HomeMy WebLinkAbout4. C4 Street CIP
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of Updates to the Street Impact Fee Fund Capital
Improvement Plan (CIP) for FY16-20.
AGENDA ITEM TYPE: Consent
MEETING DATE: January 12, 2015
RECOMMENDATION: Adopt the UPDATED Street Impact Fee Fund Capital
Improvement Plan (CIP) for FY16-20.
NOTES: There are 2 changes to the Street Impact Fee Fund Capital Improvement Plan proposed
for the FY16-20 schedule:
1. As per the City Commission vote of approval on December 8th, 2014, City Staff has split
the previous SIF62 – DURSTON (WESTERN CITY LIMITS TO FOWLER) into two
separate projects:
a. SIF62 – DURSTON (COTTONWOOD TO FOWLER), which is unscheduled for
$1,613,000.
b. SIF64 – DURSTON (WESTERN CITY LIMITS TO COTTONWOOD), which is
included in FY16 for $1,012,000.
2. Update: SIF54 – FERGUSON (BAXTER TO OAK) has an updated cost of $900,000.
This cost will be split equally between Impact Fees, the creation of an SID/ County
funds. The entire cost of the project is included in the CIP request, with the Financial
Summary showing the SID/County contributions.
41
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY16.
Report compiled on: December 31, 2014
Attached: Draft Street Impact Fee Fund CIP
42
Street Impact Fee
Capital Improvement Plan
Financial Summary Current Year
FY15 FY16 FY17 FY18 FY19 FY20 Unscheduled
Projected Beginning Reserve Balance Dedicated to CIP 9,793,964$ 10,441,733$ 5,422,317$ 2,247,746$ 1,509,144$ 2,513,289$
Plus: Impact Fee Revenues Dedicated to CIP 1,872,769$ 1,910,224$ 1,948,429$ 1,987,397$ 2,027,145$ 2,067,688$ -$
Plus: Urban Funds: SIF09, Kagy (Willson to 19th) 4,000,000$
Plus: Urban Funds: SIF46, Oak (New Holland to Ferguson)2,000,000$
Plus: Local Share of Intersections (40% of Total)792,000$ 396,000$ 264,000$ 396,000$
Plus: SID or other sources 525,000$ 1,242,000$ -$ 495,000$ 1,000,000$
Plus: County Funds 300,000$
Plus: TOP Funds for SIF55 & 56, Baxter/Cottonwood 1,800,000$
Plus: Developer Contribution for SIF40 - Broadway /Main 396,000$
Less: Scheduled CIP Project Costs (1,225,000)$ (8,150,640)$ (11,157,000)$ (3,122,000)$ (1,782,000)$ (8,044,000)$ (18,758,000)$
Projected Year-End Cash Dedicated to CIP 10,441,733$ 5,422,317$ 2,247,746$ 1,509,144$ 2,513,289$ 1,732,977$ (18,758,000)$
Assumptions Made for Revenue Estimates:Current Year
FY15 FY16 FY17 FY18 FY19 FY20
Estimated Annual Street Impact Fee Revenues 1,872,769$ 1,872,769$ 1,910,224$ 1,948,429$ 1,987,397$ 2,027,145$
Estimated Annual Increase 0.0%2%2%2%2%2%
Total Estimated Revenues 1,872,769$ 1,910,224$ 1,948,429$ 1,987,397$ 2,027,145$ 2,067,688$
Current Revenues Dedicated to CIP %100.0%100.0%100.0%100.0%100.0%100.0%
Plus: Increase Dedicated to Street Capacity Expansion CIP 0.0%0.0%0.0%0.0%0.0%0.0%
Total % Dedicated to CIP 100.0%100.0%100.0%100.0%100.0%100.0%
Total Estimated Revenues Dedicated to CIP 1,872,769$ 1,910,224$ 1,948,429$ 1,987,397$ 2,027,145$ 2,067,688$
Projected
Projected
CURRENT
26,000,000
21,000,000
16,000,000
11,000,000
6,000,000
1,000,000
Street Impact Fee Projects
43
PROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20RATINGFY17FY18FY19CIP PROJECT FUND:Impact Fees StreetsSorted by Funding Year and RatingSIF01STREET IFRIGHT OF WAY ACQUISITION$132,000$132,00025$132,000$132,000$132,000SIF40STREET IFBROADWAY & MAIN (INTERSECTION)$660,00035SIF48STREET IFCOTTONWOOD (FALLON TO ALPHA)$2,543,64040SIF49STREET IFOAK STREET (15TH TO 19TH)$330,00040SIF50STREET IFLAUREL PARKWAY (DURSTON TO BABCOCK)$700,00020SIF52STREET IFKAGY (WILLSON TO 19TH) ‐ ENGINEERING SERVICES$858,00025SIF53STREET IFOAK (L STREET TO COTTONWOOD) ‐ ENGINEERING SERVICES$500,00025SIF54STREET IFFERGUSON (BAXTER TO OAK)$900,00040SIF59STREET IFDURSTON (FOLWER TO WEST CITY LIMIT) ‐ ENGINEERING SERVICES$265,00025SIF63STREET IFCOTTONWOOD (FALLON TO BAXTER) ‐ ENGINEERING DESIGN$250,000SIF64STREET IFDURSTON (WESTERN CITY LIMITS TO COTTONWOOD)$1,012,000SIF09STREET IFKAGY (WILLSON TO 19TH)32$7,920,000SIF39STREET IFFERGUSON & DURSTON (INTERSECTION)35$990,000SIF47STREET IFN 27TH (OAK TO CATTAIL)35$1,125,000SIF58STREET IFN. 27TH &OAK (INTERSECTION)30$990,000SIF56STREET IFCOTTONWOOD (FALLON TO BAXTER)40$2,000,000SIF60STREET IFN. 27TH & TSCHACHE (INTERSECTION)30$990,000SIF27STREET IFCOTTONWOOD & DURSTON (INTERSECTION)30$660,000SIF36STREET IFCOTTONWOOD (BABCOCK TO OAK)40$990,00044
PROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20RATINGFY17FY18FY19SIF46STREET IFOAK (NEW HOLLAND TO FERGUSON)$2,500,00040SIF55STREET IFBAXTER (19TH TO COTTONWOOD)$4,422,00040SIF61STREET IFOAK & FERGUSON (INTERSECTION)$990,00030SIF05STREET IFCOLLEGE (11TH TO 19TH)$3,168,0007SIF23STREET IFHIGHLAND (MAIN TO KAGY)$10,032,00030SIF24STREET IFHIGHLAND & ELLIS (INTERSECTION)$660,00030SIF33STREET IF7TH & GRIFFIN (INTERSECTION)$660,00030SIF51STREET IFN 27TH (OAK TO CATTAIL) ‐ ENGINEERING SERVICES$125,00025SIF57STREET IFOAK (FERGUSON TO COTTONWOOD)$2,500,00040SIF62STREET IFDURSTON (COTTONWOOD TO FOWLER)$1,613,000Summary for Impact Fees Streets (29 items)Totals by year:$8,044,000$8,150,640 $11,157,000 $3,122,000$18,758,000FY20FY16FY17FY18UnscheduledFY19$1,782,00045
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF01
DEPARTMENT
STREET IF
PROJECT NAME
RIGHT OF WAY ACQUISITION
FY16
$132,000
FY17
$132,000
Unscheduled
DESCRIPTION OF PROJECT
Annual allocation available for right-of-way purchases as they become available. Purchasing additional right-of-way is critical to expanding the
capacity of streets in the city. This is deemed to be 100% impact fee eligible – as additional right-of-way is not required if we are not expanding
the capacity of the street.
ALTERNATIVES CONSIDERED
Condemn property for right-of-way; pay court costs as well as appraised value of property. Time consuming for city staff and a
relatively expensive process.
ADVANTAGES OF APPROVAL
Provides dollars for the purchase of necessary right-of-way as it becomes available on the market. Avoids the expensive,
antagonistic condemnation process where possible.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Street Impact Fees can not be spent on operating and maintaining facilities. There is
expected to be a very minimal, incremental cost to the Street Maintenance District from this expenditure.
FUNDING SOURCES
100% Street Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:25
FY18
$132,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)10
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19
$132,000
FY20
$132,000.00
46
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF05
DEPARTMENT
STREET IF
PROJECT NAME
COLLEGE (11TH TO 19TH)
FY16 FY17 Unscheduled
$3,168,000
DESCRIPTION OF PROJECT
Reconstruct West College Street from 8th Avenue to 19th Avenue to a minor arterial standard as shown in the Transportation Plan. This
section of West College has already exceeded the volume of traffic it was projected to carry in 2020 according to the Transportation Plan.
