALL RIGHTS RESERVED DATE: FILE: PROJECT NO: CAD: QUALITY ASSURANCE: REVISIONS DATE DESCRIPTION 10/26/2015 15022_STORM_EXHIBIT.DWG 15022 CMK 87654321 A B C D E F 9 G - - - - - - - - - - - - - - - - - - - - -AVENUE TO COTTONWOOD ROAD400100200 NORTH 0 200 SCALE: 1" = 200' NOTE: -EXISTING UNDERGROUND INSTALLATIONS & PRIVATE UTILITIES SHOWN ARE INDICATED ACCORDING TO THE BEST INFORMATION AVAILABLE TO THE ENGINEER. THE ENGINEER DOES NOT GUARANTEE THE ACCURACY OF SUCH INFORMATION. SERVICE LINES (WATER, POWER, GAS, STORM, SEWER, TELEPHONE & TELEVISION) MAY NOT BE STRAIGHT LINES OR AS INDICATED ON THE PLANS. STATE LAW REQUIRES CONTRACTOR TO CALL ALL UTILITY COMPANIES BEFORE EXCAVATION FOR EXACT LOCATIONS. -ALL IMPROVEMENTS SHALL BE PERFORMED IN ACCORDANCE WITH MONTANA PUBLIC WORKS STANDARD SPECIFICATIONS 6TH EDITION, APRIL, 2010, INCLUDING ALL ADDENDA, AND THE CITY OF BOZEMAN MODIFICATIONS TO MONTANA PUBLIC WORKS STANDARD SPECIFICATIONS SIXTH EDITION, APPROVED MARCH 31, 2011 AND ANY ADDENDA THERETO. -UNLESS OTHERWISE SPECIFIED, ALL CONSTRUCTION LAYOUT AND STAKING SHALL BE PERFORMED UNDER THE RESPONSIBLE CHARGE OF A LAND SURVEYOR LICENSED IN THE STATE OF MONTANA AND BY A PARTY CHIEF OR ENGINEERING TECHNICIAN EXPERIENCED IN CONSTRUCTION LAYOUT AND STAKING TECHNIQUES AS ARE REQUIRED BY THE SPECIFIC TYPE OF WORK BEING PERFORMED. C3.0STREET IMPROVEMENTS FROM NORTH ROUSEOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSBOZEMAN, MONTANASTORMWATER EXHIBIT - NORTH 19TH AVENUE TO DAVIS LANEC 2015 ALL RIGHTS RESERVED DATE: FILE: PROJECT NO: CAD: QUALITY ASSURANCE: REVISIONS DATE DESCRIPTION 10/26/2015 15022_STORM_EXHIBIT.DWG 15022 CMK 87654321 A B C D E F 9 G - - - - - - - - - - - - - - - - - - - - -AVENUE TO COTTONWOOD ROAD400100200 NORTH 0 200 SCALE: 1" = 200' NOTE: -EXISTING UNDERGROUND INSTALLATIONS & PRIVATE UTILITIES SHOWN ARE INDICATED ACCORDING TO THE BEST INFORMATION AVAILABLE TO THE ENGINEER. THE ENGINEER DOES NOT GUARANTEE THE ACCURACY OF SUCH INFORMATION. SERVICE LINES (WATER, POWER, GAS, STORM, SEWER, TELEPHONE & TELEVISION) MAY NOT BE STRAIGHT LINES OR AS INDICATED ON THE PLANS. STATE LAW REQUIRES CONTRACTOR TO CALL ALL UTILITY COMPANIES BEFORE EXCAVATION FOR EXACT LOCATIONS. -ALL IMPROVEMENTS SHALL BE PERFORMED IN ACCORDANCE WITH MONTANA PUBLIC WORKS STANDARD SPECIFICATIONS 6TH EDITION, APRIL, 2010, INCLUDING ALL ADDENDA, AND THE CITY OF BOZEMAN MODIFICATIONS TO MONTANA PUBLIC WORKS STANDARD SPECIFICATIONS SIXTH EDITION, APPROVED MARCH 31, 2011 AND ANY ADDENDA THERETO. -UNLESS OTHERWISE SPECIFIED, ALL CONSTRUCTION LAYOUT AND STAKING SHALL BE PERFORMED UNDER THE RESPONSIBLE CHARGE OF A LAND SURVEYOR LICENSED IN THE STATE OF MONTANA AND BY A PARTY CHIEF OR ENGINEERING TECHNICIAN EXPERIENCED IN CONSTRUCTION LAYOUT AND STAKING TECHNIQUES AS ARE REQUIRED BY THE SPECIFIC TYPE OF WORK BEING PERFORMED. C4.0STREET IMPROVEMENTS FROM NORTH ROUSEOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSOAK STREET IMPROVEMENTSBOZEMAN, MONTANASTORMWATER EXHIBIT - DAVIS LANE TO COTTONWOOD ROADC 2015 ALL RIGHTS RESERVED DATE: FILE: PROJECT NO: CAD: QUALITY ASSURANCE: REVISIONS DATE DESCRIPTION 10/26/2015 15022_STORM_EXHIBIT.DWG 15022 CMK 87654321 A B C D E F 9 G - - - - - - - - - - - - - - - - - - - - -AVENUE TO COTTONWOOD ROAD400100200 APPENDIX G: WETLAND DELINEATION REPORT i WETLAND DELINATION REPORT FOR OAK STREET IMPROVEMENTS BOZEMAN, MONTANA PREPARED FOR CITY OF BOZEMAN PO BOX 1230 BOZEMAN, MT 59771 September 2015 15022 ii TABLE OF CONTENTS List of Figures iii 1.0 Introduction 1 2.0 Site Description 1 3.0 Methods 1 4.0 Results and Discussion 2 5.0 Waters of the US 4 6.0 References Cited 5 Figures Appendix A: Photographs Appendix B: Delineation Data Sheets Appendix C: Additional Methodology Information iii List of Figures Figure 1. Aerial photo showing approximate project location Figure 2. Locations of drainageway crossings on Oak Street that are part of the Oak Street Improvements project Figure 3. Wetland Delineation Maps 3-1. Stormwater drainage east of North 7th Avenue 3-2. Mandeville Creek 3-3. Stormwater drainage and Farmers Canal 3-4. East Fork of East Catron Creek 3-5. Unnamed tributary of East Catron Creek 3-6. Abandoned historic channel of Cattail Creek 3-7. Upper Cattail Creek 3-8. Section Line Ditch 3-9. Unnamed tributary of Baxter Creek 3-10. Maynard-Border Ditch Overflow Figure 4. Montana Natural Resources Heritage Program and US Fish and Wildlife Service wetland and riparian mapping Figure 5. Natural Resource Conservation Service Soil Map P:15022_Oak_Street_Wetland_Report_101215_SC 1 (10/12/15) CT/jil 1.0 INTRODUCTION A wetland delineation and waters of the U.S. evaluation was conducted by Sanderson Stewart for the proposed improvements to Oak Street, Bozeman, MT (Figure 1). The assessment was performed as part of the initial site evaluation at the request of the City of Bozeman. Site visits performed in September of 2015 identified ten drainageways that cross the Oak Street corridor within the scope of work of this project. (Note: the area of the proposed Oak Street alignment between Ferguson Avenue and Flanders Mill Roads was not within the scope of work). At each crossing, wetlands were delineated and an evaluation of likely connection to waters of the US was conducted. Sanderson Stewart personnel performing the work were Carol Lee-Roark, PhD and Chris Thelen, PE. 2.0 SITE DESCRIPTION This project includes proposed improvements to Oak Street from North Rouse to Ferguson Avenue, and Flanders Mill Road to Cottonwood Road (Figure 1), in Bozeman MT. Improvements that will be considered include additional lanes, turning lanes, curb and gutter, storm drainage, lighting, signage, striping, and utilities. The sections of Oak Street included in the evaluation are within Sections 1, 2, and 3 of Township 2 South, Range 5 East, PMM, in Gallatin County. 3.0 METHODS The field investigation and delineation of wetland areas followed the methods of the U.S. Army Corps of Engineers (COE) as authorized by 1977 Executive Order and Section 404 of the Clean Water Act, and explained in the 1987 COE Wetlands Manual (COE, 1987; WTI, 1999). The recently published Regional Supplements to the Corps of Engineers Wetland Delineation Manual: Western Mountains, Valleys, and Coast Region (Version 2.0) were also followed (COE, 2010a). A Level 3 Routine Determination method was used to delineate wetlands (COE, 1987). The area assessed extended a minimum of 75 feet on both sides of the center of Oak Street so that any area of wetlands that may be impacted as a result of considered street improvements would be included. On-site evaluations used aerial photos, calibrated and quantified survey data from Sanderson Stewart, LIDAR topographic data from the City of Bozeman, field investigations, and field measurements. In addition, a review of published records, survey maps, and interviews with appropriate experts or persons with specific knowledge of the site were used to finalize the delineation. Representative site photos of the wetlands and drainageways are included in Appendix A. Field delineation forms are included in Appendix B. Additional methodology information describing the delineation process and indicators, jurisdictional determination, and specific references used, are included in Appendix C. 4.0 RESULTS AND DISCUSSION The scope of the wetland evaluation included assessment of ten drainageways that cross Oak Street within the proposed project area (Figures 1 and 2). The drainageways include stormwater drainage ditches, irrigation ditches, and streams, or a combination of those features. Regional drainage in the vicinity of Oak Street is to the north to the East Gallatin River, with local small-scale variations. Oak Street trends perpendicular to regional slope, so that flows within each drainageway are approximately P:15022_Oak_Street_Wetland_Report_101215_SC 2 (10/12/15) CT/jil right angles to the street. There is a strong influence of land use on the vegetation, and therefore, Cowardin wetland classification. Several of the wetlands associated with a single source of hydrology have distinctly different vegetation across different property boundaries and on opposite sides of the street. The following Table identifies the drainageway, wetland, Cowardin classification of any wetland, area of wetland delineated, and anticipated jurisdictional status. Drainageway Wetland Wetland Classification (Cowardin) Area (acres) Anticipated Jurisdictional Status 1 Ephemeral stormwater ditch Not likely WOUS 2 Mandeville Creek 2 N: emergent S: scrub-shrub 0.027 Likely 3 Ephemeral stormwater ditch; Farmers Canal 3 Scrub-shrub 0.019 Not likely 4 East Fork of East Catron Creek 4 Emergent 0.028 Likely 5 Un-named tributary to East Catron Creek 5 N: emergent S: scrub-shrub 0.017 Likely Stormwater detention pond 5a Emergent 0.023 Not likely 6 Abandoned channel Cattail Creek 6 Emergent 0.018 Not likely 7 Cattail Creek 7 Scrub-shrub 0.002 Likely Stormwater detention pond 7a Scrub-shrub 0.008 Not likely 8 Section Line Ditch 8 Scrub-shrub 0.011 Likely 9 Tributary of Baxter Creek 9 Emergent 0.046 