HomeMy WebLinkAbout14- Energy Performance Contract- City of Bozeman and McKinstry Essention, LLC ENERGY PERFORMANCE CONTRACT
BETWEEN
CITY OF BOZEMAN AND
MCKINSTRY ESSENTION, LLC
ENERGY PERFORMANCE CONTRACT
Table of Contents
ARTICLE 1. DEFINITIONS, SCHEDULES, EXHIBITS AND APPENDICES
Section 1 .1. Definitions, Acceptance of Investment Grade Audit Report,
Other Documents
Section 1.2. Investment Grade Audit Report
Section 1.3. Other Documents
PAYMENTS AND SCHEDULES
ARTICLE 2. PURCHASE AND SALE; CONSIDERATION/PAYMENT;
SERVICES AND/OR SUPPLIES; COMMENCEMENT DATE AND
TERMS
Section 2.1. Purchase and Sale
Section 2.2. Consideration/Payment
Section 2.3. Services and/or Supplies
Section 2.4. Commencement Date
Section 2.5. Effective Date/Duration
ARTICLE 3. SAVINGS GUARANTEE; ANNUAL
RECONCILIATION; PAYMENTS TO CONTRACTOR
Section 3.1. Energy and Cost Savings Guarantee
Section 3.2. Annual Review and Reimbursement/Reconciliation
Section 3.3. Contractor Compensation and Fees
Section 3.4. Payment
Section 3.5. Effective Date of Payment Obligation
Section 3.6. Open Book Pricing; Independent Contractor Status; Labor
Relations
Section 3.7. Construction Savings and Owner-Directed Change Orders
ARTICLE 4. FISCAL FUNDING
Section 4.1. Non-appropriation of Funds
Section 4.2. Non-substitution
AUDIT AND CONSTRUCTION PHASE
ARTICLE 5. ENERGY USAGE RECORDS AND DATA
ARTICLE 6. LOCATION AND ACCESS
ARTICLE 7. PERMITS AND APPROVALS; COORDINATION
Section 7.1. Permits and Approvals
Section 7.2. Coordination During Installation
City of Bozeman Energy Performance Contract Page 2
ARTICLE 8. CONSTRUCTION SCHEDULE AND EQUIPMENT INSTALLATION;
APPROVAL
Section 8.1. Construction Schedule; Equipment Installation
Section 8.2. Award of Subcontracts
Section 8.3. Systems Startup Approval
ARTICLE 9. EQUIPMENT WARRANTIES
ARTICLE 10. STANDARDS OF COMFORT
ARTICLE 11. ENVIRONMENTAL
REQUIREMENTS
Section 11.1. Excluded Material and Activities
Section 11.2. Polychlorinated Biphenyl (PCB) Ballasts; Mercury Lamps
ARTICLE 12. TRAINING BY CONTRACTOR
POST-CONSTRUCTION PHASE
ARTICLE 13. EQUIPMENT SERVICE
Section 13.1. Actions by Contractor
Section 13.2. Malfunctions and Emergencies
Section 13.3. Actions by [insert agency name'
ARTICLE 14. MODIFICATION, UPGRADE OR ALTERATION OF THE
EQUIPMENT
Section 14.1. Modification of Equipment
Section 14.2. Upgrade or Alteration of Equipment
ARTICLE 15. MATERIAL CHANGES
Section 15.1. Material Change Defined
Section 15.2. Reported Material Changes; Notice by City of Bozeman
Section 15.3. Other Adjustments
ARTICLE 16. PERFORMANCE BY CONTRACTOR
Section 16.1. Corrective Action; Accuracy of the Services
Section 16.2. Annual Reporting Requirements; Annual ENERGY STAR
Rating
ADMINISTRATION
ARTICLE 17. OWNERSHIP OF CERTAIN PROPRIETARY RIGHTS; EXISTING
EQUIPMENT
Section 17.1. Ownership of Certain Proprietary Property Rights
Section 17.2. Ownership of Existing Equipment
ARTICLE 18. INSURANCE AND BONDS
Section 18.1. Claims, Disputes, and Controversies
City of Bozeman Energy Performance Contract Page 3
Section 18.2. Resolution of Claims, Disputes, and Controversies
Section 18.3. Mediation
ARTICLE 19. DELAYS; CONDITIONS BEYOND CONTROL OF THE PARTIES
Section 19.1. Delays Within Control of Contractor
Section 19.2. Conditions Beyond Control of the Parties; Force Majeure
ARTICLE 20. ADDITIONAL DUTIES AND REPRESENTATIONS OF THE
PARTIES
ARTICLE 21. MISCELLANEOUS DOCUMENTATION PROVISIONS
Section 21 .1. Construction Performance and Payment Bonds, Labor and
Material Payment Bonds
Section 21.2. Further Documents
Section 21.3. City of Bozeman Responsibilities
Section 21.4. Waiver Of Liens
ARTICLE 22. CONFLICTS OF INTEREST
ARTICLE 23. SCOPE, AMENDMENT AND INTERPRETATION
ARTICLE 24. CHOICE OF LAW AND VENUE
ARTICLE 25. DISPUTE RESOLUTION
ARTICLE 26. LIAISON AND SERVICE OF NOTICES
ARTICLE 27. GENERAL TERMS AND CONDITIONS
Section 27.1. Design/Engineering
Section 27.2. Access and Retention of Records
Section 27.3. Assignment, Transfer and Subcontracting
Section 27.4. Compliance With Laws
Section 27.5. Nondiscrimination
Section 27.6. Intoxicants, DOT Drug and Alcohol Regulations; Safety and
Training
Section 27.7. Modification
Section 27.8. Severability
Section 27.9. Shipping
CONTRACT ATTACHMENT I: Schedules, Exhibits, and Appendices
SAVINGS GUARANTEE
Schedule A Energy and Cost Savings Guarantee
Schedule B Baseline Energy Consumption
City of Bozeman Energy Performance Contract Page 4
Schedule C Savings Measurement and Verification Plan; Methodology to
Adjust Baseline
PAYMENTS AND SCHEDULE
Schedule D Final Project Cost & Project Cash Flow Analysis
Schedule E Not Used
Schedule F Not Used
AUDIT AND CONSTRUCTION PHASE
Schedule G Not Used
Schedule H Scope of Work
Schedule I Construction and Equipment Installation Schedule
Schedule J Systems Start-Up and Commissioning; Operating
Parameters of Installed Equipment
Schedule K Standards of Comfort
Schedule L Contractor's Training Responsibilities
POST-CONSTRUCTION
Schedule M Not Used
Schedule N Not Used
Schedule 0 Facility Maintenance Checklist
ADMINISTRATION
Schedule P Annual Reporting Requirements
Exhibits
Exhibit I Performance Bond
Exhibit II Labor and Material Payment Bond
Exhibit III (i) Certificate of Acceptance—Investment Grade Audit
Report
Exhibit III (ii) Certificate of Acceptance—Installed Equipment
Exhibit III (iii) Notice of Substantial Completion – Individual FIMs
Exhibit IV Equipment Warranties
Exhibit V Montana Prevailing Wage Schedule
Appendices
Appendix A Investment Grade Audit Report
City of Bozeman Energy Performance Contract Page 5
THIS CONTRACT is entered into by and between the City of Bozeman, (hereinafter
referred to as the "City"), and McKinstry Essention, LLC (hereinafter referred to as the
"Contractor"). This Contract is entered into in accordance with Title 18, Montana Code
Annotated (MCA), Title 90, Chpt. 4, Part 11, MCA and the Administrative Rules of
Montana (ARM), Title 2, chapter 5, for the purpose of installing certain energy and
water cost saving equipment, described in Schedule H (Scope of Work), and
providing other services designed to save energy for the City property and buildings
listed on Schedule H (the "Project Site(s)").
ARTICLE 1. DEFINITIONS; ACCEPTANCE OF INVESTMENT GRADE
AUDIT REPORT; OTHER DOCUMENTS
Section 1.1. Definitions
Certificate of Acceptance: The certificate substantially in the form provided in
Exhibit III (i) and (ii).
Commencement Date: The date described in Section 2.4 (Commencement Date).
Contract: This Energy Performance Contract and all attached Schedules and
Exhibits.
Contract Sum: The sum of all materials, labor, auditing, design, engineering, project
construction management fees, overhead, profit, contingency, subcontracted services
related to the project.
Energy and Cost Savings Guarantee: The guarantee that is achieved as a result of
the installation and operation of the Equipment and provision of services provided for
in this Contract, and in accordance with the Savings Calculation Formula, shown in
Schedule C (Savings Measurement and Verification Plan; Methodology to
Adjust Baseline).
Equipment: The goods to be installed in accordance with the Investment Grade
Audit Report.
Independent Auditor: Independent Auditor means an Engineering Consulting firm or
an ESCO with a registered Professional Engineer.
Interim Period: The period from contract execution until the Commencement Date.
Investment Grade Audit Report: A study that includes detailed descriptions of the
improvements recommended for the project, the estimated costs of the
improvement and the utility and operations and maintenance cost savings projected
to result from the recommended improvements.
City of Bozeman Energy Performance Contract Page 6
Project Site(s): The City facilities in need of energy and water saving equipment,
as listed on Schedule H (Scope of Work).
Guaranteed Maximum Price: The maximum "not to exceed" amount that the City
will have to pay for the Work to implement the energy conservation measures
("ECMs") identified in Schedule D (Final Project Cost & Project Cash Flow
Analysis).
Work: Collectively, the Equipment, professional services and project construction
related to the project.
Section 1.2. Investment Grade Audit Report
Contractor has prepared the Investment Grade Audit Report of the Project Site(s) set
forth in Appendix A (Investment Grade Audit Report) and dated July 9, 2014, as
revised in Revision 1 dated October 16, 2014, which has been approved and
accepted by the City as set forth in Exhibit III (i) (Certificate of Acceptance—
Investment Grade Audit Report). The audit includes all ECMs agreed upon by the
parties.
Section 1.3. Other Documents
Acceptance by the City of the Investment Grade Audit Report is reflected in Exhibit III
(i). This Contract and the attached Schedules govern in the event of any
inconsistencies between the Investment Grade Audit Report and this Contract.
PAYMENTS AND SCHEDULES
ARTICLE 2. PURCHASE AND SALE; CONSIDERATION/PAYMENT;
SERVICES AND/OR SUPPLIES; COMMENCEMENT DATE AND
TERMS
Section 2.1. Purchase and Sale
Contractor agrees to provide the Equipment, together with installation, maintenance
and other services as provided in Schedule H (Scope of Work) and in Schedule I
(Construction and Equipment Installation Schedule).
Section 2.2. Consideration/Payment
In Consideration for the services to be provided, the City shall pay the Contractor up
to a Guaranteed Maximum Price of$494,008, in conformance with Schedule D (Final
Project Cost& Project Cash Flow Analysis). Payment terms are described in
Section 3.4.
City of Bozeman Energy Performance Contract Page 7
Section 2.3. Services and/or Supplies
Contractor shall provide to the City the services identified in Schedule H (Scope of
Work) and Schedule L (Contractor's Training Responsibilities). Equipment to be
installed and the quality of materials selected are subject to approval of the City in the
design review process. Contractor shall supervise and direct the Work and shall be
responsible for all construction means, methods, techniques, sequences, and
procedures and for coordinating all portions of the Work under this Contract.
Contractor shall be responsible to pay for all labor, materials, equipment, tools,
construction equipment and machinery, transportation and other facilities and services
necessary for the proper execution and completion of the Work.
Section 2.4. Commencement Date
The Commencement Date shall be the first day of the month after the month in which
all schedules are in final form and accepted by the City and the Contractor has
delivered a Notice to the City that it has installed and commenced operating all of the
Equipment specified in Schedule H (Scope of Work) in accordance with Article 8
(Construction Schedule and Equipment Installation; Approval), Schedule I
(Construction and Equipment Installation Schedule) and Schedule J (Systems
Start-Up and Commissioning; Operating Parameters of Installed Equipment),
and the City has inspected and accepted the installation and operation as evidenced
by the Certificate of Acceptance, Exhibit Ill (ii) (Certificate of Acceptance—
Installed Equipment).
Notwithstanding anything to the contrary in this Article 2 (Purchase and Sale;
Commencement Date and Terms, Interim Period), the Commencement Date shall
not occur and the City shall not be required to accept the work under this Contract
unless and until all Equipment installation for the Project Site(s) is completed by
Contractor in accordance with the terms of this Contract. The City shall have 15 days
after notification by Contractor to inspect and accept the Equipment. The City
reserves the right to reject the Equipment if installation fails to meet reasonable
standards of workmanship, does not comply with applicable building codes, or is
otherwise not in compliance with this Contract. Contractor shall not be paid in full,
including retainage, until after a final walk-through is completed and the City has
accepted the installed equipment, and Contractor has satisfied all claims for labor
and materials and the Certificate of Acceptance has been signed.
Section 2.5. Effective Date/Duration
Contract Term. This Contract shall take effect immediately upon its execution by all
parties and terminate three years from the Commencement Date, unless terminated
earlier in accordance with this Contract or extended by the parties in accordance with
Schedule C (Savings Measurement and Verification Plan; Methodology to Adjust
Baseline) to include the full term of the Measurement and Verification time period. (§
18-4-313, MCA.). The period from contract execution until the Commencement Date
City of Bozeman Energy Performance Contract Page 8
constitutes the "Interim Period." All energy savings achieved during the Interim Period
are to be credited to the City.
ARTICLE 3. SAVINGS GUARANTEE; ANNUAL RECONCILIATION;
PAYMENTS TO CONTRACTOR
Section 3.1. Energy and Cost Savings Guarantee
Contractor has formulated and, subject to the adjustments provided for in Article 15
(Material Changes), guarantees the annual level of energy and water cost savings to
be achieved as a result of the installation and operation of the Equipment and
provision of services provided for in this Contract to the extent necessary to pay for
the conservation measures, in accordance with 90-4-1107, MCA. The Energy and
Cost Savings Guarantee during the Contract term is set forth in annual increments
as specified in Schedule A (Energy and Cost Savings Guarantee), and has been
structured by Contractor to be sufficient to cover all payments required to be made by
the City, as set forth in Schedule D (Final Project Cost & Project Cash Flow
Analysis).
Section 3.2. Annual Review and Reimbursement/Reconciliation
For each one-year period of the Contract after the Commencement Date, Contractor
shall measure and/or calculate energy related cost savings, as specified in Schedule
C (Savings Measurement and Verification Plan; Methodology to Adjust
Baseline), and provide a report of the cost savings to the City within ninety (90) days
after the end of the one-year period.
If Energy and Cost Savings achieved during a savings measurement year are less
than the Guaranteed Energy and Cost Savings for that year, as defined in Schedule
A (Energy and Cost Savings Guarantee), Contractor shall pay the City an amount
equal to the deficiency. Contractor shall remit such payments to the City within thirty
(30) days after Contractor has submitted the annual report to the City. In addition, if
Energy and Cost Savings achieved during a savings measurement year are less
than the Guaranteed Energy and Cost Savings for that year, Contractor and the City
agree to work together in good faith to identify appropriate corrective measures.
Contractor will implement such corrective measures promptly and at Contractor's
sole expense.
When the total energy savings in any one year during the savings measurement
period exceed the Energy and Cost Savings Guarantee set forth in Schedule A
(Energy and Cost Savings Guarantee), the excess savings shall first be applied to
reimburse Contractor for any payment Contractor made to the City to meet
Contractor's guarantee for previous years in which the energy savings fell short of
Contractor's Energy and Cost Savings Guarantee under the terms of Schedule A
(Energy and Cost Savings Guarantee). In no event shall credit for excess savings
be used to satisfy saving guarantees in future years of the Contract.
City of Bozeman Energy Performance Contract Page 9
In the event of any disagreement in the annual reconciliation, the City shall notify the
Contractor in writing of the alleged discrepancy within thirty (30) calendar days. Any
deficiency amounts not in dispute shall be paid in accordance with this section.
The Contractor and the City agree to work in good faith to resolve any disagreement
over the calculation of the annual energy savings. Should the parties be unable to
resolve the disagreement, then either party may provide written notice to the other
party and both parties will then agree that an independent auditor will be engaged to
provide a binding decision on whether the calculation, as prepared by the Contractor, is
fairly stated in accordance with this Contract. If the parties cannot agree on an auditing
firm, then each shall designate a firm, and the two designated firms shall identify a
mutually agreeable third firm and such third firm alone shall perform the audit. The
independent auditing firm shall include in its report any exceptions determined by its
review. Each party agrees to reasonably cooperate with the auditing firm, including
without limitation, delivering to such firm any records, documents or information
reasonably requested in electronic format, if available, or otherwise. Any payments
between the parties that are necessary to resolve any irregularities identified in the
review will be made within sixty (60) calendar days after submission of the review to the
parties.
