HomeMy WebLinkAboutA2. Street Impact Fee CIP
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
Craig Woolard, Public Works Director
Chris Kukulski, City Manager
SUBJECT: Adoption of the Street Impact Fee Fund Capital Improvement Plan
(CIP) for FY17-21.
AGENDA ITEM TYPE: Action
MEETING DATE: December 14, 2015
RECOMMENDATION: Adopt the Street Impact Fee Fund Capital Improvement Plan
(CIP) for FY17-21.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. The City’s Impact Fee
Advisory Committee (IFAC) met on November 17th and December 3rd to review and make
recommendations for the planned expenditures of Street Impact Fees. The Committee had no
quorum on December 3rd to make a vote; their general recommendations are embodied in this
plan.
Items of Note:
1. The Street Impact Fee schedule (and our plans for street projects in general) has
significantly changed since last year’s CIP. Numerous new policies are proposed that
can help build out the street network within the next 5 years.
2. Public Works recommends building larger projects as “corridors”, including the
intersection controls and coordinated the water and wastewater upsizing. This has a
303
significant effect on the projects planned on the Street and Water & Wastewater
Impact Fee schedules (as well as the Arterial & Collector District schedule).
3. We have a desire to expand the overall capacity of the transportation network. In
some cases this can be best done by connecting streets where no adjacent
development is taking place. Therefore, at time of construction these projects are
100% impact fee eligible. If/when adjacent property develops, the adjacent
developer will be required to reimburse the Impact Fee Fund for the costs of its
project-level improvements (local share.)
• We see this working to complete more street network improvements,
including important Street Impact Fee projects that have been on hold, waiting
for adjacent properties to develop. This was a significant topic of discussion
with the IFAC, and was generally supported, as a concept, by the group and
others in attendance.
• In FY18 & FY19, the Fund will be providing the “local share” of some
projects in advance of development. These projects are noted with an “*”.
The city will create a payback district to recover the “local share” once an
adjacent project is developed. This payback will be deposited to the Street
Impact Fee Fund. At the end of this 5-year plan, payback improvements are
estimated to total over $2.9 million.
• We have recorded the amount of “local share” payback improvements are
funded each year on the Financial Summary, below the Projected Year-End
Cash.
• We anticipate that some of these payback amounts will come back to the
Street Impact Fee Fund as projects develop; but, for purposes of this plan we
have not relied on receiving any of that money to fund projects. This is a
conservative approach to a difficult-to-estimate cash flow.
• We anticipate a payback for “local share” of these projects would be made at
the time a development project is approved.
4. The new Arterial & Collector District will also be providing some “Local Share”
amounts in advance of the local projects, so that critical portions of the street network
can be connected (See the Arterial & Collector CIP). The Arterial & Collector
304
District will also be made whole, in the future, if/when the local project moves
forward, or upon annexation – via a Payback District arrangement.
• The Arterial & Collector District, created this summer, was designed with this
concept in mind (fronting “local share” contributions in advance of
development). The District cannot provide funding for any elements of a
project that are impact fee eligible.
5. The question of intersection funding is critical in scheduling both the Street Impact
Fee and Arterial & Collector District CIP’s. Our recommendation is to fund
intersections at 80% impact fee eligible and 20% from the Arterial & Collector
District.
• This is a policy change from a 60% Impact Fee/40% Local Share split that
currently exists for intersections. However, such a change will not affect the
amount of impact fees we collect because the impact fee study contained full-
costs for intersection improvements.
• By using the Arterial & Collector District to help fund intersections at 20%,
we are able to build more intersection improvements than if the district were
required to contribute 40% to the projects. Therefore, this policy
recommendation maximizes improvements to the transportation network over
the 5 year capital improvement plan.
6. A new Street Impact Fee Study is included in this plan for FY17. The fee update
could address policy questions regarding the “local share” of arterial & collector
streets; potentially classifying these as “system” system improvements (not “local”
improvements) in the future.
7. Revenues have been updated to reflect the 5-year average for Street Impact Fee
collections. Fiscal Year 2015 collections mark a record for the program at $4 million.
This is up from the previous high-marks of $3.6 million collected in FY05 and $3.3
million in FY07. The 5 year average is calculated to be $2.4 million and has been
included as an estimate of revenue in the plan. We have also estimated annual growth
at 5% per year.