Likely Stormwater detention pond 9a Emergent 0.057 Likely Stormwater detention pond 9b Emergent 0.107 Not likely 10 Maynard Border Ditch Overflow 10 Emergent 0.016 Likely Notes to table: Drainageway names are primarily based upon City of Bozeman waterways GIS layer labels. N: North side of Oak Street S: South side of Oak Street WOUS: Waters of the US A summary discussion of the characteristics of each of the drainageways and associated wetlands are presented below. Representative site photos of drainageways and wetlands are included in Appendix A. Specific descriptions and details of the vegetation, hydrology, and soils of the sites are presented in the field delineation data sheets (Appendix B). The Montana Natural Heritage and US Fish and Wildlife Service mapping of riparian and wetland areas is shown in Figure 5 and the Natural Resources Conservation Service soil map (NRCS, 2015) for the project area is shown in Figure 6. #1 – Un-named Stormwater Ditch Drainageway #1 is located approximately 0.15 miles east of N 7th Ave. (Figure 3-1). The drainageway is part of the Bozeman stormwater system that consists of an open ditch on the south side of Oak Street, which then connects to underground piping that directs flows north under and beyond Oak Street. Culverted flows do not daylight in the near vicinity of Oak Street on the north side of the street. The City stormwater system ties into the East Gallatin River. A fringe of facultative (FAC) and facultative- P:15022_Oak_Street_Wetland_Report_101215_SC 3 (10/12/15) CT/jil wetland (FACW) vegetation is present within and along the edges of the ditch, indicating that flows are frequent enough to sustain some hydrophytic vegetation. However, flows within the ditch are ephemeral and only occur during stormwater runoff events, which does not meet the hydrologic requirement for continuity of saturated soils. The ditch was historically used for irrigation, but has not been employed for irrigation for many years (pers. comm.). Groundwater within the area is within the range of 20 feet below ground surface (MBMG, 2015). The US COE hydrology requirement for a wetland is not met at this drainageway. #2 – Mandeville Creek Drainageway #2 is Mandeville Creek, which crosses Oak Street approximately 0.17 miles west of North 7th Avenue (Figure 3-2). Mandeville Creek is a perennial stream. The stream has been re-aligned and impacted during construction of Oak Street and development of properties bordering the stream. The stream channel on the north side has been landscaped close to the edge of water with Kentucky bluegrass (FAC), but a diverse community of facultative-wetland (FAC-W) and obligate wetland vegetation persists in the stream fringes and channel. On the south side of Oak Street, the stream edges are characterized by vegetation that has been less altered and impacted, but the system has still been heavily impacted from fill materials related to street construction and adjacent land management practices. There are both fringe and in-channel wetlands in the Mandeville Creek drainageway. The stream channel and adjacent area show both wetland hydrology indicators and hydrophytic vegetation (Appendix B). On the north side, soil test pits were not dug due to inundation. The inundation in the Kentucky bluegrass lawn area was likely a mixture of water from the drainageway system and water due to heavy landscaping irrigation. Soil test pits that were dug adjacent to the creek on the south side of Oak Street encountered abundant near-surface cobbles. The cobbles may reflect historic stream channel meandering or simply be due to fill related to construction of Oak Street or the developments adjacent to the stream. An historic shrub/scrub area on the south side of Oak Street, west of the stream and outside of the fringe area influenced by current stream hydrology, has been impacted by road construction and development and no longer has a connection to hydrology that meets the US COE requirements for wetland hydrology. #3 – Farmers Canal Drainageway #3 crosses Oak Street approximately 0.22 miles east of N 19th Avenue (Figure 3-3). On the south side of Oak Street is an open stormwater ditch that directs flows underground and connects to Farmers Canal, which daylights on the north side of Oak Street. This stormwater ditch is an ephemeral ditch that only flows during runoff events. Historical uses likely included irrigation use prior to the surrounding land development. Discussions with the current landowner indicated that this ditch has not been used for irrigation for a number of years and only flows during runoff events. A depressional swale on the north side of Oak Street, upstream of the location at which Farmers Canal emerges from underground piping, contains wetlands (Wetland 3). This swale area is likely part of the historic drainageway that was present before impacts from development. Hydrophytic vegetation is present. Although the swale area was dry during the site visit, watermarks, drainage patterns and the geomorphic position of the depressional swale present evidence that there is accumulation and ponding of water in this depression during the early growing season. P:15022_Oak_Street_Wetland_Report_101215_SC 4 (10/12/15) CT/jil #4 – East Fork of East Catron Creek Drainageway #4 contains the East Fork of East Catron Creek, crossing Oak Street approximately 0.1 miles west of North 19th Avenue (Figure 3-4). Flows within the creek are perennial. The stream channel has been altered/re-aligned during development of the surrounding area. Wetland 4 is within and bordering the creek channel, on both the south and north side of Oak Street. There are residences surrounding the creek channel on the south side, with landscaped yards bordering the emergent vegetated wetland corridor. On the north side of Oak Street, the stream corridor is bordered by streets and commercial development. The wetland vegetation on the south side is relatively diverse, with numerous herbaceous wetland species present. On the north side, the wetland is strongly dominated by reed canary grass. #5 – West Fork of East Catron Creek Drainageway #5 is a tributary to East Catron Creek (informally, the West Fork of East Catron Creek) that crosses Oak Street approximately 0.25 miles west of North 19th Avenue (Figure 3-5). The flows within the creek are perennial; however the creek channel has been altered/re-aligned as a result of surrounding development. Wetland 5 is within and along the edge of the stream channel, on both sides of Oak Street. Residences are located on both sides of the creek channel on the south side, with landscaped yards bordering the emergent vegetated wetland corridor. The herbaceous strata of the wetland vegetation on the north side of Oak Street is strongly dominated by reed canary grass. As in Drainageway #4, there is much more diverse broadleaf wetland vegetation adjacent to the stream in the residential development. It seems likely that there are impacts of broadleaf herbicides reducing the diversity of the wetland vegetation in the non-residential areas. Wetland 5a is located on the north side of Oak Street, just east of Wetland 5. Wetland 5a is a constructed stormwater detention basin component of the stormwater drainage system of the City of Bozeman. The wetland is characterized by an obligate wetland vegetation community, mainly cattails, and was inundated during the site visit. Wetland 5a is connected to the West Fork of East Catron Creek on the north end of the basin. #6 – Abandoned Channel of Cattail Creek Wetland 6 is located just north of Oak Street, approximately 0.15 miles west of North 27th Avenue (Figure 3-6). The wetland is located in an abandoned channel of Cattail Creek. The straight channel and steep-sides of the linear depression suggest that this historic reach of Cattail Creek was likely channelized at some time. There is currently no observable inlet or outlet structure in the isolated ditch segment, and the depression was dry during the site visit. Hydrology within the isolated ditch segment is likely intermittent, provided by surface water runoff, and perhaps seasonal groundwater. Groundwater depths within the area have been measured at 3 to 8 feet below ground surface (MBMG, 2015). The steep sides of the depression are vegetated by reed canary grass, a facultative-wetland (FAC-W) species. #7 – Cattail Creek Drainageway #7 is Cattail Creek, crossing Oak Street approximately 0.2 miles west of North 27th Avenue (Figure 3-7). Cattail Creek is an intermittent stream that was dry at the time of fieldwork. South of Oak Street the creek has been channelized and lined with rock. There is no wetland vegetation in or P:15022_Oak_Street_Wetland_Report_101215_SC 5 (10/12/15) CT/jil adjacent to the stream and therefore, no wetland associated with the stream on the south side of Oak Street. West of Cattail Creek, south of Oak Street, there is an excavated stormwater detention pond that is a component of the stormwater system for the City of Bozeman. There is a wetland established within this excavated depression, Wetland 