If the independent auditor determines that Contractor's determination of the
difference between the annual Energy Savings Guarantee and the amount of the
actual energy savings achieved at the Project Site(s) was in error in the City's favor
(i.e. contractor showed greater savings than determined by independent audit) by
more than 5%, the Contractor shall pay the entire cost of the audit; however, if the
Contractor's determination of the Energy Savings Guarantee is not in error or is in
error in the Contractor's favor, the City shall pay for the entire cost of the audit. In
any case, the calculation of energy savings shall be changed to reflect the findings
of the audit, and the calculations of savings related to the Energy Savings
Guarantee will be modified to reflect such.
Section 3.3. Contractor Compensation and Fees
Contractor has structured the Energy and Cost Savings Guarantee, referred to in
Section 3.1 above, to be sufficient to include all payments required to be made by the
City in connection with this Contract. Actual energy and operations' savings achieved
by the City through the operation of Equipment and through the performance of
services by Contractor shall be sufficient to cover all fees to be paid by the City to
Contractor for its services, as set forth in, and in accordance with, Schedule D (Final
Project Cost& Project Cash Flow Analysis).
Section 3.4. Payment Procedure for Work Completed During Interim Period
Contractor will invoice the City monthly for progress payments during the Interim
Period, calculated in accordance with the provisions in Schedule D (Final Project
Cost and Project Cash Flow Analysis). The Contractor shall provide the City with
an itemized monthly invoice of amount due along with any other evidence reasonably
City of Bozeman Energy Performance Contract Page 10
required by the City to demonstrate amount of required payment, including a Notice
of Substantial Completion – Individual FIMs (Exhibit III(iii)) if applicable.
Contractor fixed fees shall be invoiced and substantiated to the City's satisfaction on a
percent complete basis. All invoices submitted by the Contractor, less a five percent
(5%) retainage (0% if a retention bond is provided by the Contractor), shall be due and
payable within thirty (30) calendar days of receipt of the invoice. Five percent (5%)
retainage will not be withheld on any Audit fee or Design Services fees. Contractor
may be required to provide banking information at the time of contract execution in
order to facilitate the City's electronic funds transfer payments.
Pursuant to 15-50-205 and 206, MCA, the Contractor shall withhold the 1% license
fee required for public contracts from payments to any subcontractors and inform the
Montana Department of Revenue on prescribed forms of the amount of the 1%
license fee in the Contractor's account to be allocated and transferred to the
subcontractor. The notification to transfer portions of the 1% license fee must be filed
within 30 days after each payment is made to subcontractors.
Pursuant to 15-50-206 MCA, the City shall withhold, in addition to other amounts
withheld as provided by law, 1% of all payments due the Contractor and shall
transmit that money to the Montana Department of Revenue. Each subcontractor
who performs work greater than $5,000 shall have 1% of its gross receipts withheld
by the Contractor. The Contractor shall notify the Department of Revenue on the
department's prescribed forms. All gross receipts tax obligations withheld shall be
handled, disbursed, and otherwise processed as dictated by the Department of
Revenue.
Once payments made to the Contractor total ninety-five percent (95%) of the Total
Maximum Project Cost in accordance with Schedule D (Final Project Cost & Final
Cash Flow Analysis), as increased or decreased by approved change orders
requested by the City, the City shall not make further payments other than the five
percent (5%) retainage in accordance with this Section 3, unless a retention bond is
provided by Contractor in which case there shall be 0% retainage.
Section 3.5. Effective Date of Payment Obligation
Notwithstanding the above provisions in Section 3, the City is not required to begin
any payments to Contractor under this Contract until all equipment is installed by
Contractor in accordance with Article 8 (Construction Schedule and Equipment
Installation; Approval) and Schedule J (Systems Start-Up and Commissioning;
Operating Parameters of Installed Equipment) and accepted by the City, as
evidenced by the signed Certificate of Acceptance, Exhibit Ill (ii) (Certificate of
Acceptance—Installed Equipment), and until this equipment is fully and properly
functioning.
City of Bozeman Energy Performance Contract Page 11
Section 3.6. Open Book Pricing; Independent Contractor Status; Labor
Relations
Open book pricing is required. Contractor shall fully disclose all direct construction
costs, including all subcontract costs and equipment costs. These costs, excluding
Contractor fixed fees, will be reconciled to the City upon formal completion in the
event of any construction cost savings. Contractor will maintain cost accounting
records on authorized work performed under actual costs for labor and material, or
other basis requiring accounting records.
The parties agree that Contractor is an independent contractor for purposes of this
Agreement and is not to be considered an employee of the City for any purpose.
Contractor is not subject to the terms and provisions of the City's personnel policies
handbook and may not be considered a City employee for workers' compensation or
any other purpose. Contractor is not authorized to represent the City or otherwise
bind the City in any dealings between Contractor and any third parties.
Contractor shall comply with the applicable requirements of the Workers'
Compensation Act, Title 39, Chapter 71, MCA, and the Occupational Disease Act of
Montana, Title 39, Chapter 71, MCA. Contractor shall maintain workers'
compensation coverage for all members and employees of Contractor's business,
except for those members who are exempted by law.
Contractor shall furnish the City with copies showing one of the following: (1) a binder
for workers' compensation coverage by an insurer licensed and authorized to provide
workers' compensation insurance in the State of Montana; or (2) proof of exemption
from workers' compensation granted by law for independent contractors.
Contractor shall post a legible statement of all wages and fringe benefits to be paid to
the Contractor's employees and the frequency of such payments (i.e., hourly wage
employees shall be paid weekly). Such posting shall be made in a prominent and
accessible location at the Contractor's normal place of business and shall be made
no later than the first day of services provided under this Agreement. Such posting
shall be removed only upon expiration or termination of this Agreement.
In performing the services under this Agreement, Contractor shall give preference to
the employment of bona fide residents of Montana, as required by §18-2-403, MCA,
and as such term is defined by §18-2-401(1), MCA. When making assignments of
work, Contractor shall use workers both skilled in their trade and specialized in their
field of work for all work to which they are assigned.
City of Bozeman Energy Performance Contract Page 12
Pursuant to §§18-2-403 and 18-2-422, MCA, Contractor shall pay wages, fringe
benefits, and expenses including travel allowances as set forth in the Montana
Prevailing Wage Rates for Building Construction effective July 11, 2014 and
applicable to Gallatin County, Montana which schedule is set forth in Exhibit V,
Montana Prevailing Wage Rate Schedule. Contractor shall pay all hourly wage
employees on a weekly basis. Violation of the requirements set forth in the above
State of Montana schedule of prevailing wage rates may subject the Contractor to
the penalties set forth in §18-2-407, MCA. Contractor shall maintain payroll records
during the term of this Agreement and for a period of three (3) years following
termination of this Agreement.
The Contractor shall ensure that any person, firm or entity performing any portion of
the services under this Agreement for which the contractor, subcontractor or
employer is responsible, is paid the applicable standard prevailing rate of wages.
In the event that, during the term of this Agreement, any labor problems or disputes
of any type arise or materialize which in turn cause any services to cease for any
period of time, Contractor specifically agrees to take immediate steps, at its own
expense and without expectation of reimbursement from City, to alleviate or resolve
all such labor problems or disputes. The specific steps Contractor shall take to
services shall be left to the discretion of Contractor; provided, however, that
Contractor shall bear all costs of any related legal action. Contractor shall provide
immediate relief to the City so as to permit the services to continue at no additional
cost to City.
Contractor shall indemnify, defend, and hold the City harmless from any and all
claims, demands, costs, expenses, damages, and liabilities arising out of, resulting
from, or occurring in connection with any claims regarding underpaid prevailing
wages.
Section 3.7. Construction Savings and Owner Directed Change Orders
Upon the execution of a Certificate of Acceptance— Installed Equipment (Exhibit III(ii)),
if the total project cost is less than the Total Guaranteed Cost, then the difference
between the actual and estimated costs as reconciled in accordance with Section 3.7
may at the City's discretion be used to implement more projects per the terms of this
Contract, provided that the difference is sufficient to fund additional project(s). The
Contractor shall apply the fee structure to those additional projects per Schedule D,
Table 4.1: Budget Summary Report. For purposes of those additional project(s), a
new Certificate of Acceptance — Installed Equipment shall be executed, which date
shall be the Commencement Date, for purposes of this Contract, as to those project(s)
City of Bozeman Energy Performance Contract Page 13
only. Otherwise the difference between the actual and estimated costs will be identified
as project savings that can be used to offset other ECM project costs such as change
orders. If there is a net project savings from all ECM projects installed, the net savings
belongs to the City to be applied according to the terms of the financing requirements
for the total project.
In the event the City issues change orders that increase costs, the amount of those
const increases shall be identified by the Contractor and accounted for in a separate
budget beyond the original Total Guaranteed Cost. It will be the City's responsibility to
pay these costs as the project is being constructed. The Contractor shall use the mark-
up structure indicated in Schedule D, Table 4.1: Budget Summary Report as the
original basis for the pricing of change orders. However, if either party believes that the
scale and/or scope of the change order is not properly reflected in the pricing in
Schedule D, then the parties will negotiate a mutually agreed-upon fee, recorded in a
written change order and signed by authorized representatives of both parties.
ARTICLE 4. FISCAL FUNDING
Section 4.1. Non-appropriation of Funds
The City is dependent upon state and federal appropriations for its funding. If state
or federal government funds are not appropriated or otherwise made available to
support continued performance of this Contract in subsequent fiscal periods, the
City shall terminate this contract. The City shall provide Contractor the date the
City's termination shall take effect. The City shall not be liable to the Contractor for
any payment that would have been payable had the contract not been terminated
under this provision. The City shall be liable to the Contractor only for the payment,
or prorated portion of that payment, owed to the Contractor up to the date the City's
termination takes effect. This is the Contractor's sole remedy.
Section 4.2. Non-substitution
In the event of a termination of this contract due to the non-appropriation of funds or in
the event this Contract is terminated by Contractor due to a default by the City, the City
agrees, to the extent permitted by state law, not to purchase, lease, rent, borrow, seek
appropriations for, acquire or otherwise receive the benefits of any of the same and
unique services performed by Contractor from another Energy Service Company for a
period of three-hundred sixty five (365) calendar days following such default by the
City, or termination of this Contract due to non-appropriations.
AUDIT AND CONSTRUCTION PHASE
ARTICLE 5. ENERGY USAGE RECORDS AND DATA
The City has furnished, and shall continue to furnish (or authorize its energy
suppliers to furnish) during the Term of this Contract to Contractor or its designee,
City of Bozeman Energy Performance Contract Page 14
upon its request, all of its records and complete data concerning energy and water
usage and related maintenance for the Project Site(s).
ARTICLE 6. LOCATION AND ACCESS
Contractor acknowledges that there exists sufficient space on the Project Site(s) for
the installation and operation of the Equipment. Contractor is responsible for all
aspects of protecting the equipment during construction. The City shall take
reasonable steps to protect the Equipment from harm, theft, and misuse after final
acceptance has been obtained. The City shall provide access to the Project Site(s)
for Contractor to perform any function related to this Contract during regular business
hours, or such other reasonable hours as may be requested by Contractor and
acceptable to the City. The City shall grant Contractor immediate access to make
emergency repairs or corrections as it may, in its discretion, determine are needed.
Contractor shall immediately notify the City when emergency action is taken and
follow up with written notice within three (3) business days, specifying the action
taken, the reasons for the action, and the impact upon the Project Site(s), if any.
ARTICLE 7. PERMITS AND APPROVALS; COORDINATION
Section 7.1. Permits and Approvals
The City shall use its best efforts to assist Contractor in obtaining all necessary
permits and other approvals for installation of the Equipment. However, the City is
not responsible for payment of any permit or other approval fees. The equipment,
and the operation of the equipment by Contractor, shall conform to all federal, state,
and local code requirements. Contractor shall furnish to the City copies of each
permit and license required to perform the work before Contractor commences the
portion of the work requiring the permit or license.
Section 7.2. Coordination During Installation
The Contractor shall coordinate the activities of its equipment installers with those of
the City, its employees, and agents. Contractor shall not commit or permit any act
that will interfere with the performance of business activities conducted by the City or
its employees, without prior written approval of the City.
ARTICLE 8. CONSTRUCTION SCHEDULE AND EQUIPMENT
INSTALLATION; AWARD OF SUBCONTRACTS; SYSTEMS
STARTUP APPROVAL
Section 8.1. Construction Schedule; Equipment Installation
Construction and Equipment installation shall proceed in accordance with the
construction schedule approved by the City and attached as Schedule
(Construction and Equipment Installation Schedule).
City of Bozeman Energy Performance Contract Page 15
Section 8.2. Award of Subcontracts
The Contractor shall furnish the City with the names of subcontractors and suppliers
proposed for each principle portion of the work. This shall occur within 30 days of
Contract award. The City will promptly acknowledge receipt of this subcontractor and
supplier plan and advise if there is reasonable objection to any listed person or entity.
The Contractor shall not enter into an agreement with any subcontractor or supplier to
which the City raises a timely objection.
The Contractor and all subcontractors must comply with all Montana Department of
Labor and Industry requirements, regulations, rules and statutes.
Section 8.3. Systems Startup and Equipment Commissioning Approval
Contractor shall conduct a thorough and systematic performance test of each
element and the total system of the installed Equipment in accordance with Schedule
J (Systems Start-Up and Commissioning; Operating Parameters of Installed
Equipment) and prior to acceptance of the project by the City, as specified in Exhibit
III (i) (Certificate of Acceptance-Investment Grade Audit Report). Testing must
be designed to determine whether the Equipment is functioning in accordance with
both its published specifications and the Schedules to this Contract and whether
modified building systems, subsystems, and components are functioning properly.
Contractor shall notify the City of the scheduled test(s) and the City and/or its
designees have the right to be present at any tests conducted by Contractor and/or
manufacturers of the Equipment. Contractor is responsible for correcting and/or
adjusting any deficiencies in systems and Equipment operations observed during
system commissioning procedures, as specified in Schedule J (Systems Start-Up
and Commissioning; Operating Parameters of Installed Equipment). Contractor
also is responsible for correcting and/or adjusting any deficiencies in Equipment
operation observed during system testing procedures. Prior to the City's acceptance
of the Equipment, Contractor also shall provide the City with reasonable
documentation that the Equipment installed is the Equipment specified in Schedule
H (Scope of Work).
ARTICLE 9. EQUIPMENT WARRANTIES
The Contractor warrants to the City that materials and equipment furnished under the
Contract will be new and of good quality unless otherwise required or permitted by the
Contract Documents, that the Work will be free from defects not inherent in the quality
required or permitted, and that the Work will conform to the requirements of the
Contract.
The Contractor warrants and guarantees all work, workmanship, and materials for
the full warranty period. The warranty period shall be defined as started upon
documented approval of Substantial Completion and continue for one (1) calendar
year.
City of Bozeman Energy Performance Contract Page 16
Substantial Completion means the stage in the progress of the Work where the Work
is sufficiently complete in accordance with the Contract Documents so that the City
can take beneficial use of the Work for its intended purpose. Substantial Completion
does not occur until the Equipment or system has been commissioned, accepted, and
the "Substantial Completion" form fully executed.
After the warranty period, Contractor is not responsible for performing maintenance or
repairs or making manufacturer warranty claims relating to the Equipment.
Manufacturer and product warranties and guarantees, as provided by the
manufacturer or as specified in the Contract Documents, are in addition to the
Contractor's warranty. Contractor shall assign to the City all available manufacturer's
warranties relating to the Equipment and deliver the written warranties to the City for
attachment to this Contract as Exhibit IV (Equipment Warranties). Contractor shall
pursue rights and remedies against the manufacturers under the warranties in the
event of Equipment malfunction, improper or defective function, or defects in parts,
workmanship, or performance. Contractor shall, during the warranty period, notify the
City whenever defects in Equipment parts or performance occur that give rise to rights
and remedies and when those rights and remedies are exercised by Contractor.
During this period, Contractor shall be liable to the City for the cost of any risk of
damage or damage to the Equipment and its performance, including damage to
property and equipment of the City or the Project Site(s), due to Contractor's failure to
exercise its warranty rights.
All warranties, to the extent transferable, shall be transferable and extend the City.
