HomeMy WebLinkAbout7 Wastewater Impact Fee
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Wastewater Impact Fee Fund Capital Improvement
Plan (CIP) for FY16-20.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 8, 2014
RECOMMENDATION: Adopt the Wastewater Impact Fee Fund Capital Improvement
Plan (CIP) for FY16-20.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. The City’s Impact Fee
Advisory Committee (IFAC) met on November 20th to review and make recommendations for
the planned expenditures of Wastewater Impact Fees. There was not a quorum of the
committee, however, those present made suggestions and asked that the schedules move forward
to the Commission.
1. The WWIF15- Flanders Mill – Hidden Valley Trunk Main and Lift Station project to
expand service in the West part of town (from the Huffine Lane area back to the Water
Reclamation Facility). The early design, and identification and purchase of utility right-
of-way could prove to save millions of dollars, if done before more development occurs
in the area. With the recent annexations and subdivisions that have occurred in west area
of town, it is felt that this project will need to move forward over the next 3 years.
a. While the project is generally seen as entirely capacity expanding, there will not
be cash on hand to construct. The Wastewater Utility will need to borrow money
52
for the project (a pledge by our rate-payers) with debt payments made by the
Impact Fee Fund each year.
2. The Impact Fee portion of debt payments on the Water Reclamation Facility will be
completed by the end of FY15, and therefore have been removed from the Capital Plan.
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY16.
Report compiled on: November 21, 2014
Attached: Draft Wastewater Impact Fee Fund CIP
53
Wastewater Impact Fee Capital Improvement PlanFinancial SummaryCurrent YearFY15FY16FY17 FY18 FY19 FY20UnscheduledProjected Beginning Reserve Balance Dedicated to CIP‐$ 646,235$ 1,671,636$ 341,545$ 1,222,372$ 1,860,536$ ‐$ Plus: Impact Fee Revenues Dedicated to CIP1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ 1,088,164$ 1,109,927$ ‐$ Plus: Loan for WWIF15 ‐ Flanders Mill Trunk and Lift Stn.2,000,000$ 5,000,000$ 10,556,000$ Less: WRF Debt Payments(159,060)$ Less: Scheduled CIP Project Costs(200,000)$ (2,000,000)$ (7,376,000)$ (10,742,000)$ (450,000)$ (1,120,000)$ (24,101,840)$ Projected Year‐End Cash Dedicated to CIP646,235$ 1,671,636$ 341,545$ 1,222,372$ 1,860,536$ 1,850,462$ Assumptions Made for Revenue Estimates:Current YearFY15FY16FY17FY18FY19FY20Estimated Annual Wastewater Impact Fee Revenues1,005,295$ 1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ 1,088,164$ Estimated Annual Increase0.0%2%2%2%2%2%Total Estimated Revenues1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ 1,088,164$ 1,109,927$ Current Revenues Dedicated to CIP %100.0%100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to Wastewater Capacity Expansion CIP0.0%0.0%0.0%0.0%0.0%0.0% Total % Dedicated to CIP100.0%100.0% 100.0% 100.0% 100.0% 100.0%TlEi dRDdi dCIP1 005 295$1 025 401$1 045 909$1 066 827$1 088 164$1 109 927$ProjectedProjectedTotal Estimated Revenues Dedicated to CIP1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ 1,088,164$ 1,109,927$ CURRENT30,000,00025,000,00020,000,00015,000,00010,000,0005,000,0000Wastewater Impact Fee Projects 54
PROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20RATINGFY17FY18FY19CIP PROJECT FUND:Impact Fees WastewaterSorted by Funding Year and RatingWWIF15WWATER IFFLANDERS MILL ‐ HIDDEN VALLEY TRUNK MAIN AND LIFT STATION ‐ INFRASTRUCTURE$2,000,00030$5,000,000$10,556,000WWIF11WWATER IFREPLACE FRONT STREET: TAMARACK/ROUSE27$2,376,000WWIF16WWATER IFFLANDERS MILL ‐ HIDDEN VALLEY TRUNK MAIN DEBT RETIREMENT$1,120,000$20,700,00030$120,000$450,000WWIF12WWATER IFGRAF STREET EXTENSION35$66,000WWIF17WWATER IF#4 DIGESTER$2,000,00030WWIF05WWATER IFHOSPITAL TRUNK LINE: HAGGERTY TO KAGY$1,401,84027Summary for Impact Fees Wastewater (6 items)Totals by year:$1,120,000$2,000,000 $7,376,000 $10,742,000$24,101,840FY20FY16FY17FY18UnscheduledFY19$450,00055
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF05
DEPARTMENT
WWATER IF
PROJECT NAME
HOSPITAL TRUNK LINE: HAGGERTY TO KAGY
FY15 FY17 Unscheduled
$1,401,840
DESCRIPTION OF PROJECT
Construct ~7,900 LF of 12" and 15" sewer collector from manhole C0507 to 1E22.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating
the long-term future growth in this area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater
utility will pay for these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $743,400 30% Developer Contribution = $318,600
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:27
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)2
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
56
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF11
DEPARTMENT
WWATER IF
PROJECT NAME
REPLACE FRONT STREET: TAMARACK/ROUSE
FY15 FY17
$2,376,000
Unscheduled
DESCRIPTION OF PROJECT
This project consists of construction of ~11,000 LF 18", 21" & 24" sewer pipe from manhole F0330 to C0507. The lower portion of the
existing sewer is at capacity. Additional capacity is needed to serve the future Bozeman Deaconess Hospital development and lands to the
south. It is estimated that 70% of this project costs will be due to capacity expansion and will be eligible for Wastewater Impact Fees. The
remaining 30% of the project costs will need to be provided by a developer contribution or other source. At this time, the City’s Wastewater
Utility does not have a need to replace the existing facility; as such, no utility dollars are scheduled to be spent.