305
Revenue History - Street Impact Fees Amount Change
2011 1,303,020.0 -
2012 1,152,556.0 -12%
2013 2,549,256.0 121%
2014 2,934,549.0 15%
2015 4,016,986.0 37%
Average 2,391,273.4
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY16.
Report compiled on: December 8, 2015
Attached: Draft Street Impact Fee Fund CIP
-
500,000.0
1,000,000.0
1,500,000.0
2,000,000.0
2,500,000.0
3,000,000.0
3,500,000.0
4,000,000.0
4,500,000.0
2011 2012 2013 2014 2015 Average
Street Impact Fees
306
Street Impact Fee Capital Improvement Plan Financial SummaryCurrent YearFY16FY17FY18FY19FY20 FY21UnscheduledProjected Beginning Reserve Balance Dedicated to CIP13,824,839$ 10,099,199$ 7,331,224$ 2,292,723$ 864,726$ (26,758)$ Plus: Impact Fee Revenues Dedicated to CIP2,390,000$ 2,509,500$ 2,634,975$ 2,766,724$ 2,905,060$ 3,050,313$ ‐$ Plus: Urban Funds: SIF09, Kagy (Willson to 19th) 4,000,000$ Plus: Arterial & Collector District 555,000$ Less: Scheduled CIP Project Costs ‐ adjusted(6,670,640)$ (5,277,475)$ (7,673,476)$ (4,194,721)$ (7,796,544)$ (466,000)$ (2,769,600)$ Projected Year‐End Cash Dedicated to CIP10,099,199$ 7,331,224$ 2,292,723$ 864,726$ (26,758)$ 2,557,555$ (2,769,600)$ Beginning Balance of Payback Improvements:‐$ ‐$ 1,592,475$ 2,994,725$ 2,994,725$ 2,994,725$ New Payback Projects‐$ 1,592,475$ 1,402,250$ ‐$ ‐$ ‐$ Ending Balance of Payback Improvements:‐$ 1,592,475$ 2,994,725$ 2,994,725$ 2,994,725$ 2,994,725$ Assumptions Made for Revenue Estimates:Current YearFY16FY17FY18FY19FY20FY21Estimated Annual Street Impact Fee Revenues2,390,000$ 2,390,000$ 2,509,500$ 2,634,975$ 2,766,724$ 2,905,060$ Estimated Annual Increase0.0%5%5%5%5%5%Total Estimated Revenues2,390,000$ 2,509,500$ 2,634,975$ 2,766,724$ 2,905,060$ 3,050,313$ Current Revenues Dedicated to CIP %100.0%100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to Street Capacity Expansion CIP0.0%0.0%0.0%0.0%0.0%0.0% Total % Dedicated to CIP100.0%100.0% 100.0% 100.0% 100.0% 100.0%Total Estimated Revenues Dedicated to CIP2,390,000$ 2,509,500$ 2,634,975$ 2,766,724$ 2,905,060$ 3,050,313$ *Note: This schedule no longer contains the portions of project coststhat will be paid by other sources, with the exception of FederalUrban Funds. See the "Funding Sources" discussion at the bottom of each project item sheet. ProjectedProjected"See Arterial & Collector District CIP"CURRENT11,000,0009,000,0007,000,0005,000,0003,000,0001,000,000FY17 FY18 FY19 FY20 FY21 UnscheduledStreet Impact Fee Projects 307
