Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adopt the Wastewater Fund Capital Improvement Plan (CIP) for
Fiscal Years 2017-2021.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 14, 2015
RECOMMENDATION: Adopt the Wastewater Fund Capital Improvement Plan (CIP)
for Fiscal Years 2017-2021.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. Similar to recent years
past, we are bringing the various parts of the plan forward as items on the Consent agenda. We
will be prepared to address questions, if they arise, at the public meeting.
The Public Works, City Manager, and other city staff met in October to develop the attached
Capital Plan for the equipment and capital needs of the Wastewater Fund. The Wastewater Fund
CIP tracks the capital equipment replacements and construction projects for Wastewater
Operations (collection system) and the Water Reclamation Facility (WRF).
Item of Note:
• After review of the allocation of vehicle replacements for the Water Operations
department in the Water Fund, we moved a number of vehicles to the Wastewater Fund
201
for replacement. The Water Operations and Wastewater Operations crews function as
one unit and share equipment that is purchased by both funds.
• PW02: Shops Facility Expansion Construction has been added to both the Water and
Wastewater Fund, totaling $700,000 (50/50 split), to allow for an addition to our space
available for shops crews and equipment.
• WW73 – Wastewater Rate Study was added ($50,000). We are conducting a similar
study in for the water system this year and would like to follow with a wastewater study.
• WW71 – Facility Master Plan Update has been added ($150,000).
• Numerous other items have been adjusted or added based on current projections.
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission does not
wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY17.
Report compiled on: December 7, 2015
Attached: Wastewater Fund CIP
202
Wastewater Fund Capital Improvement PlanFinancial SummaryCurrent YearFY16FY17FY18 FY19 FY20 FY21UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 1,112,180$ 1,354,455$ 1,137,472$ 827,589$ 1,562,035$ 2,204,589$ ‐$ Plus: Wastewater Revenues Dedicated to CIP1,864,094$ 1,920,017$ 1,977,617$ 2,036,946$ 2,098,054$ 2,160,996$ ‐$ Less: Scheduled CIP Project Costs(1,621,819)$ (2,137,000)$ (2,287,500)$ (1,302,500)$ (1,455,500)$ (1,182,500)$ (16,853,703)$ Projected Year‐End Cash Dedicated to CIP1,354,455$ 1,137,472$ 827,589$ 1,562,035$ 2,204,589$ 3,183,085$ (16,853,703)$ Assumptions Made for Revenue Estimates:Current YearFY16FY17FY18FY19 FY20 FY21Estimated Annual Wastewater Revenues7,456,376$ 7,456,376$ 7,680,067$ 7,910,469$ 8,147,783$ 8,392,217$ Estimated Annual Increase0.0%3%3%3%3%3%Total Estimated Revenues7,456,376$ 7,680,067$ 7,910,469$ 8,147,783$ 8,392,217$ 8,643,983$ Current Revenues Dedicated to CIP %25.0%25.0% 25.0% 25.0% 25.0% 25.0% Plus: Increase Dedicated to CIP0.0%0.0%0.0%0.0% 0.0%0.0% Total % Dedicated to CIP25.0%25.0% 25.0% 25.0% 25.0% 25.0%Total Estimated Revenues Dedicated to CIP1,864,094$ 1,920,017$ 1,977,617$ 2,036,946$ 2,098,054$ 2,160,996$ ProjectedProjectedCURRENT18,000,00016,000,00014,000,00012,000,00010,000,0008,000,0006,000,0004,000,0002,000,0000Wastewater Fund Projects & Equipment 203
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY17UnscheduledFY21FY18FY19FY20Wastewater FundGF227FINANCEERP REPLACEMENT "SUNGARD REPLACEMENT/UPGRADE"$333,333$333,333Wastewater FundWW27WRFWATERSHED STUDY & STREAM MODELING$60,000$200,000$60,000$60,000$60,000WW28WRFDESIGN PHASE II ‐ WRF PLANT IMPROVEMENTS$5,230,000WW29WRFMETHANE COGENERATION PROJECT DESIGN$350,000WW35WRFCOMMERCIAL MOWER$13,000WW39WRFSANDBLAST & PAINT CLARIFIER DRIVES, BEACH, BAFFLES & WEIRS$85,000$90,000$90,000WW42WRFPRIMARY CLARIFIER COVER$1,050,000WW44WRFFLOTATION THINKENER$500,000WW45WRFFINAL CLARIFIER LAUNDER COVER$40,000$40,000WW49WRFROLL‐OFF BUILDING AND 2ND SCREW PRESS & SCREW PRESS ENCLOSURE$600,000WW50WRFREFRIGERATED AUTOMATIC SAMPLERS$30,000WW53WRFPOSITIVE DISPLACEMENT LOBE PUMP$20,000$20,000$20,000WW58WRFCHIP SEAL WRF ASPHALT$47,370WW59WRFSPLITTER STRUCTURE AIR DIFFUSER$15,000WW60WRFNUTRIENT RECOVERY PROCESS CONSTRUCTION$2,000,000WW61WRFONLINE AMMONIA PROBES$35,000WW62WRFMETHANE COGENERATION PROJECT CONSTRUCTION$2,200,000WW66WRFODOR CONTROL FOR OLD PRETREATMENT BUILDINGS$15,000WW67WRFCONVERT BIO‐TRAIN #1 TO 5 STAGE BARDENPHO$5,000,000204
