Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Storm Water Fund Capital Improvement Plan (CIP)
for FY16-20.
AGENDA ITEM TYPE: Action
MEETING DATE: December 8, 2014
RECOMMENDATION: Adopt the Storm Water Fund Capital Improvement Plan (CIP)
for FY16-20.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th.
The Public Works and other city staff met in October and November to develop the attached
Capital Plan for the equipment and capital needs of the Storm Water Fund.
With the anticipated adoption of the new Stormwater Utility rate model (based on the budgeted
“bronze plan”), items that were previously unscheduled have now been placed on the 5 year CIP
plan for the Stormwater Fund, beginning with fiscal year 2016. Adoption of a new rate model
this winter/spring is critical to our ability to implement this plan for capital projects.
New items:
• STRM04 – Annual Stormwater Pipe Rehab design has been scheduled out at
$22,500/year
159
• STRM10 – Annual Stormwater System Enhancement design has been scheduled out at
$22,500/year
• STRM11 – Contracted Services for tasks outside staff purview has been scheduled out at
$25,000/year
• STRM12 & STRM13– Annual Stormwater Deferred Maintenance Program & Annual
Stormwater Pipe Rehabilitation Program have been scheduled based on the Bronze plan
level of funding
• STRM16 – Stormwater Facility Plan
• STRM17 – Cityworks PLL Permit Software
Specific Projects scheduled for system enhancements:
• STRM14 = N. 11th & W. Lamme
• STRM15 – S. Rouse & E. Lincoln
• STRM18 – County Fair Grounds
• STRM19 – N. Black & E. Mendenhall
• STRM20 – N. Wallace & E. Tamarack
• STRM21 – S. Black & W. Cleveland
• STRM 22 – S. Bozeman & E. Cleveland
• STRM23 – Remaining funds for system enhancements; specific projects are unscheduled
until more information is available.
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY16.
Report compiled on: November 24, 2014
Attached: Draft Storm Water Fund CIP
160
Storm Water Utility
Capital Improvement Plan
Financial Summary Current Year
FY15 FY16 FY17 FY18 FY19 FY20 Unscheduled
Projected Beginning Reserve Balance Dedicated to CIP -$ -$ -$ -$ -$ -$
Plus: Storm Water Utility Fees Dedicated to Capital -$ 650,000$ 650,000$ 650,000$ 650,000$ 650,000$
Less: Scheduled CIP Project Costs -$ (650,000)$ (650,000)$ (650,000)$ (650,000)$ (650,000)$ (404,300)$
Projected Year-End Cash Dedicated to CIP -$ -$ -$ -$ -$ -$ (404,300)$
Assumptions Made for Revenue Estimates:Current Year
FY15 FY16 FY17 FY18 FY19 FY20
Estimated Annual Storm Water Utility Revenue 718,125$ 1,200,000$ 1,212,000$ 1,272,600$ 1,336,230$ 1,416,404$
Estimated Annual Increase - Attributed to Growth 1%1%1%2%2%
Estimated Annual Increase - Rate Increase 4%4%4%4%4%
Total Estimated Revenues 718,125$ 1,212,000$ 1,272,600$ 1,336,230$ 1,416,404$ 1,501,388$
Current Revenues Dedicated to CIP %0.0%50.0%50.0%50.0%50.0%50.0%
Plus: Increase Dedicated to Capital 0.0%0.0%0.0%0.0%0.0%0.0%
Total % Dedicated to CIP 0.0%50.0%50.0%50.0%50.0%50.0%
Total Estimated Revenues Dedicated to CIP -$ 606,000$ 636,300$ 668,115$ 708,202$ 750,694$
Projected
Projected
700,000
600,000
500,000
400,000
300,000
200,000
100,000
0
Storm Water Projects
161
