Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Solid Waste Fund (Collection & Recycling) Capital
Improvement Plan (CIP) for FY16-20.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 15, 2014
RECOMMENDATION: Adopt the Solid Waste Fund (Collection & Recycling) Capital
Improvement Plan (CIP) for FY16-20.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th.
Public Works and other city staff met in October to develop the attached Capital Plan for the
equipment and capital needs of the Solid Waste Fund. The attached capital replacement
schedule is needed to continue operations for garbage collection and the recycling program as
they currently stand.
This plan works in concert with the existing Solid Waste Rate study that was in FY13; funding
annual capital replacement at an amount similar to annual depreciation expense noted in the rate
study.
There are three new items for this year, with details found on the items sheets attached:
• SW42 – Storage Building for $75,000 in FY18
78
• SW43 – Convenience Site Relocation Construction - $100,000 unscheduled
• SW44 – Compost Turner - $80,000 in FY16
There are two changes to items previously listed in the Solid Waste CIP:
• SW37 – Side Load Packer Replacement has been moved from FY18, to FY16, FY17 &
FY20
• SW38 – Side Load Truck Replacement has been added to FY16 (in addition to FY19 as
in the previous CIP)
UNRESOLVED ISSUES: SW41 – Convenience Site Relocation anticipates some funding
support coming from the Solid Waste District, who manages the site. This will need to be
developed and negotiated with the District.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY16.
Report compiled on: December 3, 2014
Attached: Draft - Solid Waste Fund CIP
79
Solid Waste Collection & RecyclingCapital Improvement PlanFinancial SummaryCurrent YearFY15FY16FY17 FY18 FY19 FY20Projected Beginning Reserve Balance Dedicated to CIP496,500$ 685,695$ (32,412)$ 195,842$ 538,228$ 669,788$ Plus: Revenues Dedicated to CIP347,238$ 379,936$ 413,254$ 417,386$ 421,560$ 425,776$ Less: Scheduled CIP Project Costs(158,043)$ (1,098,043)$ (185,000)$ (75,000)$ (290,000)$ (700,000)$ Projected Year‐End Cash Dedicated to CIP685,695$ (32,412)$ 195,842$ 538,228$ 669,788$ 395,564$ Assumptions Made for Revenue Estimates:Current YearFY15FY16FY17FY18 FY19 FY20Estimated Annual Revenues2,893,650$ 2,893,650$ 2,922,587$ 2,951,812$ 2,981,330$ 3,011,144$ Estimated Annual Increase in Revenues ‐ 1%1%1%1%1%Total Estimated Revenues2,893,650$ 2,922,587$ 2,951,812$ 2,981,330$ 3,011,144$ 3,041,255$ Current Revenues Dedicated to CIP %10.0%12.0% 13.0% 14.0% 14.0% 14.0% Plus: Increase Dedicated to CIP2.0%1.0%1.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP12.0%13.0% 14.0% 14.0% 14.0% 14.0%ProjectedProjectedTotal Estimated Revenues Dedicated to CIP347,238$ 379,936$ 413,254$ 417,386$ 421,560$ 425,776$ Note: 2012 Rate Study identifies $367,000 in total annual depreciation expense.CURRENT1,200,0001,000,000800,000600,000400,000200,0000Solid Waste Projects & Equipment 80
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20FY17FY18FY19Solid WastePW01COLLECTIONSHOPS FACILITY EXPANSION PLAN$10,000SW32COLLECTIONFRONTLOAD REPLACEMENT TRUCK$270,000$270,000SW36COLLECTIONSIDE LOAD NEW ‐ (ADDITIONAL ROUTE)$290,000SW37COLLECTIONSIDE LOAD PACKER REPLACEMENT$140,000$138,043$140,000SW38COLLECTIONSIDE LOAD TRUCK REPLACEMENT$290,000$290,000SW39COLLECTIONUPDATE SOLID WASTE RATE STUDY$35,000SW40COLLECTIONOVERLAY LANDFILL ROAD$20,000SW41COLLECTIONCONVENIENCE SITE RELOCATION DESIGN$10,000SW42COLLECTIONSTORAGE BUILDING$75,000SW43COLLECTIONCONVENIENCE SITE RELOCATION CONSTRUCTION$100,000SW44COLLECTIONCOMPOST TURNER$80,000$700,000$808,043$185,000$75,000$290,000$100,000Totals by DEPARTMENTSolid WasteSW35CURBSIDECURBSIDE RECYCLING TRUCK REPLACEMENT$290,000$290,000Totals by DEPARTMENTSummary for Solid Waste (12 items)Totals by year:$700,000$1,098,043 $185,000$100,000FY20FY16FY17UnscheduledFY19$290,000$75,000FY1881
CIP Project Fund
Solid Waste
PROJECT NUMBER
PW01
DEPARTMENT
COLLECTION
PROJECT NAME
SHOPS FACILITY EXPANSION PLAN
FY16 FY17
$10,000
Unscheduled
DESCRIPTION OF PROJECT
The construction of the new Vehicle Maintenance Shop at the Lower Yards on Rouse Avenue in FY10/FY11 was Phase I in
expanding and improving our ability to service equipment, store vehicles, and provide work space for Public Works, Parks, and