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY17UnscheduledFY21FY18FY19FY20WW68WRFSECONDARY LAUNDER COVER$30,000$30,000$30,000WW69WRFWRF FACILITY R & R$50,000$50,000$50,000$50,000$50,000WW70WRFWRF FACILITY ENGINEERING & OPTIMIZATION$50,000$50,000$50,000$50,000$50,000WW71WRFWRF FACILITY MASTER PLAN UPDATE$150,000$160,000$510,000$1,090,000$280,000$160,000$16,470,370Wastewater FundGF262WW OPSPAVING AT SHOPS$37,500PW01 ‐ SHWW OPSSHOPS FACILITY EXPANSION PLAN$10,000PW02 ‐ SHWW OPSSHOPS FACILITY EXPANSION CONSTRUCTION$350,000STR67WW OPSCOVERED STORAGE AT SHOPS COMPLEX$50,000WW07WW OPSANNUAL PIPE REPLACEMENT PROGRAM ‐ DESIGN$22,500$22,500$22,500$22,500$22,500WW08‐17WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ FY17$1,000,000WW08‐18WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ FY18$1,000,000WW08‐19WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ FY19$1,000,000WW08‐20WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ FY20$1,000,000WW08‐21WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ FY21$1,000,000WW52WW OPSREPLACE #2683 ‐ 1999 JOHN DEERE 310SE BACKHOE$105,000WW54WW OPSREPLACE #1783 ‐ 1995 FORD DUMP TRUCK$95,000WW55WW OPSREPLACE #3232 ‐ 2004 3/4 TON FORD PICKUP$33,000WW63WW OPSCHEMICAL ROOT CONTROL APPLICATOR$45,000WW64WW OPSSEWER FLOW METER$15,000WW65WW OPSDIGITAL UNIVERSAL CAMERA DUC$70,000205
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY17UnscheduledFY21FY18FY19FY20WW73WW OPSRATE STUDY ‐ WASTEWATER$50,000WW74WW OPSREPLACE #2915 ‐ 2001 1 TON DODGE FLATBED/VALVE TRUCK$70,000WW75WW OPSREPLACE #1677 ‐ 1995 CHEVY S‐10 PICKUP$27,000WW76WW OPSREPLACE #3030 ‐ 2001 JOHN DEERE SKID STEER$40,000WW77WW OPSREPLACE #3157 ‐ 2003 STERLING DUMP TRUCK$105,000$1,022,500$1,627,000$1,197,500$1,022,500$1,295,500$50,000Summary for Wastewater Fund (44 items)Totals by year:$1,182,500$2,137,000 $2,287,500$16,853,703FY21FY17FY18UnscheduledFY20$1,455,500$1,302,500FY19206
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
GF227
DEPARTMENT
FINANCE
PROJECT NAME
ERP REPLACEMENT "SUNGARD REPLACEMENT/UPGRADE"
FY17 FY18 Unscheduled
$333,333
DESCRIPTION OF PROJECT
Replacing/upgrading the current system installed in 1999. This is the system that runs all the financial, community development,
land records, utility and business license applications.
ALTERNATIVES CONSIDERED
Continue running current SunGard package. Use SunGard.net (NaviLine EDGE) as an improvement to the current system, but not a full
replacement.
ADVANTAGES OF APPROVAL
Simplified package. Easier to integrate the various applications/programs. Easier to pull out information for end users. Easier compiliation of
Commission reports and packets for Community Development.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Unknown. Dependent on the option chosen.
FUNDING SOURCES
General Fund 33%; Water Fund 33%; Wastewater Fund 33%
New
Replacement
Equipment
Project
FY19 FY20 FY21
207
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
GF262
DEPARTMENT
WW OPS
PROJECT NAME
PAVING AT SHOPS
FY17
$37,500
FY18 Unscheduled
DESCRIPTION OF PROJECT
Demolish and replace old asphalt. The existing parking lot tends to be very muddy as it’s only partially paved. Paving the lot will
reduce the amount of sediment leaving the site and going into Bozeman Creek. This project is phase 2 of CIP project GF237
approved for FY16, installation of stormwater system improvements at the Shops Complex.
ALTERNATIVES CONSIDERED
Do nothing and risk overwhelming the new stormwater infrastructure.