ALTERNATIVES CONSIDERED
Limit development to only that capacity of the existing sewer.
ADVANTAGES OF APPROVAL
This project will significantly increase the service area and capacity of the trunk sewer.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater
utility will pay for these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $1,260,000 30% Developer Contribution = $540,000
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:27
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)2
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
57
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF12
DEPARTMENT
WWATER IF
PROJECT NAME
GRAF STREET EXTENSION
FY15 FY17 Unscheduled
DESCRIPTION OF PROJECT
This project is to extend Wastewater Mains below Graf Street approximately ¼ mile in order to connect infrastructure east from 19th
Avenue. This is an important connection for public safety purposes – allowing fire service to meet their response time requirements in areas
where they currently cannot. The Wastewater infrastructure should be installed at the same time the street connection is made.
ALTERNATIVES CONSIDERED
Do nothing and wait for development to connect the infrastructure.
ADVANTAGES OF APPROVAL
Improved traffic flow and better emergency response to the local area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Impact Fee – to be recovered by developer payback.
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:35
FY18
$66,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)10
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
58
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF15
DEPARTMENT
WWATER IF
PROJECT NAME
FLANDERS MILL - HIDDEN VALLEY TRUNK MAIN AND LIFT STATION - INFRASTRUCTURE
FY15
$2,000,000
FY17
$5,000,000
Unscheduled
DESCRIPTION OF PROJECT
This project consists of the installation of large diameter sewer from Huffine Lane to the City Water Reclamation Facility along the
Cottonwood-Flanders Mill- Hidden Valley alignment as identified in the Wastewater Facility Plan. It also includes a Regional Lift Station located
at the north of the alignment and the installation of the force-main necessary to complete the project. $200,000 in design costs and $13,300,000
in construction costs
ALTERNATIVES CONSIDERED
Limit development in the area served by this trunk sewer to that which can currently be served.
ADVANTAGES OF APPROVAL
This project will significantly increase the area which can be served by the City’s wastewater treatment infrastructure making
development in this corridor possible.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs. Impact fees may not be used to finance those costs. The City’s wastewater utility will
pay for these costs which are estimated to be a small increment of the City’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees (est.) = $9.3M 30% Development contribution =$4M
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
$10,556,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
59
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF16
DEPARTMENT
WWATER IF
PROJECT NAME
FLANDERS MILL - HIDDEN VALLEY TRUNK MAIN DEBT RETIREMENT
FY15 FY17 Unscheduled
$20,700,000
DESCRIPTION OF PROJECT
This items reflects the amount of Impact Fee dollars that are estimated to be available for retirement on the debt used to financine the Flanders
Mill - Hidden Valley sewer trunk main and lift station.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Wastewater Impact Fees
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
$120,000
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19
$450,000
FY20
$1,120,000.00
60
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF17
DEPARTMENT
WWATER IF
PROJECT NAME
#4 DIGESTER
FY15 FY17 Unscheduled
$2,000,000
DESCRIPTION OF PROJECT
Fund the design and construction of a fourth anaerobic digester.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
Additional Capacity for wastewater treatment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Not known at this time.
FUNDING SOURCES
Wastewater Impact Fee Fund
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
61