Facilitiy services. Questions remain about the long-term plan for construction, location, and expansion for: Streets, Sign & Signal,
Forestry, Water/Sewer Operations, Solid Waste Collection & Recycling, Facilities, and Parks & Cemetery departments. This
project would develop a master plan. In scheduling this project, we are recommending waiting until after the Vehicle Maintenance
Division is relocated to its new shop and the interior improvements are made to the Shop at Rouse and Tamarack Street for the
remaining divisions.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
From related divisions: General Fund 20% ($10,000), Water Fund 20% ($10,000), Wastewater Fund 20% ($10,000), Street Maintenance Fund
20% ($10,000), Solid Waste Fund 20% ($10,000).
New
Replacement
Equipment
Project
FY18 FY19 FY20
82
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW32
DEPARTMENT
COLLECTION
PROJECT NAME
FRONTLOAD REPLACEMENT TRUCK
FY16
$270,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
This truck is a replacement for existing front-load truck currently collecting residential and commercial refuse. The new truck will
ensure continued efficient, cost-effective refuse collection that will allow the Division to meet the demands of a growing city
while maintaining the standards the Bozeman residents expect.
ALTERNATIVES CONSIDERED
Leasing a front-load truck.
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Average maintenance costs: $10,000/year
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
$270,000
83
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW35
DEPARTMENT
CURBSIDE
PROJECT NAME
CURBSIDE RECYCLING TRUCK REPLACEMENT
FY16
$290,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
This truck and side-load packer is used in the collection of residential/commercial single stream recycling. This single stream
program started in October 2013 and has experienced tremendous growth.
ALTERNATIVES CONSIDERED
Leasing a side-load truck
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs = $30,000
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
84
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW36
DEPARTMENT
COLLECTION
PROJECT NAME
SIDE LOAD NEW - (ADDITIONAL ROUTE)
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Additional Side Load truck for new route
ALTERNATIVES CONSIDERED
Leasing a side-load truck
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs = $30,000
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
$290,000
85
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW37
DEPARTMENT
COLLECTION
PROJECT NAME
SIDE LOAD PACKER REPLACEMENT
FY16
$138,043
FY17
$140,000
Unscheduled
DESCRIPTION OF PROJECT
This replacement packer will be placed on an existing chassis, thus extending the life of the overall unit. The old packer will be
traded in or kept for replacement parts. New packers advancement in materials used have led to extend the life of the packer.
New packers wear out within 4 years (7,000 hours) of use.
ALTERNATIVES CONSIDERED
To continue to operate existing packer with increased repair costs and down time. Leasing side-load equipment.
ADVANTAGES OF APPROVAL
To minimize repair costs and having reliable equipment to provide high customer service expectations.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs = $6,000
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
$140,000
86
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW38
DEPARTMENT
COLLECTION
PROJECT NAME
SIDE LOAD TRUCK REPLACEMENT
FY16
$290,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
This truck is a replacement for existing side-load truck currently collecting residential refuse. The new truck will ensure
continued efficient, cost-effective refuse collection that will allow the Division to meet the demands of a growing city while
maintaining the standards the Bozeman residents expect.
ALTERNATIVES CONSIDERED
To continue to operate existing truck with increased repair costs and down time. Leasing side-load truck.
ADVANTAGES OF APPROVAL
Reliable equipment to ensure routes completed in an efficient manner. Maintenance costs of new equipment will be lower.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs = $30,000
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19
$290,000
FY20
87
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW39
DEPARTMENT
COLLECTION
PROJECT NAME
UPDATE SOLID WASTE RATE STUDY
FY16 FY17
$35,000
Unscheduled
DESCRIPTION OF PROJECT
Update to 2012 Rate Study.