ADVANTAGES OF APPROVAL
This will allow the City to meet Stormwater permit goals and requirements.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
25% Street Maintenance, 25% Water Funds, 25% Wastewater Funds and 25% General Fund (Parks)
New
Replacement
Equipment
Project
FY19 FY20 FY21
208
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
PW01 - SH
DEPARTMENT
WW OPS
PROJECT NAME
SHOPS FACILITY EXPANSION PLAN
FY17
$10,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
The construction of the new Vehicle Maintenance Shop at the Lower Yards on Rouse Avenue in FY10/FY11 was Phase I in
expanding and improving our ability to service equipment, store vehicles, and provide work space for Public Works, Parks, and
Facilitiy services. Questions remain about the long-term plan for construction, location, and expansion for: Streets, Sign & Signal,
Forestry, Water/Sewer Operations, Solid Waste Collection & Recycling, Facilities, and Parks & Cemetery departments. This
project would develop a master plan. In scheduling this project, we are recommending waiting until after the Vehicle Maintenance
Division is relocated to its new shop and the interior improvements are made to the Shop at Rouse and Tamarack Street for the
remaining divisions.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
From related divisions: General Fund 20% ($10,000), Water Fund 20% ($10,000), Wastewater Fund 20% ($10,000), Street Maintenance Fund
20% ($10,000), Solid Waste Fund 20% ($10,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
209
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
PW02 - SH
DEPARTMENT
WW OPS
PROJECT NAME
SHOPS FACILITY EXPANSION CONSTRUCTION
FY17
$350,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
The City Shops currently houses Water Operations, Wastewater Operations, Streets and Parks and is at full capacity. The
Vehicle Maintenance Shop on North Rouse was originally intended to have two phases but only one has been completed. This
project would allow Public Works to look at other options to open up space at the existing location.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
50/50 Water and Wastewater Utility Share
New
Replacement
Equipment
Project
FY19 FY20 FY21
210
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
STR67
DEPARTMENT
WW OPS
PROJECT NAME
Covered Storage at Shops Complex
FY17 FY18 Unscheduled
$50,000
DESCRIPTION OF PROJECT
Covered storage at the Shops Complex to allow for storage of vehicles and equipment.
ALTERNATIVES CONSIDERED
Continue storing millions of dollars worth of equipment in the elements.
ADVANTAGES OF APPROVAL
Building covered storage for all vehicles and equipment currently parked at the City Shops will help keep this equipment out of the weather thus
prolonging the life of the equipment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal Maintenance Costs
FUNDING SOURCES
Cost will be split between Water Operations (25%), Wastewater Operations (25%) and Streets (50%)
New
Replacement
Equipment
Project
FY19 FY20 FY21
211
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW07
DEPARTMENT
WW OPS
PROJECT NAME
ANNUAL PIPE REPLACEMENT PROGRAM - DESIGN
FY17
$22,500
FY18
$22,500
Unscheduled
DESCRIPTION OF PROJECT
This item provides for design work to be completed every-other year, in anticipation of the Annual System Upgrades. As the
Wastewater Operations Division televises (views) the existing system, maintenance projects become apparent. As annual
televising continues, other more-urgent projects may be identified and designed under this project heading.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for design of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY19
$22,500
FY20
$22,500
FY21
$22,500
212
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-17
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - FY17
FY17
$1,000,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2017. $149,603 of the project will
cover E Olive from Black to Church to correspond with the FY18 street reconstruction on E Olive. $233,046 will cover W Koch
from 8th to Grand to correspond with the FY23 street reconstruction on W Koch. The balance of $617,351 will be used to slip
line and or replace some of the remaining deferred maintenance identified in the 2015 deferred maintenance exercise (40.1 miles
@ $19.2M as of 11/19/15).
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
213
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-18
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - FY18
FY17 FY18
$1,000,000
Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2018. $91,959 will cover S Black from
College to the southern cul-de-sac to coincide with the FY19 street reconstruction on S Black. The balance of $908,041 will be
used to slip line and or replace some of the remaining deferred maintenance identified in the 2015 deferred maintenance exercise
(40.1 miles @ $19.2M as of 11/19/15).
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
214
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-19
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - FY19
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2019. $218,049 will cover S Tracy from
Babcock to College to coincide with the FY20 street reconstruction on S Tracy. The balance of $781,951 will be used to slip line
and or replace some of the remaining deferred maintenance identified in the 2015 deferred maintenance exercise (40.1 miles @
$19.2M as of 11/19/15).
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY19
$1,000,000
FY20 FY21
215
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-20
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - FY20
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2020. $78,329 will cover N Tracy from
Villard to Peach to coincide with the FY21 street reconstruction on S Tracy. The balance of $921,671 will be used to slip line and
or replace some of the remaining deferred maintenance identified in the 2015 deferred maintenance exercise (40.1 miles @
$19.2M as of 11/19/15).
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Utility
New
Replacement
Equipment
Project
FY19 FY20
$1,000,000
FY21
216
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-21
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - FY21
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project would complete design, bid and begin construction in the Spring/Summer of 2021. The money will be used to slip
line and or replace some of the remaining deferred maintenance identified in the 2015 deferred maintenance exercise (40.1 miles
@ $19.2M as of 11/19/15).
ALTERNATIVES CONSIDERED
None
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
This project results in a net decrease in overall maintenance costs over the lifecycle of all pipes.
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
$1,000,000
217
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW27
DEPARTMENT
WRF
PROJECT NAME
WATERSHED STUDY & STREAM MODELING
FY17
$200,000
FY18
$60,000
Unscheduled
DESCRIPTION OF PROJECT
Develop a comprehensive, multi-year watershed study and computer model for the East Gallatin River which would enable the
City and DEQ to better determine stream load allocations and develop a more scientifically valid TMDL for the river segment we
discharge to. This will require annual field sample collection, laboratory analytical work and detailed computer modeling using
calibrated data. This multi-year study would consist of $45,000 in consulting and computer modeling fees for at least two fiscal
years (FY14 and FY15) and stream sampling/lab fees of $15,000 each year. Craig recommends we should be prepared to continue
this work beyond FY15 as necessary.
ALTERNATIVES CONSIDERED
Not undertake this work and risk having to accept the TMDL and waste load allocations the DEQ has proposed in their original draft
documents. This decision could greatly limit our ability to appeal future nutrient limitations and could result in non-compliance.
