Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Water Impact Fee Fund Capital Improvement Plan
(CIP) for FY16-20.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 8, 2014
RECOMMENDATION: Adopt the Water Impact Fee Fund Capital Improvement Plan
(CIP) for FY16-20.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. The City’s Impact Fee
Advisory Committee (IFAC) met on November 20th to review and make recommendations for
the planned expenditures of Water Impact Fees. There was not a quorum of the committee,
however, those present made suggestions and asked that the schedules move forward to the
Commission.
Item of Note:
• The impact fee portion of the debt service payments for the Water Treatment Plant will
be paid off in FY16. Debt service payments for WIF03 – 5.3MG Concrete Water Storage
Reservoir project have been added to the schedule.
• W35 – Lyman Tank has been added to both the Water Impact Fee schedule, and the
Water Fund schedule. The total estimated cost of improving the tank is $7,000,000; with
62
$2,000,000 considered as “capacity-adding”, and is therefore the Impact fee portion of
the project scheduled for FY18.
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY16.
Report compiled on: November 21, 2014
Attached: Draft Water Impact Fee Fund CIP
63
Water Impact Fee
Capital Improvement Plan
Financial Summary Current Year
FY15 FY16 FY17 FY18 FY19 FY20 Unscheduled
Projected Beginning Reserve Balance Dedicated to CIP -$ -$ 362,960$ 1,069,965$ (398,490)$ 354,046$ -$
Plus: Impact Fee Revenues Dedicated to CIP 1,113,992$ 1,083,242$ 1,127,005$ 1,149,545$ 1,172,536$ 1,195,987$ -$
Plus: Loan for WIF03 - 5.3MG Storage Reservoir 6,600,000$
Less: WTP Debt Service Final Payments (413,992)$ (588,282)$
Less: Scheduled CIP Project Costs (700,000)$ (6,732,000)$ (420,000)$ (2,618,000)$ (420,000)$ (420,000)$ (40,941,600)$
Projected Year-End Cash Dedicated to CIP -$ 362,960$ 1,069,965$ (398,490)$ 354,046$ 1,130,033$
Assumptions Made for Revenue Estimates:Current Year
FY15 FY16 FY17 FY18 FY19 FY20
Estimated Annual Water Impact Fee Revenues 1,113,992$ 1,083,242$ 1,104,907$ 1,127,005$ 1,149,545$ 1,172,536$
Estimated Annual Increase 0.0%2%2%2%2%2%
Total Estimated Revenues 1,113,992$ 1,104,907$ 1,127,005$ 1,149,545$ 1,172,536$ 1,195,987$
Current Revenues Dedicated to CIP %100.0%100.0%100.0%100.0%100.0%100.0%
Plus: Increase Dedicated to Water Capacity Expansion CIP 0.0%0.0%0.0%0.0%0.0%0.0%
Total % Dedicated to CIP 100.0%100.0%100.0%100.0%100.0%100.0%
Total Estimated Revenues Dedicated to CIP 1,113,992$ 1,104,907$ 1,127,005$ 1,149,545$ 1,172,536$ 1,195,987$
Projected
Projected
CURRENT
45,000,000
40,000,000
35,000,000
30,000,000
25,000,000
20,000,000
15,000,000
10,000,000
5,000,000
0
Water Impact Fee Projects
64
PROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20RATINGFY17FY18FY19CIP PROJECT FUND:Impact Fees WaterSorted by Funding Year and RatingWIF03WATER IF5.3MG CONRETE WATER STORAGE RESERVOIR$6,600,00035WIF08WATER IFWATER TREATMENT PLANT DEBT SERVICE PAYMENT$588,28250WIF11WATER IFWATER MAIN EXTENSION ‐ FERGUSON AVE (DURSTON TO OAK STREET)$132,00030WIF14WATER IF5.3MG CONRETE WATER STORAGE RESERVOIR ‐ DEBT PAYMENTS$420,000$6,720,00035$420,000$420,000$420,000W35WATER IFLYMAN TANK25$2,000,000WIF07WATER IFGRAF STREET EXTENSION35$198,000WIF05WATER IFWEST WATER TRANSMISSION MAIN LOOP$28,617,60010WIF09WATER IFCOTTONWOOD/STUCKY TRUNK MAIN LOOP$5,544,00045WIF16WATER IFWATER RIGHTS CHANGE APPLICATION$60,00025Summary for Impact Fees Water (9 items)Totals by year:$420,000$7,320,282 $420,000 $2,618,000$40,941,600FY20FY16FY17FY18UnscheduledFY19$420,00065
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
W35
DEPARTMENT
WATER IF
PROJECT NAME
LYMAN TANK
FY15 FY17 Unscheduled
DESCRIPTION OF PROJECT
The current water reservoir is at the end of its useful life and leaking badly and cannot be repaired. Replacement of the existing storage volume
will be paid by the Water Fund. However, if the project can allow for added water storage capacity, Impact Fees will pay for that system
expansion
ALTERNATIVES CONSIDERED
Do not add water storage capacity to the Lyman Tank.