ALTERNATIVES CONSIDERED
Continue basing rates on 2012 Study
ADVANTAGES OF APPROVAL
Updating the rate study every 5 years will allow the division to ensure that they can continue operating and providing services at a fair rate
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
88
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW40
DEPARTMENT
COLLECTION
PROJECT NAME
OVERLAY LANDFILL ROAD
FY16
$20,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Overlay Landfill Road, as it extends through the property from Story Mill Road to the Solid Waste Division Shop.
ALTERNATIVES CONSIDERED
Let the road continue to deteriorate which will require constant patching; eventually have to reconstruct
ADVANTAGES OF APPROVAL
An overlay will extend the life of the road
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Reduce maintenance costs for many years
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
89
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW41
DEPARTMENT
COLLECTION
PROJECT NAME
CONVENIENCE SITE RELOCATION DESIGN
FY16
$10,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
This project would identify a more suitable location for the existing Logan Landfill Convenience Station, located at the City
Landfill property on Story Mill Road. The first year would fund the engineering work to determine a more suitable site on the
Landfill property; likely to include features such as below grade roll-off containers for more convenient disposal. The second year
would fund the actual construction costs related to the relocation of the existing equipment.
ALTERNATIVES CONSIDERED
Continue to operate at its existing site.
ADVANTAGES OF APPROVAL
The Site would have easier-to-use disposal options, like grade-level disposal containers. The Convenience Station would become less-obtrusive
use on the property; less of the activities would be visible to ajacent properties.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Make the site less visible and make use of the site more convenient.
FUNDING SOURCES
Solid Waste Fund, with potential reimbursement from the Solid Waste District.
New
Replacement
Equipment
Project
FY18 FY19 FY20
90
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW42
DEPARTMENT
COLLECTION
PROJECT NAME
STORAGE BUILDING
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
This pole construction cold storage building would shelter some equipment and many of the containers currently stored outside.
ALTERNATIVES CONSIDERED
Continue to store items outside
ADVANTAGES OF APPROVAL
Protect equipment from the elements of weather; All of our containers can be stored inside, not collecting water, exposure to sun and be less
visible to adjacent properties.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Operating costs, electricity for lights = < $1,000/ year
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18
$75,000
FY19 FY20
91
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW43
DEPARTMENT
COLLECTION
PROJECT NAME
CONVENIENCE SITE RELOCATION CONSTRUCTION
FY16 FY17 Unscheduled
$100,000
DESCRIPTION OF PROJECT
This project would identify a more suitable location for the existing Logan Landfill Convenience Station, located at the City
Landfill property on Story Mill Road. The first year would fund the engineering work to determine a more suitable site on the
Landfill property; likely to include features such as below grade roll-off containers for more convenient disposal. The second year
would fund the actual construction costs related to the relocation of the existing equipment.
ALTERNATIVES CONSIDERED
Continue to operate at its existing site.
ADVANTAGES OF APPROVAL
The Site would have easier-to-use disposal options, like grade-level disposal containers. The Convenience Station would become less-obtrusive
use on the property; less of the activities would be visible to adjacent properties. Allow City of Bozeman residents access to discard of refuse,
compost, brush, household hazardous waste, white goods and recycling commodities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Operations financed by the Gallatin Solid Waste Management District
FUNDING SOURCES
Solid Waste Fund, with potential reimbursement from the Solid Waste District.
New
Replacement
Equipment
Project
FY18 FY19 FY20
92
CIP Project Fund
Solid Waste
PROJECT NUMBER
SW44
DEPARTMENT
COLLECTION
PROJECT NAME
COMPOST TURNER
FY16
$80,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Purchase of a used 100 horsepower tractor and windrow turner. Currently compost operations takes about 3 years to fully
develop compost. The current equipment used is a front-end loader, which is not very efficient to mix the compost thoroughly.
The tractor/windrow turner will accelerate the composting process allowing the windrows to compost more quickly(estimated
time 6 months). Compost piles will be turned three times per week. The fall leaf cleanup brings in over 1,000 tons per year of
leaves, Various City departments bring in about 400 tons per year, residential compost collection during summer months brings
in about 250 tons per year and the general public self-haul compost to the Bozeman Convenience Site, off Story Mill Road, 150
tons per year. Total compost processed is about 1,800 tons per year.
ALTERNATIVES CONSIDERED
Continue with current operations; Use a smaller tractor/windrow turner (will need more flat land area to compost upon)
ADVANTAGES OF APPROVAL
Compost would be produced more quickly and efficiently utilizing the current composting area; Finished compost would be tested and
potentially used in City parks to improve soil structure;
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs = $2,000
FUNDING SOURCES
100% Solid Waste Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20