Loading...
HomeMy WebLinkAboutAppendix 7 - Sewer Main Extension Engineer's Report Cannery District Planned Unit Development Preliminary PUD Application Cannery District Partners, llc Appendix 7 Sewer Main Extension Engineer’s Report Sewer Main Extension Engineer’s Report Cannery District PUD February, 2015 For Submittal to: City of Bozeman Engineering Department 20 East Olive Bozeman, MT 59715 Montana Department of Environmental Quality Permitting and Compliance Division Public Water and Subdivisions Bureau PO Box 200901 Helena, MT 59620-0901 Prepared by: Stahly Engineering and Associates 851 Bridger Drive, Suite 1 Bozeman, MT 59715 (406) 522-9526 Sewer Mains 1 2/5/2015 Engineer’s Report Contents Note: The Engineer’s Report format for the Cannery District PUD Sewer Main Extension follows DEQ-2 organization. Additional information required by the City of Bozeman Design Standards is added where required. Report Narrative Chapter 10 – Engineering Reports & Facility Plans 11.1 Engineering Report 11.11 Problem Defined 11.12 Design Conditions 11.13 Impact on Existing Wastewater Facilities 11.14 Project Description 11.15 Design Criteria 11.16 Site Information 11.17 Environmental Impacts Figures and Tables Figure 1. Vicinity Map Figure 2. Sewer Site Plan (C3.0 – included separately) Table 1. Cannery District Sewer Flow Estimates Table 2. Capacity of 8” and 10” SDR 35 PVC Sewer Main Sewer Mains 2 2/5/2015 11.1 Engineering Report The Cannery District is a multi-phase development located on the north side of East Oak Street and Rouse Avenue, north of the Gallatin County Fairgrounds. The existing property consists of several parcels of land within the City and County, with 3.30 acres within the City and 8.94 acres within the county. The development consists of four phases. The first phase was approved by the City of Bozeman and MDEQ in November 2014. This phase consists of remodeling four existing buildings originally constructed as part of the original pea canning operation in 1917. During this phase, the existing water and sewer infrastructure will be replaced and upgraded to current City standards. Phases 2, 3 and 4 involve the construction of six new buildings on the Cannery District property. The wastewater flows from these future phases were accounted for in the design of the approved Phase 1 system. These future phases will be annexed prior to development in order to receive municipal services for new buildings. The developer’s contact information is: Cannery District Partners, LLC 1006 W Main Street Bozeman, MT 59715 Water supply and wastewater treatment will continue to be provided by the City of Bozeman’s municipal systems. The system owner’s contact information is: City of Bozeman Public Service Department PO Box 1230 Bozeman, MT 59771-1230 The location of the Cannery District is shown on the Vicinity Map in Figure 1. See C3.0 for the overall sewer system plan. Sewer Mains 3 2/5/2015 Figure 1. Vicinity Map, Bozeman, Montana 11.11 Problem Defined City of Bozeman sewer mains were constructed in 1917 to serve the existing buildings. Nearing 100 years in age, these existing 15” sewer mains have reached the end of their useful life. In addition, the existing sewer network is not configured to support future phases within the development. The approved Phase 1 sewer upgrades will replace the existing mains, however, additional sewer mains and services require extensions in order to serve the future phases. The location of the existing mains, approved Phase 1 sewer mains, and proposed extensions to the sewer system are shown in C3.0, a large map included separately. 11.12 Design Conditions The sewer flow contributed by the Cannery District was determined using wastewater flow rates for zoned undeveloped areas from the City of Bozeman Design Standards and Specifications Policy, Table V-1. For the Northside PUD and the portion of the Cannery District that is currently within city limits, the zoning designation is B-2. The rest of the Cannery district currently outside of city limits must be annexed prior to development, with the plan being to maintain the same zoning designation of B-2. Table V-1 shows a flow rate of 2000 Gal./Acre/Day for zoning designation B-2. To evaluate the overall sewer network, all four phases of the Cannery District and the Northside PUD were evaluated. The Northside PUD has three existing sewer services that connect to the existing sewer main that serves the Cannery District. As this sewer main will be abandoned, the Northside sewer services will be connected to the approved Phase 1 Sewer Mains 4 2/5/2015 sewer main, and are accounted for in the wastewater flow estimates shown in Table 1, below. Table 1 Cannery District Sewer Flow Estimates The approved Phase 1 sewer network consists of both 8” and 10” SDR 35 PVC sewer mains. 