ADVANTAGES OF APPROVAL
This watershed study will greatly enhance the City’s understand of our impact on the East Gallatin River and enable us to more successfully
negotiate future permit limitations with the DEQ.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None, unless additional stream sampling is desired in subsequent years.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY19
$60,000
FY20
$60,000
FY21
$60,000
218
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW28
DEPARTMENT
WRF
PROJECT NAME
DESIGN PHASE II - WRF PLANT IMPROVEMENTS
FY17 FY18 Unscheduled
$5,230,000
DESCRIPTION OF PROJECT
In January 2006 Morrison & Maierle Consulting Engineers completed a comprehensive Wastewater Facilities Plan. The plan
recommends the City proceed with a 3-phased project schedule that includes the construction of the new Water Reclamation
Facility (WRF), capable of handling our increased flows while also reducing the amount of Total Nitrogen discharged to the East
Gallatin River. Phase two is expected to include one new primary clarifier, more BNR reactor basins, clarifiers, tertiary
membrane filtration, liquid sludge storage tanks, anaerobic digestion, and an effluent re-use pumping station. The capacity
expanding (impact fee eligible) elements are: bioreactor basins, clarifiers, and pumping station. It is possible that this phase of the
project could be further divided into phase 2A and phase 2B, if necessary.
ALTERNATIVES CONSIDERED
A variety of treatment technologies and alternatives are presented in the January 2006 Wastewater Facilities Plan.
ADVANTAGES OF APPROVAL
Major capital expansion of the Bozeman WRF will enable the City to meet its estimated demand for wastewater services and still produce a high
quality effluent that is in full compliance with the City’s MPDES discharge permit. Expansion of the Bozeman WRF is consistent with the City’s
long-term need to accommodate rapid growth and economic development in the Gallatin Valley.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: no estimates at this time.
FUNDING SOURCES
Total Design Cost: $5,230,000. We estimate the majority of the project costs are related to regulation and maintenance issues and would be
borne by the Utility Fund. Half are related to capacity expansion, and would be borne by Impact Fees. 50% Wastewater Fund, 50% Wastewater
Impact Fee Fund.
New
Replacement
Equipment
Project
FY19 FY20 FY21
219
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW29
DEPARTMENT
WRF
PROJECT NAME
METHANE COGENERATION PROJECT DESIGN
FY17 FY18 Unscheduled
$350,000
DESCRIPTION OF PROJECT
Consistent with the goals of the City’s Climate Action Plan & Sustainability Programs, the Bozeman WRF staff and Public
Works Director recommend we move forward with our proposed investigation and installation of a methane recovery and co-
generation system. This system will produce an average of 175 kW of electricity and 974,000 BTU/hour of thermal output using a
generator powered entirely by WRF digester gas. This project has the potential to save the City at least $180,000 in electricity
costs and substantially lower the carbon footprint of the new Bozeman WRF. This project would be implemented in 3 phases
including (1) a feasibility / cost effectiveness study, (2) project engineering / design and (3) the purchase and installation of
appropriate technology for the co-generation of electricity at the Bozeman WRF. Year 1: Project Feasibility Study. Year 2: Project
Engineering Design - $350,000. Year 3: Equipment Purchase and Installation - $2,200,000.
ALTERNATIVES CONSIDERED
Continue to flare our digester methane gas. Micro-turbines and fuel-cells have been analysed and continue to be possible alternative energy
recovery technologies for this project. Our research to date suggests the most proven technology currently available to help us accomplish our
energy recovery goals is likely to be a GE Jenbacher internal combustion engine and heat recovery system.
ADVANTAGES OF APPROVAL
Current plant waste gases will be captured and utilized to reduce plant operating costs. The project has an estimated net dollar savings of
$230,000 per year. It supports the City's Municipal Climate Action Plan goals.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Once construction is funded, this project results in an estimated net dollar SAVINGS of $230,000/year.
FUNDING SOURCES
Wastewater Fund, other grants or community partners.
New
Replacement
Equipment
Project
FY19 FY20 FY21
220
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW35
DEPARTMENT
WRF
PROJECT NAME
COMMERCIAL MOWER
FY17 FY18 Unscheduled
$13,000
DESCRIPTION OF PROJECT
Replacement of 2001 Mower for use on the WRF grounds.
ALTERNATIVES CONSIDERED
Continue replacing parts as needed.
ADVANTAGES OF APPROVAL
Replacement parts will become more difficult to find as the mower ages. The increasing maintenance will mean less time for groundskeeping.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs. May reduce maintenance costs.
FUNDING SOURCES
Wastewater Funds.
