HomeMy WebLinkAbout15- Task Order No. 3 Dowl for Professional Services Task for Aquisition of Right of Way and EasmentsExhibit A to Master Task Order Agreement for Professional Services
TASK ORDER NUMBER 03
Issued under the authority of Professional Services Master Task Order Agreement between the City of
Bozeman and DOWL for: Professional and technical services for the acquisition of right of way,
easements and real property to allow for the construction of various sheet and utilities
improvements within the Citv of Bozeman
This Task Order is dated 11 20 between City of Bozeman (City) and
DOWL (Contractor).
The following representatives have been designated for the work performed under this Task Order:
City: Brit Fontenot
Contractor: Tony Becken-Gaddo, P.E.
SCOPE OF WORK:
The scope of work for Task Order No. 3 is detailed in the attached Project Scope of Services.
COMPENSATION:
Contractor shall be reimbursed on a time and materials basis with a total cost not to exceed $26,165.00. The
total cost for Task Order No. 3 is detailed in the attached Project Cost Estimate. Contractor shall invoice no
more often than monthly for services provided in the prior month.
The provisions of the Professional Services Master Task Order Agreement and any Special Terms and
Conditions and/or Exhibits or Attachments to this Task Order shall govern the Work.
IN WITNESS WHEREOF, the parties authorized to commit resources of the companies have executed this
Task Order:
City of Bozeman
Title:' Y4
Contractor
By: �1s�
Title: Y'cg
Date: 2- Date: o�_ - 117-1-5
Fed. ID. No. 92-0166301
January 23, 2015
Professional Services Agreement for Streets and Utilities Land Agent Services
Project Scope of Services
Task Order No. 3
The City of Bozeman plans to construct the North 7"' Avenue Lighting Improvements project,
and requires the acquisition of private property interests, in this case easements, to facilitate
construction. This Task Order No. 3 is intended to outline the Scope ,of Services that DOWL
will provide to get that project to construction.
The scope of this project includes acquiring public access and utility easements for the N. 7"'
Avenue corridor from W. Main Street to Juniper Street. The North 7t" Avenue Lighting
Improvements project plans and documents split the project into four separate phases of the
project: Phase 1: I-90 to Juniper Street (completed); Phase 2: Juniper Street to Durston Road;
Phase 3: Durston Road to W. Beal Street; Phase 4: W. Beal Street to W. Main Street. For this
R/W acquisition project, DOWL will obtain easements for 33 properties, 5 of which are in Phase
2 and 28 in combined Phases 3 and 4.
Upon acceptance of this Task, DOWL will meet with the City and the City's design consultant to
review the work to date and to understand the previous attempts to acquire the required easement
areas by donation from the respective property owners. Immediately following that meeting
DOWL will begin the process of title research (as necessary), document preparation, and actual
meetings with 33 private property owners to acquire the easements necessary for the project.
Easement documents, parcel exhibits, plats, figures, property owner contact and ownership data,
and construction plans will be provided by the City. DOWL will coordinate with the City staff
on project progress and meetings with project team members.
The intent of this scope of services and corresponding cost estimate is to provide basic title
research and easement acquisition services on a time and materials, not to exceed basis. Since
the acquisition of these easements is currently on a voluntary basis, DOWL cannot guarantee that
all property owners will agree to donate, however DOWL will use all reasonable efforts to
illustrate the inherent benefits that the North 7t" Avenue project will have for each private
property. Additional costs related to engineering, surveys, property appraisals, and any costs
associated with eminent domain proceedings are not included in this scope of services or cost
estimate.
The following activities will be conducted as outlined below.
1_0 PROJECT RESEARCH
• Obtain and review available construction plans.
• Obtain and review available project documentation.
• Obtain and review proposed easement documents.
• Obtain current ownership information.
Page 1 of 2
FOWL
January 23, 2015
2_0 PROPERTY OWNER CONTACT
• Compile contact information.
• Initiate contact with owners to inform them of this project and the process.
• Work with property owners and the City to come to an agreement on the donation of the
necessary easements.
3.0 TITLE COMMITMENTS
• Title commitments are not included in this scope.
4_0 APPRAISALS AND REVIEW APPRAISALS
• Appraisals are not included in this scope.
5.0 ACQUISITIONS
• Conduct meetings with property owners to acquire donated easements.
6_0 RELOCATION SERVICES
• Relocation services are not included in this scope.
7_0 CLOSING
• There will be no title closings required. DOWL will submit the complete final title
transfer documents to the City for recording.
8_0 FINAL SUBMITTAL AND CLOSEOUT
• Deliver completed title transfer documents.
• Project closeout.
• QA/QC of deliverables.
