INTRODUCTION
Our proposal and cost estimate are based on DEQ's request for Addendums to the 2013
Environmental Assessment and 2013 Voluntary Cleanup Plan for the remaining unremediated
properties within the subject Facility.
SCOPE OF WORK
This Modification is for the following work, which is outside the scope of our previously approved
September 2014 Task Order. Tetra Tech will conduct the following work tasks to close out the
Heebs East Sidewalk contaminated soil removal project.
Complete the Addendum to the 2013 Environmental Assessment Component of the
2013 CMC Voluntary Clean-up Plan (VCP) to address all remaining unremediated areas
within the CMC Bozeman Facility. A portion of this document was completed under the
previous task order, however, DEQ's request to include additional properties and to
secure new landowner access agreements have increased our costs.
Prepare an Amendment to the 2013 CMC Voluntary Clean-up Plan (VCP) to address all
remaining unremediated areas within the CMC Bozeman Facility. We anticipate that this
document will identify the location of the Heebs Sidewalk excavation area as well as
outlining an approach to any future soil removal projects. A draft of this document was
produced last year, however, DEQ has changed the scope of this document, so
considerable new text will be necessary.
Reporting
Tetra Tech will submit the following documents for City review prior to DEQ submittal.
• Final Addendum to Environmental Assessment
• Draft and Final VCP Amendment
August 2015 Task Order for Addendum to EA and VCP
August 11, 2015
COST ESTIMATE
Tetra Tech estimates that our costs to perform the scope of work outlined above on a time and
materials basis is $17,710.
Special Conditions
Execution of this Task Order constitutes acceptance of all terms and conditions contained in Tetra
Tech's Professional Services Agreement with the City of Bozeman, dated May 29th, 2014.
CLIENT: CONSULTANT:
City of Bozeman Tetra Tech
By: CQ�l4 By: ;4"- a, . NA
Its: '�T4 _6L4�QQF Its: Sr. Project Manager
Date: Date: _August 11, 2015
Page 2 of 2
Tetra Tech Page 1 of 1
Cost Estimate
2015 Environmental Assesment and Voluntary Cleanup Plan Task Order
South Wallace Avenue, Bozeman, Montana
August 11, 2015
VCP Addendum
RATE
QUANTITY
COST
Labor
Project Manager
$170.00
12.0
$2,040.00
Asbestos Manager
$120.00
16.0
$1,920.00
Staff Scientist
$95.00
24.0
$2,280.00
CADD
$65.00
12.0
$780.00
Clerical
$55.00
12.0
$660.00
Subtotal
$7,680.00
Other Direct Costs
Photocopies
$0.10
300.0
$30.00
Vehicle Mileage, per mile
$0.60
1500.0
$900.00
$930.00
Task Total
$8,610.00
Environmental Assessment Addendum RATE
QUANTITY
COST
Labor
Project Manager
$170.00
12.0
$2,040.00
Asbestos Manager
$120.00
16.0
$1,920.00
Staff Scientist
$95.00
32.0
$3,040.00
CADD
$65.00
8.0
$520.00
Clerical
$55.00
12.0
$660.00
Subtotal
$8,180.00
Other Direct Costs
Photocopies
$0.10
200.0
$20.00
Vehicle Mileage, per mile
$0.60
1500.0
$900.00
$920.00
Task Total
$9,100.00
TOTAL
$17,710.00