Improvements to South 19th and increased development in the South 19th corridor will only further increase traffic demand on this facility.
Additionally this facility lacks pedestrian and bicycle facilities.
ALTERNATIVES CONSIDERED
Use of Urban funds for full financing, CTEP grants if available.
ADVANTAGES OF APPROVAL
Improved safety and capacity, both for motorized vehicles as well as bicycles and pedestrians. The use of street impact fee funds
enables the community to leverage the available State Urban transportation funds to complete other projects and address more
of the city’s pressing transportation needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Improved safety and capacity, both for motorized vehicles as well as bicycles and pedestrians. The use of street impact fee funds
enables the community to leverage the available State Urban transportation funds to complete other projects and address more
of the city’s pressing transportation needs.
FUNDING SOURCES
60% - Street Impact Fees = $2,000,000, 40% Urban, CTEP or other Funds - $1,300,000
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:7
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)0
DIRECT BENEFITS: (Up to 10 pts)2
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
47
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF09
DEPARTMENT
STREET IF
PROJECT NAME
KAGY (WILLSON TO 19TH)
FY16 FY17
$7,920,000
Unscheduled
DESCRIPTION OF PROJECT
This project consists of widening Kagy Boulevard from the intersection of S. 19th Avenue to Willson Avenue to a three lane urban arterial
standard. This includes one travel lane in each direction, bike lanes on each side, curb and gutter throughout, boulevard, sidewalks and a raised
median. Kagy serves as an important element of Bozeman's perimeter street system connecting Highland Blvd., Willson Ave. and S.19th. It also
serves as the primary access to Montana State University and the University's major athletic facilities.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Kagy is a State Urban Route and is eligible for expenditure of State urban funds designated annually for the City of Bozeman;
however, the availability of urban funds cannot match the pace of the City's transportation improvement needs. The need for this
project comes from increased traffic due to growth in the Bozeman area and the project is eligible for Impact Fee Funds. Use of
Street Impact Funds enables the community to leverage the available State Urban transportation funds to complete projects and
address more of its pressing transportation needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost
estimate of $8,725 per street mile maintained annually.
FUNDING SOURCES
Total Project: $6,650,000. 60% - Street Impact Fees = $3,990,000; 40% - Urban Funds = $2,660,000
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:32
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)7
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
48
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF23
DEPARTMENT
STREET IF
PROJECT NAME
HIGHLAND (MAIN TO KAGY)
FY16 FY17 Unscheduled
$10,032,000
DESCRIPTION OF PROJECT
This project consists of widening Highland Boulevard from the intersection with Main Street to the intersection with Ellis Street to a five-lane
urban arterial standard, and from the intersection with Ellis Street south to the intersection with Kagy Boulevard to a three-lane urban arterial
standard. This roadway is currently a minor arterial roadway with one travel lane in each direction. This project serves as a long-term need that
will be necessary to accommodate future development patterns in the region and serve north-south traffic flow. It is expected that a minimum
of two travel lanes in each direction from Main Street to Ellis Street, one travel lane in each direction from Ellis Street to Kagy Boulevard, bike
lanes on each side, curb and gutter, boulevard, sidewalk, and a raised median will be required.
ALTERNATIVES CONSIDERED
Use of Urban Funds, developer contributions and/or creation of an SID for full financing.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians. The use of street
impact fees enables the community to leverage the available State Urban Funds to complete other needed projects.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current
cost estimate of $8,725 per street mile maintained annually.
FUNDING SOURCES
Estimated: 50% Street Impact fees ($3,600,000.00), and 50% Urban Funds, Special Improvement District (SID) or Other,
$3,600,000.00.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
49
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF24
DEPARTMENT
STREET IF
PROJECT NAME
HIGHLAND & ELLIS (INTERSECTION)
FY16 FY17 Unscheduled
$660,000
DESCRIPTION OF PROJECT
Identified as TSM -20 in the 2007 Transportation Plan Update. Includes installation of a traffic signal, roundabout or other adequate traffic
control device when warrants are met. Highland Boulevard is currently a two-lane minor arterial roadway and Ellis Street is a two-lane local
street. This intersection currently has stop control on Ellis Street.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential
sources of funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: None
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
50
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF27
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD & DURSTON (INTERSECTION)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Includes installation of a traffic signal, roundabout or other adequate traffic control device when warrants are met. Cottonwood Road is
currently a two-lane principal arterial roadway and Durston Road is a three-lane minor arterial.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential
sources of funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: None
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19
$660,000
FY20
51
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF33
DEPARTMENT
STREET IF
PROJECT NAME
7TH & GRIFFIN (INTERSECTION)
FY16 FY17 Unscheduled
$660,000
DESCRIPTION OF PROJECT
Control of the intersection of 7th Avenue and Griffin Drive. Includes the installation of a traffic signal or roundabout. Future development and
the resulting increased traffic indicate that intersection improvements will be needed.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by the Montana Department of Transportation. Create an SID or identify
and apply for other potential sources of funding (CMAQ…)
ADVANTAGES OF APPROVAL
Improved traffic flow and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
52
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF36
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD (BABCOCK TO OAK)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
This project consists of widening Cottonwood Road from West Babcock Street to Oak Street to a three lane urban arterial standard. This
includes one travel lane in each direction, bike lanes on each side, curb and gutter throughout, boulevard, sidewalks and a raised median.