Warranties must specify that only new, not reconditioned, parts will be installed when
repair is necessitated by malfunction. All extended warranties must be addressed as
the property of the City and appropriately documented and titled.
ARTICLE 10. STANDARDS OF COMFORT
Contractor shall maintain and operate the Equipment in a manner that provides the
standards of heating, cooling, ventilation, hot water supply, and lighting quality and
levels described in Schedule K (Standards of Comfort). During the term of this
Contract, Contractor and the City shall maintain, according to Schedule M
(Contractor's Maintenance Responsibilities) and Schedule N (City of Bozeman
Maintenance Responsibilities), and operate the Equipment in a manner that
provides the standards of comfort and levels of operation described in Schedule K
(Standards of Comfort).
ARTICLE 11. ENVIRONMENTAL REQUIREMENTS
Section 11.1. Excluded Material and Activities
In connection with the installation and/or service or maintenance of Equipment at the
Project Site(s), Contractor is not responsible for any work relating to: (i) asbestos,
City of Bozeman Energy Performance Contract Page 17
materials containing asbestos, or the existence, use, detection, removal, containment
or
treatment of asbestos; (ii) fungus, including any type or form of fungi, including mold
or mildew, and myotoxins, spores, scents or by-products produced or released by
fungi;
(iii) pre-existing incomplete or damaged work or systems or code violations
discovered during, or prior to, the work under this Contract; or (iv) pollutants,
hazardous wastes, hazardous materials, contaminants other than those described in
this Section below (collectively "Hazardous Materials"), or the storage, handling, use,
transportation, treatment, or the disposal, discharge, leakage, detection, removal, or
containment of such materials. The materials and activities listed in the foregoing
sentence are referred to as "Excluded Materials and Activities". If performance of
work involves any Excluded Materials and Activities, the City shall perform, or arrange
for the performance of, such work and shall bear the sole risk and responsibility for
such work. If Contractor discovers Hazardous or Excluded Materials, Contractor shall
immediately cease work, remove all Contractor personnel and subcontractors from
the site, and notify the City. The City is responsible for handling such materials at its
expense. Contractor shall undertake no further work on the area of the Project site
affected by such materials, except as authorized by the City in writing. Any such
discovery or remediation by the City does not constitute a default by the City. In the
event of such stoppage of work by Contractor, the Time for Completion of Work is
automatically extended by the amount of time of the work stoppage, and any
additional costs incurred by Contractor in performing the work under this Contract as
a result will be added by Change Order.
Contractor is responsible for any hazardous or other materials, including, without
limitation, those listed in this section that it brings to the Project Site(s).
Section 11.2. Polychlorinated Biphenyl (PCB) Ballasts; Mercury Lamps
Contractor shall enter into an agreement with an approved PCB ballast disposal
company that will provide an informational packet, packing receptacles and
instructions, labels and shipping materials, transportation, and recycling or
incineration services for PCB ballasts. All capacitors and asphalt potting compound
materials removed from City PCB ballasts must be incinerated in a federally approved
facility. After proper disposal, a Certificate of Destruction must be provided by the
approved facility to the City. Contractor is responsible for proper and legal
management of all City PCB ballasts removed as a result of installation of the
Equipment until PCB ballasts are loaded onto the approved PCB ballast disposal
company's vehicle for transportation.
Contractor shall enter into an agreement with an approved mercury lamp disposal
company that will provide approved containers, materials required for labeling,
transportation, and recycling or incineration, in accordance with EPA requirements,
and a copy of the manifest.
City of Bozeman Energy Performance Contract Page 18
The City agrees to sign manifests of ownership for all PCB ballasts and mercury lamps
removed from the Project Site(s).
ARTICLE 12. TRAINING BY CONTRACTOR
Contractor shall conduct the training program described in Schedule L (Contractor's
Training Responsibilities). The training specified in Schedule L (Contractor's
Training Responsibilities) must be completed prior to acceptance of the Equipment
installation by the City, unless otherwise noted in Schedule L. Contractor shall
provide ongoing training whenever needed concerning updated or altered Equipment,
including upgraded software. Such training shall be provided by Contractor at no
charge to the City and shall have no effect on prior acceptance of Equipment
installation.
POST-CONSTRUCTION PHASE
ARTICLE 13. EQUIPMENT
SERVICE
Section 13.1. Actions by Contractor
Contractor shall provide all service, repairs, and adjustments to the Equipment
installed under this Contract. The City shall incur no cost for Equipment service,
repairs, and adjustments. However, if the Contractor demonstrates that the need for
maintenance or repairs principally arises due to the negligence or willful misconduct of
the City or any employee or other agent of the City, Contractor may charge the City for
the cost of the maintenance or repair if the cost is not covered by any warranty or
insurance.
Section 13.2. Malfunctions and Emergencies
The City shall use its best efforts to notify Contractor or its designated subcontractors
within 24 hours after the City's actual knowledge and occurrence of: (i) any
malfunction in the operation of the Equipment or in any preexisting energy related
equipment that might materially impact guaranteed energy savings; (ii) any
interruption or alteration to the energy supply to the Project Site(s); or (iii) any
alteration or modification in any energy-related equipment or its operation.
When the City exercises due diligence in attempting to assess the existence of a
malfunction, interruption, or alteration, it is not liable to Contractor for additional costs
for failing to correctly identify such conditions as having a material impact upon the
guaranteed energy savings. The City shall notify Contractor within 24 hours upon
learning of any emergency condition affecting the Equipment. Contractor shall
respond, or cause its designee(s) to respond, within 24 hours and shall promptly
proceed with corrective measures. Any telephonic notice of such conditions by the
City must be followed within three business days by written notice to Contractor from
City of Bozeman Energy Performance Contract Page 19
the City. If the City unreasonably delays in notifying Contractor of a malfunction or
emergency, and the malfunction or emergency is not otherwise corrected or
remedied, the City is liable to Contractor for its loss, due to the delay, associated with
the guaranteed savings under this Contract for the particular time period, if Contractor
demonstrates a direct causal connection between the delay and the loss.
Contractor shall provide a written record of all service work performed. This record
must state the reason for the service, a description of the problem, and the corrective
action performed.
Section 13.3. Actions by the City
The City may not move, remove, modify, alter, or change the Equipment or any part of
the Equipment without prior written approval of Contractor, except as stated in
Schedule N (City of Bozeman Maintenance Responsibilities). The City may take
reasonable steps to protect the Equipment if, due to an emergency, it is not possible or
reasonable to notify Contractor before taking action. If there is an emergency, the City
shall take reasonable steps to protect the Equipment from damage or injury and shall
follow any instructions for emergency action provided in advance by Contractor. The
City shall maintain the Project Site(s) in good repair and protect and preserve all
portions that may affect operation or maintenance of the Equipment.
ARTICLE 14. MODIFICATION, UPGRADE OR ALTERATION OF THE
EQUIPMENT
Section 14.t Modification of Equipment
During the Term of this Contract, the City may not, without prior written consent of
Contractor, install any accessory Equipment or device on any of the Equipment if the
addition will change or impair the originally intended functions, value, or use of the
Equipment.
Section 14.2. Upgrade or Alteration of Equipment
Contractor may, subject to the City's prior written approval, which approval may not
unreasonably be withheld, change the Equipment, revise any procedures for
operation of the Equipment, or implement other energy saving actions in the Project
Site(s), if: (i) Contractor complies with the standards of comfort and services specified
in Schedule K (Standards of Comfort); (ii) modifications or additions to, or
replacement of the Equipment, and any operational changes, or new procedures are
necessary to enable Contractor to achieve the guaranteed energy and cost savings at
the Project Site(s) and; (iii) Contractor bears any cost incurred relative to such
modifications, additions, or replacement of the Equipment, or operational changes or
new procedures.
All modifications, additions, or replacements of the Equipment, or revisions to
City of Bozeman Energy Performance Contract Page 20
operating or other procedures, must be described by Contractor in a supplemental
Schedule(s) provided to the City for approval, which may not be unreasonably
withheld, and any replacement Equipment must, unless otherwise agreed, be new
and have equal or better potential to reduce energy consumption at the Project
Site(s) than the Equipment being replaced. Contractor may update any software to
be used in connection with the Equipment, in accordance with Section 17.1
(Ownership of Certain Proprietary Property Rights) and Schedule M
(Contractor's Maintenance Responsibilities). All replacements of, and alterations
or additions to, the Equipment become part of the Equipment described in Schedule
H (Scope of Work) and are covered by the terms of Article 8 (Construction
Schedule and Equipment Installation; Award of Subcontracts; Systems Startup
Approval).
ARTICLE 15. MATERIAL CHANGES
Section 15.1. Material Change Defined
A Material Change includes any change in, or to, the Project Site(s), whether
structural, operational, or otherwise in nature that reasonably could be expected, in
the sole judgment of the City, to increase or decrease annual energy consumption, in
accordance with Schedule B (Baseline Energy Consumption) and Schedule C
(Savings Measurement and Verification Plan; Methodology to Adjust Baseline)
by at least 3%, after adjustments for climatic variations. Actions by the City that may
result in a Material Change include, but are not limited to, the following:
(i) manner of use of the Project Site(s) by the City;
(ii) hours of operation for the Project Site(s), or for any equipment or energy
using systems operating at the Project Site(s);
(iii) Permanent changes in the comfort and service parameters specified in
Schedule K (Standards of Comfort);
(iv) occupancy of the Project Site(s);
(v) structure of the Project Site(s);
(vi) types and quantities of equipment used at the Project Site(s);
(vii) modification, renovation or construction at the Project Site(s);
(viii) any other conditions other than climate affecting energy use at the Project
Site(s), including, but not limited to, replacement, addition, or removal of
energy and water consuming devices, whether plug in or fixed assets;
(ix) casualty or condemnation of the Project Site(s) or Equipment;
(x) changes in utility provider or utility rate classification;
(xi) any other conditions other than climate affecting energy or water use at the
Project Site(s); or
(xii) modifications, alterations, or overrides of the energy management system
schedules or hours of operation, set back/start up, or holiday schedules.
City of Bozeman Energy Performance Contract Page 21
Section 15.2. Reported Material Changes; Notice by the City
The City shall use its best efforts to deliver to Contractor a written notice describing all
actual or proposed Material Changes in the Project Site(s) or in the operations of the
Project Site(s) at least 30 calendar days before any actual or proposed Material
Change is implemented, or as soon as is practicable after an emergency or other
unplanned event. Notice to Contractor of Material Changes that result because of an
emergency or other situation that precludes advance notice is sufficient if given by the
City within 48 hours after the City knew or discovered that the event constituting the
Material Change occurred.
Section 15.3. Other Adjustments
The City shall alert Contractor of known Materials Changes. Contractor shall work with
the City to investigate, identify, and correct any changes that prevent the guaranteed
savings from being realized. Based on the investigation, Contractor and the City shall
determine what, if any, adjustments to the baseline are to be made in accordance with
Schedule C (Savings Measurement and Verification Plan; Methodology to Adjust
Baseline) and Schedule B (Baseline Energy Consumption). Any disputes between
the City and Contractor concerning any such adjustment shall be resolved in
accordance with Schedule Q (Alternative Dispute Resolution Procedures).
ARTICLE 16. PERFORMANCE BY CONTRACTOR
Section 16.1. Corrective Action; Accuracy of the Services
Contractor shall perform all tasks/phases under the Contract, including construction,
and install the Equipment in such a manner so as not to harm the structural integrity of
the buildings or their operating systems and in conformance with the standards in
Schedule K (Standards of Comfort) and the construction schedule specified in
Schedule I (Construction and Equipment Installation Schedule). Contractor shall
repair and restore to its original condition any area of damage caused by Contractor's
performance under this Contract. The City may review the work performed by
Contractor and direct Contractor to take corrective action reasonably necessary to
remedy damage caused by Contractor if the structural integrity of the Project Site(s) or
its operating system is or will be harmed. Contractor shall bear all costs associated
with such corrective action.
Contractor is responsible for the professional and technical accuracy of all services
performed, whether by Contractor or its subcontractors or others on its behalf,
throughout the term of this Contract.
City of Bozeman Energy Performance Contract Page 22
Section 16.2. Annual Reporting Requirements: Annual ENERGY STAR Rating
Within ninety (90) days after the end of each year during the guarantee period, as
specified in Schedule A (Energy and Water Cost Savings Guarantee), Contractor
shall complete and submit to the City the data required in Schedule P (Annual
Reporting Requirements).
ADMINISTRATION
ARTICLE 17. OWNERSHIP OF CERTAIN PROPRIETARY PROPERTY RIGHTS;
EXISTING EQUIPMENT
Section 17.1. Ownership of Certain Proprietary Property Rights
The City does not, by virtue of this Contract, acquire any interest in any formulas,
patterns, devices, secret inventions or processes, copyrights, patents, other intellectual
or proprietary rights, or similar items of property used in connection with the Equipment.
Contractor grants to the City a perpetual, irrevocable royalty-free license for any and all
software or other intellectual property rights necessary for the City to continue to
operate, maintain, and repair the Equipment in a manner that will yield guaranteed
utility consumption reductions for the specified contract term. Contractor shall provide
new versions of software or other enhancements if new versions or enhancements are
necessary to achieve the guaranteed utility consumption reductions.
Section 17.2. Ownership of Existing Equipment
Equipment and materials existing at the Project Site(s) at the time of execution of this
Contract remain the property of the City, even if replaced or operation is made
unnecessary by work performed by Contractor pursuant to this Contract. At least
fourteen (14) calendar days prior to replacement, Contractor shall provide the City with
written advance notice of all equipment and materials to be replaced at the Project
Site(s). Within 10 calendar days after receipt of the notice, the City shall identify in
writing to Contractor the equipment and materials that are not to be disposed of off-site
by Contractor, and Contractor may not dispose of any such equipment or materials off
site. The City shall designate the location and manner of storage for any equipment
and materials that are to be stored on-site. Contractor is responsible for disposal, in
accordance with all applicable laws and regulations, of all equipment and materials
designated by the City as disposable off-site.
City of Bozeman Energy Performance Contract Page 23
ARTICLE 18. INDEMNIFICATION; LIMITATION OF LIABILITY; INSURANCE;
CLAIMS
For other than professional services rendered, to the fullest extent permitted by law,
Contractor agrees to release, defend, indemnify, and hold harmless the City, its
agents, representatives, employees, and officers (collectively referred to for purposes
of this Section as the City) from and against any and all claims, demands, actions, fees
and costs (including attorney's fees and the costs and fees of expert witness and
consultants), losses, expenses, liabilities (including liability where activity is inherently
or intrinsically dangerous) or damages of whatever kind or nature that may be asserted
against, recovered from or suffered by the City occasioned by, growing or arising out of
or resulting from or in any way related to: (i) the negligent, reckless, or intentional
misconduct of the Contractor; or (ii) any negligent, reckless, or intentional misconduct
of any of the Contractor's agents.
For the professional services rendered, to the fullest extent permitted by law,
Contractor agrees to indemnify and hold the City harmless against claims, demands,
suits, damages, losses, and expenses, including reasonable defense attorney fees, to
the extent caused by the negligence or willful misconduct of the Contractor or
Contractor's agents or employees.
Such obligations shall not be construed to negate, abridge, or reduce other rights or
obligations of indemnity that would otherwise exist. The indemnification obligations of
this Section must not be construed to negate, abridge, or reduce any common-law or
statutory rights of the indemnitee(s) which would otherwise exist as to such
indemnitee(s).
Contractor's indemnity under this Section shall be without regard to and without any
right to contribution from any insurance maintained by City.
Should any indemnitee described herein be required to bring an action against the
Contractor to assert its right to defense or indemnification under this Agreement or
under the Contractor's applicable insurance policies required below the indemnitee
shall be entitled to recover reasonable costs and attorney fees incurred in asserting its
right to indemnification or defense but only if a court of competent jurisdiction
determines the Contractor was obligated to defend the claim(s) or was obligated to
indemnify the indemnitee for a claim(s) or any portion(s) thereof.
In the event of an action filed against City resulting from the City's performance under
this Contract, the City may elect to represent itself and incur all costs and expenses of
suit.
Contractor also waives any and all claims and recourse against the City or its officers,
agents or employees, including the right of contribution for loss or damage to person or
property arising from, growing out of, or in any way connected with or incident to the
performance of this Contract except "responsibility for his own fraud, for willful injury to
the person or property of another, or for violation of law, whether willful or negligent" as
City of Bozeman Energy Performance Contract Page 24
per 28-2-702, MCA.