7a. Although the adjacent stream was dry at the time of the site visit, there was standing water in Wetland 7a. Vegetation in Wetland 7a includes obligate wetland vegetation (cattails) just south of the area that was formally delineated. These observations suggest that Wetland 7a is also groundwater fed and is evidence of the depth to groundwater in the vicinity of Cattail Creek. Groundwater depths within the area have been measured at 3 to 8 feet below ground surface (MBMG, 2015). On the north side of Oak Street, Wetland 7 contains a narrow fringe of wetlands adjacent to the eroded channel of Cattail Creek and on the narrow lowest stream terrace. Surrounding the incised stream on a terrace higher than the stream bed is a large area of willows. It is likely these willows were established when the surrounding area was irrigated agricultural fields. Upgradient flood irrigation, augmented with flows from Cattail Creek, may have supported a higher groundwater table to facilitate establishment of the willows. #8 – Section Line Ditch Section Line Ditch crosses Oak Street at the intersection of Davis Lane (Figure 3-8). Wetland 8 is a fringe wetland associated with flows in Section Line Ditch on both the north and south side of Oak Street. Section Line Ditch is an excavated irrigation ditch that is well-maintained, with negligible channel vegetation. Flows are present in the ditch throughout the irrigation season. #9 – Unnamed Tributary to Baxter Creek Drainageway #9 is an unnamed tributary to Baxter Creek that crosses Oak Street approximately 0.1 mile east of Ferguson Avenue (Figure 3-9). Water was flowing within the tributary at the time of the site visit. The channel has been impacted by surrounding development and road construction. Wetland 9 contains wetlands within and along the edge of the stream on both the north and south sides of Oak Street. South of Oak Street the stream is relatively straight and channelized, with narrow associated fringe wetlands. For approximately 50 feet north of Oak Street the stream has been remediated, with a slightly meandering course and minor terrace development and wetland vegetation on those terraces. Beyond the remediated section of stream north of Oak Street, the stream reverts to a linear channelized and excavated course with narrow fringe wetlands reflecting the steep banks of the stream. Stormwater detention basins have been excavated to both the east and west of the stream on the south side of Oak Street. Both stormwater detention basins were inundated during fieldwork and each are characterized by a wetland vegetation community that includes obligate species (cattails). These detention basins are part of the City stormwater detention system. It is likely that these ponds are fed by groundwater in addition to the surface runoff. Wetland 9a was directly connected to the stream by a surface channel connection. No surface connection was observed between Wetland 9b and the stream. #10 – Maynard-Border Ditch Overflow Maynard-Border Overflow Ditch flows north along the west side of Flanders Mill Road (Figure 3-10). The ditch is narrow, but well defined with in-channel and fringe wetlands, Wetland 10. Water was P:15022_Oak_Street_Wetland_Report_101215_SC 6 (10/12/15) CT/jil flowing in the ditch at the time of the site visit. Hydrophytic vegetation consisted predominantly of reed canary grass. 5.0 WATERS OF THE U.S. The anticipated jurisdictional status of the wetlands is listed in the above table in Section 4. Irrigation ditches can be considered connected to waters of the US if the headwaters and return waters are both tied to a water of the US. City stormwater drainage system components may be considered jurisdictional if there is a surface channel connection to waters of the US as of the date of this delineation. At the time of this delineation, the COE is responsible for final decisions on jurisdictional determinations. Any waters or wetlands that are considered waters of the U.S. as defined by Section 404 of the Clean Water Act (Appendix C) fall under the jurisdiction of the COE and may need Section 404 permitting through the COE if impacts (fill) occur. It is important to note that the COE makes the final determination regarding the status of waters of the U.S., jurisdictional wetlands and mitigation requirements. P:15022_Oak_Street_Wetland_Report_101215_SC 7 (10/12/15) CT/jil 6.0 REFERENCES COE –see U.S. Army Corps of Engineers Department of Natural Resource Conservation, 2015. "Water Right Query System." Retrieved April 2013, http://nris.state.mt.us/apps/dnrc2002/waterrightmain.asp MBMG – see Montana Bureau of Mines and Geology MNHP – see Montana Natural Heritage Program Montana Natural Heritage Program, 2015. Community Field Guide Juncus balticus Herbaceous Vegetation: http://mtnhp.org/ecology/Guide_Report.asp? elcode=CEGL001838 . Montana Bureau of Mines and Geology, 2015. "Ground Water Information Center." Retrieved September 2015, from http://mbmggwic.mtech.edu/ Natural Resource Conservation Service, 2015. Web Soil Survey for Gallatin County. Retrieved September 2015 from http://websoilsurvey.nrcs.usda.gov/app/HomePage.htm Natural Resource Information System Montana State Library, 2015. "Online Interactive Map Builder." Retrieved from http://nris.state.mt.us/mapper/ September 2015. NRCS – see Natural Resource Conservation Service NRIS – see Natural Resource Information System - Montana State Library US Army Corps of Engineers, 1987. “Corps of Engineers Wetlands Delineation Manual.” US Army Corps of Engineers Technical Report Y-87-1: Vicksburg, MS. US Army Corps of Engineers, 2010a. “Regional Supplement to the Corps of Engineers Wetland Delineation Manual: Western Mountains, Valleys, and Coast Region (Version 2.0)”. May 2010. US Geological Survey, 1987. "Bozeman, Montana" 7.5 Minute Topographic Quadrangle Map. WTI, 1999. Wetland Training Institute, Inc. “Wetland Delineation Lecture Notes Based on Corps of Engineers 1987 Manual.” With revisions through 2001, WTI 99-1: Glenwood, NM. FIGURES mileskm58 Soil Unit Label Explanation for Figure 5 Soil Unit Label Soil Unit Name 450C Blackdog‐Quagle silt loams, 4 to 8 percent slopes 457A Turner loam, moderately wet, 0 to 2 percent slopes 509B Enbar loam, 0 to 4 percent slopes 50B Blackdog silt loam, 0 to 4 percent slopes 510B Meadowcreek loam, 0 to 4 percent slopes 53B Amsterdam silt loam, 0 to 4 percent slopes 542A Blossberg loam, 0 to 2 percent slopes 64B Straw loam, 0 to 4 percent slopes UL Urban land APPENDIX A Photographs Photo 1. Wetland 2, north side of Oak Street, looking north. Photo 2. Wetland 2, south side of Oak Street, looking south. Photo 3. Stormwater drainage ditch, south side of Oak Street (SP-3S), looking south-southeast. Photo 4. Farmers Canal, north side of Oak Street, looking north. Photo 5. Wetland 3, north side of Oak Street, looking north. Photo 6. Wetland 4, north side of Oak Street, looking north. Photo 7. Wetland 4, south side of Oak Street, looking south. Photo 8. Wetland 5, south side of Oak Street, looking south. Photo 9. Wetland 5, north side of Oak Street, looking north. Photo 10. Wetland 5a, stormwater detention basin, north side of Oak Street, looking north. Photo 11. Wetland 6 north side of Oak Street, looking south. Photo 12. Cattail Creek, south side of Oak Street, looking south. Photo 13. Stormwater detention pond (Wetland 7a) located south side of Oak Street, just west of Upper Cattail Creek. Looking south. Photo 14. Section Line Ditch, shrub / scrub Wetland 8, north side of Oak Street, looking north. (Between northbound and southbound lanes of Davis Lane.) Photo 15. Wetland 8 along Section Line Ditch, looking south. Photo 16. Wetland 9 located on south side of Oak Street, looking south. Wetland 9a is in the stormwater detention pond to the right (west) and Wetland 9b is in stormwater detention pond to the left (east). Photo 17. Wetland 9a in stormwater detention pond adjacent (west) of Wetland 9 on south side of Oak Street, looking west. Photo 18. Wetland 9 on north side of Oak Street, looking north. Photo 19. Wetland 10, looking south along west edge of Flanders Mill Road. APPENDIX B Delineation Data Sheets APPENDIX C Additional Methodology Information APPENDIX H: GEOTECHNICAL MEMORANDUM Responsive ■ Resourceful ■ Reliable i October 23, 2015 Sanderson Stewart 106 East Babcock Bozeman, Montana 59102 Attn: Ms. Danielle Scharf P: 406-922-4325 E: dscharf@sandersonstewart.com Subject: Preliminary Pavement Section Recommendations Proposed Oak Street Improvements – L Street to Cottonwood Road Bozeman, Montana Terracon Project No. AJ155000 Dear Ms. Scharf : Terracon Consultants, Inc. (Terracon) has completed the preliminary pavement section thickness recommendations for the proposed Oak Street Improvements -- L Street to Cottonwood Road project located on the west side of Bozeman, Montana. These recommendations are provided in accordance with our contract dated August 28, 2015. Our preliminary recommendations for flexible pavements for the Oak Street corridor under consideration are included in attached Table 1. Individual