Cottonwood Road serves as an important element in Bozeman's west side street system and serves as a primary north-south corridor on the
west side of the city.
ALTERNATIVES CONSIDERED
SID for full financing, Urban funds or incremental construction by developers.
ADVANTAGES OF APPROVAL
Improved traffic flow and safety in this corridor.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Street Impact Fees, SID for upgrade of existing roadway portion, Urban funds or incremental construction by developers.
Current estimate is 50% SID/50% Impact Fees.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19
$990,000
FY20
53
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF39
DEPARTMENT
STREET IF
PROJECT NAME
FERGUSON & DURSTON (INTERSECTION)
FY16 FY17
$990,000
Unscheduled
DESCRIPTION OF PROJECT
Intersection Control
ALTERNATIVES CONSIDERED
Accept the current level of service (do nothing). Alternative financing could be provided by creating an SID or Payback District.
ADVANTAGES OF APPROVAL
Improved traffic flow and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:35
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
54
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF40
DEPARTMENT
STREET IF
PROJECT NAME
BROADWAY & MAIN (INTERSECTION)
FY16
$660,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Intersection Control
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by the Montana Department of Transportation. Create an SID, Payback or
identify and apply for other potential sources of funding (CMAQ…). Developer Contribution.
ADVANTAGES OF APPROVAL
Improved traffic flow and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:35
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)10
FY19 FY20
55
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF46
DEPARTMENT
STREET IF
PROJECT NAME
OAK (NEW HOLLAND TO FERGUSON)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
This Project is the completion of the street segment of Oak Street, from New Holland to Ferguson. Currently, the south half of the street is
missing, creating a bottleneck in the street network. We anticipate that by the time this project is built, the City will have designated Oak
Street as an Urban Route, eligilbe for Urban Funds.</div>
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
minimal
FUNDING SOURCES
Street Impact Fees - 60%, Developer Contribution for local share - 40%. Total cost estimates are shown.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)10
FY19 FY20
$2,500,000.00
56
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF47
DEPARTMENT
STREET IF
PROJECT NAME
N 27TH (OAK TO CATTAIL)
FY16 FY17
$1,125,000
Unscheduled
DESCRIPTION OF PROJECT
This Project is the completion of the street segment of N 27th Avenue, between Oak Street and Cattail Street. This project area contains a
completed section of 27th (from Tschache to Baxter) that will be able to be utilized once north and south portions are added.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
Street Impact Fees - 60%, Developer Contribution for local share - 40%. Total cost estimates are shown.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:35
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)15
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
57
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF48
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD (FALLON TO ALPHA)
FY16
$2,543,640
FY17 Unscheduled
DESCRIPTION OF PROJECT
Widen Cottonwood Road from 2 and 3 lane sections to five lanes. This will match the section presently existing from Babcock to Fallon Street.
This widening is required to ensure the configuration of Cottonwood Road on either side of Huffine Lane is consistent as required by the
Montana Department of Transportation who have jurisdiction over Huffine Lane and south Cottonwood Road. This project will also include
installation of bicycle lanes and completion of sidewalk connections on both sides of Cottonwood Road. This will complete the full build out of
a principal arterial in a rapidly developing area of the community and leverage private development improvements.
ALTERNATIVES CONSIDERED
This project is needed to enable a Commission approved site development to proceed. The City could take no action which
would prevent the private development from being constructed.