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20FY17FY18FY19Storm Water FundSTRM01STORMWATERVALLEY UNIT PARK$80,000STRM02STORMWATERROCKY CREEK STORMWATER IMPROVEMENTS$20,000STRM04STORMWATERANNUAL STORMWATER PIPE REHABILITATION PROGRAM DESIGN$22,500$22,500$22,500$22,500$22,500STRM08STORMWATERROUSE AVENUE INFRSATRUCTURE$279,300STRM10STORMWATERANNUAL STORMWATER SYSTEM EHNAHANCEMENTS DESIGN$22,500$22,500$22,500$22,500$22,500STRM11STORMWATERCONTRACTED SERVICES$25,000$25,000$25,000$25,000$25,000STRM12STORMWATERANNUAL STORMWATER DEFERRED MAINTENANCE PROGRAM$161,000$104,000$142,000$152,000$164,000STRM13STORMWATERANNUAL STORMWATER PIPE REHABILITATION PROGRAM$241,500$206,000$288,000$228,000$246,000STRM14STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM ‐ N 11TH AND W LAMME $20,000STRM15STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM ‐ S ROUSE AND E LINCOLN$40,000STRM16STORMWATERSTORMWATER FACILITY PLAN$100,000STRM17STORMWATERCITYWORKS PLL PERMIT SOFTWARE$30,000STRM18STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM ‐ COUNTY FAIR GROUNDS$150,000STRM19STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM ‐ N BLACK AND E MENDENHALL$150,000STRM20STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM ‐ N WALLACE AND E TAMARACK$50,000STRM21STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM ‐ S BLACK AND W CLEVELAND$50,000162
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY20FY17FY18FY19STRM22STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM ‐ S BOZEMAN AND E CLEVELAND$40,000STRM23STORMWATERANNUAL STORMWATER SYSTEM ENHANCEMENTS$177,500$60,000STRM24STORMWATERSTORMWATER TV VAN REFURBISHMENT$125,000$650,000$650,000$650,000$650,000$650,000$404,300Totals by DEPARTMENTSummary for Storm Water Fund (19 items)Totals by year:$650,000$650,000 $650,000$404,300FY20FY16FY17UnscheduledFY19$650,000$650,000FY18163
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM01
DEPARTMENT
STORMWATER
PROJECT NAME
VALLEY UNIT PARK
FY16
$80,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Improvements to the detention pond at Valley Unit Park, as described on page 6-5 in the Stormwater Facility Plan. A new outlet
structure and overflow is required to alleviate the current flooding issues.
ALTERNATIVES CONSIDERED
Continue to experience localized flooding as a result of the detention ponds deficiencies.
ADVANTAGES OF APPROVAL
Will reduce flooding along Meagher Avenue and Durston Road
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
164
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM02
DEPARTMENT
STORMWATER
PROJECT NAME
ROCKY CREEK STORMWATER IMPROVEMENTS
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Improvements to increase and restore the native vegetation cover and diversity, thereby reducing sedimentation and improving
water quality in Rocky Creek, as described on page 6-7 of the Stormwater Facility Plan.
ALTERNATIVES CONSIDERED
N/A
ADVANTAGES OF APPROVAL
Reduced sedimentation and improved water quality.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19
$20,000
FY20
165
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM04
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER PIPE REHABILITATION PROGRAM DESIGN
FY16
$22,500
FY17
$22,500
Unscheduled
DESCRIPTION OF PROJECT
Contracting of a qualified firm to complete engineering design for rehabilitation projects scheduled each individual fiscal year.
ALTERNATIVES CONSIDERED
Utilize internal engineering design services.
ADVANTAGES OF APPROVAL
Professional design will be incorporated into all rehabilitation projects allowing for the accurate assessment and selection of repair type.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18
$22,500
FY19
$22,500
FY20
$22,500
166
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM08
DEPARTMENT
STORMWATER
PROJECT NAME
ROUSE AVENUE INFRSATRUCTURE
FY16 FY17 Unscheduled
$279,300
DESCRIPTION OF PROJECT
This project is to be completed in coordination with the MDOT improvements to Rouse Avenue. It entails the upsizing of
Stormwater Infrastructure on Rouse. We will need to be prepared to fund this project in according the construction timeline
established by MDOT, which is fairly fluid at this point.
ALTERNATIVES CONSIDERED
MDOT covers the cost for all improvements.