pavement sections were developed for six different traffic scenarios within the corridor. Some grouping of segments of the corridor with similar traffic conditions was performed for expediency. AASHTO 1993 pavement thickness design manual procedures were used in our analysis along with the assumptions listed below Table 1. Our recommended pavements sections require that the upper six inches of the in-place subgrade soils are scarified in place and compacted to 95% of the maximum laboratory dry density determined in accordance with AASHTO T99 procedures. Some of the subgrades may require geotextile to be placed on the subgrade prior to crushed base course. We further recommend that final pavement recommendations be based on a soil survey of the corridor that includes soil borings and laboratory testing of samples obtained during the survey. Such a survey would take into consideration existing pavement and aggregate quantity and quality, with the possibility of reuse of existing materials. Responsive ■ Resourceful ■ Reliable ii We appreciate the opportunity to be of service to you on this project. If you have any questions concerning these preliminary recommendations, or if we may be of further service, please contact us. Sincerely, Terracon Consultants, Inc. Jim Pierce, P.E. Ken Munski, P.E. Project Engineer Principal, Sr. Materials Engineer Copies: Client (3) File (1) TABLE 1 Preliminary Flexible Pavement Designs Oak Street Corridor , Terracon Project Number AJ155000 October 20, 2015 Section #Corridor 2035 Design 2015 AWT MAWT % Trucks 18K TEF Design Life Mr SN Asphalt CBC AWT Composite ESALs (psi) Required Thick. (Ins)Thick. (ins) 1 E of Cottonwood 6,250 4,206 5,228 1 0.0089 169,833 4500 3.2 4 12 & E of Flanders Mill Road 2 E of Ferguson Ave.14,900 10,027 12,464 1 0.0089 404,881 4500 3.6 4 14 3 E of Davis Lane 12,800 8,614 10,707 2 0.0089 347,817 4500 3.4 4 13 4 E of N 27th Ave. 13,500 9,085 11,293 3 0.0133 548,197 4500 3.8 4 16 & W of Rouse Ave. 5 E of N 7th Ave. 17,300 11,642 14,471 3 0.0133 702,505 4500 3.9 4 16 6 E of 11th, 15th 20,000 13,459 16,730 3 0.0133 812,144 4500 4 4 17 and 19th Aves. Note: 2035 AWT and % Trucks provided by Marvin and Associates Design Assumptions: Annual Growth Rate = 2% Abbreviations: AWT - Average Weekday Traffic 50% of MAWT in Design Lane MAWT - Mean Average Weekday Traffic TEF from Zimmerman Trail used (1.4% trucks) TEF - Truck Equivalency Factor, Composite of cars and trucks CBR = 3 psi ESAL - Equivalent Single 18k Axle Load Reliabilty = 95% Mr - Subgrade Modulus Standard Deviation = 0.35 CBC - Crushed Base Course Initial Serviceability = 4.2 E - East Terminal Serviceability = 2.0 ins - inches a1= 0.41 SN - Structural Number a2=0.14 m1=1.0 m2=1.0 January 11, 2016 Sanderson Stewart 106 East Babcock Bozeman, Montana 59102 Attn: Ms. Danielle Scharf P: 406-922-4325 E: dscharf@sandersonstewart.com Subject: Additional Preliminary Pavement Section Recommendations Proposed Oak Street Improvements – L Street to Cottonwood Road Bozeman, Montana Terracon Project No. AJ155000 Dear Ms. Scharf : Terracon Consultants, Inc. (Terracon) has completed the additional preliminary pavement section thickness recommendations for the proposed Oak Street Improvements -- L Street to Cottonwood Road project located on the west side of Bozeman, Montana. These recommendations include flexible pavement options that incorporate subbase and a minimum amount of crushed base course (6 inches) for each of the Oak Street sections. Our additional preliminary recommendations for flexible pavements for the Oak Street corridor under consideration are included as Option B in attached Table 1. As we indicated in our original report, our recommended pavements sections require that the upper six inches of the in-place subgrade soils are scarified in place and compacted to 95% of the maximum laboratory dry density determined in accordance with AASHTO T99 procedures. Some of the subgrades may require geotextile to be placed on the subgrade prior to crushed base course. We appreciate the opportunity to be of service to you on this project. If you have any questions concerning these preliminary recommendations, or if we may be of further service, please contact us. Sincerely, Terracon Consultants, Inc. Jim Pierce, P.E. Ken Munski, P.E. Project Engineer Principal, Sr. Materials Engineer TABLE 1 Preliminary Flexible Pavement Designs Oak Street Corridor , Terracon Project Number AJ155000 January 11, 2016 Flexible Pavement Components Thickness (inches) Section #Corridor 2035 Design 2015 AWT MAWT % Trucks 18K TEF Design Life Mr Min. SN SN Asphalt CBC Subbase Total AWT Composite ESALs (psi) Required Actual Option A E of Cottonwood 6,250 4,206 5,228 1 0.0089 169,833 4500 3.2 3.2 4 11 0 15 Option B & E of Flanders 3.2 3 6 11 20 Mill Road Option A E of Ferguson Ave.14,900 10,027 12,464 1 0.0089 404,881 4500 3.6 3.6 4 14 0 18 Option B 3.6 4 6 11 21 Option A E of Davis Lane 12,800 8,614 10,707 2 0.0089 347,817 4500 3.4 3.5 4 13 0 17 Option B 3.4 4 6 9 19 Option A E of N 27th Ave. 13,500 9,085 11,293 3 0.0133 548,197 4500 3.8 3.9 4 16 0 20 Option B & W of Rouse Ave.3.8 4 6 13 23 Option A E of N 7th Ave. 17,300 11,642 14,471 3 0.0133 702,505 4500 3.9 3.9 4 16 0 20 Option B 3.9 4 6 14 24 Option A E of 11th, 15th 20,000 13,459 16,730 3 0.0133 812,144 4500 4 4.0 4 17 0 21 Option B and 19th Aves. 4.0 4 6 15 25 Note: 2035 AWT and % Trucks provided by Marvin and Associates Design Assumptions: Annual Growth Rate = 2% Abbreviations: AWT - Average Weekday Traffic 50% of MAWT in Design Lane MAWT - Mean Average Weekday Traffic TEF from Zimmerman Trail used (1.4% trucks) TEF - Truck Equivalency Factor, Composite of cars and trucks CBR = 3 psi ESAL - Equivalent Single 18k Axle Load Reliabilty = 95% Mr - Subgrade Modulus Standard Deviation = 0.35 CBC - Crushed Base Course Initial Serviceability = 4.2 E - East , W - West Terminal Serviceability = 2.0 ins - inches Structural Coefficients : a1 (asphalt) = 0.41, a2 (CBC) = 0.14, a3 (SB) = 0.10 SN - Structural Number Drainage Coefficients: m1 = 1.0, m2 = 1.0 APPENDIX I: OPINIONS OF PROBABLE COST Oak Street Improvements - Preliminary Opinion of Probable CostTotal CostQuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal QuantityUnit Price Subtotal101 Mobilization/Demobilization LS 1 166,407.77$ 166,407.77$ 1 205,654.61$ 205,654.61$ 1 106,140.55$ 106,140.55$ 1 148,490.26$ 148,490.26$ 1 130,252.40$ 130,252.40$ 1 48,183.77$ 48,183.77$ 1 160,271.06$ 160,271.06$ 1 41,431.65$ 41,431.65$ 1 60,360.14$ 60,360.14$ 1 58,600.07$ 58,600.07$ 1 52,237.41$ 52,237.41$ 1 172,846.58$ 172,846.58$ 1,350,876.27$ 102Taxes, Bonds, Insurance LS 1 69,336.57$ 69,336.57$ 1 85,689.42$ 85,689.42$ 1 44,225.23$ 44,225.23$ 1 61,870.94$ 61,870.94$ 1 54,271.83$ 54,271.83$ 1 20,076.57$ 20,076.57$ 1 66,779.61$ 66,779.61$ 1 17,263.19$ 17,263.19$ 1 25,150.06$ 25,150.06$ 1 24,416.70$ 24,416.70$ 1 21,765.59$ 21,765.59$ 1 72,019.41$ 72,019.41$ 562,865.11$ 103Traffic Control LS 1 66,034.83$ 66,034.83$ 1 81,608.97$ 81,608.97$ 1 42,119.27$ 42,119.27$ 1 58,924.71$ 58,924.71$ 1 51,687.46$ 51,687.46$ 1 19,120.54$ 19,120.54$ 1 63,599.63$ 63,599.63$ 1 45,034.40$ 45,034.40$ 1 23,952.44$ 23,952.44$ 1 23,254.00$ 23,254.00$ 1 56,779.79$ 56,779.79$ 1 68,589.91$ 68,589.91$ 600,705.94$ 104 Stormwater Management and Erosion Control LS 1 13,076.20$ 13,076.20$ 1 16,160.19$ 16,160.19$ 1 8,340.45$ 8,340.45$ 1 11,668.26$ 11,668.26$ 1 10,235.14$ 10,235.14$ 1 3,786.25$ 3,786.25$ 1 12,593.99$ 12,593.99$ 1 2,972.57$ 2,972.57$ 1 4,743.06$ 4,743.06$ 1 4,604.75$ 4,604.75$ 1 3,747.84$ 3,747.84$ 1 13,582.16$ 13,582.16$ 105,510.85$ 105 Clearing and GrubbingLS 1 2,584.23$ 2,584.23$ 1 3,193.71$ 3,193.71$ 1 1,648.31$ 1,648.31$ 1 2,305.98$ 2,305.98$ 1 2,022.76$ 2,022.76$ 1 748.27$ 748.27$ 1 2,488.93$ 2,488.93$ 1 587.46$ 587.46$ 1 937.36$ 937.36$ 1 910.03$ 910.03$ 1 740.68$ 740.68$ 1 2,684.22$ 2,684.22$ 20,851.95$ 106 DewateringLS 1 12,921.15$ 12,921.15$ 1 15,968.57$ 15,968.57$ 1 8,241.55$ 8,241.55$ 1 11,529.90$ 11,529.90$ 1 10,113.78$ 10,113.78$ 1 3,741.35$ 3,741.35$ 1 12,444.65$ 12,444.65$ 1 2,937.32$ 2,937.32$ 1 4,686.82$ 4,686.82$ 1 4,550.15$ 4,550.15$ 1 3,703.40$ 3,703.40$ 1 13,421.11$ 13,421.11$ 104,259.74$ 107Topsoil Stripping and Stockpile LS 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 0 2,000.00$ -$ 0 2,000.00$ -$ 1 1,000.00$ 1,000.00$ 1 2,000.00$ 2,000.00$ 1 2,000.00$ 2,000.00$ 1 1,000.00$ 1,000.00$ 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 24,000.00$ 108 Unclassified Excavation CY4,800 7.00$ 33,600.00$ 6,000 7.00$ 42,000.00$ 1,900 7.00$ 13,300.00$ 3,600 7.00$ 25,200.00$ 2,520 7.00$ 17,640.00$ 0 7.00$ -$ 3,600 7.00$ 25,200.00$ 500 7.00$ 3,500.00$ 1,300 7.00$ 9,100.00$ 580 7.00$ 4,060.00$ 600 7.00$ 4,200.00$ 2,150 7.00$ 15,050.00$ 192,850.00$ 109 Subexcavation CY5,385 12.00$ 64,620.00$ 6,500 12.00$ 78,000.00$ 1,900 12.00$ 22,800.00$ 3,600 12.00$ 43,200.00$ 2,660 12.00$ 31,920.00$ 0 12.00$ -$ 3,250 12.00$ 39,000.00$ 460 12.00$ 5,520.00$ 1,100 12.00$ 13,200.00$ 500 12.00$ 6,000.00$ 535 12.00$ 6,420.00$ 1,910 12.00$ 22,920.00$ 333,600.00$ 110 Sawcut Existing AsphaltLF 60 1.00$ 60.00$ 0 