Neither Party shall be liable to the other Party for any consequential, indirect,
special, incidental, exemplary, or similar, damages or losses, including loss of
profits, arising out of or relating to this Agreement, whether based on contract or
tort or any other theory, even if a Party has been advised of the possibility of
such damages.
These obligations shall survive termination of this Contract and the services performed
hereunder.
In addition to and independent from the above, Contractor shall at Contractor's
expense secure insurance coverage through an insurance company or companies duly
licensed and authorized to conduct insurance business in Montana which insures the
liabilities and obligations specifically assumed by the Contractor in this Section. The
insurance coverage shall not contain any exclusion for liabilities specifically assumed
by the Contractor in subsection (a) of this Section.
The insurance shall cover and apply to all claims, demands, suits, damages, losses,
and expenses that may be asserted or claimed against, recovered from, or suffered by
the City without limit and without regard to the cause therefore and which is acceptable
to the City and Contractor shall furnish to the City an accompanying certificate of
insurance and accompanying endorsements in amounts not less than as follows:
• Workers' Compensation — statutory;
• Employers' Liability - $1,000,000 per occurrence; $2,000,000 annual
aggregate;
• Commercial General Liability - $2,000,000 per occurrence; $4,000,000
annual aggregate;
• Automobile Liability - $1,000,000 property damage/bodily injury; $2,000,000
annual aggregate; and
• Professional Liability - $1,000,000 per claim; $2,000,000 annual aggregate.
The City of Bozeman, its officers, agents, and employees, shall be endorsed as an
additional or named insured on a primary non-contributory basis on both the
Commercial General and Automobile Liability policies. The insurance and required
endorsements must be in a form suitable to City and shall include no less than a sixty
(60) day notice of cancellation or non-renewal. The City must approve all insurance
coverage and endorsements prior to the Contractor commencing work. Contractor shall
notify City within two (2) business days of Contractor's receipt of notice that any
required insurance coverage will be terminated or Contractor's decision to terminate
any required insurance coverage for any reason.
The City must approve all insurance coverage and endorsements prior to the
Contractor commencing work.
City of Bozeman Energy Performance Contract Page 25
Section 18.1. Claims, Disputes and Controversies
18.1.1. Definition. A Claim is a demand or assertion by one of the parties
seeking, as a matter of right, adjustment or interpretation of Contract terms,
payment of money, extensions of time or other relief with respect to the terms of
the Contract. The term "Claim" includes all disputes, controversies, and matters
in question between the City and Contractor arising out of or relating to the
Contract. Claims must be initiated by written notice to the other party. The
responsibility to substantiate Claims shall rest solely with the party making the
Claim.
18.1.1.1. All Claims must contain sufficient justification and substantiation
or they may be rejected without consideration by the other party with no
additional impact or consequence to the Contract.
18.1.1.2. If additional compensation is claimed, the exact amount
claimed and a breakdown of that amount into the following categories shall
be provided with each and every claim:
18.1.1.2.1. Direct costs;
18.1.1.2.2. Indirect costs.
18.1.1.3. If additional time is claimed the following shall be provided with
each and every claim:
18.1.1.3.1. The specific number of days and specific dates for which the
additional time is sought;
18.1.1.3.2. The specific reasons, causes, and/or effects whereby
the Contractor believes that additional time should be granted; and,
18.1.1.3.3. The Contractor shall provide analyses, documentation, and
justification of its claim for additional time.
18.1.2. Continuing Contract Performance. Pending final resolution of a Claim
except as otherwise agreed in writing or as provided in this Contract,
the Contractor shall proceed diligently with performance of the Contract
and the City shall continue to make payments in accordance with the
Contract on portions of the Work not involved in a Claim.
City of Bozeman Energy Performance Contract Page 26
Section 18.2. Resolution of Claims. Disputes and Controversies
18.2.1. Upon receipt of a Claim against the Contractor or at any time
thereafter, the City may, but is not obligated to, notify the surety of the nature
and amount of the Claim. If the Claim relates to a possibility of a Contractor's
default, the City may, but is not obligated to, notify the surety and request the
surety's assistance in resolving the controversy.
18.2.2. A Claim subject to or related to liens or bonds shall be governed by
applicable law regarding notices, filing deadlines, and resolution of such Claim
prior to any resolution of such Claim by the City or by mediation, except for
claims made by the City against the Contractor's bonds.
Section 18.3. Mediation
18.3.1. Any Claim arising out of or related to the Contract, except Claims
waived elsewhere in the Contract, shall be subject to mediation as a
condition precedent to the institution of legal or equitable proceedings by
either party.
18.3.2. The parties shall endeavor to resolve their Claims by mediation which,
unless the parties mutually agree otherwise in writing, shall be in accordance
with the Construction Industry Mediation Rules of the American Arbitration
Association currently in effect and/or those rules specified in the contract
documents or separately agreed upon between the parties. Construction
Industry Mediation Rule M-2 (filing with AAA) does not apply, unless the parties
mutually agree in writing to use AAA, and no filing of a request for mediation
shall be made to AAA by either party until such mutual agreement has been
made. Unless the parties agree to use AAA, the parties shall mutually agree
upon a mediator who shall then take the place of AAA in the Construction
Industry Mediation Rules. Request for mediation shall be filed in writing with the
other party to the Contract and with the American Arbitration Association, if the
parties have agreed to use AAA. The request may be made concurrently with the
filing of a demand for arbitration but, in such event, mediation shall proceed in
advance of arbitration or legal or equitable proceedings, which shall be stayed
pending mediation for a period of 60 days from the date of filing, unless stayed
for a longer period by agreement of the parties or court order.
18.3.3. The parties shall share the mediator's fee and any filing fees
equally. The mediation shall be held in the place where the Project is located,
unless another location is mutually agreed upon in writing. Agreements
reached in mediation shall be enforceable as settlement agreements in any
court having jurisdiction thereof.
City of Bozeman Energy Performance Contract Page 27
ARTICLE 19. DELAYS; CONDITIONS BEYOND CONTROL OF THE PARTIES
Section 19.1. Delays within the control of the Contractor
In no event shall the City be liable to the Contractor, any subcontractor, any supplier,
Contractor's surety, or any other person or organization, for damages or costs arising
out of or resulting from delays caused by or within the control of the Contractor which
include but are not limited to labor issues or labor strikes on the Project, federal, state,
or local jurisdiction enforcement actions related directly to the Contractor's Work (e.g.
safety or code violations, etc.).
Section 19.2 Conditions Beyond Control of the Parties; Force Majeure
If a party ("performing party") reasonably is unable to perform any of its obligations
under this Contract due to unforeseeable events beyond that parties' control, at the
other parties' option, the Contract shall: (i) remain in effect but the performing parties'
obligations are suspended until such events have ended; or, (ii) the other party may
terminate the Contract upon ten (10) days written notice to the performing party, in
which event neither party has any further liability to the other under this Contract.
ARTICLE 20. ADDITIONAL DUTIES AND REPRESENTATIONS OF THE PARTIES
Section 20.1. For the term of this Contract, the City shall, within thirty (30) days of
receipt of Contractor's request, provide the Contractor with accurate and complete
copies of all records relating to the Contract, including, but not limited to, records
relating to energy usage and energy-related maintenance of Project Site(s) requested
by Contractor that have not already been provided.
Section 20.2. The City represents that it has not entered into any lease or other
contract regarding energy efficiency equipment, provision of energy management
services for the Project Site(s), or servicing of any energy related equipment located in
the Project Site(s). If the City enters into any such lease or other contract, within ten
(10) calendar days after execution, it shall provide Contractor with a copy of the lease
or other contract.
Section 20.3. Contractor represents that it is financially solvent, able to pay its debts
as they mature, and has sufficient working capital to perform its duties under this
Contract.
Section 20.4. Within thirty (30) calendar days after executing this Contract, and before
commencing performance of this Contract, Contractor shall provide the City with written
documentation that it is licensed to perform its duties under this Contract within the
State of Montana and that all insurance and bonding requirements applicable to
Contractor under this Contract have been met. Contractor must also have a valid City
of Bozeman business license before commencing performance.
Section 20.5. Upon request, Contractor shall make available to the City all documents
relating to its performance under this Contract, including all contracts and subcontracts.
City of Bozeman Energy Performance Contract Page 28
Section 20.6. All subcontractors used by Contractor in performing its duties under this
Contract must be qualified, licensed, and bonded in the State of Montana to perform the
subcontracted work. All subcontractors must also have a valid City of Bozeman
business license before commencing performance.
Section 20.7. All Equipment installed by Contractor under this Contract must meet, or
exceed, the requirements specified in Section 8.2 (Systems Start Up and Equipment
Commissioning) and in Schedule J (Systems Start-Up and Commissioning;
Operating Parameters of Installed Equipment).
Section 20.8. All Equipment installed by Contractor under this Contract must be
compatible with all other Project Site(s) mechanical and electrical systems, subsystems,
and components with which the Equipment interacts.
Section 20.9. Contractor has familiarized itself with all local conditions and federal,
state and local laws, ordinances, rules, and regulations that in any manner may affect
cost, progress, or Contractor's performance of this Contract.
Section 20.10. Contractor represents and warrants to City that it has the experience
and ability to perform the services required by this Agreement; that it will perform said
services in a professional, competent and timely manner and with diligence and skill;
that it has the power to enter into and perform this Agreement and grant the rights
granted in it; and that its performance of this Agreement shall not infringe upon or violate
the rights of any third party, whether rights of copyright, trademark, privacy, publicity,
libel, slander or any other rights of any nature whatsoever, or violate any federal, state
and municipal laws. The City will not determine or exercise control as to general
procedures or formats necessary to have these services meet this warranty.
ARTICLE 21. MISCELLANEOUS DOCUMENTATION PROVISIONS
Section 21.1. Construction Performance and Payment Bonds. Labor and
Material Payment Bonds; Bond Clarification
Contractor shall furnish performance and payment Bonds, each in an amount equal to the
Contract value. The Bonds shall cover completion of the physical work per the approved design,
and shall not guarantee or warranty efficiency or system performance. The Bonds shall not
cover any obligation of the contractor to ensure that the work as constructed will result in any
particular level of energy savings.
Any system performance guarantee or warranty in this Contract and referenced in Section 3
and Schedule A, Energy and Cost Savings Guarantee, will be provided by Contractor.
Section 21.2. Further Documents
The parties shall timely execute and deliver to each other all documents and
shall perform all further acts reasonably necessary to effectuate the provisions of
this Contract.
City of Bozeman Energy Performance Contract Page 29
Section 21.3. City of Bozeman Responsibilities
(a) Methods of Operation by the City
The parties agree that the guaranteed Energy and Cost Savings may not be obtained
unless the procedures and methods of operation designed for energy and water
conservation that are identified in the Investment Grade Audit Report are implemented
and followed by the City on a regular and continuous basis.
(b) inspection of Project Site(s)
Once per month, with 48 hours prior notice to the City, Contractor may inspect the
Project Site(s) to determine whether the City is complying with Section 21.3(b).
Compliance is to be determined by Contractor using the checklist shown in Schedule
O (Facility Maintenance Checklist), as completed by Contractor during its monthly
inspections. The City shall make the Project Site(s) available to Contractor during
each monthly inspection and may witness each inspection and Contractor's notations
on the checklist. The City may complete its own checklist at the same time.
Contractor may not interfere with the City's operations during any monthly inspection.
Section 21.4. Waiver Of Liens
Contractor shall obtain, and furnish to the City a Waiver of Liens from each vendor,
material manufacturer, and laborer related to the supply, installation, and servicing of
each piece of Equipment.
ARTICLE 22. CONFLICTS OF INTEREST
Section 22.1. Conflicts of interest relating to this Contract are strictly prohibited.
Neither party to this Contract, nor any director, employee, or agent of either party may
give to, or receive from, any director, employee, or agent of the other party any gift,
entertainment, or other favor of significant value, or any commission, fee, or rebate in
connection with this Contract.
Section 22.2. Neither party to this Contract, nor any director, employee, or agent of
either party may, without prior notice to the other party, enter into any business
relationship with any director, employee, or agent of the other party or of any affiliate of
the other party.
Section 22.3. The parties to this Contract promptly shall notify the other party of any
violation of this article, and any consideration received as a result of such violation shall
be paid or credited to the other party.
Section 23.4. Any representative of a party to this Contract, authorized by that party,
may, upon reasonable notice to the other party and during regular business hours, audit
the records of the other party related to this Contract, including the expense records of
the parties' employees involved in this Contract, for the purpose of determining whether
there has been compliance with this section.
City of Bozeman Energy Performance Contract Page 30
ARTICLE 23. CONTRACT, AMENDMENT AND INTERPRETATION
Contract. This Contract consists of numbered pages, Attachments, and
Contractor's response to request for qualification. In the case of dispute or
ambiguity about the minimum levels of performance required of Contractor, the order
of precedence of document interpretation is in the same order.
Entire Contract. These documents contain the entire Contract of the parties. Any
enlargement, alteration or modification requires a written amendment signed by both
parties.
ARTICLE 24. CHOICE OF LAW AND VENUE
This Contract is governed by the laws of Montana. The parties agree that any litigation
concerning this Contract must be brought in the District Court of the Eighteenth Judicial
District, Gallatin County, State of Montana, and each party shall pay its own costs and
attorney fees. (Mont. Code Ann. § 18-1-401)
ARTICLE 25. DISPUTE RESOLUTION
Questions of fact that arise in relation to interpretation of this Contract are subject to the
alternative dispute resolution procedures described in Section 18.2 (Resolution of
Claims, Disputes and Controversies) and Section 18.3 (Mediation). Unless the
Parties agree otherwise, or the Work cannot be continued without a resolution of the
question of fact, alternative dispute resolution procedures are not cause for delay of the
Work under this Contract. Continuation of the Work does not constitute a waiver of any
rights accruing to Contractor or the City.
ARTICLE 26. LIAISON AND SERVICE OF NOTICES
All project management and coordination on behalf of the City shall be through a single
point of contact designated as the City liaison. Contractor shall designate a liaison who
will provide the single point of contact for management and coordination of Contractor's
work. All work performed pursuant to this Contract shall be coordinated between the
City's liaison and Contractor's liaison. All written notices required by this Contract shall
be sent by U.S. mail or electronically by e-mail.
Natalie Meyer will be the liaison for the City of Bozeman.
121 N. Rouse Ave., P.O. Box 1230
Bozeman, MT 59771-1230
Telephone: 406-582-2317
Fax: 406-582-2344
E-mail: nmeyer@bozeman.net
Karen Hedglin will be the liaison for Contractor.
1982 Stadium Drive, unit#1
Bozeman, MT 59715
Telephone: 406-582-7668
City of Bozeman Energy Performance Contract Page 31
Fax: 406-586-0486
E-mail: khedglin@mckinstry.com
The City's liaison and Contractor's liaison may be changed by written notice to the other
party. Written notices, requests, or complaints must first be directed to the liaison.
ARTICLE 27. GENERAL TERMS AND CONDITIONS
Section 27.1. Design/Engineering
All analysis, design, equipment selections, specifications, and all aspects connected
with design, installation, and construction of energy-savings measures, done by the
Contractor shall be performed by an engineer licensed in the State of Montana in
accordance with 18-2-121 and 12-2-122, MCA. Contractor will include at least two City
representatives to serve on the review and selection committee(s) for any request for
proposals (RFPs) or request for qualifications (RFQs) issued by Contractor in
connection with this Contract.
Contractor will use the Department of Energy's Model Specification for LED Roadway
Luminaires in the design specifications for the LED Street Light FIM in Schedule D,
Table 4.2.
Section 27.2. Access and Retention of Records
Access to Records The Contractor agrees to provide the City, Legislative Auditor, or
their authorized agents, access to any records necessary to determine contract
compliance. (Montana Code Annotated § 18-1-118).
Retention Period The Contractor agrees to create and retain records supporting the
services rendered or supplies delivered for a period of three years after either the
completion date of this Contract or the conclusion of any claim, litigation, or exception
relating to this Contract taken by the City or third party.
Section 27.3. Assignment, Transfer and Subcontracting
The Contractor may not assign, transfer or subcontract any portion of this Contract
without the express written consent of the City. (Montana Code Annotated § 18-4-141)
The City will not unreasonably withhold consent. The Contractor shall be responsible to
the City for the acts and omissions of all subcontractors or agents and of persons
directly or indirectly employed by such subcontractors, and for the acts and omissions
of persons employed directly by the Contractor. No contractual relationships exist
between subcontractor and the City.
