HomeMy WebLinkAboutC4. Baxter Meadows Final Plat1
REPORT TO: Honorable Mayor and City Commission
FROM: Tim Cooper, Assistant City Attorney Wendy Thomas, Director of Community Development
SUBJECT: Authorize the Director of Public Works to approve the Baxter Square Phase 3
Major Subdivision Final Plat, Application P15016
MEETING DATE: September 14, 2015
AGENDA ITEM TYPE: Consent
RECOMMENDATION: That the City Commission approve the Final Plat for the Baxter Square Phase 3 Major Subdivision Final Plat, Application P15016 and authorize the Director of Public Works to
execute the same on behalf of the City of Bozeman upon review and approval by the City Attorney’s
Office.
BACKGROUND: On December 1, 2014, the City Commission approved the findings of fact
completing the preliminary plat approval to subdivide 2.57 acres into 22 townhouse lots, and the remaining area as streets and open space. The developer has applied for final plat review and approval
for Baxter Square Phase 3 subdivision. The preliminary plat was unanimously approved (5:0) by the
City Commission on November 3, 2014.
Staff has concluded that all terms and conditions of the preliminary plat approval have been met. An
improvements agreement has been completed for the future installation of sidewalks, park improvements, and completion of seeding. The appropriate financial guarantee has been received.
UNRESOLVED ISSUES: None determined at this time.
ALTERNATIVES: 1) Approve the final plat as presented and recommended. 2) Deny the final plat.
FISCAL EFFECTS: Fiscal impacts are undetermined at this time, but will include increased property
tax revenues from new development, along with increased costs to deliver municipal services to the
property.
Attachments: Staff Memo; Final Plat
Report compiled on September 3, 2015
Commission Memorandum
73
74
75