Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Fire Impact Fee Fund Capital Improvement Plan
(CIP) for FY16-20.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 8, 2014
RECOMMENDATION: Adopt the Fire Impact Fee Fund Capital Improvement Plan
(CIP) for FY16-20.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. The City’s Impact Fee
Advisory Committee (IFAC) met on November 20th to review and make recommendations for
the planned expenditures of Fire Impact Fees. There was not a quorum of the committee,
however, those present made suggestions and asked that the schedules move forward to the
Commission.
Item of Note:
• Based on the Impact Fee Study that was adopted in FY13, both of the items listed need an
outside source of funds for 25% of their costs. This source could be General Funds, grant
revenues, or could be an additional voter-approved tax levy. Once these items are
scheduled, we will need to identify this 25% source, totaling approximately $1,125,000.
UNRESOLVED ISSUES: None.
19
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY16.
Report compiled on: November 21, 2014
Attached: Draft Fire Impact Fee Fund CIP
20
Fire Impact Fee
Capital Improvement Plan
Financial Summary Current Year
FY15 FY16 FY17 FY18 FY19 FY20 Unscheduled
Projected Beginning Reserve Balance Dedicated to CIP 678,819$ 1,025,174$ 1,378,456$ 1,738,804$ 2,106,358$ 2,481,264$ -$
Plus: Impact Fee Revenues Dedicated to CIP 346,355$ 353,282$ 360,348$ 367,555$ 374,906$ 382,404$ -$
Less: Scheduled CIP Project Costs -$ -$ -$ -$ -$ -$ (4,500,000)$
Projected Year-End Cash Dedicated to CIP 1,025,174$ 1,378,456$ 1,738,804$ 2,106,358$ 2,481,264$ 2,863,668$
Assumptions Made for Revenue Estimates:Current Year
FY15 FY16 FY17 FY18 FY19 FY20
Estimated Annual Fire Impact Fee Revenues 346,355$ 346,355$ 353,282$ 360,348$ 367,555$ 374,906$
Estimated Annual Increase 0.0%2%2%2%2%2%
Total Estimated Revenues 346,355$ 353,282$ 360,348$ 367,555$ 374,906$ 382,404$
Current Revenues Dedicated to CIP %100.0%100.0%100.0%100.0%100.0%100.0%
Plus: Increase Dedicated to Fire Capacity Expansion CIP 0.0%0.0%0.0%0.0%0.0%0.0%
Total % Dedicated to CIP 100.0%100.0%100.0%100.0%100.0%100.0%
Total Estimated Revenues Dedicated to CIP 346,355$ 353,282$ 360,348$ 367,555$ 374,906$ 382,404$
Projected
Projected
5,000,000
4,500,000
4,000,000
3,500,000
3,000,000
2,500,000
2,000,000
1,500,000
1,000,000
500,000
0
Fire Impact Fee Projects
21
PROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20RATINGFY17FY18FY19CIP PROJECT FUND:Impact Fees FireSorted by Funding Year and RatingFIF06FIRE IFFIRE STATION #4$3,900,00030FIF07FIRE IFFIRE ENGINE, STATION #4$600,00030Summary for Impact Fees Fire (2 items)Totals by year:$4,500,000FY20FY16FY17FY18UnscheduledFY1922
CIP Project Fund
Impact Fees Fire
PROJECT NUMBER
FIF06
DEPARTMENT
FIRE IF
PROJECT NAME
FIRE STATION #4
FY15 FY17 Unscheduled
$3,900,000
DESCRIPTION OF PROJECT
This project is identified as a priority in the adopted Fire Facility Plan because most of the City's north and west areas are located such that our
response time exceeds four to six minutes for fire and medical emergencies. Land acquisition costs are not included. The City currently owns
the site on the southwest corner of 19th Avenue and Graf Street, which is ideally situated for this station. This station will be needed as our
community grows in its South West quadrant. We will need to watch annexations and subdivisions within the area and schedule this project
accordingly.
ALTERNATIVES CONSIDERED
Many are available: Scale down the project size and/or materials used in construction to accommodate a residential type facility
similar to Station #2; require automatic sprinkler systems as built-in protection for all new construction located outside of
existing stations' response time service districts; continue operating under current resources; relocated existing stations; accept
longer-than-historical response times and high life and fire losses; acquire fire district's fixed facilities as annexation by the City
continues.
ADVANTAGES OF APPROVAL
The completion of this project would enhance our ability to respond to growing parts of the community within a time frame that
has been historically acceptable to the citizens of Bozeman. Station #1 and #2 are located in areas which ineffectively serve the
area station 4 would be placed in. Current response times to the areas South of Kagy are approaching being out of our desired
response time of 6 minutes or less 90% of the time.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be spent on operations and maintenance costs. The City’s General
Fund will bear the annual operating and maintenance expenses associated with this facility, estimated at $1,200,000, including all
crew personnel.
FUNDING SOURCES
75% Fire Impact Fees ($2,925,000), 25% other source ($975,000.)
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
23
CIP Project Fund
Impact Fees Fire
PROJECT NUMBER
FIF07
DEPARTMENT
FIRE IF
PROJECT NAME
FIRE ENGINE, STATION #4
FY15 FY17 Unscheduled
$600,000
DESCRIPTION OF PROJECT
This project is the purchase of an engine and accompanying equipment for use out of new Fire Station 4. It will be necessary to have this engine
at the Station when it opens. There is an estimated 12 month lead time in delivery of this type of equipment. This engine will be needed for
Station #4, which will be required as our community grows in its South West Quadrant. We will need to watch annexations and subdivisions
within the area and schedule this project accordingly.
ALTERNATIVES CONSIDERED
Use of 1989 Pierce Reserve Pumper Darley; buy a used engine; lease/purchase an engine.
ADVANTAGES OF APPROVAL
Purchase of this unit will adequately equip Station #4 for fire and other emergency responses.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Impact Fees can not be used for annual operating and maintenance costs. The City’s
General Fund will pay for the increased fuel, maintenance and insurance costs associated with this engine, estimated at less than
$30,000 per year.
FUNDING SOURCES
75% Fire Impact Fees ($450,000), 25% other source ($150,000).
New
Replacement
Equipment
Project
Impact Fee Funds Project and Equipment Scoring TOTAL SCORE:30
FY18
REQUIRED - CAPITAL or DEBT SERVICE
REQUIRED - USEFUL LIFE 10+ YEARS
REQUIRED - CAPACITY EXPANDING BENEFITS TO NEW DEVELOPMENT: (Up to 20 pts)20
DIRECT BENEFITS: (Up to 10 pts)5
FUNDING CERTAINTY: (Up to 10 pts)5
COMMISSION WORK PLAN PRIORITY: (Up to 10 pts)0
FY19 FY20
24