Section 27.4. Compliance with Laws
The Contractor and any subcontractor must, in performance of work under this
Contract, fully comply with all applicable federal, state, or local laws, rules and
regulations, including the generation and disposal of hazardous waste, the
City of Bozeman Energy Performance Contract Page 32
Section 27.8. Severability
A declaration by any court, or any other binding legal source, that any provision of the
Contract is illegal and void shall not affect the legality and enforceability of any other
provision of the Contract, unless the provisions are mutually dependent.
Section 27.9. Shipping
Supplies shall be shipped prepaid, F.O.B. Destination, unless the Contract specifies
otherwise.
The parties through their authorized agents have executed this contract on the dates
set out below.
IN WITNESS WHEREOF, the parties hereto have executed this instrument the day and
year first above written.
CITY OF BOZEMAN, MONTANA Nj2Kinstcy Essention, LLC
0
BY ( 1 ' Sc
�- Y� � 6/
Chas Kukulski, City Manager
Deeet4er 2 0/y Print Name: kSeOh Nagar
Print Title: 1 i ( 1. vv ®f' i'Kcrru�
APPROVED O FORM:
By 7/'
re•C ullivan, Bozeman City Attorney
City of Bozeman Energy Performance Contract Page 34
CONTRACT ATTACHMENT I: Schedules, Exhibits, and Appendices
SAVINGS GUARANTEE
SCHEDULE A. ENERGY AND COST SAVINGS GUARANTEE
SCHEDULE B. BASELINE ENERGY CONSUMPTION
SCHEDULE C. SAVINGS MEASUREMENT AND VERIFICATION PLAN;
METHODOLOGY TO ADJUST BASELINE
PAYMENTS AND SCHEDULE
SCHEDULE D. FINAL PROJECT COST & PROJECT CASH FLOW ANALYSIS
SCHEDULE E. NOT USED
SCHEDULE F. NOT USED
AUDIT AND CONSTRUCTION PHASE
SCHEDULE G. NOT USED
SCHEDULE H. SCOPE OF WORK
SCHEDULE I. CONSTRUCTION AND EQUIPMENT INSTALLATION SCHEDULE
SCHEDULE J. SYSTEMS START-UP AND COMMISSIONING OF
EQUIPMENT; OPERATING PARAMETERS OF INSTALLED EQUIPMENT
The Contractor shall maintain at the site for the City one record copy of the Drawings,
Specifications, Addenda, Change Orders and other Modifications, in good order
and accurately marked to record current field changes and selections made
during construction, and one record copy of approved Shop Drawings, Product
Data, Samples and similar required submittals.
The City is not required to process final payment until all documentation and data
required is submitted to and accepted by the City including, but not limited to, the as-
built Drawings.
The as-built drawings shall be neatly and clearly marked during construction, to
record all deviations, variations, changes, and alterations as they occur during
construction, along with such supplementary notes and details necessary to clearly
and accurately represent the as-built condition.
SCHEDULE K. STANDARDS OF COMFORT
City of Bozeman Energy Performance Contract Page 35
SCHEDULE L. CONTRACTOR'S TRAINING RESPONSIBILITIES
POST CONSTRUCTION
SCHEDULE M. NOT USED
SCHEDULE N. NOT USED
ADMINISTRATION
SCHEDULE O. FACILITY MAINTENANCE CHECKLIST
SCHEDULE P. ANNUAL REPORTING REQUIREMENTS
City of Bozeman Energy Performance Contract Page 36
Schedule P-Annual Reporting Requirements
Agency Name/Agency Contact(Include Email
and Phone Number)
Facility Name/Facility Contact(Include Email and
Phone Number)
Contractor Name/Contractor Contact(Include
Email and Phone Number)
Total Square Footage of Project Site/Contract
Start Date/Contract End Date
Current Repayment Year(ex.Yr. 3/ 2005)
Reporting Timeframe (ex. Jan 1-Dec. 31)
Installed Project Cost(no financing costs)
Total Contract Value of Guaranteed Savings
Annual Value of Guaranteed Savings
Measured Energy Savings
Operational Savings
Avoided Capital Cost(if applicable)
Annual Dollar Value of Achieved Savings
I '
Total Annual Achieved Energy Savings (MMBTU)
Electric
Natural Gas
Oil
Coal
Steam
Other
Annual Water Savings (kgal)
City of Bozeman Energy Performance Contract Page 37
Annual Avoided NOx Emissions (Tons)
Annual Avoided SOx Emissions(Tons)
Annual Avoided CO2 Emissions (Tons)
ENERGY STAR Rating (if applicable)
EXHIBITS
EXHIBIT I Performance Bond
EXHIBIT II Labor and Material Payment Bond
EXHIBIT III (i) Certificate of Acceptance—Investment Grade Audit
Report
EXHIBIT III (ii) Certificate of Acceptance—Installed Equipment
EXHIBIT III (iii) Notice of Substantial Completion — Individual FIMs
EXHIBIT IV Equipment Warranties
EXHIBIT V Montana Prevailing Wage Rate Schedule
APPENDICES
APPENDIX A Investment Grade Audit Report
City of Bozeman Energy Performance Contract Page 38
CONTRACT ATTACHMENT I: Schedules, Exhibits, and Appendices
City of Bozeman - Energy Performance Contract
SCHEDULE A. ENERGY AND COST SAVINGS GUARANTEE
This Performance Contract guarantees the rate of energy consumption as specified in the
Investment Grade Audit Report which, when multiplied by the stipulated key factors as
agreed upon by McKinstry and City of Bozeman, and as specified in Section 3 of the
Investment Grade Audit Report, results in guaranteed cost-avoided savings inclusive of a
calculated annual utility escalation rate sufficient to pay for the conservation measures, in
accordance with 90-4-1107, MCA.
The guaranteed annual savings included in Table A below are based on the utility rates as
of October 1, 2014 (electricity), March 1, 2014 (gas), and September 1, 2013 (water and
sewer) as agreed upon with City of Bozeman, with a stipulated annual utility escalation rate
of 3.0%. Refer to Section 3 of the Investment Grade Audit Report dated July 9, 2014
Revision 1 October 16, 2014 for a detailed listing of the utility rates used in the calculation of
the annual energy cost avoidance dollars.
Table A: Guaranteed Energy Savings During Savings Measurement Period (Years 1
through 3)
Year Units of Energy Units of Energy Units of Energy Units of Energy Total Energy
Saved (kW) Saved (kWh) Saved (Therm) Saved, Water& Saved ($)
Sewer(kGal)
1 280.3 486,078 3,576 100 _ $49,645
2 280.3 486,078 3,576 100 $51,134
3 280.3 486,078 3,576 100 $52.668
Table A provides a summary of the total guaranteed utility cost avoided savings for the
three-year savings measurement period for the City of Bozeman-selected FIMs as
presented in the Investment Grade Audit Report dated July 9, 2014/Revision 1 October 16,
2014. The measurement and verification plan defined in the Investment Grade Audit Report
includes three (3) years of Measurement & Verification. Annual M&V Reports will be
generated and presented to City of Bozeman on an annual basis, and these reports will
demonstrate a reconciliation of guaranteed savings. In the event that City of Bozeman
makes material changes to installed FIMs, Article 15 Material Changes shall apply. For a
detailed review of the building and FIM specific M&V plans, refer to Section 3 of the
Investment Grade Audit Report dated July 9, 2014/Revision 1 October 16, 2014.
City of Bozeman - Energy Performance Contract
Mc instry
Far TA. Ifs Of roar Raffling
Table 3. 1 - Energy Savings Summary
Project City of Bozeman
Scenario FY15 Construction
Date 11/14/2014 FINAL REVISION FOR CONTRACT
Electricity Natural Gas Water Sewer Total**
Facility Improvement Facility kW kW($) kWh kWh($) Therm Therm($) kGal kGal($) kGal kGal($) CO •
Measures
BEA 04.01 Modify Beall Park 0.0 $0 0 $0 86 $75 0 $0 0 $0 $75
Thermostat Schedules
BEA 09.01 Exterior Beall Park 0.0 $0 6,282 $481 0 $0 0 $0 0 $0 $481
Lighting
BEA 13.01 Envelope Beall Park 0.0 $0 0 $0 228 $199 0 $0 0 $0 $199
Improvements
BOG 01.01 Boiler Bogert Pool 0.0 $0 0 $0 2,416 $2,110 0 $0 0 $0 $2,110
Commissioning
CTY 09.02 Daylight Bozeman City Hall 0.0 $0 3,145 $241 0 $0 0 $0 0 $0 $241
Controls
KRK 09.01 Lighting Kirk Park 0.0 $0 1,860 $202 0 $0 0 $0 0 $0 $202
Upgrade
LIB 09.02 Lighting Bozeman Public Library 0.0 $0 14,630 $1,120 0 $0 0 $0 0 $0 $1,120
Controls
LIB 18.01 Water Bozeman Public Library 0.0 $0 0 $0 265 $231 100 $223 100 $388 $842
Conservation
OM 04.01 Custom Overall Measures 0.0 $0 0 $0 0 $0 0 $0 0 $0 $0
Systems Training
OM 26.01 Green IT: PC Overall Measures 0.0 $0 65,408 $5,009 0 $0 0 $0 0 $0 $5,009
Power Mgmt
PKG 09.03 Lighting Bozeman Parking Garage 181.1 $1,678 129,439 $9,912 0 $0 0 $0 0 $0 $11,590
Upgrades Excl.Roof
PRO 25.02 Controls Professional Building 0.0 $0 0 $0 0 $0 0 $0 0 $0 $0
Sequence
SEN 03.01 Kitchen Bozeman Senior Center 0.0 $0 27,537 $2,109 0 $0 0 $0 0 $0 $2,109
Economizer
SEN 12.01 Hot Water Bozeman Senior Center 0.0
System Improvements $0 2,186 $167 964 $842 0 $0 0 $0 $1,009
SEN 13.01 Exterior Door Bozeman Senior Center 0.0 $0 0 $0 96 $84 0 $0 0 $0 $84
Seals
STR 09.01 LED Street Street Lighting 0.0 $0 164,184 $18,604 0 $0 0 $0 0 $0 $18,604
Lights
VEH 01.01 Boiler Vehicle Maintenance Buildin
Temperature Reset 9 0.0 $0 0 $0 143 $125 0 $0 0 $0 $125
WRF 09.01 Lighting Water Reclamation Facility 99.2 $919 71,406 $5,468 -621 -$542 0 $0 0 $0 $5,845
Improvements
280.3 $2,596 486,078 $43,314 3,576 $3,123 100 $223 100 $388 $49,645
*The savings shown in this table are less than the calculated savings unless a guarantee multiplier of 100%is shown.
** The guarantee is based on Key Performance Indicators shown in Table 3,2. Refer to Section 3 of the ESP for the method of converting Key Performance Indicators to dollars during the M&V period.
*** The guarantee is based on the aggregate savings for all FIMs,not on individual F1M savings.
Confidential and Proprietary Sheet 1 of 1
SCHEDULE B. BASELINE ENERGY CONSUMPTION
Refer to sections 3 and 5 of the Investment Grade Audit Report, dated July 9,
2014/Revision 1 October 16, 2014 for details regarding the methodology and supporting
documentation used to calculate the baseline for each FIM. These sections also include
unit consumption and current utility rates for each energy type.
City of Bozeman - Energy Performance Contract
Mc instry
for Th Ite Of Your Bufldlag
Table 3. 3 - Base Utility Rates
Project City of Bozeman
Scenario FY15 Construction
Date 11/14/2014 FINAL REVISION FOR CONTRACT
.•.• k.u- -- y • ••r -u• iii y y.• P. - 1- I•
-. I.
Kirk Park NorthWestern Energy LLC(Montana) E090 GS-1 2nd,Non-Demand Electricity $0.108797 kWh 3/1/2014
Beall Park NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Bozeman City Hall NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Bozeman Parking Garage NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Bozeman Public Library NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Bozeman Senior Center NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Overall Measures NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Vehicle Maintenance Building NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Water Reclamation Facility NorthWestern Energy LLC(Montana) E110 GS-1 Secondary,Demand Electricity $0.076578 kWh 10/1/2014
Bozeman Parking Garage NorthWestern Energy LLC(Montana) .10 GS-1 Secondary,Demand kilectricity Demand $9.263819 kW 10/1/2014
Water Reclamation Facility NorthWestern Energy LLC(Montana) _10 GS-1 Secondary,Demand k:lectricity Deman $9.263819 kW 10/1/2014
Street Lighting NorthWestern Energy LLC(Montana) Electric Lighting Electricity $0.113311 kWh 3/1/2014
Beall Park NorthWestern Energy LLC(Montana) General Service NG Natural Gas $0.873410 Therms 3/1/2014
Bogert Pool NorthWestern Energy LLC(Montana) General Service NG Natural Gas $0.873410 Therms 3/1/2014
Bozeman Public Library NorthWestern Energy LLC(Montana) General Service NG Natural Gas $0.873410 Therms 3/1/2014
Bozeman Senior Center NorthWestern Energy LLC(Montana) General Service NG Natural Gas $0.873410 Therms 3/1/2014
Vehicle Maintenance Building NorthWestern Energy LLC(Montana) General Service NG Natural Gas $0.873410 Therms 3/1/2014
Water Reclamation Facility NorthWestern Energy LLC(Montana) General Service NG Natural Gas $0.873410 Therms 3/1/2014
Bozeman Public Library City of Bozeman(MT) Sewer Sewer(kgal) $3.873000 kgal 9/1/2013
Bozeman Public Library City of Bozeman(MT) Water Water(kgal) $2.224000 kgal 9/1/2013
Sheet 1 of 1
SCHEDULE C. SAVINGS MEASUREMENT AND VERIFICATION PLAN;
METHODOLOGY TO ADJUST BASELINE
Savings Measurement and Verification Plan
Refer to Schedule A of this contract, as well as sections 3 and 5 of the Investment Grade
Audit Report, dated July 9, 2014/Revision 1 October 16, 2014, for details regarding energy
savings measurement, monitoring, and calculation procedures used to verify and compute
the savings performance of the installed equipment.
International Performance Measurement &Verification Protocol (IPMVP) Option A and Non-
Measured were agreed to be the M&V methodologies for the upcoming performance
contract with McKinstry. These Options were chosen based on overall utility savings value
and utility savings risk perception by the City of Bozeman, application of the Option to the
scope of the facility improvement measures (FIMs), and first cost.
The scope of work represented by the Investment Grade Audit Report and this performance
contract is best matched with Options A and Non-Measured for the following reasons:
• The performance of only the systems affected by the FIMs to be implemented are of
primary concern, due to the guaranteed savings of individual FIMs being insignificant
compared to the overall utility usage of facilities.
• Interactive effects between FIMs can be easily calculated.
• Isolation of the FIM from the rest of the facility and stipulation of key factors will avoid
possibly difficult and costly non-routine Baseline Adjustments for future changes to
the facility.
• The independent variables that affect energy use are not complex and excessively
difficult or expensive to monitor.
• The uncertainty created by stipulations is acceptable.
• The continued effectiveness of the FIM can be assessed by routine visual inspection
or via on-site access to control systems.
Overview of M&V Reporting and Guarantee Period
The language below defines the start date and duration of M&V Reporting that will be
provided for all FIMs, and the method of energy savings reconciliation during the savings
measurement period.
The Commencement Date for the project starts the timeline associated with required M&V
reporting. The FIMs are set forth in Schedule D Table 4.2 — FIM Summary. An initial Post-
Commissioning Report will be submitted within three (3) months of the Commencement
Date. Subsequent Annual M&V Reports i.e. M&V1, M&V2 and M&V3 will be submitted
within three (3) months of one, two, and three years after the Commencement Date.
Specific Post Commissioning Report tasks are further defined in section 3 of the Investment
Grade Audit Report dated July 9, 2014/Revision 1 October 16, 2014.
The Post Commissioning Report will contain a summary of the results of the Post-Retrofit
measurements taken and a revised calculation of energy savings based on these
measurements, which shall be compared to the energy and performance guarantee as
City of Bozeman - Energy Performance Contract
outlined in the Investment Grade Audit Report. The Post Commissioning Report is for
information purposes only and is not reconciled during the savings measurement period.
Annual M&V Report M&V1 will be a summary of the results of the First-Year measurements
taken, the three Quarterly Monitoring Reports submitted during year 1, and a revised
calculation of energy savings based on these measurements, which shall be compared to
the energy and performance guarantee as outlined in the Investment Grade Audit Report.
This revised calculation of energy savings will be reconciled in year 1.