1.00$ -$ 350 1.00$ 350.00$ 160 1.00$ 160.00$ 1,000 1.00$ 1,000.00$ 415 1.00$ 415.00$ 4,050 1.00$ 4,050.00$ 362 1.00$ 362.00$ 1,211 1.00$ 1,211.00$ 90 1.00$ 90.00$ 590 1.00$ 590.00$ 5,290 1.00$ 5,290.00$ 13,578.00$ 111 Remove Existing AsphaltSY400 12.00$ 4,800.00$ 0 12.00$ -$ 80 12.00$ 960.00$ 730 12.00$ 8,760.00$ 1,070 12.00$ 12,840.00$ 185 12.00$ 2,220.00$ 1,800 12.00$ 21,600.00$ 80 12.00$ 960.00$ 2,206 12.00$ 26,472.00$ 790 12.00$ 9,480.00$ 260 12.00$ 3,120.00$ 250 12.00$ 3,000.00$ 94,212.00$ 112 Remove Curb and Gutter LF 180 5.00$ 900.00$ 0 5.00$ -$ 350 5.00$ 1,750.00$ 100 5.00$ 500.00$ 1,160 5.00$ 5,800.00$ 350 5.00$ 1,750.00$ 3,650 5.00$ 18,250.00$ 362 5.00$ 1,810.00$ 0 5.00$ -$ 40 5.00$ 200.00$ 585 5.00$ 2,925.00$ 400 5.00$ 2,000.00$ 35,885.00$ 113 Remove SidewalkSY40 12.00$ 480.00$ 0 12.00$ -$ 20 12.00$ 240.00$ 0 12.00$ -$ 100 12.00$ 1,200.00$ 50 12.00$ 600.00$ 1,650 12.00$ 19,800.00$ 270 12.00$ 3,240.00$ 0 12.00$ -$ 50 12.00$ 600.00$ 270 12.00$ 3,240.00$ 250 12.00$ 3,000.00$ 32,400.00$ 114 Imported Fill CY5,385 25.00$ 134,625.00$ 6,500 25.00$ 162,500.00$ 1,900 25.00$ 47,500.00$ 3,600 25.00$ 90,000.00$ 2,660 25.00$ 66,500.00$ 0 25.00$ -$ 3,250 25.00$ 81,250.00$ 460 25.00$ 11,500.00$ 1,100 25.00$ 27,500.00$ 500 25.00$ 12,500.00$ 535 25.00$ 13,375.00$ 1,910 25.00$ 47,750.00$ 695,000.00$ 115 1 1/2-inch Minus Crushed Base Course CY3,600 26.00$ 93,600.00$ 4,300 26.00$ 111,800.00$ 4,745 26.00$ 123,370.00$ 2,800 26.00$ 72,800.00$ 1,920 26.00$ 49,920.00$ 200 26.00$ 5,200.00$ 2,880 26.00$ 74,880.00$ 400 26.00$ 10,400.00$ 1,050 26.00$ 27,300.00$ 470 26.00$ 12,220.00$ 475 26.00$ 12,350.00$ 1,700 26.00$ 44,200.00$ 638,040.00$ 116 Geotextile Fabric (Street Base) SY10,800 2.00$ 21,600.00$ 13,000 2.00$ 26,000.00$ 3,800 2.00$ 7,600.00$ 7,025 2.00$ 14,050.00$ 5,320 2.00$ 10,640.00$ 460 2.00$ 920.00$ 6,500 2.00$ 13,000.00$ 920 2.00$ 1,840.00$ 2,206 2.00$ 4,412.00$ 1,000 2.00$ 2,000.00$ 1,070 2.00$ 2,140.00$ 3,820 2.00$ 7,640.00$ 111,842.00$ 117 4-inch Asphalt Pavement (2 lifts) SY10,800 20.00$ 216,000.00$ 13,000 20.00$ 260,000.00$ 3,800 20.00$ 76,000.00$ 7,025 20.00$ 140,500.00$ 5,320 20.00$ 106,400.00$ 460 20.00$ 9,200.00$ 6,500 20.00$ 130,000.00$ 920 20.00$ 18,400.00$ 2,206 20.00$ 44,120.00$ 1,000 20.00$ 20,000.00$ 1,070 20.00$ 21,400.00$ 3,820 20.00$ 76,400.00$ 1,118,420.00$ 118 Curb and Gutter LF 4,100 15.00$ 61,500.00$ 7,750 15.00$ 116,250.00$ 2,200 15.00$ 33,000.00$ 4,350 15.00$ 65,250.00$ 2,065 15.00$ 30,975.00$ 115 15.00$ 1,725.00$ 3,650 15.00$ 54,750.00$ 325 15.00$ 4,875.00$ 1,200 15.00$ 18,000.00$ 730 15.00$ 10,950.00$ 563 15.00$ 8,445.00$ 5,090 15.00$ 76,350.00$ 482,070.00$ 119 Curb Return FilletSF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 2,000 9.00$ 18,000.00$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 400 9.00$ 3,600.00$ 21,600.00$ 120 Concrete Valley Gutter SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 800 9.00$ 7,200.00$ 0 9.00$ -$ 0 9.00$ -$ 1,000 9.00$ 9,000.00$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 200 9.00$ 1,800.00$ 18,000.00$ 121 Concrete Drive Approach SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 185 9.00$ 1,665.00$ 850 9.00$ 7,650.00$ 9,315.00$ 122 SidewalkSF 16,400 6.00$ 98,400.00$ 23,292 6.00$ 139,752.00$ 7,580 6.00$ 45,480.00$ 14,425 6.00$ 86,550.00$ 6,080 6.00$ 36,480.00$ 800 6.00$ 4,800.00$ 20,200 6.00$ 121,200.00$ 2,060 6.00$ 12,360.00$ 12,100 6.00$ 72,600.00$ 3,000 6.00$ 18,000.00$ 3,000 6.00$ 18,000.00$ 14,520 6.00$ 87,120.00$ 740,742.00$ 123 Stamped Rollover Concrete SF 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ -$ 124 ADA Ramps SF 800 15.00$ 12,000.00$ 800 15.00$ 12,000.00$ 480 15.00$ 7,200.00$ 2,000 15.00$ 30,000.00$ 480 15.00$ 7,200.00$ 480 15.00$ 7,200.00$ 1,100 15.00$ 16,500.00$ 400 15.00$ 6,000.00$ 0 15.00$ -$ 540 15.00$ 8,100.00$ 120 15.00$ 1,800.00$ 300 15.00$ 4,500.00$ 112,500.00$ 125Truncated Domes SF 64 20.00$ 1,280.00$ 64 20.00$ 1,280.00$ 64 20.00$ 1,280.00$ 160 20.00$ 3,200.00$ 64 20.00$ 1,280.00$ 64 20.00$ 1,280.00$ 88 20.00$ 1,760.00$ 32 20.00$ 640.00$ 0 20.00$ -$ 72 20.00$ 1,440.00$ 16 20.00$ 320.00$ 32 20.00$ 640.00$ 14,400.00$ 126 Grass Seeding and Fertilizer SY6,800 2.25$ 15,300.00$ 11,300 2.25$ 25,425.00$ 4,300 2.25$ 9,675.00$ 11,400 2.25$ 25,650.00$ 2,970 2.25$ 6,682.50$ 500 2.25$ 1,125.00$ 4,500 2.25$ 10,125.00$ 100 2.25$ 225.00$ 874 2.25$ 1,966.50$ 500 2.25$ 1,125.00$ 600 2.25$ 1,350.00$ 4,667 2.25$ 10,500.75$ 109,149.75$ 127 Landscaping/Street Trees LS 1 5,000.00$ 5,000.00$ 1 20,000.00$ 20,000.00$ 1 5,000.00$ 5,000.00$ 1 20,000.00$ 20,000.00$ 1 5,000.00$ 5,000.00$ 0 200.00$ -$ 1 20,000.00$ 20,000.00$ 0 200.00$ -$ 0 200.00$ -$ 1 2,000.00$ 2,000.00$ 1 2,000.00$ 2,000.00$ 150 200.00$ 30,000.00$ 109,000.00$ 128 New Sign on New PostEA 20 500.00$ 10,000.00$ 30 500.00$ 15,000.00$ 20 500.00$ 10,000.00$ 30 500.00$ 15,000.00$ 20 500.00$ 10,000.00$ 10 500.00$ 5,000.00$ 20 500.00$ 10,000.00$ 1 500.00$ 500.00$ 0 500.00$ -$ 20 500.00$ 10,000.00$ 4 500.00$ 2,000.00$ 15 500.00$ 7,500.00$ 95,000.00$ 129 Remove or Relocate Existing Signs EA 15 250.00$ 3,750.00$ 0 250.00$ -$ 12 250.00$ 3,000.00$ 20 250.00$ 5,000.00$ 12 250.00$ 3,000.00$ 20 250.00$ 5,000.00$ 20 250.00$ 5,000.00$ 1 250.00$ 250.00$ 6 250.00$ 1,500.00$ 4 250.00$ 1,000.00$ 4 250.00$ 1,000.00$ 25 250.00$ 6,250.00$ 34,750.00$ 130Thermoplastic StripingLF 8,000 10.00$ 80,000.00$ 8,000 10.00$ 80,000.00$ 3,360 10.00$ 33,600.00$ 4,752 10.00$ 47,520.00$ 5,920 10.00$ 59,200.00$ 5,100 10.00$ 51,000.00$ 12,760 10.00$ 127,600.00$ 850 10.00$ 8,500.00$ 2,270 10.00$ 22,700.00$ 2,100 10.00$ 21,000.00$ 3,320 10.00$ 33,200.00$ 17,800 10.00$ 178,000.00$ 742,320.00$ 131Thermoplastic Words & Symbols EA 55 350.00$ 19,250.00$ 16 350.00$ 5,600.00$ 21 350.00$ 7,350.00$ 16 350.00$ 5,600.00$ 32 350.00$ 11,200.00$ 30 350.00$ 10,500.00$ 30 350.00$ 10,500.00$ 8 350.00$ 2,800.00$ 6 350.00$ 2,100.00$ 24 350.00$ 8,400.00$ 20 350.00$ 7,000.00$ 42 350.00$ 14,700.00$ 105,000.00$ 132 Street Lights EA 4 7,000.00$ 28,000.00$ 14 7,000.00$ 98,000.00$ 4 7,000.00$ 28,000.00$ 14 7,000.00$ 98,000.00$ 4 7,000.00$ 28,000.00$ 4 7,000.00$ 28,000.00$ 10 7,000.00$ 70,000.00$ 3 7,000.00$ 21,000.00$ 6 7,000.00$ 42,000.00$ 4 7,000.00$ 28,000.00$ 4 7,000.00$ 28,000.00$ 11 7,000.00$ 77,000.00$ 574,000.00$ 133 Connect to Existing Storm Drain EA 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 2 1,500.00$ 3,000.00$ 1 1,500.00$ 1,500.00$ 0 1,500.00$ -$ 2 1,500.00$ 3,000.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 3 1,500.00$ 4,500.00$ 22,500.00$ 134 Storm Drain Main (15-Inch to 36-Inch) LF 675 90.00$ 60,750.00$ 1,950 90.00$ 175,500.00$ 700 90.00$ 63,000.00$ 1,965 90.00$ 176,850.00$ 1,250 90.00$ 112,500.00$ 0 90.00$ -$ 1,750 90.00$ 157,500.00$ 50 90.00$ 4,500.00$ 800 90.00$ 72,000.00$ 200 90.00$ 18,000.00$ 0 90.00$ -$ 3,000 90.00$ 270,000.00$ 1,110,600.00$ 135 12-Inch Storm Drain Inlet Pipe LF 100 50.00$ 5,000.00$ 1,000 50.00$ 50,000.00$ 100 50.00$ 5,000.00$ 1,000 50.00$ 50,000.00$ 280 50.00$ 14,000.00$ 0 50.00$ -$ 900 50.00$ 45,000.00$ 225 50.00$ 11,250.00$ 250 50.00$ 12,500.00$ 200 50.00$ 10,000.00$ 220 50.00$ 11,000.00$ 725 50.00$ 36,250.00$ 250,000.00$ 136 New Curb InletEA 4 3,500.00$ 14,000.00$ 20 3,500.00$ 70,000.00$ 4 3,500.00$ 14,000.00$ 20 3,500.00$ 70,000.00$ 4 3,500.00$ 14,000.00$ 0 3,500.00$ -$ 18 3,500.00$ 63,000.00$ 3 3,500.00$ 10,500.00$ 6 3,500.00$ 21,000.00$ 2 3,500.00$ 7,000.00$ 2 3,500.00$ 7,000.00$ 29 3,500.00$ 101,500.00$ 392,000.00$ 137 Storm Drain Manhole EA 1 4,000.00$ 4,000.00$ 10 4,000.00$ 40,000.00$ 1 4,000.00$ 4,000.00$ 10 4,000.00$ 40,000.00$ 1 4,000.00$ 4,000.00$ 0 4,000.00$ -$ 9 4,000.00$ 36,000.00$ 1 4,000.00$ 4,000.00$ 2 4,000.00$ 8,000.00$ 1 4,000.00$ 4,000.00$ 1 4,000.00$ 4,000.00$ 17 4,000.00$ 68,000.00$ 216,000.00$ 138 Private Utilities Relocation LS 0 -$ -$ 0 -$ -$ 1 31,500.00$ 31,500.00$ 0 -$ -$ 1 117,000.00$ 117,000.00$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 148,500.00$ 139 Detention Ponds CY1,500 15.00$ 22,500.00$ 2,150 15.00$ 32,250.00$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 500 15.00$ 7,500.00$ 0 15.00$ -$ 500 15.00$ 7,500.00$ 190 15.00$ 2,850.00$ 0 15.00$ -$ 3,000 15.00$ 45,000.00$ 117,600.00$ 140 Outfall Structures and PipingEA 1 25,000.00$ 25,000.00$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 0 25,000.00$ -$ 0 25,000.00$ -$ 0 25,000.00$ -$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 1 25,000.00$ 25,000.00$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 3 25,000.00$ 75,000.00$ 200,000.00$ 141 Water/Sewer/Storm Adjustments LS 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 60,000.00$ 142Traffic Signal Improvements LS 1 247,600.00$ 247,600.00$ 0 -$ -$ 1 220,700.00$ 220,700.00$ 0 -$ -$ 1 240,500.00$ 240,500.00$ 1 233,200.00$ 233,200.00$ 0 -$ -$ 1 140,300.00$ 140,300.00$ 0 -$ -$ 1 203,500.00$ 203,500.00$ 1 165,300.00$ 165,300.00$ 0 -$ -$ 1,451,100.00$ 143 Roundabout Hawk Signals EA 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ -$ Subtotal 1,622,475.75$ 2,005,132.49$ 1,034,870.35$ 1,447,780.05$ 1,269,960.86$ 469,791.75$ 1,562,642.87$ 403,958.59$ 588,511.37$ 571,350.70$ 509,314.70$ 1,685,254.14$ 13,171,043.61$ 15% Design & CA 243,371.36$ 