New
Replacement
Equipment
Project
FY19 FY20 FY21
221
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW39
DEPARTMENT
WRF
PROJECT NAME
SANDBLAST & PAINT CLARIFIER DRIVES, BEACH, BAFFLES & WEIRS
FY17
$85,000
FY18
$90,000
Unscheduled
DESCRIPTION OF PROJECT
Sandblast and paint old clarifier drives, beaches, baffles weirs.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Replace lost & chipping paint on old clarifiers to prevent further deterioration of existing infrastructure. These clarifiers have not been painted
since they were installed in 1985.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No new operating costs.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY19
$90,000
FY20 FY21
222
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW42
DEPARTMENT
WRF
PROJECT NAME
PRIMARY CLARIFIER COVER
FY17 FY18 Unscheduled
$1,050,000
DESCRIPTION OF PROJECT
INSTALLING A GEODESIC DOME COVER WITH 8 FOOT SIDE WALLS ON A PRIMARY CLARIFIER. THE INSTALLATION
WOULD INCLUDE A DOOR, TWO SKYLIGHTS AND A VENT TUBE. ALSO CLARIFIER DRIVE MOTOR AND CONTROLS
WOULD HAVE TO BE EXPLOSION PROOF.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
COVERING THE PRIMARY CLARIFIERS WILL ALLOW ODOR CONTROL & ELIMINATE CLEANING & PAINTING. CLEANING &
PAINTING OF ALL RAILINGS AND CATWALKS IS AN ON-GOING MAINTENANCE ISSUE TO REMOVE GREASE & DROPPINGS
DEPOSITED BY BIRDS. COVERS ON PRIMARY CLARIFIERS WOULD ALLOW SOME CLARIFIERS NOT TO BE USED DURING THE
WINTER ALLOWING MORE NEEDED CARBON TO ENTER THE BIO-TRAINS.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Only maintenance of odor control would be additional.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY19 FY20 FY21
223
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW44
DEPARTMENT
WRF
PROJECT NAME
FLOTATION THINKENER
FY17 FY18 Unscheduled
$500,000
DESCRIPTION OF PROJECT
Modify the existing flotation thickener to treat the high levels of ammonia in the supernatant going back to the head of the plant
from the screw press that is dewatering anaerobic sludge This modification will improve WRF processes.
ALTERNATIVES CONSIDERED
Increase the bio-train mass, add Mg(OH)2 to increase alkalinity and add Micro C 2000 provide carbon for de-nitrification in the post anoxic
zones to treat the increased ammonia load
ADVANTAGES OF APPROVAL
Treating the return side stream will reduce the load on the bio-trains and reduce chemical costs associated with these loads.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Electrical costs for compressor, mixer and pumps.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY19 FY20 FY21
224
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW45
DEPARTMENT
WRF
PROJECT NAME
FINAL CLARIFIER LAUNDER COVER
FY17
$40,000
FY18
$40,000
Unscheduled
DESCRIPTION OF PROJECT
To cover effluent launder of one final clarifier a year (4 total) to eliminate algal growth in the launder. THE BRUSH SYSTEM
REQUIRES CONTINUAL MAINTENANCE. THERE IS RISK OF BRUSHES BREAKING OFF AND FALLING INTO THE
CLARIFIER THAT MAY BLOCK THE WASTING HOPPER
ALTERNATIVES CONSIDERED
CURRENTLY A BRUSH SYSTEM IS USED TO REDUCE THE AMOUNT OF ALGAL GROWTH WHICH REQUIRES CONTINUAL
MAINTENANCE.
ADVANTAGES OF APPROVAL
COVERING THE CLARIFIERS WILL ELIMINATE CURRENT MAINTENANCE AND HELP REDUCE POTENTIAL HAZZARDS.
MAINTENANCE WOULD BE CUT TO TWICE A YEAR ALLOWING OPERATORS TO SPEND TIME ON OTHER DUTIES AT THE PLANT.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Reduce operating costs (time & materials)
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY19 FY20 FY21
225
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW49
DEPARTMENT
WRF
PROJECT NAME
Roll-off Building and 2nd Screw Press & Screw Press Enclosure
FY17 FY18
$600,000
Unscheduled
DESCRIPTION OF PROJECT
Roll-off Building, Screw Press & 2nd Screw Press Enclosure - Construction
ALTERNATIVES CONSIDERED
Construction of an additional screw press, screw press enclosure & roll-off building.
ADVANTAGES OF APPROVAL
The second screw press would provide needed redundancy if a screw press breaks down. It would provide extra sludge processing capacity
now and for future needs. This building would also serve as storage for the sludge roll-offs to keep them from freezing.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
OPERATING COSTS COULD BE REDUCED.
FUNDING SOURCES
WASTEWATER FUNDS
New
Replacement
Equipment
Project
FY19 FY20 FY21
226
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW50
DEPARTMENT
WRF
PROJECT NAME
REFRIGERATED AUTOMATIC SAMPLERS
FY17 FY18 Unscheduled
$30,000
DESCRIPTION OF PROJECT
PURCHASE (3) NEW REFRIGERATED SAMPLERS FOR THE INFLUENT, PRIMARY AND EFFLUENT
ALTERNATIVES CONSIDERED
Keep repairing old samplers until they fail.
ADVANTAGES OF APPROVAL
The samplers we are using have been in service since 2000 and we have been replacing worn out parts. We need to start replacing them before
the circuit boards fail.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
NO ADDITIONAL COSTS.
FUNDING SOURCES
WASTEWATER FUNDS
New
Replacement
Equipment
Project
FY19 FY20 FY21
227
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW52
DEPARTMENT
WW OPS
PROJECT NAME
REPLACE #2683 - 1999 JOHN DEERE 310SE BACKHOE
FY17 FY18
$105,000
Unscheduled
DESCRIPTION OF PROJECT
This vehicle replaces a 1999 John Deere backhoe with 2,904 hours on it. This vehicle is used to dig and backfill ditches that we
dig to maintain our distribution and collection systems.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Waste Water utility.