For those FIMs that do not require M&V in Years 2 through 3 (Building Envelope, Water
Conservation, PC Power Management, etc. Reference Table 3.2), the calculated energy
savings for these FIMs will be stipulated to remain constant at year-1 calculated levels plus
the agreed upon utility escalation rate for years 2 and 3. Should there be a savings shortfall
in year-1, McKinstry shall make corrections to remedy the shortfall and provide a second
year of M&V, at their own expense, which shall be used to reconcile during Guarantee year
2. The year 2 calculated energy savings will then be stipulated to remain constant for the
remainder of the three-year savings measurement period for these FIMs.
For the Parking Garage Lighting Upgrades FIM, M&V shall include measuring circuit energy
for the duration of at least two weeks on at least 10% of the total lighting circuits. For the
LED Street Lights FIM, M&V shall include measuring circuit energy on at least 10% of the
total lighting circuits. M&V for these FIMs will be performed annually after the
Commencement Date for a minimum of three years, or until M&V results show three
consecutive years of verified annual utility savings at or above the amounts set forth in
Schedule D, Table 4.2 -- Facility Improvement Measurement (FIM) Summary, at no
additional cost to the City. Should annual M&V activities for these FIMs extend past Year 3,
the term of the Contract will be extended for additional one-year terms until three
consecutive years of verified annual utility savings is achieved.
The Savings Measurement Period is defined as the three (3) fiscal years immediately
following the Commencement Date. During year 1 of the Savings Measurement Period,
Annual M&V Report M&V1 will be reconciled against the guarantee of annual savings in
Schedule A, Table A (the "Annual Guarantee"). During year 2 of the Savings Measurement
Period, the results of Annual M&V Report M&V1 for Building Envelope, Water Conservation,
PC Power Management, plus the results of Annual M&V Report M&V2 for all other FIMs will
be combined and the aggregate results will be reconciled against the Annual Guarantee for
year 2. During year 3 of the Savings Measurement Period the results of Annual M&V Report
M&V1 for Building Envelope, Water Conservation, PC Power Management, plus the results
of Annual M&V Report M&V3 for all other FIMs will be combined and the aggregate results
will be reconciled against the Annual Guarantee for year 3.
For any given Annual M&V Report, excess savings from any one FIM can be used to cover
a shortfall in savings for any other FIM within any one Guarantee year.
As possible and determined by McKinstry, data necessary for Annual M&V reporting will be
monitored and accumulated via site control/monitoring systems. If data is not available from
control and monitoring systems, site loggers or specific point in time measurements will be
utilized. Associated with M&V responsibilities, necessary performance expectation-
City of Bozeman -Energy Performance Contract
monitoring and system conformance activities will be performed via remote access and
control/monitoring systems. As determined by McKinstry, site visits will be utilized in order
to perform testing that is not possible remotely via control/monitoring systems.
All data will be accumulated to McKinstry's data base for archiving, calculation, and
reporting functionality. City of Bozeman will allow the use of their Internet and digital control
system(s) and network(s) for the purposes of transporting data and the City of Bozeman
internal IT resources will assist McKinstry with the setup of this interface all at no cost to
McKinstry.
Methodology to Adjust Baseline
McKinstry and the City of Bozeman acknowledge that material changes such as
unanticipated changes in facility use, occupancy, schedule and/or utility will affect the
estimated annual energy savings. If and when these changes occur, the same methodology
described in Schedule A used in calculating the original baseline for the portion of the
Premises affected by the change shall be used to re-establish the new baseline. The
difference in the two baselines shall be used to adjust the overall estimated annual savings.
Performance Assurance Plan Outline
Following this page is the Performance Assurance Plan Outline from the IGAR report with
revisions dated October 16, 2014.
City of Bozeman - Energy Performance Contract
SCHEDULE D. FINAL PROJECT COST & PROJECT CASH FLOW ANALYSIS
The Tables for this project are attached following this page for reference:
• Schedule D: Table 4.1 - Budget Summary Report
• Table 4.2 - FIM Summary Report
• Table 4.3 — Cash Flow for Financed LED Street Lights
City of Bozeman - Energy Performance Contract
Mc instry
For Th lie Of Your Building
Table 4.2 - Facility Improvement Measure (FIM) Summary
Project City of Bozeman
Scenario FY15 Construction FINAL REVISION FOR CONTRACT
Date ###########
Annual
Annual Utility Simple Payback Potential Net Customer Cost(with Simple Payback(,SPB)
Facility Improvement Measures GMAX Savings Operational (SPB) Incentives*** Incentives) (with Incentives) •
Savings
BEA 04.01 Modify Thermostat Schedules $483 $75 $0 6.5 $0 $483 6.5
BEA 09.01 Exterior Lighting $5,662 $481 $92 10.8 $254 $5,408 10.3
BEA 13.01 Envelope Improvements $3,515 $199 $0 17.7 $0 $3,515 17.7
BOG 01.01 Boiler Commissioning $2,047 $2,110 $1,000 0.0 $0 $2,047 0.0
CTY 09.02 Daylight Controls $1,015 $241 $0 4.2 $0 $1,015 4.2
KRK 09.01 Lighting Upgrade $1,588 $202 $92 5.6 $100 $1,488 5.1
LIB 09.02 Lighting Controls $2,144 $1,120 $0 1,9 $0 $2,144 1.9
LIB 18.01 Water Conservation $4,460 $842 $1,000 0.0 $0 $4,460 0.0
OM 04.01 Custom Systems Training $7,840 $0 $0 0.0 $0 $7,840 0.0
OM 26.01 Green IT: PC Power Mgmt $12,230 $5,009 $0 2.4 $2,550 $9,680 1.9
PKG 09.03 Lighting Upgrades Excl.Roof $182,506 $11,590 $5,627 13.3 $0 $182,506 13.3
PRO 25.02 Controls Sequence $7,552 $0 $0 0.0 $0 $7,552 0.0
SEN 03.01 Kitchen Economizer $13,251 $2,109 $0 6.3 $0 $13,251 6.3
SEN 12.01 Hot Water System Improvements $7,486 $1,009 $0 7.4 $0 $7,486 7.4
SEN 13.01 Exterior Door Seals $1,062 $84 $0 12.6 $0 $1,062 12.6
STR 09.01 LED Street Lights $222,057 $18,604 $1,009 11.4 $0 $222,057 11.4
VEH 01.01 Boiler Temperature Reset $630 $125 $0 5.0 $0 $630 5.0
WRF 09.01 Lighting Improvements $18,480 $5,845 $282 2.9 $979 $17,501 2.8
$494,008 $49,645 $9,103 9.0 $3,883 $490,125 9.0
* Since design cost,audit cost,etc.are distributed among the FIM5,the total project cost will not go up or down by exactly the amounts shown here if a FIM or FIMs are dropped.
** For non recurring operational savings,the values are averaged over the 30 year length of this analysis.
*** Incentives are contingent on final approval and are not guaranteed. Funds are shown for reference only.
Confidential and Proprietary
Sheet 1 of 1
SCHEDULE E. - NOT USED
City of Bozeman - Energy Performance Contract
SCHEDULE F. COMPENSATION TO CONTRACTOR FOR ANNUAL SERVICES
No Annual Services are included in this phase of work.
City of Bozeman - Energy Performance Contract
SCHEDULE G. — NOT USED
City of Bozeman - Energy Performance Contract
SCHEDULE H. SCOPE OF WORK
Building Facility Improvement Measure
Beall Park BEA 04.01 Modify Thermostat Schedules
Beall Park BEA 09.01 Exterior Lighting
Beall Park BEA 13.01 Envelope Improvements
Bogert Pool BOG 01.01 Boiler Commissioning
City Hall CTY 09.02 Daylight Controls
Kirk Park KRK 09.01 Lighting Upgrade
Bozeman Public Library LIB 09.02 Lighting Controls
Bozeman Public Library LIB 18.01 Water Conservation
Overall OM 04.01 Custom Systems Training
Overall OM 26.01 PC Power Management
Parking Garage PKG 09.03 Lighting Upgrades Excl. Roof
Professional Building PRO 25.02 Controls Sequence
Senior Center SEN 03.01 Kitchen Economizer
Senior Center SEN 12.01 Hot Water System Improvements
Senior Center SEN 13.01 Exterior Door Seals
Streets STR 09.01 LED Street Lights
Vehicle Maintenance VEH 01.01 Boiler Temperature Reset
Water Reclamation Facility WRF 09.01 Lighting Improvements
City of Bozeman - Energy Performance Contract
SCHEDULE 1. CONSTRUCTION AND EQUIPMENT INSTALLATION SCHEDULE
The project design and construction schedule for this project is attached following this page
for reference:
City of Bozeman - Energy Performance Contract
SCHEDULE J. SYSTEMS START-UP AND COMMISSIONING; OPERATING
PARAMETERS OF INSTALLED EQUIPMENT
To be provided following contract execution in the form of Operation and Maintenance
Manuals and Commissioning reports.
City of Bozeman - Energy Performance Contract
SCHEDULE K. STANDARDS OF COMFORT
Refer to section 3 of the Investment Grade Audit Report dated July 9, 2014/Revision 1
October 16, 2014 for details regarding heating, cooling, lighting, ventillation and other
standards of comfort applicable to this project.
City of Bozeman - Energy Performance Contract
SCHEDULE L. CONTRACTOR'S TRAINING RESPONSIBILITIES
McKinstry will provide digital controls systems training per building where new digital
controls equipment is to be installed. McKinstry will also cause to be provided additional
training provided by subcontractors as it relates to their specific mechanical equipment and
systems, as identified during the RFP process for each FIM.
The City of Bozeman has the option to negotiate additional training and service support at
their discretion.
Table L-1: Matrix of City of Bozeman Training to Be Conducted by Contractor
FIM Type Training Timing Training Duration and Notes
Lighting Training to be completed in Revised sequences of
conjunction with the final operation for the lighting
punchlist/acceptance walk through controls system at the
of each building. Library will be reviewed in
detail with Facilities.
PC Power Initial training to be provided during Follow up conference call
Management deployment of the software. for City of Bozeman IT
Training on the back-end will be personnel approximately 6
hands-on with documentation. months after the
Training for the end users can be Commencement Date.
done through videos, classroom or
documentation.
Mechanical at Senior Initial training to be provided during Approx. 1 hour classroom
Center the start-up phase, plus a follow up session within 30 calendar
for City of Bozeman personnel days of the
approximately 6 months after the Commencement Date,
Commencement Date. plus an additional 1 hour at
6 months after
Commencement Date.
Envelope, Water, Training to be completed in
Boiler Reset, Tstats conjunction with the final
punchlist/acceptance walk through
of each building/FIM.
City of Bozeman - Energy Performance Contract
SCHEDULE M. — NOT USED
City of Bozeman - Energy Performance Contract
SCHEDULE N. — NOT USED
City of Bozeman - Energy Performance Contract
SCHEDULE 0. FACILITY MAINTENANCE CHECKLIST
To be provided following contract execution and design completion.
City of Bozeman - Energy Performance Contract
SCHEDULE P. - NOT USED
City of Bozeman - Energy Performance Contract
SCHEDULE Q. — NOT USED
City of Bozeman - Energy Performance Contract
SCHEDULE R. PRE-EXISTING SERVICE CONTRACTS
City of Bozeman - Energy Performance Contract
SCHEDULE S. CURRENT AND KNOWN CAPITAL PROJECTS AT FACILITY
City of Bozeman - Energy Performance Contract
EXHIBITS
EXHIBIT I NOT USED
EXHIBIT II NOT USED
EXHIBIT III (i) Certificate of Acceptance—Investment Grade Audit Report
EXHIBIT III (ii) Certificate of Acceptance—Installed Equipment
EXHIBIT III (iii) Notice of Substantial Completion—Individual FIMs
EXHIBIT IV NOT USED
EXHIBIT V Montana Prevailing Wage Rate Schedule
EXHIBIT VI NOT USED
APPENDICES
APPENDIX A Investment Grade Audit Report July 9, 2014/Revision 1
October 16, 2014
City of Bozeman - Energy Performance Contract
EXHIBIT III (i): Certificate of Acceptance — Investment Grade Audit
City of Bozeman - Energy Performance Contract
Acceptance Letter — Exhibit III
Notice of Acceptance of Investment Grade Audit Report
Notice is hereby given that City of Bozeman accepts the McKinstry Investment Grade Audit Report (IGAR)
dated July 9, 2014.
Agency Name City of Bozeman
Agency Representative ' .
Date /I y��y
ESCO Name McKinstry
ESCO Representative
Date ` i /4--
When completely executed, this form is to be sent by certified mail to McKinstry by the City of Bozeman.
Please mail to this address:
Karen Hedglin
McKinstry
1982 Stadium Drive, Unit #1
Bozeman, Montana 59715
Mc t y ACCEPTANCE LETTER-EXHIBIT III
CITY OF BOZEMAN I INVESTMENT GRADE AUDIT REPORT
sx r .1Y M R..AM,/
EXHIBIT III (ii): Certificate of Acceptance — Installed Equipment
Covered under Substantial Completion and Final Acceptance by the City of
Bozeman.
City of Bozeman - Energy Performance Contract
EXHIBIT III (iii): Notice of Substantial Completion — Individual FIMs
City of Bozeman - Energy Performance Contract
"THE
._.%. 59�cn
, STATE OF MONTANA
F >._�3`j DEPARTMENT OF ADMINISTRATION
ARCHITECTURE AND ENGINEERING DIVISION
`� A 1520 East Sixth Avenue•P.O.Box 200103•Helena M"1'59620-0103
Phone:406 444-3104•Fax:406 444-3399
CERTIFICATE OF SUBSTANTIAL COMPLETION
Project Name: A&E#:
Project Address: Date:
Project Location:
Agency:
Address:
Contact Name:
Contact#:
To: MONTANA DEPARTMENT OF ADMINISTRATION
ARCHITECTURE AND ENGINEERING DIVISION
1529 E.SIXTH AVENUE, P.O. BOX 200103
HELENA MT 59620-0103
Architect/Engineer:
Contractor: Contract Date:
Contract Amount:
PROJECT OR DESIGNATED PORTION SHALL INCLUDE:
The work performed under this Contract has been reviewed and found to be substantially complete. The Date of Substantial
Completion of the Project or portion thereof designated above, which is also the date of commencement of applicable warranties
required by the Contract Documents, except as stated below is hereby established as:
BASIC PROJECT INFORMATION NEW REMODEL/RENOVATION
(required by Risk&Tort Defense Division)
Total Square Footage
General Construction Material
(e.g.masonry,metal panel,wood,etc.)
Total Construction Cost
Fire Sprinklers Installed(yes/no)
Estimated Date of Occupancy
(if different from date of Substantial)
Building Usage:
Additional Comments:
Definition of Date of Substantial Completion
The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect/Engineer when
construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or
designated portion thereof for the use for which it is intended, as expressed in the Contract Documents.
C:\Users\nmeyer\AppData\Local\Microsoft\Windows\Temporary Internet
Files\Content.Outlook1X596Q1TF\Form_107_Certificate_of_Substantial_Completion(2).doc FORM 107
Last form revision(12-01-2006) Page 1 of 2
A list of items to be completed or corrected, prepared by the Contractor and verified and amended by the Architect/Engineer, is
attached hereto. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all the Work
in accordance with the Contract Documents. The warranty period is defined as commencing with Substantial Completion (or with each
Substantial Completion if there is more than one) of the Project, or any portion thereof, and continuing for one (1) calendar year from
the date of Final Acceptance of the entire project unless otherwise modified in writing as part of the Substantial Completion or Final
Acceptance.
Architect/Engineer By Date
The Contractor will complete or correct the Work on the list of items attached hereto within days from the above Date of
Substantial Completion.
Contractor By Date
The Owner accepts the Work or designated portion thereof as substantially complete and will assume full possession thereof at
(time)on (date).
State of Montana Department of Administration,
Architecture and Engineering Division
Owner By Date
The responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities, damage to the Work and
insurance will be as follows (use attachments as necessary):
C:\Users\nmeyer\AppData\Local\Microsoft\Windows\Temporary Internet
Files\Content.Outlook\X596Q1TF\Form_107_Certificate_of Substantial_Completion(2).doc FORM 107
Last form revision(12-01-2006) Page 2 of 2
EXHIBIT V: Montana Prevailing Wage Rate Schedule
City of Bozeman - Energy Performance Contract
MONTANA
PREVAILING WAGE RATES FOR BUILDING CONSTRUCTION SERVICES 2014
Effective: July 11 , 2014
Steve Bullock, Governor
State of Montana
Pam Bucy, Commissioner
Department of Labor and Industry
To obtain copies of prevailing wage rate schedules, or for information relating to public works projects and payment of
prevailing wage rates, visit ERD at www.mtwagehourbopa.com or contact:
Employment Relations Division
Montana Department of Labor and Industry
P. O. Box 201503
Helena, MT 59620-1503
Phone 406-444-5600
TDD 406-444-5549
The Labor Standards Bureau welcomes questions, comments and suggestions from the public. In addition,we'll
do our best to provide information in an accessible format, upon request, in compliance with the Americans with
Disabilities Act.