300,769.87$ 155,230.55$ 217,167.01$ 190,494.13$ 70,468.76$ 234,396.43$ 60,593.79$ 88,276.71$ 85,702.60$ 76,397.20$ 252,788.12$ 1,975,656.54$ 15% Construction Contingency243,371.36$ 300,769.87$ 155,230.55$ 217,167.01$ 190,494.13$ 70,468.76$ 234,396.43$ 60,593.79$ 88,276.71$ 85,702.60$ 76,397.20$ 252,788.12$ 1,975,656.54$ Subtotal Plus Contingency2,109,218.48$ 2,606,672.23$ 1,345,331.46$ 1,882,114.06$ 1,650,949.11$ 610,729.27$ 2,031,435.73$ 525,146.17$ 765,064.78$ 742,755.91$ 662,109.11$ 2,190,830.38$ 17,122,356.69$ Signal Alternative19th to 15th SignalSignal 7th to RouseSignal Signal 27th to 19th SignalOak & 11th Oak & 7th Oak StreetSignal Cottonwood to FergusonSignal Ferguson to DavisOak & 27th Oak Street Oak & 19th Oak StreetOak Street Oak & Ferguson Oak Street Oak & DavisSignalized AlternativeItem No. Description UnitOak & Cottonwood Oak Street Improvements - Preliminary Opinion of Probable CostTotal CostQuantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal101 Mobilization/DemobilizationLS 1 184,565.75$ 184,565.75$ 1 205,654.61$ 205,654.61$ 1 144,817.64$ 144,817.64$ 1 148,490.26$ 148,490.26$ 1 138,974.95$ 138,974.95$ 1 134,168.88$ 134,168.88$ 1 160,271.06$ 160,271.06$ 1 41,431.65$ 41,431.65$ 1 60,360.14$ 60,360.14$ 1 136,786.54$ 136,786.54$ 1 52,237.41$ 52,237.41$ 1 172,846.58$ 172,846.58$ 1,580,605.47$ 102Taxes, Bonds, Insurance LS 1 76,902.40$ 76,902.40$ 1 85,689.42$ 85,689.42$ 1 60,340.68$ 60,340.68$ 1 61,870.94$ 61,870.94$ 1 57,906.23$ 57,906.23$ 1 55,903.70$ 55,903.70$ 1 66,779.61$ 66,779.61$ 1 17,263.19$ 17,263.19$ 1 25,150.06$ 25,150.06$ 1 56,994.39$ 56,994.39$ 1 21,765.59$ 21,765.59$ 1 72,019.41$ 72,019.41$ 658,585.61$ 103Traffic Control LS 1 73,240.38$ 73,240.38$ 1 81,608.97$ 81,608.97$ 1 57,467.32$ 57,467.32$ 1 58,924.71$ 58,924.71$ 1 55,148.79$ 55,148.79$ 1 53,241.62$ 53,241.62$ 1 63,599.63$ 63,599.63$ 1 45,034.40$ 45,034.40$ 1 23,952.44$ 23,952.44$ 1 54,280.37$ 54,280.37$ 1 56,779.79$ 56,779.79$ 1 68,589.91$ 68,589.91$ 691,868.32$ 104 Stormwater Management and Erosion Control LS 1 14,503.04$ 14,503.04$ 1 16,160.19$ 16,160.19$ 1 11,379.67$ 11,379.67$ 1 11,668.26$ 11,668.26$ 1 10,920.55$ 10,920.55$ 1 10,542.89$ 10,542.89$ 1 12,593.99$ 12,593.99$ 1 2,972.57$ 2,972.57$ 1 4,743.06$ 4,743.06$ 1 10,748.59$ 10,748.59$ 1 3,747.84$ 3,747.84$ 1 13,582.16$ 13,582.16$ 123,562.81$ 105 Clearing and Grubbing LS 1 2,866.21$ 2,866.21$ 1 3,193.71$ 3,193.71$ 1 2,248.95$ 2,248.95$ 1 2,305.98$ 2,305.98$ 1 2,158.21$ 2,158.21$ 1 2,083.58$ 2,083.58$ 1 2,488.93$ 2,488.93$ 1 587.46$ 587.46$ 1 937.36$ 937.36$ 1 2,124.23$ 2,124.23$ 1 740.68$ 740.68$ 1 2,684.22$ 2,684.22$ 24,419.53$ 106 Dewatering LS 1 14,331.07$ 14,331.07$ 1 15,968.57$ 15,968.57$ 1 11,244.73$ 11,244.73$ 1 11,529.90$ 11,529.90$ 1 10,791.06$ 10,791.06$ 1 10,417.88$ 10,417.88$ 1 12,444.65$ 12,444.65$ 1 2,937.32$ 2,937.32$ 1 4,686.82$ 4,686.82$ 1 10,621.14$ 10,621.14$ 1 3,703.40$ 3,703.40$ 1 13,421.11$ 13,421.11$ 122,097.64$ 107Topsoil Stripping and Stockpile LS 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 1 2,000.00$ 2,000.00$ 1 1,000.00$ 1,000.00$ 1 1,000.00$ 1,000.00$ 1 2,000.00$ 2,000.00$ 1 2,000.00$ 2,000.00$ 1 2,000.00$ 2,000.00$ 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 28,000.00$ 108 Unclassified Excavation CY 4,930 7.00$ 34,510.00$ 6,000 7.00$ 42,000.00$ 3,740 7.00$ 26,180.00$ 3,600 7.00$ 25,200.00$ 3,150 7.00$ 22,050.00$ 4,535 7.00$ 31,745.00$ 3,600 7.00$ 25,200.00$ 500 7.00$ 3,500.00$ 1,300 7.00$ 9,100.00$ 4,315 7.00$ 30,205.00$ 600 7.00$ 4,200.00$ 2,150 7.00$ 15,050.00$ 268,940.00$ 109 Subexcavation CY 5,550 12.00$ 66,600.00$ 6,500 12.00$ 78,000.00$ 3,740 12.00$ 44,880.00$ 3,600 12.00$ 43,200.00$ 3,340 12.00$ 40,080.00$ 0 12.00$ -$ 3,250 12.00$ 39,000.00$ 460 12.00$ 5,520.00$ 1,100 12.00$ 13,200.00$ 0 12.00$ -$ 535 12.00$ 6,420.00$ 1,910 12.00$ 22,920.00$ 359,820.00$ 110 Sawcut Existing AsphaltLF 60 1.00$ 60.00$ 0 1.00$ -$ 75 1.00$ 75.00$ 160 1.00$ 160.00$ 105 1.00$ 105.00$ 240 1.00$ 240.00$ 4,050 1.00$ 4,050.00$ 362 1.00$ 362.00$ 1,211 1.00$ 1,211.00$ 226 1.00$ 226.00$ 590 1.00$ 590.00$ 5,290 1.00$ 5,290.00$ 12,369.00$ 111 Remove Existing AsphaltSY 1,700 12.00$ 20,400.00$ 0 12.00$ -$ 2,830 12.00$ 33,960.00$ 730 12.00$ 8,760.00$ 2,870 12.00$ 34,440.00$ 10,915 12.00$ 130,980.00$ 1,800 12.00$ 21,600.00$ 80 12.00$ 960.00$ 2,206 12.00$ 26,472.00$ 8,900 12.00$ 106,800.00$ 260 12.00$ 3,120.00$ 250 12.00$ 3,000.00$ 390,492.00$ 112 Remove Curb and Gutter LF 460 5.00$ 2,300.00$ 0 5.00$ -$ 900 5.00$ 4,500.00$ 100 5.00$ 500.00$ 2,060 5.00$ 10,300.00$ 2,472 5.00$ 12,360.00$ 3,650 5.00$ 18,250.00$ 362 5.00$ 1,810.00$ 0 5.00$ -$ 2,500 5.00$ 12,500.00$ 585 5.00$ 2,925.00$ 400 5.00$ 2,000.00$ 67,445.00$ 113 Remove Sidewalk SY 85 12.00$ 1,020.00$ 0 12.00$ -$ 230 12.00$ 2,760.00$ 0 12.00$ -$ 280 12.00$ 3,360.00$ 500 12.00$ 6,000.00$ 1,650 12.00$ 19,800.00$ 270 12.00$ 3,240.00$ 0 12.00$ -$ 800 12.00$ 9,600.00$ 270 12.00$ 3,240.00$ 250 12.00$ 3,000.00$ 52,020.00$ 114 Imported Fill CY 5,550 25.00$ 138,750.00$ 6,500 25.00$ 162,500.00$ 3,740 25.00$ 93,500.00$ 3,600 25.00$ 90,000.00$ 3,340 25.00$ 83,500.00$ 0 25.00$ -$ 3,250 25.00$ 81,250.00$ 460 25.00$ 11,500.00$ 1,100 25.00$ 27,500.00$ 0 25.00$ -$ 535 25.00$ 13,375.00$ 1,910 25.00$ 47,750.00$ 749,625.00$ 115 1 1/2-inch Minus Crushed Base Course CY 3,700 26.00$ 96,200.00$ 4,300 26.00$ 111,800.00$ 2,900 26.00$ 75,400.00$ 2,800 26.00$ 72,800.00$ 2,410 26.00$ 62,660.00$ 3,630 26.00$ 94,380.00$ 2,880 26.00$ 74,880.00$ 400 26.00$ 10,400.00$ 1,050 26.00$ 27,300.00$ 3,500 26.00$ 91,000.00$ 475 26.00$ 12,350.00$ 1,700 26.00$ 44,200.00$ 773,370.00$ 116 Geotextile Fabric (Street Base) SY 11,088 2.00$ 22,176.00$ 13,000 2.00$ 26,000.00$ 7,475 2.00$ 14,950.00$ 7,025 2.00$ 14,050.00$ 6,700 2.00$ 13,400.00$ 8,164 2.00$ 16,328.00$ 6,500 2.00$ 13,000.00$ 920 2.00$ 1,840.00$ 2,206 2.00$ 4,412.00$ 7,400 2.00$ 14,800.00$ 1,070 2.00$ 2,140.00$ 3,820 2.00$ 7,640.00$ 150,736.00$ 117 4-inch Asphalt Pavement (2 lifts) SY 11,088 20.00$ 221,753.20$ 13,000 20.00$ 260,000.00$ 7,475 20.00$ 149,500.00$ 7,025 20.00$ 140,500.00$ 6,700 20.00$ 134,000.00$ 8,164 20.00$ 163,280.00$ 6,500 20.00$ 130,000.00$ 920 20.00$ 18,400.00$ 2,206 20.00$ 44,120.00$ 7,400 20.00$ 148,000.00$ 1,070 20.00$ 21,400.00$ 3,820 20.00$ 76,400.00$ 1,507,353.20$ 118 Curb and Gutter LF 6,562 15.00$ 98,430.00$ 7,750 15.00$ 116,250.00$ 4,424 15.00$ 66,360.00$ 4,350 15.00$ 65,250.00$ 3,560 15.00$ 53,400.00$ 4,710 15.00$ 70,650.00$ 3,650 15.00$ 54,750.00$ 325 15.00$ 4,875.00$ 1,200 15.00$ 18,000.00$ 4,180 15.00$ 62,700.00$ 563 15.00$ 8,445.00$ 5,090 15.00$ 76,350.00$ 695,460.00$ 119 Curb Return Fillet SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 2,000 9.00$ 18,000.00$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 400 9.00$ 3,600.00$ 21,600.00$ 120 Concrete Valley Gutter SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 800 9.00$ 7,200.00$ 0 9.00$ -$ 0 9.00$ -$ 1,000 9.00$ 9,000.00$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 200 9.00$ 1,800.00$ 18,000.00$ 121 Concrete Drive Approach SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 185 9.00$ 1,665.00$ 850 9.00$ 7,650.00$ 9,315.00$ 122 Sidewalk SF 20,273 6.00$ 121,638.00$ 23,292 6.00$ 139,752.00$ 13,668 6.00$ 82,008.00$ 14,425 6.00$ 86,550.00$ 7,806 6.00$ 46,836.00$ 1,350 6.00$ 8,100.00$ 20,200 6.00$ 121,200.00$ 2,060 6.00$ 12,360.00$ 12,100 6.00$ 72,600.00$ 13,220 6.00$ 79,320.00$ 3,000 6.00$ 18,000.00$ 14,520 6.00$ 87,120.00$ 875,484.00$ 123 Stamped Rollover Concrete SF 3,920 15.00$ 58,800.00$ 0 15.00$ -$ 3,920 15.00$ 58,800.00$ 0 15.00$ -$ 3,920 15.00$ 58,800.00$ 3,920 15.00$ 58,800.00$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 3,920 15.00$ 58,800.00$ 0 15.00$ -$ 0 15.00$ -$ 294,000.00$ 124 ADA Ramps SF 480 15.00$ 7,200.00$ 800 15.00$ 12,000.00$ 480 15.00$ 7,200.00$ 2,000 15.00$ 30,000.00$ 480 15.00$ 7,200.00$ 480 15.00$ 7,200.00$ 1,100 15.00$ 16,500.00$ 400 15.00$ 6,000.00$ 0 15.00$ -$ 480 15.00$ 7,200.00$ 120 15.00$ 1,800.00$ 300 15.00$ 4,500.00$ 106,800.00$ 125Truncated Domes SF 160 20.00$ 3,200.00$ 64 20.00$ 1,280.00$ 160 20.00$ 3,200.00$ 160 20.00$ 3,200.00$ 160 20.00$ 3,200.00$ 160 20.00$ 3,200.00$ 88 20.00$ 1,760.00$ 32 20.00$ 640.00$ 0 20.00$ -$ 160 20.00$ 3,200.00$ 16 20.00$ 320.00$ 32 20.00$ 640.00$ 23,840.00$ 126 Grass Seeding and Fertilizer SY 5,720 2.25$ 12,870.00$ 11,300 2.25$ 25,425.00$ 4,000 2.25$ 9,000.00$ 11,400 2.25$ 25,650.00$ 3,100 2.25$ 6,975.00$ 4,100 2.25$ 9,225.00$ 4,500 2.25$ 10,125.00$ 100 2.25$ 225.00$ 874 2.25$ 1,966.50$ 3,650 2.25$ 8,212.50$ 600 2.25$ 1,350.00$ 4,667 2.25$ 10,500.75$ 121,524.75$ 127 Landscaping/Street Trees LS 1 15,000.00$ 15,000.00$ 1 20,000.00$ 20,000.00$ 1 15,000.00$ 15,000.00$ 1 20,000.00$ 20,000.00$ 1 15,000.00$ 15,000.00$ 1 15,000.00$ 15,000.00$ 1 20,000.00$ 20,000.00$ 0 200.00$ -$ 0 200.00$ -$ 1 15,000.00$ 15,000.00$ 1 2,000.00$ 2,000.00$ 150 200.00$ 30,000.00$ 167,000.00$ 128 New Sign on New PostEA25 500.00$ 12,500.00$ 30 500.00$ 15,000.00$ 25 500.00$ 12,500.00$ 30 500.00$ 15,000.00$ 25 500.00$ 12,500.00$ 25 500.00$ 12,500.00$ 20 500.00$ 10,000.00$ 1 500.00$ 500.00$ 0 500.00$ -$ 25 500.00$ 12,500.00$ 4 500.00$ 2,000.00$ 15 500.00$ 7,500.00$ 