New
Replacement
Equipment
Project
FY19 FY20 FY21
228
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW53
DEPARTMENT
WRF
PROJECT NAME
POSITIVE DISPLACEMENT LOBE PUMP
FY17
$20,000
FY18
$20,000
Unscheduled
$20,000
DESCRIPTION OF PROJECT
Replacement of older wasting pump that cannot provide the necessary wasting rates.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
Controlling mixed liquor inventory is critical to producing high quality effluent. If solids in the mixed liquor cannot be removed fast enough, total
suspended solids will increase in the effluent which will also increase the total phosphorus to the river.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No new operating costs. Replacement of the lobe pump may actually increase efficiency.
FUNDING SOURCES
WASTEWATER FUNDS
New
Replacement
Equipment
Project
FY19 FY20 FY21
229
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW54
DEPARTMENT
WW OPS
PROJECT NAME
REPLACE #1783 - 1995 FORD DUMP TRUCK
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project will replace a 1995 Ford Dump Truck that has 25,117 miles on it.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Will be a more fuel efficient and lower emissions vehicle. The new vehicle will improve safety of the crews, there would be lower repair costs
and it would help maintain current operations levels.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Waste Water Fund
New
Replacement
Equipment
Project
FY19 FY20
$95,000
FY21
230
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW55
DEPARTMENT
WW OPS
PROJECT NAME
REPLACE #3232 - 2004 3/4 TON FORD PICKUP
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project will replace a 2004 Ford Pickup truck with 43,355 miles on it.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Waste Water Fund
New
Replacement
Equipment
Project
FY19 FY20
$33,000
FY21
231
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW58
DEPARTMENT
WRF
PROJECT NAME
Chip Seal WRF Asphalt
FY17 FY18 Unscheduled
$47,370
DESCRIPTION OF PROJECT
Chip Seal WRF Asphalt to keep it from deteriorating.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
Chip seal will protect the already paid for infrastructure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
WASTEWATER FUNDS
New
Replacement
Equipment
Project
FY19 FY20 FY21
232
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW59
DEPARTMENT
WRF
PROJECT NAME
SPLITTER STRUCTURE AIR DIFFUSER
FY17 FY18 Unscheduled
$15,000
DESCRIPTION OF PROJECT
Install air diffusers to the end of the air lances in the flow splitter structure.
ALTERNATIVES CONSIDERED
Keep using air lances as is.
ADVANTAGES OF APPROVAL
AIR IS NEEDED IN THE FLOW SPLITTER STRUCTURE TO PREVENT SECONDARY PHOSPHORUS RELEASE. AIR DIFFUSERS PROVIDE A
HIGHER OXYGEN TRANSFER RATE TO THE FLOW AND THEREFORE WILL REDUCE THE LOAD ON THE AIR TURBINES SAVING
ELECTRICITY.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Will lower operating costs by lowering air flow needed to aerate sludge.
FUNDING SOURCES
WASTEWATER FUNDS
New
Replacement
Equipment
Project
FY19 FY20 FY21
233
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW60
DEPARTMENT
WRF
PROJECT NAME
NUTRIENT RECOVERY PROCESS CONSTRUCTION
FY17 FY18 Unscheduled
$2,000,000
DESCRIPTION OF PROJECT
CONSTRUCTION OF NUTRIENT RECOVERY PROCESS TO CAPTURE NITROGEN AND PHOSPHORUS FROM
ANAEROBICLY DIGESTED SLUDGE.
ALTERNATIVES CONSIDERED
DO NOTHING AND LOOSE A COMMODITY THAT IS A BI-PRODUCT OF ANAEROBIC DIGESTION
ADVANTAGES OF APPROVAL
THE PRODUCTION OF MAGNESIUM AMMONIUM PHOSPHATE TO BE SOLD AS A SLOW RELEASE FERTILIZER WILL RECYCLE
LIMITED NUTRIENTS BACK INTO THE ECOSYSTEM. THIS PROCESS WILL REDUCE THE NITROGEN AND PHOSPHORUS IN OUR
SIDESTREAM RETURNING TO THE HEAD OF THE PLANT WHICH WILL IN TURN REDUCE THE LOADING ON THE PROCESS.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
MAINTENANCE AND OPERATING COSTS THAT WILL BE OFF SET BY INCOME FROM THE SALE OF THE SLOW RELEASE FERTILIZER.
FUNDING SOURCES
WASTEWATER FUNDS
New
Replacement
Equipment
Project
FY19 FY20 FY21
234
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW61
DEPARTMENT
WRF
PROJECT NAME
ONLINE AMMONIA PROBES
FY17
$35,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Buy 2 online ammonia probes.
ALTERNATIVES CONSIDERED
DO NOTHING AND ALWAYS WAIT 24 HOURS TO SEE IF THE AMMONIA LIMIT WAS MET.
ADVANTAGES OF APPROVAL
Continual readings of the effluent ammonia would allow operators to detect problems with the de-nitrification process before the 24 hour
composite is tested. Early detection of problems would prevent violations.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance to the probes and a slight increase in electrical costs.