ADVANTAGES OF APPROVAL
The pipe segment under Rouse Avenue has seen past failures and continues to function in a severely degraded state. Improvements to this
section of pipe are necessary to avoid future structural and public safety issues.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
167
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM10
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM EHNAHANCEMENTS DESIGN
FY16
$22,500
FY17
$22,500
Unscheduled
DESCRIPTION OF PROJECT
Contracting of a qualified firm to complete engineering design for system enhancement projects scheduled each fiscal year.
ALTERNATIVES CONSIDERED
Utilize internal engineering design services.
ADVANTAGES OF APPROVAL
Professional design will be incorporated into all system enhancement projects ensuring an effective improvement and reduction of pollutants is
achieved.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18
$22,500
FY19
$22,500
FY20
$22,500
168
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM11
DEPARTMENT
STORMWATER
PROJECT NAME
CONTRACTED SERVICES
FY16
$25,000
FY17
$25,000
Unscheduled
DESCRIPTION OF PROJECT
Annual funding appropriated for contracted services including public relations consulting, community outreach material
development, and infrastructure modeling.
ALTERNATIVES CONSIDERED
Leverage internal resources necessary to complete tasks.
ADVANTAGES OF APPROVAL
Consistent program branding, a professionally developed community education campaign, and an improved technical understanding (through
annual modeling) of the City’s stormwater pipe network. These services are all critical in supporting the Stormwater Programs goals,
maximizing efficiency, and ensuring MS4 Permit compliance.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18
$25,000
FY19
$25,000
FY20
$25,000
169
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM12
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER DEFERRED MAINTENANCE PROGRAM
FY16
$104,000
FY17
$142,000
Unscheduled
DESCRIPTION OF PROJECT
Contracting of a qualified firm on an annual basis to complete city-owned stormwater infrastructure deferred maintenance.
Historically, the City has completed minimal system maintenance allowing its contained pipes, inlets, and detention ponds to
accumulate excessive amounts of sediment, vegetation, rocks, and debris.
ALTERNATIVES CONSIDERED
City staff completes all backlogged stormwater system maintenance in addition to recurring annual operating activities.
ADVANTAGES OF APPROVAL
The use of contracted services to clean and dredge deferred issues will reduce the strain on internal resources allowing crews to focus on
typical recurring maintenance activities, pollution response, and structural spot repairs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stornwater Fund
New
Replacement
Equipment
Project
FY18
$152,000
FY19
$164,000
FY20
$161,000
170
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM13
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER PIPE REHABILITATION PROGRAM
FY16
$206,000
FY17
$288,000
Unscheduled
DESCRIPTION OF PROJECT
Contracting of a qualified firm on an annual basis to conduct underground pipe repair. Types of work include full replacement
and slip lines. Condition scoring, underground assessment video, and close coordination with other utility improvemetns will
determine the type of repair(s) necessary for each individual pipe segment.
ALTERNATIVES CONSIDERED
Continue to administer a response based program limited to staff addressing issues as they become apparent or obvious through
system failures. Past failures include flooding, pipe collapse, and regulatory warnings.
ADVANTAGES OF APPROVAL
Funding will allow the City to be proactive in the repair of stormwater infrastructure that has or is likely to fail reducing flooding, meeting
permit requirements, and improving public safety.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18
$228,000
FY19
$246,000
FY20
$241,500
171
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM14
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM - N 11TH AND W LAMME
FY16
$20,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Installation of a stormwater sediment, garbage, and oil separation system on city-owned property in close proximity to the
intersection of N 11th and W Lamme. This unit will treat stormwater originating from a 4-Acre urban drainage area prior to
being discharged into Mandeville Creek. In addition, this device will be located adjacent to the Bozeman High School Property
and be leveraged as a public outreach tool through the use of educational signage.
ALTERNATIVES CONSIDERED
Continue to discharge untreated stormwater directly into Mandeville Creek.