112,500.00$ 129 Remove or Relocate Existing Signs EA15 250.00$ 3,750.00$ 0 250.00$ -$ 12 250.00$ 3,000.00$ 20 250.00$ 5,000.00$ 12 250.00$ 3,000.00$ 20 250.00$ 5,000.00$ 20 250.00$ 5,000.00$ 1 250.00$ 250.00$ 6 250.00$ 1,500.00$ 20 250.00$ 5,000.00$ 4 250.00$ 1,000.00$ 25 250.00$ 6,250.00$ 38,750.00$ 130Thermoplastic StripingLF 9,000 10.00$ 90,000.00$ 8,000 10.00$ 80,000.00$ 6,100 10.00$ 61,000.00$ 4,752 10.00$ 47,520.00$ 5,000 10.00$ 50,000.00$ 6,460 10.00$ 64,600.00$ 12,760 10.00$ 127,600.00$ 850 10.00$ 8,500.00$ 2,270 10.00$ 22,700.00$ 5,750 10.00$ 57,500.00$ 3,320 10.00$ 33,200.00$ 17,800 10.00$ 178,000.00$ 820,620.00$ 131Thermoplastic Words & Symbols EA32 350.00$ 11,200.00$ 16 350.00$ 5,600.00$ 32 350.00$ 11,200.00$ 16 350.00$ 5,600.00$ 32 350.00$ 11,200.00$ 32 350.00$ 11,200.00$ 30 350.00$ 10,500.00$ 8 350.00$ 2,800.00$ 6 350.00$ 2,100.00$ 32 350.00$ 11,200.00$ 20 350.00$ 7,000.00$ 42 350.00$ 14,700.00$ 104,300.00$ 132 Street Lights EA8 7,000.00$ 56,000.00$ 14 7,000.00$ 98,000.00$ 8 7,000.00$ 56,000.00$ 14 7,000.00$ 98,000.00$ 8 7,000.00$ 56,000.00$ 8 7,000.00$ 56,000.00$ 10 7,000.00$ 70,000.00$ 3 7,000.00$ 21,000.00$ 6 7,000.00$ 42,000.00$ 10 7,000.00$ 70,000.00$ 4 7,000.00$ 28,000.00$ 11 7,000.00$ 77,000.00$ 728,000.00$ 133 Connect to Existing Storm DrainEA1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 2 1,500.00$ 3,000.00$ 1 1,500.00$ 1,500.00$ 0 1,500.00$ -$ 2 1,500.00$ 3,000.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 3 1,500.00$ 4,500.00$ 22,500.00$ 134 Storm Drain Main (15-Inch to 36-Inch) LF 675 90.00$ 60,750.00$ 1,950 90.00$ 175,500.00$ 700 90.00$ 63,000.00$ 1,965 90.00$ 176,850.00$ 1,340 90.00$ 120,600.00$ 50 90.00$ 4,500.00$ 1,750 90.00$ 157,500.00$ 50 90.00$ 4,500.00$ 800 90.00$ 72,000.00$ 0 90.00$ -$ 0 90.00$ -$ 3,000 90.00$ 270,000.00$ 1,105,200.00$ 135 12-Inch Storm Drain Inlet Pipe LF 400 50.00$ 20,000.00$ 1,000 50.00$ 50,000.00$ 400 50.00$ 20,000.00$ 1,000 50.00$ 50,000.00$ 400 50.00$ 20,000.00$ 400 50.00$ 20,000.00$ 900 50.00$ 45,000.00$ 225 50.00$ 11,250.00$ 250 50.00$ 12,500.00$ 400 50.00$ 20,000.00$ 220 50.00$ 11,000.00$ 725 50.00$ 36,250.00$ 316,000.00$ 136 New Curb Inlet EA4 3,500.00$ 14,000.00$ 20 3,500.00$ 70,000.00$ 4 3,500.00$ 14,000.00$ 20 3,500.00$ 70,000.00$ 4 3,500.00$ 14,000.00$ 4 3,500.00$ 14,000.00$ 18 3,500.00$ 63,000.00$ 3 3,500.00$ 10,500.00$ 6 3,500.00$ 21,000.00$ 4 3,500.00$ 14,000.00$ 2 3,500.00$ 7,000.00$ 29 3,500.00$ 101,500.00$ 413,000.00$ 137 Storm Drain Manhole EA3 4,000.00$ 12,000.00$ 10 4,000.00$ 40,000.00$ 3 4,000.00$ 12,000.00$ 10 4,000.00$ 40,000.00$ 3 4,000.00$ 12,000.00$ 3 4,000.00$ 12,000.00$ 9 4,000.00$ 36,000.00$ 1 4,000.00$ 4,000.00$ 2 4,000.00$ 8,000.00$ 3 4,000.00$ 12,000.00$ 1 4,000.00$ 4,000.00$ 17 4,000.00$ 68,000.00$ 260,000.00$ 138 Private Utilities Relocation LS 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ -$ 139 Detention Ponds CY 1,500 15.00$ 22,500.00$ 2,150 15.00$ 32,250.00$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 500 15.00$ 7,500.00$ 500 15.00$ 7,500.00$ 0 15.00$ -$ 500 15.00$ 7,500.00$ 190 15.00$ 2,850.00$ 0 15.00$ -$ 3,000 15.00$ 45,000.00$ 125,100.00$ 140 Outfall Structures and Piping EA1 25,000.00$ 25,000.00$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 0 25,000.00$ -$ 0 25,000.00$ -$ 1 25,000.00$ 25,000.00$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 1 25,000.00$ 25,000.00$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 3 25,000.00$ 75,000.00$ 225,000.00$ 141 Water/Sewer/Storm Adjustments LS 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 60,000.00$ 142Traffic Signal Improvements LS 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 1 140,300.00$ 140,300.00$ 0 -$ -$ 0 -$ -$ 1 165,300.00$ 165,300.00$ 0 -$ -$ 305,600.00$ 143 Roundabout Hawk Signals EA8 22,000.00$ 176,000.00$ 0 22,000.00$ -$ 8 22,000.00$ 176,000.00$ 0 22,000.00$ -$ 8 22,000.00$ 176,000.00$ 8 22,000.00$ 176,000.00$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 8 22,000.00$ 176,000.00$ 0 22,000.00$ -$ 0 22,000.00$ -$ 880,000.00$ Subtotal1,799,516.05$ 2,005,132.49$ 1,411,971.98$ 1,447,780.05$ 1,355,005.80$ 1,308,146.54$ 1,562,642.87$ 403,958.59$ 588,511.37$ 1,333,668.75$ 509,314.70$ 1,685,254.14$ 15,410,903.34$ 15% Design & CA 269,927.41$ 300,769.87$ 211,795.80$ 217,167.01$ 203,250.87$ 196,221.98$ 234,396.43$ 60,593.79$ 88,276.71$ 200,050.31$ 76,397.20$ 252,788.12$ 2,311,635.50$ 15% Construction Contingency269,927.41$ 300,769.87$ 211,795.80$ 217,167.01$ 203,250.87$ 196,221.98$ 234,396.43$ 60,593.79$ 88,276.71$ 200,050.31$ 76,397.20$ 252,788.12$ 2,311,635.50$ Subtotal Plus Contingency2,339,370.87$ 2,606,672.23$ 1,835,563.58$ 1,882,114.06$ 1,761,507.54$ 1,700,590.51$ 2,031,435.73$ 525,146.17$ 765,064.78$ 1,733,769.38$ 662,109.11$ 2,190,830.38$ 20,034,174.34$ Roundabout Signal 7th to RouseRoundabout AlternativeRoundabout 27th to 19th Signal 19th to 15thOak & 7th Oak StreetRoundabout Cottonwood to Ferguson Roundabout Ferguson to Davis RoundaboutOak & 27th Oak Street Oak & 19th Oak Street Oak & 11thOak Street Oak & Ferguson Oak Street Oak & DavisRoundabout AlternativeItem No. Description UnitOak & Cottonwood Oak Street Improvements - Preliminary Opinion of Probable CostTotal CostQuantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal Quantity Unit Price Subtotal101 Mobilization/DemobilizationLS 1 184,565.75$ 184,565.75$ 1 205,654.61$ 205,654.61$ 1 106,140.55$ 106,140.55$ 1 148,490.26$ 148,490.26$ 1 130,252.40$ 130,252.40$ 1 48,183.77$ 48,183.77$ 1 160,271.06$ 160,271.06$ 1 41,431.65$ 41,431.65$ 1 60,360.14$ 60,360.14$ 1 58,600.07$ 58,600.07$ 1 52,237.41$ 52,237.41$ 1 172,846.58$ 172,846.58$ 1,369,034.25$ 102Taxes, Bonds, Insurance LS 1 76,902.40$ 76,902.40$ 1 85,689.42$ 85,689.42$ 1 44,225.23$ 44,225.23$ 1 61,870.94$ 61,870.94$ 1 54,271.83$ 54,271.83$ 1 20,076.57$ 20,076.57$ 1 66,779.61$ 66,779.61$ 1 17,263.19$ 17,263.19$ 1 25,150.06$ 25,150.06$ 1 24,416.70$ 24,416.70$ 1 21,765.59$ 21,765.59$ 1 72,019.41$ 72,019.41$ 570,430.94$ 103Traffic Control LS 1 73,240.38$ 73,240.38$ 1 81,608.97$ 81,608.97$ 1 42,119.27$ 42,119.27$ 1 58,924.71$ 58,924.71$ 1 51,687.46$ 51,687.46$ 1 19,120.54$ 19,120.54$ 1 63,599.63$ 63,599.63$ 1 45,034.40$ 45,034.40$ 1 23,952.44$ 23,952.44$ 1 23,254.00$ 23,254.00$ 1 56,779.79$ 56,779.79$ 1 68,589.91$ 68,589.91$ 607,911.49$ 104 Stormwater Management and Erosion Control LS 1 14,503.04$ 14,503.04$ 1 16,160.19$ 16,160.19$ 1 8,340.45$ 8,340.45$ 1 11,668.26$ 11,668.26$ 1 10,235.14$ 10,235.14$ 1 3,786.25$ 3,786.25$ 1 12,593.99$ 12,593.99$ 1 2,972.57$ 2,972.57$ 1 4,743.06$ 4,743.06$ 1 4,604.75$ 4,604.75$ 1 3,747.84$ 3,747.84$ 1 13,582.16$ 13,582.16$ 106,937.70$ 105 Clearing and Grubbing LS 1 2,866.21$ 2,866.21$ 1 3,193.71$ 3,193.71$ 1 1,648.31$ 1,648.31$ 1 2,305.98$ 2,305.98$ 1 2,022.76$ 2,022.76$ 1 748.27$ 748.27$ 1 2,488.93$ 2,488.93$ 1 587.46$ 587.46$ 1 937.36$ 937.36$ 1 910.03$ 910.03$ 1 740.68$ 740.68$ 1 2,684.22$ 2,684.22$ 21,133.93$ 106 Dewatering LS 1 14,331.07$ 14,331.07$ 1 15,968.57$ 15,968.57$ 1 8,241.55$ 8,241.55$ 1 11,529.90$ 11,529.90$ 1 10,113.78$ 10,113.78$ 1 3,741.35$ 3,741.35$ 1 12,444.65$ 12,444.65$ 1 2,937.32$ 2,937.32$ 1 4,686.82$ 4,686.82$ 1 4,550.15$ 4,550.15$ 1 3,703.40$ 3,703.40$ 1 13,421.11$ 13,421.11$ 105,669.66$ 107Topsoil Stripping and Stockpile LS 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 0 2,000.00$ -$ 0 2,000.00$ -$ 1 1,000.00$ 1,000.00$ 1 2,000.00$ 2,000.00$ 1 2,000.00$ 2,000.00$ 1 1,000.00$ 1,000.00$ 1 2,000.00$ 2,000.00$ 1 4,000.00$ 4,000.00$ 24,000.00$ 108 Unclassified Excavation CY 4,930 7.00$ 34,510.00$ 6,000 7.00$ 42,000.00$ 1,900 7.00$ 13,300.00$ 3,600 7.00$ 25,200.00$ 2,520 7.00$ 17,640.00$ 0 7.00$ -$ 3,600 7.00$ 25,200.00$ 500 7.00$ 3,500.00$ 1,300 7.00$ 9,100.00$ 580 7.00$ 4,060.00$ 600 7.00$ 4,200.00$ 2,150 7.00$ 15,050.00$ 193,760.00$ 109 Subexcavation CY 5,550 12.00$ 66,600.00$ 6,500 12.00$ 78,000.00$ 1,900 12.00$ 22,800.00$ 3,600 12.00$ 43,200.00$ 2,660 12.00$ 31,920.00$ 0 12.00$ -$ 3,250 12.00$ 39,000.00$ 460 12.00$ 5,520.00$ 1,100 12.00$ 13,200.00$ 500 12.00$ 6,000.00$ 535 12.00$ 6,420.00$ 1,910 12.00$ 22,920.00$ 335,580.00$ 110 Sawcut Existing AsphaltLF 60 1.00$ 60.00$ 0 1.00$ -$ 350 1.00$ 350.00$ 160 1.00$ 160.00$ 1,000 1.00$ 1,000.00$ 415 1.00$ 415.00$ 4,050 1.00$ 4,050.00$ 362 1.00$ 362.00$ 1,211 1.00$ 1,211.00$ 90 1.00$ 90.00$ 590 1.00$ 590.00$ 5,290 1.00$ 5,290.00$ 13,578.00$ 111 Remove Existing AsphaltSY 1,700 12.00$ 20,400.00$ 0 12.00$ -$ 80 12.00$ 960.00$ 730 12.00$ 8,760.00$ 1,070 12.00$ 12,840.00$ 185 12.00$ 2,220.00$ 1,800 12.00$ 21,600.00$ 80 12.00$ 960.00$ 2,206 12.00$ 26,472.00$ 790 12.00$ 9,480.00$ 260 12.00$ 3,120.00$ 250 12.00$ 3,000.00$ 109,812.00$ 112 Remove Curb and Gutter LF 460 5.00$ 2,300.00$ 0 5.00$ -$ 350 5.00$ 1,750.00$ 100 5.00$ 500.00$ 1,160 5.00$ 5,800.00$ 350 5.00$ 1,750.00$ 3,650 5.00$ 18,250.00$ 362 5.00$ 1,810.00$ 0 5.00$ -$ 40 5.00$ 200.00$ 585 5.00$ 2,925.00$ 400 5.00$ 2,000.00$ 37,285.00$ 113 Remove Sidewalk SY 85 12.00$ 1,020.00$ 0 12.00$ -$ 20 12.00$ 240.00$ 0 12.00$ -$ 100 12.00$ 1,200.00$ 50 12.00$ 600.00$ 1,650 12.00$ 19,800.00$ 270 12.00$ 3,240.00$ 0 12.00$ -$ 50 12.00$ 600.00$ 270 12.00$ 3,240.00$ 250 12.00$ 