ADVANTAGES OF APPROVAL
Additional water capacity for the water system.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
The total cost of this project is estimated at $7 million. $2 million is considered capacity adding, so is included in the Water
Impact Fee schedule. The remaining $5 million is included in the Water Fund schedule
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:25
FY18
$2,000,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
66
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF03
DEPARTMENT
WATER IF
PROJECT NAME
5.3MG CONRETE WATER STORAGE RESERVOIR
FY15
$6,600,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
<div>According to the 2007 Water Facility Plan, a new 5.3MG partially buried concrete water storage reservoir was to be constructed by 2017.
The proposed location of the reservoir is on City property adjacent (to the North) of the proposed new Hyalite/Sourdough water treatment
plant. This reservoir is sized to meet the City’s storage needs up to 2025, assuming a 5% annual growth rate. Locating the storage reservoir at
the recommended site will raise the hydraulic grade line in the City’s water system, which will increase pressure for the southern part of the
City and will allow future development to occur in the south on a gravity system.</div>
ALTERNATIVES CONSIDERED
The water facility plan reviewed numerous options. This is the preferred alternative of the adopted plan.
ADVANTAGES OF APPROVAL
Increased water storage to meet the needs of our growth community, and the requirement of MDEQ. Increased system water
pressure in the southern part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Requires minimal operation and maintenance. Checking of valves, level sensors and vents on an annual basis and diver inspection
and vacuuming every five years. Estimated at $4,000 annually.
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:35
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
67
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF05
DEPARTMENT
WATER IF
PROJECT NAME
WEST WATER TRANSMISSION MAIN LOOP
FY15 FY17 Unscheduled
$28,617,600
DESCRIPTION OF PROJECT
The Water Facility Plan identifies this project as the most critical redundancy issue in the City’s water distribution system. 4,525 N/A 12" Install
New 12" $ 911,335 2,636 N/A 24" Install New 24" $ 1,101,716 5,154 N/A 36" Install New 36" $ 3,481,785 17,093 N/A 48" Install New 48"
$16,187,712 Total Project Cost $21,682,548 The precise location of the required mains is somewhat flexible, but in general will be from
Wagonwheel road (extended) in S. 19th to Goldenstein to South 3rd to Nash Road (see exhibit 5.B.3 of the facility plan). Given the priority of
the Water Treatment Plant project, the City is not currently planning to complete these projects.
ALTERNATIVES CONSIDERED
Do not build redundant transmission main.
ADVANTAGES OF APPROVAL
The city will be assured that water can be supplied even if one transmission main sustains damage and is offline for a number of
days. The City receives the majority of its water from the Water Treatment Plant through an existing 30 inch concrete
transmission main. If this main is off-line for any reason, the City will need to rely on storage from its three reservoirs. At 2005
water demand levels, storage reserves would be depleted in three days during the average day demand, and in 24 hours during
the maximum day demand. Not only will a second transmission main provide the security of redundancy if the existing 30-inch
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on annual operations and maintenance costs. The Water
Utility will see incremental increases in general maintenance costs. Current cost estimate of $12,500 per water-main mile
maintained annually.
FUNDING SOURCES
Impact Fee eligible portions are related to improvement costs beyond an 8” line capacity. At this point in time, it is estimated that
the 12” and 24” lines are most likely to be built within the next 5 years; the cost of over-sizing those lines would be eligible for
impact fees and is estimated to total $1,874,886. Given the priority of the Water Treatment Plant project, it’s relative size and
scope, these improvements have been moved to “unscheduled.”
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:10
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)5
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)0
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
68
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF07
DEPARTMENT
WATER IF
PROJECT NAME
GRAF STREET EXTENSION
FY15 FY17 Unscheduled
DESCRIPTION OF PROJECT
This project is to extend Water Mains below Graf Street approximately ¼ mile in order to connect infrastructure east from 19th Avenue. This
is an important connection for public safety purposes – allowing fire service to meet their response time requirements in areas where they
currently cannot. The Water infrastructure should be installed at the same time the street connection is made.
ALTERNATIVES CONSIDERED
Do nothing and wait for development to connect the infrastructure.