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY17UnscheduledFY21FY18FY19FY20Impact Fees StreetsSIF001STREET IFRIGHT OF WAY ACQUISITION$132,000$132,000$132,000$132,000$132,000SIF009STREET IFKAGY (WILLSON TO 19TH) ‐ CONSTRUCTION$4,000,000SIF027STREET IFCOTTONWOOD & DURSTON (INTERSECTION) ‐ CONSTRUCTION$160,000SIF036STREET IFCOTTONWOOD (BABCOCK TO DURSTON) ‐ CONSTRUCTION$1,277,942SIF039STREET IFFERGUSON & DURSTON (INTERSECTION) ‐ CONSTRUCTION$1,804,976SIF046STREET IFOAK (NEW HOLLAND TO FERGUSON)* ‐ CONSTRUCTION$1,400,000SIF055STREET IFBAXTER (19TH TO DAVIS)* ‐ CONSTRUCTION$1,000,000SIF057STREET IFOAK (FERGUSON TO COTTONWOOD) ‐ CONSTRUCTION$761,000SIF058STREET IFN. 27TH &OAK (INTERSECTION) ‐ CONSTRUCTION$800,000SIF061STREET IFOAK & FERGUSON (INTERSECTION) ‐ CONSTRUCTION$800,000SIF062STREET IFDURSTON (COTTONWOOD TO FOWLER)* ‐ CONSTRUCTION$1,073,000SIF063STREET IFFOWLER & BABCOCK (INTERSECTION) ‐ CONSTRUCTION$800,000SIF069STREET IFFERGUSON & DURSTON (INTERSECTION) ‐ DESIGN$120,000SIF071STREET IFFERGUSON (BAXTER TO OAK) ‐ DESIGN$50,000SIF072STREET IFBAXTER (FERGUSON TO COTTONWOOD)* ‐ CONSTRUCTION$764,475SIF073STREET IFFOWLER & DURSTON (INTERSECTION) ‐ CONSTRUCTION$800,000SIF074STREET IFFOWLER & OAK (INTERSECTION) ‐ CONSTRUCTION$800,000SIF076STREET IFFOWLER CONNECTION (HUFFINE TO OAK) ‐ DESIGN$334,000308
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY17UnscheduledFY21FY18FY19FY20SIF077STREET IFGRAF STREET EXTENSION (RITTER TO 19TH)* ‐ CONSTRUCTION$1,035,000SIF080STREET IFFERGUSON (BAXTER TO OAK) ‐ CONSTRUCTION$500,000SIF082STREET IFWTI TRANSPORTATION MODEL$100,000SIF084STREET IFBAXTER (DAVIS TO COTTONWOOD)* ‐ DESIGN$225,000SIF085STREET IFBAXTER (7TH TO 19TH) ‐ CONSTRUCTION$500,000SIF086STREET IFBAXTER & COTTONWOOD (INTERSECTION) ‐ CONSTRUCTION$369,600SIF087STREET IFCATAMOUNT ST (27TH TO VALLEY CENTER) ‐ CONSTRUCTION$300,000SIF088STREET IFIMPACT FEE STUDY ‐ STREET$100,000SIF093STREET IFOAK STREET (15TH TO 19TH) ‐ CONSTRUCTION$350,000SIF094STREET IFCATAMOUNT ST (27TH TO VALLEY CENTER) ‐ DESIGN$45,000SIF095STREET IFN 27TH (OAK TO TSCHACHE)* ‐ DESIGN$52,500SIF098STREET IFOAK & COTTONWOOD (INTERSECTION ‐ ROUNDABOUT) ‐ CONSTRUCTION$2,742,721SIF099STREET IFN 27TH (OAK TO TSCHACHE)* ‐ CONSTRUCTION$350,000SIF102STREET IFS 11TH AVE (KAGY BLVD TO GRAF ST EXTENSION) ‐ CONSTRUCTION$1,320,000SIF103STREET IFS 11TH AVE (KAGY BLVD TO GRAF ST EXTENSION)* ‐ DESIGN$396,000SIF104STREET IFCOTTONWOOD & BABCOCK (INTERSECTION‐SIGNAL)$1,148,269SIF105STREET IFCOTTONWOOD (DURSTON ‐ OAK) ‐ CONSTRUCTION$1,238,333$466,000$5,277,475$7,673,476$4,194,721$7,796,544$2,769,600309
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY17UnscheduledFY21FY18FY19FY20Summary for Impact Fees Streets (35 items)Totals by year:$466,000$5,277,475 $7,673,476$2,769,600FY21FY17FY18UnscheduledFY20$7,796,544$4,194,721FY19310
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF001
DEPARTMENT
STREET IF
PROJECT NAME
RIGHT OF WAY ACQUISITION
FY17
$132,000
FY18
$132,000
Unscheduled
DESCRIPTION OF PROJECT
Annual allocation available for right-of-way purchases as they become available. Purchasing additional right-of-way is critical to
expanding the capacity of streets in the city. This is deemed to be 100% impact fee eligible – as additional right-of-way is not
required if we are not expanding the capacity of the street.