ADVANTAGES OF APPROVAL
Treatment of stormwater originating within in an urban drainage area, quantifiable pollutant reduction in Mandeville Creek, and provides a
system improvement reportable within the City’s MS4 Permit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Biannual maintenance of the treatment system completed by internal crews.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
172
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM15
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM - S ROUSE AND E LINCOLN
FY16
$40,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
Installation of a stormwater sediment, garbage, and oil separation system on city-owned property in close proximity to the
intersection of S Rouse and E Lincoln. This unit will treat stormwater originating from a 100 acre urban drainage area prior to
being discharged into Bozeman Creek. In addition, this device will be located adjacent to the Christie Fields Park and be
leveraged as an outreach tool through the use of educational signage.
ALTERNATIVES CONSIDERED
Continue to discharge untreated stormwater directly into Bozeman Creek.
ADVANTAGES OF APPROVAL
Treatment of stormwater originating within in a large urban drainage area, quantifiable pollutant reduction in Bozeman Creek, and provides a
system improvement reportable within the City’s MS4 Permit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Biannual maintenance of the treatment system completed by internal crews.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
173
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM16
DEPARTMENT
STORMWATER
PROJECT NAME
STORMWATER FACILITY PLAN
FY16
$100,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
A planning update and modeling effort that will identify insufficiencies within Bozeman’s current Stormwater Program, update past
recommendations, and identify components of the City’s pipe network that requires improvement.
ALTERNATIVES CONSIDERED
Continue to use and implement recommendations established in Bozeman’s 2008 Stormwater Facility Plan.
ADVANTAGES OF APPROVAL
Receipt of an updated Stormwater Facility Plan that will contain recommendations and guidance to ensure Bozeman is on track to meet
regulatory compliance, is making cost effective investments, is strategically addressing infrastructure issues, and is staying consistent with
industry standard codes and requirements.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
174
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM17
DEPARTMENT
STORMWATER
PROJECT NAME
CITYWORKS PLL PERMIT SOFTWARE
FY16
$30,000
FY17 Unscheduled
DESCRIPTION OF PROJECT
The Stormwater Program is in the process of developing and implementing a new Construction Site Inspection Program. This
program will require permit management software and reporting capabilities that allows for custom development, maximization
of efficiencies, spatial capabilities to leverage existing GIS data, and the ability to integrate with historic asset management
information.
ALTERNATIVES CONSIDERED
Exploration of alternative software options.
ADVANTAGES OF APPROVAL
Leverages existing city-owned software (Cityworks AMS) and manages all stormwater construction site permits, inspections, reports, and local
response practices.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual maintenance fees may be required.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
175
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM18
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM - COUNTY FAIR GROUNDS
FY16 FY17
$150,000
Unscheduled
DESCRIPTION OF PROJECT
Installation of a regional detention pond, designed to hold accumulated stormwater until it infiltrates into the ground, on Gallatin
County Fairground property treating an 80 acre residential urban drainage area and a portion of the fairgrounds that currently
discharges directly into Bozeman Creek. This project will offer a collaborative opportunity between the City/County and be
leveraged as a highly visible educational space.
ALTERNATIVES CONSIDERED
Pursue other alternatives such as acquiring the land to the south of the proposed Rouse Justice Center or installing localized
treatment solutions throughout the contributing system.
ADVANTAGES OF APPROVAL
Installation will allow the City to implement an effective treatment system, leverage rare green space within the downtown core, offer a
quantifiable pollutant reduction in Bozeman Creek, and provide a system improvement reportable within the City’s MS4 Permit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Biannual maintenance of the treatment system completed by internal crews.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
176
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM19
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM - N BLACK AND E MENDENHAL
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Installation of a stormwater underground regional detention pond, designed to hold and infiltrate polluted runoff, collected from
a 250 acre urban drainage area encompassing the downtown core. This project will be completed in coordination with the
Parking Commission’s planned reconstruction of the N Black and E Mendenhall parking lot.
ALTERNATIVES CONSIDERED
Installation of numerous system improvements throughout the network upstream that would achieve a similar pollutant
reduction. Decisions regarding the long-term plan for this parking lot must be considered prior to moving this project forward.