ADVANTAGES OF APPROVAL
Improved traffic flow and better emergency response to the local area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Impact Fee – to be recovered by developer payback.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:35
FY18
$198,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
69
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF08
DEPARTMENT
WATER IF
PROJECT NAME
WATER TREATMENT PLANT DEBT SERVICE PAYMENT
FY15
$588,282
FY17 Unscheduled
DESCRIPTION OF PROJECT
Total adjusted project price for the Water Treatment Plant (WTP) construction of phase one is estimated at $40.7 Million. Of that amount,
$13.3 Million is for capacity expanding costs of construction. The impact fee account will not have enough cash on hand to pay the costs of
construction when the facility is built. As such, impact fee revenues will be dedicated to pay the outstanding debt in future years, as fee
revenues are collected. At this point, approximately $5 Million of impact fee eligible costs will be paid with a long-term loan (20 years, 4%)
through the State’s Revolving Loan Fund. A debt schedule will be updated semi-annually with the amount of impact fee dollars that have been
dedicated to debt payments until the full amount owed is paid.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Major capital expansion of the Bozeman Water Treatment Plant (WTP) will enable the City to meet its ever growing demand for
water services. Expansion of the Bozeman WTP is consistent with the City’s long-term need to accommodate growth and
economic development in the Gallatin Valley.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
FY08 Pilot Testing: $200,000. FY09,FY10, FY11 Design and Membrane equipment deposit, construction $7,267,000. FY12
$16,460,000. FY13 $16,460,000. Of this total, approximately 33% is eligible for payment via impact fees.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:50
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)10
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)10
FY19 FY20
70
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF09
DEPARTMENT
WATER IF
PROJECT NAME
COTTONWOOD/STUCKY TRUNK MAIN LOOP
FY15 FY17 Unscheduled
$5,544,000
DESCRIPTION OF PROJECT
Installation of a trunk water main loop from the intersection of Cottonwood and Huffine Lane south to Stucky Road then east to South 19th
Avenue.
ALTERNATIVES CONSIDERED
Postpone installation to some future time. It is unlikely that such an ambitious and expensive project could or would be installed
by the concerted effort of private developers. Even if that were to happen, the City would be asked to participate in the
oversizing of these mains, all of which exceed the local 8” diameter requirement.
ADVANTAGES OF APPROVAL
Provides the water main backbone which will support future growth In a large area of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Incremental increase in the cost of operation and maintenance
FUNDING SOURCES
Impact fees, developer contribution for local equivalent share.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:45
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)10
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
71
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF11
DEPARTMENT
WATER IF
PROJECT NAME
WATER MAIN EXTENSION - FERGUSON AVE (DURSTON TO OAK STREET)
FY15
$132,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Installation of a Water Main along Ferguson Avenue, from Durston to Oak Street.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Expanded water service in this area of town.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal
FUNDING SOURCES
Water Impact Fees, Developer contribution.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
72
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF14
DEPARTMENT
WATER IF
PROJECT NAME
5.3MG CONRETE WATER STORAGE RESERVOIR - DEBT PAYMENTS
FY15 FY17
$420,000
Unscheduled
$6,720,000
DESCRIPTION OF PROJECT
Repayment of debt used to finance construction of WIF03 - 5.3 Million Gallon Concrete Water Storage Reservoir.
ALTERNATIVES CONSIDERED
The water facility plan reviewed numerous options. This is the preferred alternative of the adopted plan.
ADVANTAGES OF APPROVAL
Increased water storage to meet the needs of our growth community, and the requirement of MDEQ. Increased system water
pressure in the southern part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Requires minimal operation and maintenance. Checking of valves, level sensors and vents on an annual basis and diver inspection
and vacuuming every five years. Estimated at $4,000 annually.
FUNDING SOURCES
100% Water Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:35
FY18
$420,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19
$420,000
FY20
$420,000.00
73
CIP Project Fund
Impact Fees Water
PROJECT NUMBER
WIF16
DEPARTMENT
WATER IF
PROJECT NAME
WATER RIGHTS CHANGE APPLICATION
FY15 FY17 Unscheduled
$60,000
DESCRIPTION OF PROJECT
The Bozeman Creek Reservoir Company holds two decreed water rights for storage water behind the old Mystic Lake Dam, one for irrigation
purposes and one for municipal purposes. Water right 41H 3045900 is a statement of claim for a 6000 acre-foot volume of water for municipal
purposes. The City of Bozeman is a stockholder in the Bozeman Creek Reservoir Company. The legal volume claimed by water right 41H
3045900 currently cannot be put to municipal use as the historic diversion structure, Mystic Lake Dam, was breached in 1984 due to a
hazardous geologic condition. The water right must proceed through a ‘Change Application’ with the Montana Department of Natural
Resources and Conservation to move the decreed point of diversion to a new point of diversion at a new water impoundment in the Bozeman
Creek municipal watershed. Identifying a suitable location, as well as determining the size and character of a new impoundment, is a separate
effort that must move in parallel with the Change Application funded through this CIP item.
ALTERNATIVES CONSIDERED
Change Application to move municipal water right 41H 3045900 to ‘in-stream flow’ to protect the right from claims of
abandonment.
ADVANTAGES OF APPROVAL
Makes water supply legally available to meet the long-range water demands of the City of Bozeman in accordance with adopted
recommendations of the Integration Water Resources Plan. Preserves a valuable decreed water right.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual O&M costs for a large impoundment (6,000 acre-feet) were estimated at $500,000/yr in the 1999 Sourdough Dam
Feasibility Study. An impoundment of smaller size, which more likely to be pursued, would likely be substantially less but the
degree of which is presently unknown.
FUNDING SOURCES
WIF
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:25
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)10
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)5
FY19 FY20
74