ALTERNATIVES CONSIDERED
Condemn property for right-of-way; pay court costs as well as appraised value of property. Time consuming for city staff and a relatively
expensive process.
ADVANTAGES OF APPROVAL
Provides dollars for the purchase of necessary right-of-way as it becomes available on the market. Avoids the expensive, antagonistic
condemnation process where possible.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Street Impact Fees can not be spent on operating and maintaining facilities. There is expected to be a
very minimal, incremental cost to the Street Maintenance District from this expenditure.
FUNDING SOURCES
New
Replacement
Equipment
Project
FY19
$132,000
FY20
$132,000
FY21
$132,000
311
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF009
DEPARTMENT
STREET IF
PROJECT NAME
KAGY (WILLSON TO 19TH) - CONSTRUCTION
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project consists of widening Kagy Boulevard from the intersection of S. 19th Avenue to Willson Avenue to a three lane
urban arterial standard. This includes one travel lane in each direction, bike lanes on each side, curb and gutter throughout,
boulevard, sidewalks and a raised median. Kagy serves as an important element of Bozeman's perimeter street system connecting
Highland Blvd., Willson Ave. and S.19th. It also serves as the primary access to Montana State University and the University's
major athletic facilities.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Kagy is a State Urban Route and is eligible for expenditure of State urban funds designated annually for the City of Bozeman; however, the
availability of urban funds cannot match the pace of the City's transportation improvement needs. The need for this project comes from
increased traffic due to growth in the Bozeman area and the project is eligible for Impact Fee Funds. Use of Street Impact Funds enables the
community to leverage the available State Urban transportation funds to complete projects and address more of its pressing transportation
needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($4,000,000) and Urban Funds ($4,000,000).
New
Replacement
Equipment
Project
FY19 FY20
$4,000,000
FY21
312
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF027
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD & DURSTON (INTERSECTION) - CONSTRUCTION
FY17
$160,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Further improvements to the intersection in conjunction with the improvements to Cottonwood from Babcock to Baxter.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential sources of
funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and maintenance costs: Incremental increases in sweeping, plowing & maintenance costs.
FUNDING SOURCES
This project is fund by Street Impact Fees ($160,000) and TOPS ($40,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
313
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF036
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD (BABCOCK TO DURSTON) - CONSTRUCTION
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
This project consists of widening Cottonwood Road from West Babcock Street to Baxter Street to a three lane urban arterial
standard. This includes one travel lane in each direction, bike lanes on each side, curb and gutter throughout, boulevard,
sidewalks and a raised median. Cottonwood Road serves as an important element in Bozeman's west side street system and
serves as a primary north-south corridor on the west side of the city.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Improved traffic flow and safety in this corridor.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,275,178) and the Arterial & Collector District ($1,280,705). A development payback district
will be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $1,400,000).
New
Replacement
Equipment
Project
FY19 FY20
$1,277,942
FY21
314
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF039
DEPARTMENT
STREET IF
PROJECT NAME
FERGUSON & DURSTON (INTERSECTION) - CONSTRUCTION
FY17 FY18
$1,804,976
Unscheduled
DESCRIPTION OF PROJECT
Control of the intersection of 7th Avenue and Griffin Drive. Includes the installation of a traffic signal or roundabout. Future
development and the resulting increased traffic indicate that intersection improvements will be needed.
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Improved traffic flow and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,804,976) and the Arterial & Collector District ($451,244).