3,000.00$ 32,940.00$ 114 Imported Fill CY 5,550 25.00$ 138,750.00$ 6,500 25.00$ 162,500.00$ 1,900 25.00$ 47,500.00$ 3,600 25.00$ 90,000.00$ 2,660 25.00$ 66,500.00$ 0 25.00$ -$ 3,250 25.00$ 81,250.00$ 460 25.00$ 11,500.00$ 1,100 25.00$ 27,500.00$ 500 25.00$ 12,500.00$ 535 25.00$ 13,375.00$ 1,910 25.00$ 47,750.00$ 699,125.00$ 115 1 1/2-inch Minus Crushed Base Course CY 3,700 26.00$ 96,200.00$ 4,300 26.00$ 111,800.00$ 4,745 26.00$ 123,370.00$ 2,800 26.00$ 72,800.00$ 1,920 26.00$ 49,920.00$ 200 26.00$ 5,200.00$ 2,880 26.00$ 74,880.00$ 400 26.00$ 10,400.00$ 1,050 26.00$ 27,300.00$ 470 26.00$ 12,220.00$ 475 26.00$ 12,350.00$ 1,700 26.00$ 44,200.00$ 640,640.00$ 116 Geotextile Fabric (Street Base) SY 11,088 2.00$ 22,176.00$ 13,000 2.00$ 26,000.00$ 3,800 2.00$ 7,600.00$ 7,025 2.00$ 14,050.00$ 5,320 2.00$ 10,640.00$ 460 2.00$ 920.00$ 6,500 2.00$ 13,000.00$ 920 2.00$ 1,840.00$ 2,206 2.00$ 4,412.00$ 1,000 2.00$ 2,000.00$ 1,070 2.00$ 2,140.00$ 3,820 2.00$ 7,640.00$ 112,418.00$ 117 4-inch Asphalt Pavement (2 lifts) SY 11,088 20.00$ 221,753.20$ 13,000 20.00$ 260,000.00$ 3,800 20.00$ 76,000.00$ 7,025 20.00$ 140,500.00$ 5,320 20.00$ 106,400.00$ 460 20.00$ 9,200.00$ 6,500 20.00$ 130,000.00$ 920 20.00$ 18,400.00$ 2,206 20.00$ 44,120.00$ 1,000 20.00$ 20,000.00$ 1,070 20.00$ 21,400.00$ 3,820 20.00$ 76,400.00$ 1,124,173.20$ 118 Curb and Gutter LF 6,562 15.00$ 98,430.00$ 7,750 15.00$ 116,250.00$ 2,200 15.00$ 33,000.00$ 4,350 15.00$ 65,250.00$ 2,065 15.00$ 30,975.00$ 115 15.00$ 1,725.00$ 3,650 15.00$ 54,750.00$ 325 15.00$ 4,875.00$ 1,200 15.00$ 18,000.00$ 730 15.00$ 10,950.00$ 563 15.00$ 8,445.00$ 5,090 15.00$ 76,350.00$ 519,000.00$ 119 Curb Return Fillet SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 2,000 9.00$ 18,000.00$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 400 9.00$ 3,600.00$ 21,600.00$ 120 Concrete Valley Gutter SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 800 9.00$ 7,200.00$ 0 9.00$ -$ 0 9.00$ -$ 1,000 9.00$ 9,000.00$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 200 9.00$ 1,800.00$ 18,000.00$ 121 Concrete Drive Approach SF 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 0 9.00$ -$ 185 9.00$ 1,665.00$ 850 9.00$ 7,650.00$ 9,315.00$ 122 Sidewalk SF 20,273 6.00$ 121,638.00$ 23,292 6.00$ 139,752.00$ 7,580 6.00$ 45,480.00$ 14,425 6.00$ 86,550.00$ 6,080 6.00$ 36,480.00$ 800 6.00$ 4,800.00$ 20,200 6.00$ 121,200.00$ 2,060 6.00$ 12,360.00$ 12,100 6.00$ 72,600.00$ 3,000 6.00$ 18,000.00$ 3,000 6.00$ 18,000.00$ 14,520 6.00$ 87,120.00$ 763,980.00$ 123 Stamped Rollover Concrete SF 3,920 15.00$ 58,800.00$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 58,800.00$ 124 ADA Ramps SF 480 15.00$ 7,200.00$ 800 15.00$ 12,000.00$ 480 15.00$ 7,200.00$ 2,000 15.00$ 30,000.00$ 480 15.00$ 7,200.00$ 480 15.00$ 7,200.00$ 1,100 15.00$ 16,500.00$ 400 15.00$ 6,000.00$ 0 15.00$ -$ 540 15.00$ 8,100.00$ 120 15.00$ 1,800.00$ 300 15.00$ 4,500.00$ 107,700.00$ 125Truncated Domes SF 160 20.00$ 3,200.00$ 64 20.00$ 1,280.00$ 64 20.00$ 1,280.00$ 160 20.00$ 3,200.00$ 64 20.00$ 1,280.00$ 64 20.00$ 1,280.00$ 88 20.00$ 1,760.00$ 32 20.00$ 640.00$ 0 20.00$ -$ 72 20.00$ 1,440.00$ 16 20.00$ 320.00$ 32 20.00$ 640.00$ 16,320.00$ 126 Grass Seeding and Fertilizer SY 5,720 2.25$ 12,870.00$ 11,300 2.25$ 25,425.00$ 4,300 2.25$ 9,675.00$ 11,400 2.25$ 25,650.00$ 2,970 2.25$ 6,682.50$ 500 2.25$ 1,125.00$ 4,500 2.25$ 10,125.00$ 100 2.25$ 225.00$ 874 2.25$ 1,966.50$ 500 2.25$ 1,125.00$ 600 2.25$ 1,350.00$ 4,667 2.25$ 10,500.75$ 106,719.75$ 127 Landscaping/Street Trees LS 1 15,000.00$ 15,000.00$ 1 20,000.00$ 20,000.00$ 1 5,000.00$ 5,000.00$ 1 20,000.00$ 20,000.00$ 1 5,000.00$ 5,000.00$ 0 200.00$ -$ 1 20,000.00$ 20,000.00$ 0 200.00$ -$ 0 200.00$ -$ 1 2,000.00$ 2,000.00$ 1 2,000.00$ 2,000.00$ 150 200.00$ 30,000.00$ 119,000.00$ 128 New Sign on New PostEA25 500.00$ 12,500.00$ 30 500.00$ 15,000.00$ 20 500.00$ 10,000.00$ 30 500.00$ 15,000.00$ 20 500.00$ 10,000.00$ 10 500.00$ 5,000.00$ 20 500.00$ 10,000.00$ 1 500.00$ 500.00$ 0 500.00$ -$ 20 500.00$ 10,000.00$ 4 500.00$ 2,000.00$ 15 500.00$ 7,500.00$ 97,500.00$ 129 Remove or Relocate Existing Signs EA15 250.00$ 3,750.00$ 0 250.00$ -$ 12 250.00$ 3,000.00$ 20 250.00$ 5,000.00$ 12 250.00$ 3,000.00$ 20 250.00$ 5,000.00$ 20 250.00$ 5,000.00$ 1 250.00$ 250.00$ 6 250.00$ 1,500.00$ 4 250.00$ 1,000.00$ 4 250.00$ 1,000.00$ 25 250.00$ 6,250.00$ 34,750.00$ 130Thermoplastic StripingLF 9,000 10.00$ 90,000.00$ 8,000 10.00$ 80,000.00$ 3,360 10.00$ 33,600.00$ 4,752 10.00$ 47,520.00$ 5,920 10.00$ 59,200.00$ 5,100 10.00$ 51,000.00$ 12,760 10.00$ 127,600.00$ 850 10.00$ 8,500.00$ 2,270 10.00$ 22,700.00$ 2,100 10.00$ 21,000.00$ 3,320 10.00$ 33,200.00$ 17,800 10.00$ 178,000.00$ 752,320.00$ 131Thermoplastic Words & Symbols EA32 350.00$ 11,200.00$ 16 350.00$ 5,600.00$ 21 350.00$ 7,350.00$ 16 350.00$ 5,600.00$ 32 350.00$ 11,200.00$ 30 350.00$ 10,500.00$ 30 350.00$ 10,500.00$ 8 350.00$ 2,800.00$ 6 350.00$ 2,100.00$ 24 350.00$ 8,400.00$ 20 350.00$ 7,000.00$ 42 350.00$ 14,700.00$ 96,950.00$ 132 Street Lights EA8 7,000.00$ 56,000.00$ 14 7,000.00$ 98,000.00$ 4 7,000.00$ 28,000.00$ 14 7,000.00$ 98,000.00$ 4 7,000.00$ 28,000.00$ 4 7,000.00$ 28,000.00$ 10 7,000.00$ 70,000.00$ 3 7,000.00$ 21,000.00$ 6 7,000.00$ 42,000.00$ 4 7,000.00$ 28,000.00$ 4 7,000.00$ 28,000.00$ 11 7,000.00$ 77,000.00$ 602,000.00$ 133 Connect to Existing Storm DrainEA1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 2 1,500.00$ 3,000.00$ 1 1,500.00$ 1,500.00$ 0 1,500.00$ -$ 2 1,500.00$ 3,000.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 1 1,500.00$ 1,500.00$ 3 1,500.00$ 4,500.00$ 22,500.00$ 134 Storm Drain Main (15-Inch to 36-Inch) LF 675 90.00$ 60,750.00$ 1,950 90.00$ 175,500.00$ 700 90.00$ 63,000.00$ 1,965 90.00$ 176,850.00$ 1,250 90.00$ 112,500.00$ 0 90.00$ -$ 1,750 90.00$ 157,500.00$ 50 90.00$ 4,500.00$ 800 90.00$ 72,000.00$ 200 90.00$ 18,000.00$ 0 90.00$ -$ 3,000 90.00$ 270,000.00$ 1,110,600.00$ 135 12-Inch Storm Drain Inlet Pipe LF 400 50.00$ 20,000.00$ 1,000 50.00$ 50,000.00$ 100 50.00$ 5,000.00$ 1,000 50.00$ 50,000.00$ 280 50.00$ 14,000.00$ 0 50.00$ -$ 900 50.00$ 45,000.00$ 225 50.00$ 11,250.00$ 250 50.00$ 12,500.00$ 200 50.00$ 10,000.00$ 220 50.00$ 11,000.00$ 725 50.00$ 36,250.00$ 265,000.00$ 136 New Curb Inlet EA4 3,500.00$ 14,000.00$ 20 3,500.00$ 70,000.00$ 4 3,500.00$ 14,000.00$ 20 3,500.00$ 70,000.00$ 4 3,500.00$ 14,000.00$ 0 3,500.00$ -$ 18 3,500.00$ 63,000.00$ 3 3,500.00$ 10,500.00$ 6 3,500.00$ 21,000.00$ 2 3,500.00$ 7,000.00$ 2 3,500.00$ 7,000.00$ 29 3,500.00$ 101,500.00$ 392,000.00$ 137 Storm Drain Manhole EA3 4,000.00$ 12,000.00$ 10 4,000.00$ 40,000.00$ 1 4,000.00$ 4,000.00$ 10 4,000.00$ 40,000.00$ 1 4,000.00$ 4,000.00$ 0 4,000.00$ -$ 9 4,000.00$ 36,000.00$ 1 4,000.00$ 4,000.00$ 2 4,000.00$ 8,000.00$ 1 4,000.00$ 4,000.00$ 1 4,000.00$ 4,000.00$ 17 4,000.00$ 68,000.00$ 224,000.00$ 138 Private Utilities Relocation LS 0 -$ -$ 0 -$ -$ 1 31,500.00$ 31,500.00$ 0 -$ -$ 1 117,000.00$ 117,000.00$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 0 -$ -$ 148,500.00$ 139 Detention Ponds CY 1,500 15.00$ 22,500.00$ 2,150 15.00$ 32,250.00$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 0 15.00$ -$ 500 15.00$ 7,500.00$ 0 15.00$ -$ 500 15.00$ 7,500.00$ 190 15.00$ 2,850.00$ 0 15.00$ -$ 3,000 15.00$ 45,000.00$ 117,600.00$ 140 Outfall Structures and Piping EA1 25,000.00$ 25,000.00$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 0 25,000.00$ -$ 0 25,000.00$ -$ 0 25,000.00$ -$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 1 25,000.00$ 25,000.00$ 1 25,000.00$ 25,000.00$ 0 25,000.00$ -$ 3 25,000.00$ 75,000.00$ 200,000.00$ 141 Water/Sewer/Storm Adjustments LS 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 1 5,000.00$ 5,000.00$ 60,000.00$ 142Traffic Signal Improvements LS 0 -$ -$ 0 -$ -$ 1 220,700.00$ 220,700.00$ 0 -$ -$ 1 240,500.00$ 240,500.00$ 1 233,200.00$ 233,200.00$ 0 -$ -$ 1 140,300.00$ 140,300.00$ 0 -$ -$ 1 203,500.00$ 203,500.00$ 1 165,300.00$ 165,300.00$ 0 -$ -$ 1,203,500.00$ 143 Roundabout Hawk Signals EA8 22,000.00$ 176,000.00$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 0 22,000.00$ -$ 176,000.00$ Subtotal1,799,516.05$ 2,005,132.49$ 1,034,870.35$ 1,447,780.05$ 1,269,960.86$ 469,791.75$ 1,562,642.87$ 403,958.59$ 588,511.37$ 571,350.70$ 509,314.70$ 1,685,254.14$ 13,348,083.91$ 15% Design & CA 269,927.41$ 300,769.87$ 155,230.55$ 217,167.01$ 190,494.13$ 70,468.76$ 234,396.43$ 60,593.79$ 88,276.71$ 85,702.60$ 76,397.20$ 252,788.12$ 2,002,212.59$ 15% Construction Contingency269,927.41$ 300,769.87$ 155,230.55$ 217,167.01$ 190,494.13$ 70,468.76$ 234,396.43$ 60,593.79$ 88,276.71$ 85,702.60$ 76,397.20$ 252,788.12$ 2,002,212.59$ Subtotal Plus Contingency2,339,370.87$ 2,606,672.23$ 1,345,331.46$ 1,882,114.06$ 1,650,949.11$ 610,729.27$ 2,031,435.73$ 525,146.17$ 765,064.78$ 742,755.91$ 662,109.11$ 2,190,830.38$ 17,352,509.08$ Preferred AlternativeSignal Signal 7th to RouseSignal Signal 27th to 19th Signal 19th to 15thOak & 11th Oak & 7th Oak StreetRoundabout Cottonwood to Ferguson Signal Ferguson to DavisOak & 27th Oak Street Oak & 19th Oak StreetOak Street Oak & Ferguson Oak Street Oak & DavisPreferred AlternativeItem No. Description UnitOak & Cottonwood