FUNDING SOURCES
WASTEWATER FUNDS
New
Replacement
Equipment
Project
FY19 FY20 FY21
235
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW62
DEPARTMENT
WRF
PROJECT NAME
METHANE COGENERATION PROJECT CONSTRUCTION
FY17 FY18 Unscheduled
$2,200,000
DESCRIPTION OF PROJECT
Consistent with the goals of the City’s Climate Action Plan & Sustainability Programs, the Bozeman WRF staff and Public
Works Director recommend we move forward with our proposed investigation and installation of a methane recovery and co-
generation system. This system will produce an average of 175 kW of electricity and 974,000 BTU/hour of thermal output using a
generator powered entirely by WRF digester gas. This project has the potential to save the City at least $180,000 in electricity
costs and substantially lower the carbon footprint of the new Bozeman WRF. This project would be implemented in 3 phases
including (1) a feasibility / cost effectiveness study, (2) project engineering / design and (3) the purchase and installation of
appropriate technology for the co-generation of electricity at the Bozeman WRF. Year 1: Project Feasibility Study. Year 2: Project
Engineering Design - $350,000. Year 3: Equipment Purchase and Installation - $2,200,000.
ALTERNATIVES CONSIDERED
Continue to flare our digester methane gas. Micro-turbines and fuel-cells have been analyzed and continue to be possible alternative energy
recovery technologies for this project. Our research to date suggests the most proven technology currently available to help us accomplish our
energy recovery goals is likely to be a GE Jenbacher internal combustion engine and heat recovery system.
ADVANTAGES OF APPROVAL
Current plant waste gases will be captured and utilized to reduce plant operating costs. The project has an estimated net dollar savings of
$230,000 per year. It supports the City's Municipal Climate Action Plan goals.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Once construction is funded, this project results in an estimated net dollar SAVINGS of $230,000/year
FUNDING SOURCES
Wastewater Fund, other grants or community partners.
New
Replacement
Equipment
Project
FY19 FY20 FY21
236
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW63
DEPARTMENT
WW Ops
PROJECT NAME
Chemical Root Control Applicator
FY17
$45,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
The applicator will be installed on our flusher truck and will apply the chemical. The chemical will kill the roots in the pipe
without harming the trees. It also includes an growth inhibitor which will prevent roots from growing back in the main. Roots in
our main are a problem and will help prevent sewer main backup from roots.
ALTERNATIVES CONSIDERED
We have cut roots with saws, chains and wire brushes this type of root cutting slowly damages the clay pipe.
ADVANTAGES OF APPROVAL
A more effective way to eliminate roots in the main and keep them from coming back.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
14,000.00 a year in chemical costs.
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
237
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW64
DEPARTMENT
WW OPS
PROJECT NAME
Sewer Flow Meter
FY17
$15,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
This meter can record sewer flows in the sewer main which is critical for planning for new mains. This meter will replace a 10
year old meter which is no longer working.
ALTERNATIVES CONSIDERED
Renting of meter.
ADVANTAGES OF APPROVAL
The ability to do in house monitoring of sewer flows.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Waste Water Utility Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
238
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW65
DEPARTMENT
WW OPS
PROJECT NAME
Digital Universal Camera DUC
FY17 FY18
$70,000
Unscheduled
DESCRIPTION OF PROJECT
The Digital Universal Camera (DUC) is a semi-autonomous, high resolution digital CCTV side scanning camera designed for rapid
and detailed condition assessment of our wastewater system.
ALTERNATIVES CONSIDERED
Continue to use the stop and go method (SAG) and take longer to TV the mains. We have a goal to TV the entire system every 5 years, this is
getting harder to do with the increasing growth of our collection system.
ADVANTAGES OF APPROVAL
This camera allows us to TV the main non-stop will allows us to increase the amount of pipe we TV in a day up to 5 to 10 times more than the
traditional stop and go method that we now use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Waste Water Utility Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
239
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW66
DEPARTMENT
WRF
PROJECT NAME
Odor Control for Old Pretreatment Buildings
FY17 FY18 Unscheduled
$15,000
DESCRIPTION OF PROJECT
Old Pretreatment building odor is vented out the roof next to Springhill Road.
ALTERNATIVES CONSIDERED
Run the risk of more odor complaints.
ADVANTAGES OF APPROVAL
Foul air from the sewer system coming into the old pretreatment building needs to be collected and treated.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs if another inline fan is not needed.
FUNDING SOURCES
Wastewater
New
Replacement
Equipment
Project
FY19 FY20 FY21
240
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW67
DEPARTMENT
WRF
PROJECT NAME
Convert Bio-Train #1 to 5 Stage Bardenpho
FY17 FY18 Unscheduled
$5,000,000
DESCRIPTION OF PROJECT
Modify Bio-train #1 to a 5 Stage Bardenpho configuration
ALTERNATIVES CONSIDERED
Construct two new 5 Stage Bardenpho bio-trains to treat increased flows and provide redundancy.
ADVANTAGES OF APPROVAL
Bio-train #1 uses the PNDN process which does not produce the level of nitrogen removal that the 5 Stage Bardenpho does. Modifying Bio-
train #1 to a 5 Stage Bardenpho will not degrade the quality of effluent that the plant produces and will realize the design flow of the plant
expansion at a reduced cost. Will also provide redundancy if a bio-train #2 or #3 fails.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Wastewater
New
Replacement
Equipment
Project
FY19 FY20 FY21
241
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW68
DEPARTMENT
WRF
PROJECT NAME
Secondary Launder Cover
FY17
$30,000
FY18
$30,000
Unscheduled
DESCRIPTION OF PROJECT
Cover effluent launder of one final clarifier to eliminate algal growth in the launder.