New
Replacement
Equipment
Project
FY19 FY20 FY21
315
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF046
DEPARTMENT
STREET IF
PROJECT NAME
OAK (NEW HOLLAND TO FERGUSON)* - CONSTRUCTION
FY17 FY18
$1,400,000
Unscheduled
DESCRIPTION OF PROJECT
This Project is the completion of the street segment of Oak Street, from New Holland to Ferguson. Currently, the south half of
the street is missing, creating a bottleneck in the street network. We anticipate that by the time this project is built, the
City will have designated Oak Street as an Urban Route, eligilbe for Urban Funds.</div>
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,400,000) and the Gallatin County ($600,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
316
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF055
DEPARTMENT
STREET IF
PROJECT NAME
BAXTER (19th TO DAVIS)* - CONSTRUCTION
FY17
$1,000,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete Baxter Road from 19th to Davis to a 3 lane urban minor arterial standard including sidewalks, parking, medians,
boulevards and bike lanes.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,000,000) and the Arterial & Collector District ($500,000). A development payback district will
be created to reimburse Street Impact Fees for any local share (project related) costs that may be allocated to future developments (etimated at
$500,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
317
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF057
DEPARTMENT
STREET IF
PROJECT NAME
OAK (FERGUSON TO COTTONWOOD) - CONSTRUCTION
FY17 FY18
$761,000
Unscheduled
DESCRIPTION OF PROJECT
This Project is the completion of the street segment of Oak Street, from New Holland to Ferguson. Currently, the south half of
the street is missing, creating a bottleneck in the street network.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($761,000) and the Arterial & Collector District ($239,000). A development payback district will
be created to reimburse Street Impact Fees for any local share (project related) costs that may be allocated to future developments (estimated
at $261,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
318
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF058
DEPARTMENT
STREET IF
PROJECT NAME
N. 27th &OAK (INTERSECTION) - CONSTRUCTION
FY17 FY18
$800,000
Unscheduled
DESCRIPTION OF PROJECT
Includes installation of a traffic signal, roundabout or other adequate traffic control device when warrants are met.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential sources of
funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: None
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
319
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF061
DEPARTMENT
STREET IF
PROJECT NAME
OAK & FERGUSON (INTERSECTION) - CONSTRUCTION
FY17 FY18
$800,000
Unscheduled
DESCRIPTION OF PROJECT
Includes installation of a traffic signal, roundabout or other adequate traffic control device when warrants are met.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential sources of
funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
320
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF062
DEPARTMENT
STREET IF
PROJECT NAME
DURSTON (COTTONWOOD TO FOWLER)* - CONSTRUCTION
FY17 FY18
$1,073,000
Unscheduled
DESCRIPTION OF PROJECT
Complete Durston Road from Fowler Lane to Cottonwood to an urban minor arterial standard.
ALTERNATIVES CONSIDERED
Continue with the facility as is.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,073,000) and the Arterial & Collector District ($540,000). A development payback district will
be created to reimburse Street Impact Fees for any local share (project related) costs that may be allocated to future developments (estimated
at $540,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
321
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF063
DEPARTMENT
STREET IF
PROJECT NAME
FOWLER & BABCOCK (INTERSECTION) - CONSTRUCTION
FY17 FY18 Unscheduled
$800,000
DESCRIPTION OF PROJECT
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic
control device when warrants are met.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
322
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF069
DEPARTMENT
STREET IF
PROJECT NAME
FERGUSON & DURSTON (INTERSECTION) - DESIGN
FY17
$120,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Includes design of a traffic signal, roundabout or other adequate traffic control device when warrants are met.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($120,000) and the Arterial & Collector District ($30,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
323
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF071
DEPARTMENT
STREET IF
PROJECT NAME
FERGUSON (BAXTER TO OAK) - DESIGN
FY17
$50,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Design Ferguson from Baxter to Oak to an urban collector standard.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($50,000) and developer contribution ($50,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
324
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF072
DEPARTMENT
STREET IF
PROJECT NAME
BAXTER (FERGUSON TO COTTONWOOD)* - CONSTRUCTION
FY17
$764,475
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete Baxter from Ferguson to Cottonwood to a 3 lane urban minor arterial standard with bike lanes.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
The $1,500,000 total cost of this project is funded by Street Impact Fees ($764,475), Arterial and Collector District ($500,000), and TOPS
($235,525). A development payback district will be created to reimburse TOP funds for any local share (project related) costs that may be
allocated to future developments (estimated at $264,475).