8” SDR 35 PVC sewer mains installed at the minimum slope of 0.4% have a flow capacity of 312.8 gpm using 75% of the flow depth of the pipe as required by the City of Bozeman Design Standards and Specifications Policy. 10” SDR 35 PVC sewer mains installed at the slope of 0.3% have a flow capacity of 491.2 gpm using 75% of the flow depth of the pipe. See Table 2 below for the parameters used in the flow calculation. Table 2. Capacity of 8” and 10” SDR 35 PVC Sewer Main Status Proposed Proposed Location Cannery District Cannery District Pipe Material 8" SDR 35 PVC 10" SDR 35 PVC Pipe Diameter (in) 8 10 Minimum Pipe Slope (ft/ft) 0.004 0.003 Coefficient of Roughness (n) 0.013 0.013 Depth in Pipe at 75% Full (in) 6 7.5 Depth of Flow (ft) 0.5 0.625 Pipe Radius (in) 4 5 Pipe Radius (ft) 0.33 0.42 Wetted Perimeter 1.40 1.75 Area of Flow (ft2) 0.28 0.44 Hydraulic Radius 0.20 0.25 Velocity (ft/sec) 2.48 2.49 Maximum Pipe Flowrate (gpm) 312.8 491.2 Peak Hour Flow (gpm) 212 212 Peak Flow % of Max Capacity 67.77% 43.16% The 8” sewer at the minimum allowed slope has sufficient capacity to convey the peak flow from all four phases of the Cannery District, Cannery District Water Use Phase 1 Phase 2 Phase 3 Phase 4 Total All Phases Total w/Northside Acreage (acres) 3.761 3.29 3.237 1.946 12.234 15.254 Design Water Use Rate (gpd/acre) 2000 2000 2000 2000 2000 2000 Design Daily Water Use (gpd) 7522 6580 6474 3892 24468 30508 Design Peaking Factor (Ave Day to Peak Hour) 10 10 10 10 10 10 Design Peak Hour Flow (gpm) 52 46 45 27 170 212 Sewer Mains 5 2/5/2015 including the contributions from the Northside PUD. Although 8” pipe provides capacity for the design flow of 2000 gpd/acre, future development with potentially higher densities may require a larger sewer at the downstream portion of the project. By installing a 10” sewer main at the downstream portion of the sewer collection system, a small increased installation cost will provide future flexibility over the 100+ year design life of the sewer. 11.13 Impact on Existing Wastewater Facilities As previously described, the existing wastewater facilities onsite will be abandoned and replaced during Phase 1 construction. As the majority of the sewer network will be completed during Phase 1, only one future main extension will be necessary for the remaining phases (Phase 2 – indicated by dashed green line on C3.0). During construction of the future phases, existing sewer services within Phase 1 and Northside PUD will remain in service. The Bozeman Waste Water Facility Plan does not indicate any improvements will be necessary to serve the Cannery District. 11.14 Project Description Cannery District Phase 1 is the first of four phases within the development. It consists of remodeling four existing buildings originally constructed as part of the original pea canning operation in 1917. The existing sewer infrastructure will be replaced and upgraded to current City standards prior to the construction of the approved Phase 1 site improvements. This upgrade will also serve the Northside PUD which currently has three services connecting to the existing 15” sewer main that is being replaced. The construction of Phase 1 will provide the majority of the infrastructure needed to serve the remaining phases. Sewer services will be stubbed into phases 3 and 4 for future use, while phase 2 will require an extension of the 8” main heading to the south. 11.15 Design Criteria The Cannery District sewer main extensions were designed in accordance with Montana Department of Environmental Quality Circular 2, Montana Public Works Standards and Specifications, City of Bozeman Modifications to Montana Public Works Standards and Specifications, the Uniform Plumbing Code, and the City of Bozeman Wastewater Facility Plan. Sewer Mains 6 2/5/2015 11.16 Site Information A Geotechnical Report was prepared by Allied Engineering Services, Inc. for the Cannery District site. The report identified the site to contain fine grained soils overlying gravel deposits. Geotechnical borings have determined the general soil profile consists of 1.5 to 7.0 feet of fine grain silt and clay overlying alluvial gravel. Estimated depth to groundwater obtained from the geotechnical borings is 6.5 -11 feet. If mains are installed during high groundwater times dewatering may be required. 11.17 Environmental Impacts Continued use and new extensions of City of Bozeman municipal sewer mains has the least environmental impact. No new environmental impacts will be caused by these sewer main extensions. Figure 2 Sewer Site Plan