ADVANTAGES OF APPROVAL
Traffic on Cottonwood Road is rapidly increasing with four new subdivisions in near proximity at different stages in the review
and development process. As a principal arterial, Cottonwood Road is one of the primary routes for travel within Bozeman and
becomes a state highway south of Huffine Lane. The proposed project will provide additional traffic capacity in a rapidly growing
area and will create a more functional roadway with a consistent cross section through its largest intersection at Huffine Lane.
The overall project will also coordinate improvements in association with adjacent private development to complete key links in
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine O&M will be required once constructed.
FUNDING SOURCES
Impact fees are estimated at $1,702,000. Private development south of Huffine Lane will construction approximately $100,000 of
project related improvements. Street maintenance funds (gas tax) may contribute approximately $125,000 for simultaneous
coordinated repair work on existing lanes of Cottonwood Road north of Huffine Lane. The exact extent of the maintenance
component has not been decided. These companion funds have not yet been committed. Three adjacent developments which
deferred installation of sidewalks with prior development will be required to install those at the same time as the widening
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
58
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF49
DEPARTMENT
STREET IF
PROJECT NAME
OAK STREET (15TH TO 19TH)
FY16
$330,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
59
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF50
DEPARTMENT
STREET IF
PROJECT NAME
LAUREL PARKWAY (DURSTON TO BABCOCK)
FY16
$700,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Expand 0.78 miles of Laurel Parkway from Durston Road to Fallon Street from 2 lanes to 3 lanes with initial construction of the street.
ALTERNATIVES CONSIDERED
Defer widening until a future date when it will be more costly as existing road improvements will be damaged and require repair.
ADVANTAGES OF APPROVAL
The project would allow the construction of the new street with the center turn lane as depicted in the City’s adopted
Transportation Plan. The turn lane adds approximately 33% additional capacity per Table 9-1 of the transportation plan compared
to a two lane road. To later widen a street from 2 lanes to 3 lanes after it is constructed is one of the most costly ways to add
capacity. Therefore, it is very cost advantageous to the City to fund this widening now to occur with the initial street
construction. This amendment will support the next phases of the Norton East Ranch Subdivision and Valley West Subdivision.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Routine O&M will be required once constructed.
FUNDING SOURCES
Impact fees $152,400, the balance of the work will be a subdivision project improvement.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:20
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
60
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF51
DEPARTMENT
STREET IF
PROJECT NAME
N 27TH (OAK TO CATTAIL) - ENGINEERING SERVICES
FY16 FY17 Unscheduled
$125,000
DESCRIPTION OF PROJECT
Engineering work for street design. This project area contains a completed section of 27th (from Tschache to Baxter) that will be able to be
utilized once north and south portions are added.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:25
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
61
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF52
DEPARTMENT
STREET IF
PROJECT NAME
KAGY (WILLSON TO 19TH) - ENGINEERING SERVICES
FY16
$858,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Engineering work to design the street.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:25
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
62
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF53
DEPARTMENT
STREET IF
PROJECT NAME
OAK (L STREET TO COTTONWOOD) - ENGINEERING SERVICES
FY16
$500,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Engineering work for design of this street.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Street Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:25
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
63
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF54
DEPARTMENT
STREET IF
PROJECT NAME
FERGUSON (BAXTER TO OAK)
FY16
$900,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
The construction of South Ferguson Road from Baxter Lane to Oak Street. This will be the last piece that connects Huffine Lane to West Oak
Street. The funding will come from Impact Fees, the creation of an SID and the County, split equally.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
Provide an alternative route from Huffine to Oak Street.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance
FUNDING SOURCES
1/3 Impact Fees, 1/3 SID, 1/3 County
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
64
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF55
DEPARTMENT
STREET IF
PROJECT NAME
BAXTER (19TH TO COTTONWOOD)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Impact Fees and Developer contributions (TOP Funds for areas ajacent to Sports Complex.)
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)10
FY19 FY20
$4,422,000.00
65
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF56
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD (FALLON TO BAXTER)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Impact Fees and Developer Contributions (TOP Funds for roadway ajacent to Sports Complex)
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
$2,000,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
66
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF57
DEPARTMENT
STREET IF
PROJECT NAME
OAK (FERGUSON TO COTTONWOOD)
FY16 FY17 Unscheduled
$2,500,000
DESCRIPTION OF PROJECT
This Project is the completion of the street segment of Oak Street, from New Holland to Ferguson. Currently, the south half of the street is
missing, creating a bottleneck in the street network.
ALTERNATIVES CONSIDERED
Leave as-is. Wait for the developer to build the street.