New
Replacement
Equipment
Project
FY19 FY20 FY21
325
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF073
DEPARTMENT
STREET IF
PROJECT NAME
FOWLER & DURSTON (INTERSECTION) - CONSTRUCTION
FY17 FY18 Unscheduled
$800,000
DESCRIPTION OF PROJECT
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic
control device when warrants are met.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
326
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF074
DEPARTMENT
STREET IF
PROJECT NAME
FOWLER & OAK (INTERSECTION) - CONSTRUCTION
FY17 FY18 Unscheduled
$800,000
DESCRIPTION OF PROJECT
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic
control device when warrants are met.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($800,000) and the Arterial & Collector District ($200,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
327
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF076
DEPARTMENT
STREET IF
PROJECT NAME
FOWLER CONNECTION (HUFFINE TO OAK) - DESIGN
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
Design Fowler from Huffine to Oak to an urban minor arterial standard. Design includes 3 intersections.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($334,000) and the Arterial & Collector District ($666,000). A development payback district will
be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future developments
(estimated at $334,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
$334,000
328
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF077
DEPARTMENT
STREET IF
PROJECT NAME
GRAF STREET EXTENSION (RITTER TO 19TH)* - CONSTRUCTION
FY17
$1,035,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete Graf from Ritter to 19th to a 2 lane urban collector standard with bike lanes.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,035,000). A development payback district will be created to reimburse Street Impact Fees for
any local share (project related) costs that may be allocated to future developments (estimated at $517,500).
New
Replacement
Equipment
Project
FY19 FY20 FY21
329
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF080
DEPARTMENT
STREET IF
PROJECT NAME
FERGUSON (BAXTER TO OAK) - CONSTRUCTION
FY17 FY18
$500,000
Unscheduled
DESCRIPTION OF PROJECT
Complete Ferguson from Baxter to Oak to a two lane urban collector standard with bike lanes, curb and gutter, boulevards,
parking and sidewalks.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($500,000) and Gallatin County ($500,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
330
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF082
DEPARTMENT
STREET IF
PROJECT NAME
WTI TRANSPORTATION MODEL
FY17
$100,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
The purpose of this project is to create a model capable of accurately predicting levels of service at any intersection within the
city based on current traffic and the anticipated contribution from proposed developments. The model will require more or less
constant maintenance (updates) which will be provided by the Western Transportation Institute (WTI).
ALTERNATIVES CONSIDERED
Continue relying on developer provided traffic impact studies.
ADVANTAGES OF APPROVAL
This model will provide more comprehensive and timely data than what is currently provided by developer commissioned studies. City staff is in
a better position to understand all of the models inputs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
$10,000/yr
FUNDING SOURCES
Street Impact Fees
New
Replacement
Equipment
Project
FY19 FY20 FY21
331
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF084
DEPARTMENT
STREET IF
PROJECT NAME
BAXTER (DAVIS TO COTTONWOOD)* - DESIGN
FY17
$225,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Design Baxter from Davis to Cottonwood to an urban minor arterial standard.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($225,000). A development payback district will be created to reimburse Street Impact Fees for
any local share (project related) costs that may be allocated to future developments (estimated at $112,500).
New
Replacement
Equipment
Project
FY19 FY20 FY21
332
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF085
DEPARTMENT
STREET IF
PROJECT NAME
BAXTER (7TH TO 19TH) - CONSTRUCTION
FY17
$500,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete Baxter from 7th to 19th to an urban collector standard including sidewalks on both sides and bike lanes.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded 100% by Street Impact Fees
New
Replacement
Equipment
Project
FY19 FY20 FY21
333
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF086
DEPARTMENT
STREET IF
PROJECT NAME
BAXTER & COTTONWOOD (INTERSECTION) - CONSTRUCTION
FY17 FY18 Unscheduled
$369,600
DESCRIPTION OF PROJECT
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic
control device when warrants are met.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs.
FUNDING SOURCES
This project is funded by Street Impact Fees ($369,600) and the Arterial & Collector District ($92,400).
New
Replacement
Equipment
Project
FY19 FY20 FY21
334
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF087
DEPARTMENT
STREET IF
PROJECT NAME
CATAMOUNT ST (27TH TO VALLEY CENTER) - CONSTRUCTION
FY17
$300,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete Catamount from 27th to Valley Center to an urban minor arterial standard including bike lanes.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded 50/50 by Street Impact Fees ($300,000) and Developer contribution ($300,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
335
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF088
DEPARTMENT
STREET IF
PROJECT NAME
IMPACT FEE STUDY - STREET
FY17
$100,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
<div>The city needs to update its calculation and methodologies related to the price of the Transportation (Street) Impact Fee.
</div>
ALTERNATIVES CONSIDERED
None. This is required by state law for communities that have impact fee programs.