ADVANTAGES OF APPROVAL
Treatment of stormwater originating within the City’s largest urban drainage area while maintain the parking lots size and functionality,
leverages rare available space within the downtown core, offers a quantifiable pollutant reduction in Bozeman Creek, and provides a system
improvement reportable within the City’s MS4 Permit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Biannual maintenance of the treatment system completed by internal crews.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18
$150,000
FY19 FY20
177
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM20
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM - N WALLACE AND E TAMARA
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Installation of a stormwater sediment, garbage, and oil separation system on city-owned property in close proximity to the
intersection of N Wallace and E Tamarack. This unit will treat stormwater originating from a 71 acre urban drainage area prior
to being discharged into Bozeman Creek.
ALTERNATIVES CONSIDERED
Continue to discharge untreated stormwater directly into Bozeman Creek.
ADVANTAGES OF APPROVAL
Treatment of stormwater originating within in a large urban drainage area, quantifiable pollutant reduction in Bozeman Creek, and provides a
system improvement reportable within the City’s MS4 Permit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Biannual maintenance of the treatment system completed by internal crews.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18
$50,000
FY19 FY20
178
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM21
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM - S BLACK AND W CLEVELAND
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Installation of a stormwater sediment, garbage, and oil separation system on city-owned property in close proximity to the
intersection of S Black and W Cleveland. This unit will treat stormwater originating from a 121 acre urban drainage area prior to
being discharged into Bozeman Creek.
ALTERNATIVES CONSIDERED
Continue to discharge untreated stormwater directly into Bozeman Creek.
ADVANTAGES OF APPROVAL
Treatment of stormwater originating within in a large urban drainage area, quantifiable pollutant reduction in Bozeman Creek, and provides a
system improvement reportable within the City’s MS4 Permit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Biannual maintenance of the treatment system completed by internal crews.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19
$50,000
FY20
179
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM22
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENT PROGRAM - S BOZEMAN AND E CLEVELAN
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
Installation of a stormwater sediment, garbage, and oil separation system on city-owned property in close proximity to the
intersection of S Bozeman and E Cleveland. This unit will treat stormwater originating from a 20 acre urban drainage area prior
to being discharged into Bozeman Creek
ALTERNATIVES CONSIDERED
Continue to discharge untreated stormwater directly into Bozeman Creek.
ADVANTAGES OF APPROVAL
Treatment of stormwater originating within in a large urban drainage area, quantifiable pollutant reduction in Bozeman Creek, and provides a
system improvement reportable within the City’s MS4 Permit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Biannual maintenance of the treatment system completed by internal crews.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19
$40,000
FY20
180
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM23
DEPARTMENT
STORMWATER
PROJECT NAME
ANNUAL STORMWATER SYSTEM ENHANCEMENTS
FY16 FY17 Unscheduled
DESCRIPTION OF PROJECT
The allocation of annual funding for stormwater system enhancements necessary to comply with permit requirements, meet
federal water quality standards, reduce pollutant discharge into local rivers, and protect community health. Improvements will
include the installation of treatment devices, pervious surfaces, regional detention ponds, and other industry best practice
treatment solutions designed to clean stormwater runoff. Individual projects will be selected and formally introduced through
future CIP processes.
ALTERNATIVES CONSIDERED
Continue to administer a program that does not proactively address known issues and continues to be in violation of both state
and federal requirements.
ADVANTAGES OF APPROVAL
Appropriating funding will allow the installation of system enhancements on an annual basis. In addition, having a defined funding level will allow
City staff to proactively identify and pursue unique collaborative opportunities with local organizations, developers, residents, and businesses.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
N/A
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19
$60,000
FY20
$177,500
181
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM24
DEPARTMENT
STORMWATER
PROJECT NAME
STORMWATER TV VAN REFURBISHMENT
FY16 FY17 Unscheduled
$125,000
DESCRIPTION OF PROJECT
Refurbishment of existing Stormwater TV Van routinely completed every 5 years to replace worn parts and remain consistent
with new technology.
ALTERNATIVES CONSIDERED
Purchase a new TV Van at an estimated cost of $250,000.
ADVANTAGES OF APPROVAL
Provides for the timely replacement of critical maintenance equipment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Decrease in maintenance costs.
FUNDING SOURCES
Stormwater Fund
New
Replacement
Equipment
Project
FY18 FY19 FY20
182