MONTANA PREVAILING WAGE REQUIREMENTS
The Commissioner of the Department of Labor and Industry, in accordance with Sections 18-2-401 and 18-2-402 of the
Montana Code Annotated (MCA), has determined the standard prevailing rate of wages for the occupations listed in this
publication.
The wages specified herein control the prevailing rate of wages for the purposes of 18-2-401, et seq., MCA. It is required
that each employer pay(as a minimum)the rate of wages, including fringe benefits, travel allowance, zone pay and per
diem applicable to the district in which the work is being performed as provided in the attached wage determinations.
All Montana Prevailing Wage Rates are available on the internet at www.mtwagehourbopa.com or by contacting the
Labor Standards Bureau at(406)444-5600 or TDD (406)444-5549.
In addition, this publication provides general information concerning compliance with Montana's Prevailing Wage Law and
the payment of prevailing wages. For detailed compliance information relating to public works contracts and payment of
prevailing wage rates, please consult the regulations on the internet at www.mtwagehourbopa.com or contact the Labor
Standards Bureau at(406) 444-5600 or TDD (406) 444-5549.
PAM BUCY
Commissioner
Department of Labor and Industry
State of Montana
TABLE OF CONTENTS
MONTANA PREVAILING WAGE REQUIREMENTS:
A. Date of Publication ' 3
B. Definition of Building Construction 3
C. Definition of Public Works Contract 3
O. Prevailing Wage Schedule 3
E. Rates to use for Projects 3
F. Wage Rate Adjustments for Multiyear Contracts 3
G. Fringe Benefits 4
H. Prevailing Wage Districts 4
I. Zone Pay 5
J. Computing Travel Benefits 5
K Per Diem 5
L. Apprentices 5
M. Posting Notice of Prevailing Wages 5
N. Employment Preference 5
0. Building Construction Occupations Website 5
P. Welder Rates 5
Q. Foreman Rates 5
WAGE RATES:
BOILERMAKERS 6
BR|CK, BLOCK,AND STONE MASONS 6
CARPENTERS 6
CEMENT MASONS 6
CONSTRUCTION EQUIPMENT OPERATORS
OPERATORS GROUP 1 7
OPERATORS GROUP 2 7
OPERATORS GROUP 3 8
OPERATORS GROUP 4 8
OPERATORS GROUP 6 8
OPERATORS GROUP 6 9
OPERATORS GROUP 7 9
CONSTRUCTION LABORERS
LABORERS GROUP 1 9
LABORERS GROUP 10
LABORERS GROUP 3 10
LABORERSGROUP4 11
DRYWALL APPLICATORS 11
ELECTRICIANS: INCLUDING BUILDING AUTOMATION CONTROL 11
ELEVATOR CONSTRUCTORS 12
FLOOR LAYERS 12
GLAZIERS 12
HEATING AND AIR CONDITIONING 12
INSULATION WORKERS-MECHANICAL (HEAT AND FROST) 13
IRONWORKERS-STRUCTURAL STEEL AND REBAR PLACERS 13
MILLWRIGHTS 13
PAINTERS: INCLUDING PAPERHANGER 13
PILE BUCKS 14
PLASTERERS 14
PLUK8BERQ, PIPEFITTERS, AND STEAMFITTERS 14
ROOFERS 15
SHEET METAL WORKERS 15
SPRINKLER FITTERS 15
TAPERS 15
TEAMSTERS GROUP 2 16
TELECOMMUNICATIONS EQUIPMENT INSTALLERS 16
TILE AND MARBLE SETTERS 16
2
A.Date of Publication July 11,2014
B. Definition of Building Construction
For the purposes of Prevailing Wage, the Commissioner of Labor and Industry has determined that building construction
occupations are defined to be those performed by a person engaged in a recognized trade or craft,or any skilled, semi-
skilled, or unskilled manual labor related to the construction,alteration,or repair of a public building or facility, and does
not include engineering, superintendence, management,office or clerical work.
The Administrative Rules of Montana(ARM) 24.17.501(2)—2(a), Public Works Contracts for Construction Services
Subject to Prevailing Wage Rates,states: "Building construction projects generally are the constructions of sheltered
enclosures with walk-in access for housing persons, machinery, equipment, or supplies. It includes all construction of
such structures, incidental installation of utilities and equipment, both above and below grade level, as well as incidental
grading, utilities and paving.
Examples of building construction include, but are not limited to, alterations and additions to buildings, apartment
buildings (5 stories and above), arenas (closed), auditoriums, automobile parking garages, banks and financial buildings,
barracks, churches, city halls, civic centers, commercial buildings, court houses, detention facilities, dormitories,farm
buildings,fire stations, hospitals, hotels, industrial buildings, institutional buildings, libraries, mausoleums, motels,
museums, nursing and convalescent facilities, office buildings, out-patient clinics,passenger and freight terminal
buildings,police stations,post offices,power plaints,prefabricated buildings, remodeling buildings, renovating buildings,
repairing buildings, restaurants, schools, service stations, shopping centers, stores, subway stations, theaters,
warehouses, water and sewage treatment plants (buildings only), etc. "
C.Definition of Public Works Contract
Section 18-2-401(11)(a), MCA defines"public works contract"as "...a contract for construction services let by the state,
county, municipality, school district, or political subdivision orfor nonconstruction services let by the state, county,
municipality, or political subdivision in which the total cost of the contract is in excess of$25,000... "
D.Prevailing Wage Schedule
This publication covers only Building Construction occupations and rates. These rates will remain in effect until
superseded by a more current publication. Current prevailing wage rate schedules for Heavy Construction, Highway
Construction,and Nonconstruction Services occupations can be found on the interne at www.mtwagehourbopa.com or
by contacting the Labor Standards Bureau at(406)444-5600 or TDD (406)444-5549.
E.Rates to use for Projects
Rates to be used on a public works project are those that are in effect at the time the project and bid specifications are
advertised.
F.Wage Rate Adjustments for Multiyear Contracts
Section 18-2-417, MCA states:
"(1)Any public works contract that by the terms of the original contract calls for more than 30 months to fully perform
must include a provision to adjust, as provided in subsection (2), the standard prevailing rate of wages to be paid to the
workers performing the contract.
(2) The standard prevailing rate of wages paid to workers under a contract subject to this section must be adjusted 12
months after the date of the award of the public works contract. The amount of the adjustment must he a 3% increase. The
adjustment must be made and applied every 12 months for the term of the contract.
(3)Any increase in the standard rate of prevailing wages for workers under this section is the sole responsibility of the
contractor and any subcontractors and not the contracting agency.
3
G. Fringe Benefits
Section 18-2-412, MCA states:
"(1) To fulfill the obligation...a contractor or subcontractor may:
(a)pay the amount of fringe benefits and the basic hourly rate ofpay that is part qf the standard prevailing rate of wages
directly to the worker or employee in cash;
(h) make an irrevocable contribution to a trustee or a third person pursuant to a fringe benefit fund,plan, or program that
meets the requirements of the Employee Retirement Income Security Act of 1974 or that is a bona fide program approved
by the U S. department of labor:or
(c) make payments using any combination of methods set forth in subsections (1)(a) and(1)(b)so that the aggregate of
payments and contributions is not less than the standard prevailing rate ofwages, including fringe benefits and travel
allowances, applicable to the district for the particular type of work being performed.
(2) The fringe benefit fund,plan, or program described in subsection (1)(b) must provide benefits to workers or employees
for health care,pensions on retirement or death, life insurance, disability and sickness insurance, or bonat de programs
that meet the requirements of the Employee Retirement Income Security Act of 1974 or that are approved by the U S.
department of labor. "
Fringe benefits are paid for all hours worked(straight time and overtime hours). However,fringe benefits are not to be
considered a part of the hourly rate of pay for calculating overtime, unless there is a collectively bargained agreement in
effect that specifies otherwise.
H.Prevailing Wage Districts
Montana counties are aggregated into 4 districts for the purpose of prevailing wage. The prevailing wage districts are
composed of the following counties:
Montana Prevailing Wage Districts
Glacier Darnels Sheridan
Flathead i. Libert
Valley
Blame
PhOhps Roosevelt
Sanders
Chouleau
Richland
McCone
neral
Cascade Fergus
tom Garfield Davison
Pelydeu
lir
Missoula Clark
Judith
Basin A
Meagher
Wheatland Musselshell Rosebud Farm
Golde Treasure
Deer Jefferson Valley Custer
Ravalli Lodge
Silver Yellowstone
Bow Sweet
Grass Stillwater
Big Carter
Horn Powder
Beaverhead Madison River
4
I.Zone Pay
Zone pay is not travel pay. It is an additional amount added to the base pay, which then becomes the new base wage rate
to be paid for all hours worked on the project. Zone pay, for the purposes of public works projects, shall be determined by
measuring the road miles one direction over the shortest practical maintained route from the nearest county courthouse to
the center of the job from the following listed cities:
❖ Billings,Bozeman,Butte,Glasgow,Great Falls,Helena,Kalispell,Miles City,and Missoula.
J.Computing Travel Benefits
Travel pay,for the purposes of public works projects,shall be paid for travel both to and from the job site, except those
with special provisions listed under the classification. The rate is determined by measuring the road miles one direction
over the shortest practical maintained route from the nearest county courthouse or the employee's home,whichever is
closer,to the center of the job from the following listed cities:
C. Billings,Bozeman,Butte,Glasgow, Great Falls,Helena,Kalispell,Miles City,and Missoula.
K.Per Diem
Per Diem typically covers the costs associated with board and lodging expenses and are paid when an employee is
required to work at a location outside the daily commuting distance and is required to stay overnight or longer.
L.Apprentices
Wage rates for apprentices registered in approved federal or state apprenticeship programs are contained in those
programs. Additionally, section 18-2-416(2),MCA states, "...The full amount of any applicable fringe benefits must he
paid to the apprentice while the apprentice is working on the public works contract. " Apprentices not registered in
approved federal or state apprenticeship programs will be paid the appropriate journey level prevailing wage rate when
working on a public works contract.
M. Posting Notice of Prevailing Wages
Section 18-2-406, MCA provides that contractors,subcontractors and employers who are "...performing work or
providing construction services under public works contracts, as provided in this pail, shall post in a prominent and
accessible site on the project or staging area, not later than the first day of work and continuing for the entire duration of
the project, a legible statement of all wages and fringe benefits to he paid to the employees."
N.Employment Preference
Sections 18-2-403 and 18-2-409,MCA requires contractors to give preference to the employment of bona fide Montana
residents in the performance of work on public works contracts.
O.Building Construction Occupations Website
You can find definitions for these occupations on the following Bureau of Labor Statistics website:
http://www.bis.gov/oes/current/oes_stru.htm
P.Welder Rates
Welders receive the rate prescribed for the craft performing an operation to which welding is incidental.
Q.Foreman Rates
Rates are no longer set for foremen. However, if a foreman performs journey level work,the foreman must be paid at
least the journey level rate.
5
WAGE RATES
BOILERMAKERS
Wage Benefit Travel:
District 1 $30.72 $29.45 All Districts
District 2 $30.00 $29.45 0-120 mi. free zone
District 3 $30.00 $29.45 >120 mi. federal mileage rate/mi. in effect when travel
District 4 $30.00 $29.45 occurs.
Special Provision: Travel is paid only at the beginning
and end of the job.
Per Diem:
All Districts
0-70 mi. free zone
>70-120 mi. $55.00/day
>120 mi. $70.00/day
BRICK, BLOCK, AND STONE MASONS
Wage Benefit Travel:
District 1 $25.74 $12.47 All Districts
District 2 $25.74 $12.47 0-45 mi. free zone
District 3 $25.56 $12.11 >45-60 mi. $25.00/day
District 4 $25.10 $12.47 >60-90 mi. $55.00/day
>90 mi. $65.00/day
CARPENTERS
Wage Benefit Zone Pay:
District 1 $21.09 $ 9.54 All Districts
District 2 $21.00 $11.86 0-30 mi. free zone
District 3 $21.00 $11.57 >30-50 mi. base pay+ $4.00/hr.
District 4 $19.50 $11.57 >50 mi. base pay+ $6.00/hr.
Duties Include:
Install roll and batt insulation.
CEMENT MASONS
Wage Benefit Zone Pay:
District 1 $23.55 $8.16 All Districts
District 2 $20.79 $8.31 0-30 mi. free zone
District 3 $19.25 $8.16 >30-60 mi. base pay+ $2.95/hr.
District 4 $19.35 $8.16 >60 mi. base pay + $4.75/hr.
Duties Include:
Smooth and finish surfaces of poured concrete, such as
floors,walks, sidewalks, or curbs. Align forms for
sidewalks, curbs, or gutters.
6
CONSTRUCTION EQUIPMENT OPERATORS GROUP 1
Wage Benefit Zone Pay:
District 1 $24.07 $11.40 All Districts
District 2 $24.07 $11.40 0-30 mi. free zone
District 3 $24.07 $11.40 >30-60 mi. base pay + $3.50/hr.
District 4 $24.07 $11.40 >60 mi. base pay+ $5.50/hr.
This group includes but is not limited to:
Air Compressor; Auto Fine Grader; Belt Finishing; Boring
Machine (Small); Cement Silo; Crane, A-Frame Truck
Crane; Crusher Conveyor; DW-10, 15, and 20 Tractor
Roller; Farm Tractor; Forklift; Form Grader; Front-End
Loader, under 1 cu. yd; Oiler, Heavy Duty Drills; Herman
Nelson Heater; Mucking Machine; Oiler, All Except
Cranes/Shovels; Pumpman.
CONSTRUCTION EQUIPMENT OPERATORS GROUP 2
Wage Benefit Zone Pay:
District 1 $25.54 $11.40 All Districts
District 2 $25.54 $11.40 0-30 mi. free zone
District 3 $25.54 $11.40 >30-60 mi. base pay + $3.50/hr.
District 4 $25.54 $11.40 >60 mi. base pay+ $5.50/hr.
This group includes but is not limited to:
Air Doctor; Backhoe\Excavator\Shovel, up to and incl. 3
cu. yds; Bit Grinder; Bitunimous Paving Travel Plant;
Boring Machine, Large; Broom, Self-Propelled; Concrete
Travel Batcher; Concrete Float&Spreader; Concrete
Bucket Dispatcher; Concrete Finish Machine; Concrete
Conveyor; Distributor; Dozer, Rubber-Tired, Push, &
Side Boom; Elevating Grader\Gradall; Field Equipment
Serviceman; Front-End Loader, 1 cu. yd up to and incl. 5
cu. yds; Grade Setter; Heavy Duty Drills, All Types;
Hoist\Tugger, All; Hydralift Forklifts &Similar; Industrial
Locomotive; Motor Patrol (except finish); Mountain
Skidder; Oiler, Cranes\Shovels; Pavement Breaker,
EMSCO; Power Saw, Self-Propelled; Pugmill;
Pumperete\Grout Machine; Punch Truck; Roller, other
than Asphalt; Roller, Sheepsfoot(Self-Propelled); Roller,
25 tons and over; Ross Carrier; Rotomill, under 6 ft;
Trenching Machine; Washing/Screening Plant.
7
CONSTRUCTION EQUIPMENT OPERATORS GROUP 3
Wage Benefit Zone Pay:
District 1 $25.95 $11.40 All Districts
District 2 $25.95 $11.40 0-30 mi. free zone
District 3 $25.95 $11.40 >30-60 mi. base pay + $3.50/hr.
District 4 $25.95 $11.40 >60 mi. base pay + $5,50/hr.
This group includes but is not limited to:
Asphalt Paving Machine; Asphalt Screed;
BackhoelExcavator\Shovel, over 3 cu. yds; Cableway
Highline; Concrete Batch Plant; Concrete Curing
Machine; Concrete Pump; Cranes, Creter; Cranes,
Electric Overhead; Cranes, 24 tons and under; Curb
Machine\Slip Form Paver; Finish Dozer; Front-End
Loader, over 5 cu. yds; Mechanic\Welder; Pioneer
Dozer; Roller Asphalt(Breakdown & Finish); Rotomill,
over 6 ft; Scraper, Single, Twin, or Pulling Belly-Dump;
YO-YO Cat.