ADVANTAGES OF APPROVAL
Compliant impact fee program.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
100% Street Impact Fees
New
Replacement
Equipment
Project
FY19 FY20 FY21
336
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF093
DEPARTMENT
STREET IF
PROJECT NAME
OAK STREET (15TH TO 19TH) - CONSTRUCTION
FY17
$350,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete Oak from 15th to 19th to an urban principal arterial standard including addition of 1 lane (5 lanes total), bike lanes
and sidewalks on the south side.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
Street Impact Fees
New
Replacement
Equipment
Project
FY19 FY20 FY21
337
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF094
DEPARTMENT
STREET IF
PROJECT NAME
CATAMOUNT ST (27TH TO VALLEY CENTER) - DESIGN
FY17
$45,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete S 11th from Kagy to Graf to an urban collector standard including bike lanes.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($45,000) and developer contribution ($45,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
338
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF095
DEPARTMENT
STREET IF
PROJECT NAME
N 27TH (OAK TO TSCHACHE)* - DESIGN
FY17 FY18
$52,500
Unscheduled
DESCRIPTION OF PROJECT
Complete S 11th from Kagy to Graf to an urban collector standard including sidewalks, curb and gutter and bike lanes,
boulevards and parking.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($52,500). A development payback district will be created to reimburse Street Impact Fees for any
local share (project related) costs that may be allocated to future developments (estimated at $26,250).
New
Replacement
Equipment
Project
FY19 FY20 FY21
339
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF098
DEPARTMENT
STREET IF
PROJECT NAME
OAK & COTTONWOOD (INTERSECTION - Roundabout) - CONSTRUCTION
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
Identified in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic
control device when warrants are met.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($2,742,721) and the Arterial & Collector District ($685,680).
New
Replacement
Equipment
Project
FY19
$2,742,721
FY20 FY21
340
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF099
DEPARTMENT
STREET IF
PROJECT NAME
N 27TH (OAK TO TSCHACHE)* - CONSTRUCTION
FY17 FY18
$350,000
Unscheduled
DESCRIPTION OF PROJECT
Complete N 27th from Oak to Tschache to an urban collector standard including medians for power poles.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($350,000). A development payback district will be created to reimburse Street Impact Fees for
any local share (project related) costs that may be allocated to future developments (estimated at $175,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
341
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF102
DEPARTMENT
STREET IF
PROJECT NAME
S 11TH AVE (KAGY BLVD TO GRAF ST EXTENSION) - CONSTRUCTION
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete S 11th from Kagy to Graf to an urban collector standard including sidewalks, curb and gutter and bike lanes.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,320,000) and the Arterial & Collector District ($1,320,000). A development payback district
will be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $1,320,000).
New
Replacement
Equipment
Project
FY19
$1,320,000
FY20 FY21
342
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF103
DEPARTMENT
STREET IF
PROJECT NAME
S 11TH AVE (KAGY BLVD TO GRAF ST EXTENSION)* - DESIGN
FY17
$396,000
FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete S 11th from Kagy to Graf to an urban collector standard including sidewalks, curb and gutter and bike lanes.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($396,000). A development payback district will be created to reimburse Street Impact Fees for
any local share (project related) costs that may be allocated to future developments (estimated at $198,000).
New
Replacement
Equipment
Project
FY19 FY20 FY21
343
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF104
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD & BABCOCK (INTERSECTION-SIGNAL)
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
80% IMPACT FEES, 20% ARTERIAL AND COLLECTOR DISTRICT
New
Replacement
Equipment
Project
FY19 FY20
$1,148,269
FY21
344
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF105
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD (DURSTON - OAK) - CONSTRUCTION
FY17 FY18 Unscheduled
DESCRIPTION OF PROJECT
Complete the construction of Cottonwood Road, from Durston Road - Oak street.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost estimate of
$8,725 per street mile maintained annually.
FUNDING SOURCES
This project is funded by Street Impact Fees ($1,238,333) and the Arterial & Collector District ($1,238,333). A development payback district
will be created to reimburse Arterial & Collector District for any local share (project related) costs that may be allocated to future
developments (estimated at $1,238,333).
New
Replacement
Equipment
Project
FY19 FY20
$1,238,333
FY21
345