ADVANTAGES OF APPROVAL
This project will expand the capacity of our street network and improve safety for drivers and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
minimal
FUNDING SOURCES
Street Impact Fees, Developer Contribution for local share, other. Total cost estimates are shown. Design $800,000.
Construction $4,000,000.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:40
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
67
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF58
DEPARTMENT
STREET IF
PROJECT NAME
N. 27th &OAK (INTERSECTION)
FY16 FY17
$990,000
Unscheduled
DESCRIPTION OF PROJECT
Includes installation of a traffic signal, roundabout or other adequate traffic control device when warrants are met.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential
sources of funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: None
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
68
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF59
DEPARTMENT
STREET IF
PROJECT NAME
DURSTON (FOLWER TO WEST CITY LIMIT) - ENGINEERING SERVICES
FY16
$265,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Engineering design work for 1.75 miles of urban arterial.
ALTERNATIVES CONSIDERED
Do nothing .
ADVANTAGES OF APPROVAL
Improved safety and capacity, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost
estimate of $8,725 per street mile maintained annually.
FUNDING SOURCES
Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:25
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
69
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF60
DEPARTMENT
STREET IF
PROJECT NAME
N. 27th & TSCHACHE (INTERSECTION)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Includes installation of a traffic signal, roundabout or other adequate traffic control device when warrants are met.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential
sources of funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: None
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
$990,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
70
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF61
DEPARTMENT
STREET IF
PROJECT NAME
OAK & FERGUSON (INTERSECTION)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Includes installation of a traffic signal, roundabout or other adequate traffic control device when warrants are met.
ALTERNATIVES CONSIDERED
Do nothing or consider other alternatives as suggested by MDT. Create an SID or identify other and apply for other potential
sources of funding (CMAQ…)
ADVANTAGES OF APPROVAL
Increased capacity and safety at this intersection.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: None
FUNDING SOURCES
Proposed 60% Impact Fees and 40% Local Share (other).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
$990,000.00
71
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF62
DEPARTMENT
STREET IF
PROJECT NAME
DURSTON (COTTONWOOD TO FOWLER)
FY16 FY17 Unscheduled
$1,613,000
DESCRIPTION OF PROJECT
Complete Durston Road from Fowler Lane to Cottonwood to an urban minor arterial standard.
ALTERNATIVES CONSIDERED
Continue with the facility as is.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current
cost estimate of $8,725 per street mile maintained annually.
FUNDING SOURCES
Street Impact Fees, SID
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)
DIRECT BENEFITS: (Up to 10 pts)
FUNDING CERTAINTY: (Up to 10 pts)
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)
FY19 FY20
72
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF63
DEPARTMENT
STREET IF
PROJECT NAME
COTTONWOOD (FALLON TO BAXTER) - ENGINEERING DESIGN
FY16
$250,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Design of Cottonwood Road from Fallon Street to Baxter Lane
ALTERNATIVES CONSIDERED
Wait for adjacent development to occur and build in conjunction with it.
ADVANTAGES OF APPROVAL
Cottonwood Road serves as an important element in Bozeman's west side street system and serves as a primary north-south
corridor on the west side of the city. Design and completion of this facility will greatly improve the level of service for vehicles as
well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current cost
estimate of $8,725 per street mile maintained annually.
FUNDING SOURCES
Impact Fees, Parks and Open Space Bond Funds.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)
DIRECT BENEFITS: (Up to 10 pts)
FUNDING CERTAINTY: (Up to 10 pts)
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)
FY19 FY20
73
CIP Project Fund
Impact Fees Streets
PROJECT NUMBER
SIF64
DEPARTMENT
STREET IF
PROJECT NAME
DURSTON (WESTERN CITY LIMITS TO COTTONWOOD)
FY16
$1,012,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Complete Durston Road from Cottonwood Lane to the current western city limit to an urban minor arterial standard.
ALTERNATIVES CONSIDERED
Continue with the facility as is.
ADVANTAGES OF APPROVAL
Increased capacity and safety in this corridor, both for motorized vehicles as well as bicycles and pedestrians.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Incremental increases in sweeping, plowing and general maintenance costs. Current
cost estimate of $8,725 per street mile maintained annually.
FUNDING SOURCES
Street Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)
DIRECT BENEFITS: (Up to 10 pts)
FUNDING CERTAINTY: (Up to 10 pts)
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)
FY19 FY20
74