CONSTRUCTION EQUIPMENT OPERATORS GROUP 4
Wage Benefit Zone Pay:
District 1 $26.95 $11.40 All Districts
District 2 $26.95 $11.40 0-30 mi. free zone
District 3 $26.95 $11.40 >30-60 mi. base pay + $3.50/hr.
District 4 $26.95 $11.40 >60 mi. base pay+ $5.50/hr.
This group includes but is not limited to:
Asphalt\Hot Plant Operator; Cranes, 25 tons up to and
incl. 44 tons; Crusher Operator; Finish Motor Patrol;
Finish Scraper.
CONSTRUCTION EQUIPMENT OPERATORS GROUP 5
Wage Benefit Zone Pay:
District 1 $27.95 $11.40 All Districts
District 2 $27.95 $11.40 0-30 mi. free zone
District 3 $27.95 $11.40 >30-60 mi. base pay +$3.50/hr.
District 4 $27.95 $11.40 >60 mi. base pay + $5.50/hr.
This group includes but is not limited to:
Cranes, 45 tons up to and incl. 74 tons.
8
CONSTRUCTION EQUIPMENT OPERATORS GROUP 6
Wage Benefit Zone Pay:
District 1 $28.95 $11.40 All Districts
District 2 $28.95 $11.40 0-30 mi. free zone
District 3 $28.95 $11.40 >30-60 mi. base pay + $3.50/hr.
District 4 $28.95 $11.40 >60 mi. base pay + $5.50/hr.
This group includes but is not limited to:
Cranes, 75 tons up to and incl. 149 tons; Cranes,
Whirley (All).
CONSTRUCTION EQUIPMENT OPERATORS GROUP 7
Wage Benefit Zone Pay:
District 1 $29.95 $11.40 All Districts
District 2 $29.95 $11.40 0-30 mi. free zone
District 3 $29.95 $11.40 >30-60 mi. base pay+ $3.50/hr.
District 4 $29.95 $11.40 >60 mi. base pay+ $5.50/hr.
This group includes but is not limited to:
Cranes, 150 tons up to and incl. 250 tons; Cranes, over
250 tons-add $1.00 for every 100 tons over 250 tons;
Crane, Tower (All); Crane Stiff-Leg or Derrick; Helicopter
Hoist.
CONSTRUCTION LABORERS GROUP 1/FLAG PERSON FOR TRAFFIC CONTROL
Wage Benefit Zone Pay:
District 1 $19.08 $7.42 District 1
District 2 $15.41 $8.65 0-30 mi. free zone
District 3 $18.00 $7.17 >30-60 mi. base pay+ $1.50/hr.
District 4 $18.00 $7.17 >60 mi. base pay +$3.90/hr.
District 2
0-15 mi. free zone
>15-30 mi. base pay + $0.65/hr.
>30-50 mi. base pay + $0.75/hr.
>50 mi. base pay+ $1.25/hr.
Districts 3 & 4
0-15 mi. free zone
>15-30 mi. base pay + $0.65/hr.
>30-50 mi. base pay + $0.85/hr.
>50 mi. base pay + $1.25/hr.
9
CONSTRUCTION LABORERS GROUP 2
Wage Benefit Zone Pay:
District 1 $19.07 $6.69 District 1
District 2 $18.48 $6.90 0-30 mi. free zone
District 3 $16.44 $6.17 >30-60 mi. base pay + $1.50/hr.
District 4 $18.04 $5.01 >60 mi. base pay + $3.90/hr.
This group includes but is not limited to: District 2
General Labor; Asbestos Removal; Burning Bar; Bucket 0-15 mi. free zone
Man; Carpenter Tender; Caisson Worker; Cement >15-30 mi. base pay + $0.65/hr.
Mason Tender; Cement Handler(dry); Chuck Tender; >30-50 mi. base pay + $0.75/hr.
Choker Setter; Concrete Worker; Curb Machine-lay >50 mi. base pay+ $1.25/hr.
Down; Crusher and Batch Worker; Heater Tender;
Fence Erector; Landscape Laborer; Landscaper; Lawn Districts 3&4
Sprinkler Installer; Pipe Wrapper; Pot Tender; 0-15 mi. free zone
Powderman Tender; Rail and Truck Loaders and >15-30 mi. base pay + $0.65/hr.
Unloaders; Riprapper; Sign Erection; Guardrail and >30-50 mi. base pay + $0.85/hr.
Jersey Rail; Spike Driver; Stake Jumper; Signalman; Tail >50 mi. base pay + $1.25/hr.
Hoseman; Tool Checker and Houseman and Traffic
Control Worker.
CONSTRUCTION LABORERS GROUP 3
Wage Benefit Zone Pay:
District 1 $19.48 $7.42 District 1
District 2 $18.33 $8.65 0-30 mi. free zone
District 3 $18.20 $7.17 >30-60 mi. base pay + $1.50/hr.
District 4 $18.20 $7.17 >60 mi. base pay + $3.90/hr.
This group includes but is not limited to: District 2
Concrete Vibrator; Dumpman (Grademan); Equipment 0-15 mi. free zone
Handler; Geotextile and Liners; High-Pressure >15-30 mi. base pay + $0.65/hr.
Nozzleman; Jackhammer(Pavement Breaker) Non- >30-50 mi. base pay + $0.75/hr.
Riding Rollers; Pipelayer; Posthole Digger (Power); >50 mi. base pay + $1.25/hr.
Power Driven Wheelbarrow; Rigger; Sandblaster; Sod
Cutter-Power and Tamper. Districts 3& 4
0-15 mi. free zone
>15-30 mi. base pay + $0.65/hr.
>30-50 mi. base pay + $0.85/hr.
>50 mi. base pay+ $1.25/hr.
10
CONSTRUCTION LABORERS GROUP 4
Wage Benefit Zone Pay:
District 1 $18.15 $7.62 District 1
District 2 $19.05 $7.09 0-30 mi. free zone
District 3 $19.85 $6.90 >30-60 mi. base pay + $1.50/hr.
District 4 $18.00 $6.81 >60 mi. base pay + $3.90/hr.
This group includes but is not limited to: District 2
Hod Carrier***;Water Well Laborer; Blaster; Wagon 0-15 mi. free zone
Driller; Asphalt Raker; Cutting Torch; Grade Setter; >15-30 mi. base pay + $0.65/hr.
High-Scaler; Power Saws (Faller& Concrete) >30-50 mi. base pay + $0.75/hr.
Powderman; Rock &Core Drill; Track or Truck Mounted >50 mi. base pay +$1.25/hr.
Wagon Drill and Welder incl. Air Arc.
Districts 3&4
***Hod Carriers will receive the same amount of travel 0-15 mi. free zone
and/or subsistence pay as bricklayers when requested to >15-30 mi. base pay + $0.65/hr.
travel. >30-50 mi. base pay + $0.85/hr.
>50 mi. base pay+$1.25/hr.
DRYWALL APPLICATORS
Wage Benefit Zone Pay:
District 1 $21.00 $11.57 All Districts
District 2 $21.00 $11.86 0-30 mi. free zone
District 3 $21.00 $11.57 >30-50 mi. base pay + $4.00/hr.
District 4 $21.00 $11.57 >50 mi. base pay+ $6.00/hr.
Duties Include:
Drywall and ceiling tile installation.
ELECTRICIANS: INCLUDING BUILDING AUTOMATION CONTROL
Wage Benefit
District 1 $27.04 $10.76 Travel:
District 2 $28.22 $11.53 District 1
District 3 $27.72 $10.78 0-10 mi. free zone
District 4 $30.73 $12.37 >10-45 mi. $0.585/mi. in excess of the free zone.
>45 mi, $65.00/day
Duties Include:
Electrical wiring; equipment and fixtures; street lights; Districts 2&3
electrical control systems. Installation and/or adjusting 0-08 mi. free zone
of building automation controls also during testing and >08-50 mi. federal mileage rate/mi. in effect when travel
balancing, commissioning and retro-commissioning. occurs, in excess of the free zone.
>50 mi. $62.50/day (Big Sky$77.50/day)
District 4
0-18 mi. free zone
>18-60 mi. federal mileage rate/mi. in effect when travel
occurs and employee uses own vehicle.
> 60 mi. $75.00/day in lieu of any other travel allowance.
11
ELEVATOR CONSTRUCTORS
Wage Benefit Travel:
District 1 $47.00 $30.70 All Districts
District 2 $47.00 $30.70 0-15 mi. free zone
District 3 $47.00 $30.70 >15-25 mi. $37.90/day
District 4 $47.00 $30.70 >25-35 mi. $75.80/day
>35 mi. $72.55/day or cost of receipts for hotel and
meals,whichever is greater.
FLOOR LAYERS
Wage Benefit Per Diem:
District 1 $15.55 No Rate Established All Districts
District 2 $15.88 No Rate Established $20.00/day
District 3 $15.55 No Rate Established
District 4 $15.55 No Rate Established
GLAZIERS
Wage Benefit Per Diem:
District 1 $18.11 $2.31 District 1
District 2 $16.56 $1.00 Meals + $25.00/day
District 3 $21.19 $2.40
District 4 $21.19 $2.40 Districts 2-4
$35.00/day
HEATING AND AIR CONDITIONING
Wage Benefit Travel:
Wage Benefit All Districts
District 1 $27.33 $14.44 0-51 mi. free zone
District 2 $27.33 $14.44 >51mi. $0.25/mi. in employer vehicle
District 3 $27.33 $14.44 $0.65/mi. in employee vehicle
District 4 $27.33 $14.44
Per Diem:
Duties Include: All Districts
Testing and balancing, commissioning and retro- $60.00/day
commissioning of all air-handling equipment and duct
work.
12
INSULATION WORKERS-MECHANICAL (HEAT AND FROST)
Wage Benefit Travel:
District 1 $32.32 $17.57 All Districts
District 2 $32.32 $17.57 0-30 mi. free zone
District 3 $32.32 $17.57 >30-40 mi. $20.00/day
District 4 $32.32 $17.57 >40-50 mi. $30.00/day
>50-60 mi. $40.00/day
Duties Include: >60 mi. $45.00/day+ $0.56/mi. if transportation is not
Insulate pipes, ductwork or other mechanical systems. provided/$0.20/mi. if in company vehicle.
>60 mi. $77.00/day on jobs requiring an overnight stay +
$0.56/mi. if transportation is not provided/$0.20/mi. if
in company vehicle.
IRONWORKERS-STRUCTURAL STEEL AND REBAR PLACERS
Wage Benefit Travel:
District 1 $25.90 $20.73 District 1
District 2 $26.50 $19.03 0-45 mi. free zone
District 3 $26.50 $19.03 >45-60 mi. $30.00/day
District 4 $26.50 $19.03 >60-100 mi. $55.00/day
>100 mi. $75.00/day
Duties Include:
Structural steel erection; assemble prefabricated metal Districts 3-4
buildings; cut, bend, tie, and place rebar; energy 0-45 mi. free zone
producing windmill type towers; metal bleacher seating; >45-85 mi. $45.00/day
handrail fabrication and ornamental steel. >85 mi. $75.00/day
MILLWRIGHTS
Wage Benefit Zone Pay:
District 1 $29.00 $11.86 All Districts
District 2 $29.00 $11.86 0-30 mi. free zone
District 3 $29.00 $11.86 >30-50 mi. base pay + $4.00/hr.
District 4 $29.00 $11.86 >50 mi. base pay+ $6.00/hr.
PAINTERS: INCLUDING PAPERHANGER
Wage Benefit Travel:
District 1 $22.06 $9.32 All Districts
District 2 $16.83 $9.26 0-120 mi. free zone
District 3 $18.36 $9.44 >120 mi. $45.00/day
District 4 $16.85 $9.44
13
PILE BUCKS
Wage Benefit Zone Pay:
District 1 $21.00 $11.57 All Districts
District 2 $21.00 $11.86 0-30 mi. free zone
District 3 $21.00 $11.57 >30-50 mi. base pay + $4.00/hr.
District 4 $21.00 $11.57 >50 mi. base pay + $6.00/hr.
Duties Include:
Set up crane; set up hammer; weld tips on piles; set
leads; insure piles are driven straight with the use of
level or plum bob. Give direction to crane operator as to
speed and direction of swing. Cut piles to grade.
PLASTERERS
Wage Benefit Zone Pay:
District 1 $23.55 $8.16 All Districts
District 2 $20.79 $8.31 0-30 mi. free zone
District 3 $19.25 $8.16 >30-60 mi. base pay + $2.95/hr.
District 4 $19.35 $8.16 >60 mi. base pay+ $4.75/hr.
PLUMBERS, PIPEFITTERS, AND STEAMFITTERS
Wage Benefit Districts 2& 3
District 1 $27.58 $13.21 0-40 mi. free zone
District 2 $28.32 $12.73 >40-80 mi. $30.00/day
District 3 $27.37 $12.73 >80 mi. $60.00/day
District 4 $29.94 $14.96 If employer provides transportation, travel pay will be 1/2
of the amounts listed above unless the employee stays
Duties Include: overnight. If the employee chooses to stay overnight,
Assemble, install, alter, and repair pipe-lines or pipe the employee will receive the full amount of travel listed
systems that carry water, steam, air, other liquids or above even if the employer furnishes transportation.
gases. Testing of piping systems, commissioning and
retro-commissioning. Workers in this occupation may District 4
also install heating and cooling equipment and 0-70 mi. free zone
mechanical control systems. >70 mi. $0.55/mi. if transportation is not provided.
Travel: Special Provision:
District 1 If employee travels back and forth from home to job site,
0-30 mi. free zone the employee will receive compensation for no more
>30-50 mi. $20.00/day than two trips.
>50-75 mi. $35.00/day
>75 mi. $70.00/day Per Diem:
District 4
Special Provision: $90.00/day
If transportation is not provided, an additional $0.35/mi.
is added to the amounts above for travel at the
beginning and end of job, not for every mile traveled.
14
ROOFERS
Wage Benefit Travel:
District 1 $20.38 $9.97 District 1
District 2 $21.55 $8.96 0-50 mi. free zone
District 3 $16.83 $4.46 >50 mi. $0.30/mi.
District 4 $20.35 $2.83
Special Provision: Travel is paid only one way.
Per Diem:
District 1
$53.00/day
Districts 2&3
Room + $25.00/day
District 4
Reimbursed for meals and lodging.
SHEET METAL WORKERS
Wage Benefit Travel:
District 1 $27.33 $14.44 All Districts
District 2 $27.33 $14.44 0-51 mi. free zone
District 3 $27.33 $14.44 >51 mi. $0.25/mi. in employer vehicle
District 4 $27.33 $14.44 $0.65/mi. in employee vehicle
Duties Include: Per Diem:
Testing and balancing, commissioning and retro- All Districts
commissioning of all air-handling equipment and duct $60.00/day
work.
SPRINKLER FITTERS
Wage Benefit Travel:
District 1 $30.74 $18.22 All Districts
District 2 $19.58 $18.22 0-60 mi. free zone
District 3 $20.31 $18.22 >60-80 mi. $16.50/day
District 4 $29.85 $12.07 >80-100 mi. $26.50/day
>100 mi. $80.00/day
TAPERS
Wage Benefit Travel:
District 1 $22.06 $ 9.32 All Districts
District 2 $16.83 $ 9.26 0-120 mi. free zone
District 3 $18.36 $ 9.44 >120 mi. $45.00/day
District 4 $16.85 $ 9.44
15
TEAMSTERS GROUP 2
No Rate Established
TELECOMMUNICATIONS EQUIPMENT INSTALLERS
Wage Benefit Travel:
District 1 $20.64 $5.50 All Districts
District 2 $22.74 $7.53 The federal mileage rate/mi. in effect when travel occurs
District 3 $22.78 $7.80 if using own vehicle.
District 4 $23.16 $6.13
Per Diem:
Duties Include: All Districts
Install voice; sound; vision and data systems. This Employer pays for meals and lodging up to$65.00/day.
occupation includes burglar alarms, fire alarms, fiber When jobsite is located in Big Sky, West Yellowstone
optic systems, and video systems for security or and Gardiner, lodging and meals will be provided by the
entertainment. employer for all actual and reasonable expenses
incurred.
TILE AND MARBLE SETTERS
No Rate Established
Duties Include:
Apply hard tile, marble, and wood tile to floors, ceilings, and roof decks
16
APPENDIX A
Investment Grade Audit Report July 9, 2014/Revision 1 October 16, 2014
Available for Download: http://weblink.bozeman.net/WebLink8/0/doc/74235/Electronic.aspx