Deliverables:
• Final signed and notarized title transfer documents to the City.
9_0 PROJECT MANAGEMENT
• Project administration.
• Coordination meetings.
CONTINGENCY
Due to the nature of property acquisition work, the time required to work with individual
property owners varies significantly. The scope of services as detailed in this document includes
all the necessary steps to acquire easements from private owners, but much of that work relies on
good cooperation and timely responses from all parties. The contingency item serves to capture
the possible additional costs incurred during the acquisition process due to challenging situations
with property owners.
If"D- Page 2 of
IC!ty of Bozeman R/W Acquisition: Task Order No. 3 Project Cost Estimate --N. 7th Ave. Lighting DATE: 1/23/2015
PROJECT NO: 4524.11402.03 EST. PREPARED BY: DOWL HKM PAY SCH.: Time and Materials --NTE
1,-tivity,
Tasks
Total Hours
Project
Real Estate Manager/ Right of Way
Manager Coordinator Agent
Title
Specialist
Assistant
Coordinator
Professional
Surveyor I
Survey Crew
Clerical
WORK TO BE COMPLETED
1.0 PROJECT RESEARCH
Obtain and review available construction plans. 4 4
Obtain and review proposed easement documents. 10 2 8
Obtain and review available project documentation. 4 2 2
Obtain current ownership information. 16 16
SUBTOTAL(HOURS) 34 4 14 0 16 0 0 0 0
2.0 PROPERTY OWNER CONTACT
Compile Contact Information 12 4 8
Initiate Contact 4 4
Work on Agreements 14 2 12
SUBTOTAL(HOURS) 30 2 20 0 8 0 0 0 0
3.0 TITLE COMMITMENTS
Not Applicable
SUBTOTAL(HOURS) 0 0 0 0 0 0 0 0 0
4.0 APPRAISALS AND REVIEW APPRAISALS
Not Applicable
SU13TOTAL(HOURS) 0 0 0 1 0 1 0 0 0 0 0
5.0 ACQUISITIONS
Conduct meetings with property owners 150 2 148
SUBTOTAL(HOURS) 150 2 146 0 0 0 0 0 0
6.0 RELOCATION SERVICES
Not Applicable
SUBTOTAL(HOURS) 0 0 0 0 0 0 0 0 0
7.0 CLOSING
Complete final title transfer documents. 0
SUBTOTAL (HOURS) 0 0 0 0 0 0 0 0 0
8.0 FINAL SUBMITTAL AND CLOSEOUT
Deliver Completed Title Transfer Documents 12 8 4
Project Closeout 1 1
QA/QC of Deliverables 1 1
SUBTOTAL(HOURS) 14 1 9 0 0 0 0 0 4
9.0 PROJECT MANAGEMENT
Project administration. 4 4
Coordinalion meetings. 4 4
SUBTOTAL(HOURS) 8 0 8 0 0 0 0 0 0
CONTINGENCY
Negotiation Challenges
12 8
4
Total Project Hours 246. 9 207 0 24 4 0 0 4
O W L.- Page 1 of 2
p0WL Page 2of2
COST SUMMARY
DIRECT LABOR
Hours
Rate
Extension
Real Estate Manager
9 150.00
1,350.00
Project Manager / Coordinator
207 105.00
21,735.00
Right of Way Agent
0
0.00
Title Specialist
24 90.00
2,160.00
Assistant Coordinator
4 120.00
480.00
Professional Surveyor
0
0.00
Survey Crew
0
0.00
Clerical
4 55.00
220.00
TOTAL HOURSI
1
2481 1
TOTAL LABOR
$25,945.00
DIRECT NONLABOR
Miscellaneous (atudlne pants, mylars, muibllth paper, telephone,
postage, mise equipment rental, maps, photos, survey mtls., dsgay boards, etc.)
Unit
Quantity Rate
Computer
Hours
Per Hour
0.00
Title commitments
Each
Per Parcel
0.00
Vehicle Rental
Days
Per Day
0.00
Mileage
Miles
220 Per Mile $1.00
220.00
Airline Tris
Trips
Per Trip
0.00
Lodging
Days
Per Day
0.00
Meals
Days
Per Day
0.00
TOTAL DIRECT NONLABOR
$220.00
OUTSIDE SERVICES AND SUBCONTRACTS LUMP SUM
R/W Ap raisais
R/W Review Appraisals
TOTAL OUTSIDE SERVICES AND SUBCONTRACTS
RECAPITULATION
Total Direct Labor
25,945.00
Total Direct NonLabor
220.00
Total Outside Services & Subcontracts
0.00
TOTAL ESTIMATED COST (NTE)
$267156.00