ALTERNATIVES CONSIDERED
Continue using a brush system to reduce the amount of algal growth. This method requires continual maintenance and there is a risk of brushes
breaking off and falling into the clarifier. This could block the wasting hopper in the clarifier.
ADVANTAGES OF APPROVAL
Elimination of the brush system with its maintenance and dangers. Maintenance on the launder would be cut to twice a year for a quick manual
cleaning allowing operators to spend time on other duties.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None. Would actually cut operating costs (time and materials)
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY19
$30,000
FY20 FY21
242
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW69
DEPARTMENT
WRF
PROJECT NAME
WRF Facility R & R
FY17
$50,000
FY18
$50,000
Unscheduled
DESCRIPTION OF PROJECT
Repair and replacement of equipment is an ongoing job at the Bozeman WRF. These funds would be used to repair or replace
equipment that fails unexpectedly in an emergency situation.
ALTERNATIVES CONSIDERED
Not having this fund would defer other needed maintenance.
ADVANTAGES OF APPROVAL
Most processes run 27/7 and have backup systems but when the first system fails there is no backup system and repairs need to be made
immediately. Not all repairs or equipment failures can be predicted and budgeted as a capital improvement project. Extra projects come up like
the security upgrades at the WRF. The upgrade is needed to protect city personnel and equipment but was not predicted and put into CIP.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY19
$50,000
FY20
$50,000
FY21
$50,000
243
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW70
DEPARTMENT
WRF
PROJECT NAME
WRF Facility Engineering & Optimization
FY17
$50,000
FY18
$50,000
Unscheduled
DESCRIPTION OF PROJECT
To allow engineering to be done on needed projects and to study plant optimization options before spending money on
equipment that might not be needed or the proper type. Allow studies to be conducted to make sure that proposed plant
optimizations will actually improve the effluent quality at a reasonable expense.
ALTERNATIVES CONSIDERED
Order replacement or upgrades to equipment that may not be sized correctly or made of the proper materials. Proceed with optimization
projects without knowing if the project will actually improve plant performance.
ADVANTAGES OF APPROVAL
The advantage of having funds available to do engineering studies before any project is started will make sure that the right equipment is
purchased and that it will perform properly. Optimization studies will predict actual cost/benefit over time to make sure the city is spending its
money efficiently.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Currently unknown
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY19
$50,000
FY20
$50,000
FY21
$50,000
244
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW71
DEPARTMENT
WRF
PROJECT NAME
WRF Facility Master Plan Update
FY17 FY18
$150,000
Unscheduled
DESCRIPTION OF PROJECT
The Master Plan Update will compare past predictions of the loadings on the city’s Water Reclamation Facility with current
loadings. New projections will be made using these data trends to determine the best course of action and sequencing of projects
to meet the needs of the facility.
ALTERNATIVES CONSIDERED
Not being proactive in predicting the best way to accommodate future loading at the Bozeman WRF will not fulfill the city’s needs to meet
future discharge limits.
ADVANTAGES OF APPROVAL
Bozeman’s rapid population growth dictates a review of the WRF’s treatment processes to make sure they will meet requirements now and in
the future. Establishing a clear incremental improvement process will prevent mistakes and eliminate inefficient spending of funds.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional costs
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY19 FY20 FY21
245
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW73
DEPARTMENT
WW OPS
PROJECT NAME
RATE STUDY - WASTEWATER
FY17
$50,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Wastewater Rate Study Update
ALTERNATIVES CONSIDERED
Keep the existing rate structure.
ADVANTAGES OF APPROVAL
The last wastewater rate study was completed almost 10 years ago. Updating this study will allow our user charges to better match the actual
cost of service.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Funds
New
Replacement
Equipment
Project
FY19 FY20 FY21
246
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW74
DEPARTMENT
WW OPS
PROJECT NAME
REPLACE #2915 - 2001 1 TON DODGE FLATBED/VALVE TRUCK
FY17
$70,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
This project replaces a 2001 Dodge truck with 51,311 miles on it and also replacement of the water valve mechanical turner.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
247
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW75
DEPARTMENT
WW OPS
PROJECT NAME
REPLACE #1677 - 1995 CHEVY S-10 PICKUP
FY17
$27,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
This project will replace a 1995 Chevy Pickup with 60,778 miles on it.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY19 FY20 FY21
248
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW76
DEPARTMENT
WW OPS
PROJECT NAME
REPLACE #3030 - 2001 JOHN DEERE SKID STEER
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project replaces the 2001 John Deere Skid Steer with 768 hours on it. It is a critical piece of machinery in our department.
ALTERNATIVES CONSIDERED
Continue to use older piece of equipment which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY19 FY20
$40,000
FY21
249
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW77
DEPARTMENT
WW OPS
PROJECT NAME
REPLACE #3157 - 2003 STERLING DUMP TRUCK
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project is to replace a 2003 Sterling Dump Truck which has 21,626 miles on it. This is the only front line single rear axle
dump truck in our fleet which is advantageous in working in tight areas.
ALTERNATIVES CONSIDERED
Continue to use older piece of equipment which is becoming unreliable and costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100 % Water Fund
New
Replacement
Equipment
Project
FY19 FY20
$105,000
FY21
250