West Winds Major Subdivision Findings of Fact and Order #P-04002
BEFORE THE BOZEMAN CITY COMMISSION
GALLATIN COUNTY, MONT ANA
IN THE MATTER OF THE APPLICATION OF FINDINGS
QUEST WEST, LLC REPRESENTED BY OF FACT
HKM ENGINEERING, FOR PRELIMINARY AND ORDER
APPROVAL OF WEST WINDS SUBDIVISION.
This matter came before the Bozeman City Conunission on May 24,2004, for review and
decision pursuant to the Montana Subdivision and Platting Act, Section 76-3-101 through 76-3-625,
Montana Codes Annotated, and the City of Bozeman Subdivision Regulations, City of Bozeman
Growth Policy, and City of Bozeman Unified Development Ordinance. The applicant presented to the
Commission a proposed Preliminary Subdivision Plat for a Major Subdivision of 31.05 acres, as Phase
lA and 1B of the 160.30 acre parcel, into 46 single- household, 40 townhouse and 2 multi- household lots
and a 129.25 acre remainder as submitted in its original form on March 5, 2004, # P-04009. The
Commission held a public hearing on the preliminary plat and considered all relevant evidence relating
to the public health, safety, and welfare, including the recommendation of the planning board, to
determine whether the plat should be approved, conditionally approved, or disapproved.
It appeared to the Commission that all parties wishing to appear and comment were given the
opportunity to do so, and therefore, being fully advised of all matters having come before it regarding
this application, the Commission makes the following Findings of Fact, as required:
FINDINGS OF FACT
I.
On March 4, 2004, Quest West, LLC, represented by HKM Engineering, submitted an
application for approval to create a Major Subdivision of 31.05 acres, as Phase lA and 1B of the 160.30
acre parcel, into 46 single-household, 40 townhouse and 2 multi-household lots and a 129.25 acre
I West Winds Major Subdivision Findings of Fact and Order #P-04009
remainder. The propeny is legally described as NW%, Section 2, T2S, RSE, City of Bozeman, Gallatin
County, Montana. The subject property is zoned "R-3" (Residential Medium Density District).
II.
The comments of the Development Review Committee, along with those of Planning &
Community Development Staff, were incorporated into a staff repott with suggested conditions of
approval, which was provided to the City of Bozeman Planning Board..
III.
Notice of the time and date of the public meeting and public hearing was posted at the site on
April 16, 2004. Said notice also served to inform interested persons that materials were available for
review at the Bozeman Planning & Community Development Depattment.
The City of Bozeman Planning Board opened the public meeting on April 20, 2004. The
Planning Board found that the application was properly submitted and reviewed under the procedures
of the City of Bozeman Unified Development Ordinance. Staff reviewed the staff repon and the
evidence, which justified the imposition of conditions.
The Planning Board then opened the public meeting. One developer working with the property
owner spoke in favor of the proposed subdivision. The Planning Board closed the public meeting.
The City of Bozeman Planning Board then moved to recommend approval of the subdivision
with conditions as recommended by Staff and passed on a vote of 7 in favor and 0 in opposition.
IV.
The application was considered by the Bozeman City Commission at its regular meeting on May
10,2004, at which time the recommendation of the Planning Board and information compiled by City
staff was reviewed. The City Commission voted to defertheir decision to May 24,2004.
-2-
I West Winds Major Subdivision Findings of Fact and Order #P-04009 I
V.
PRIMARY REVIE W CRITERIA
A Effects on agriculture, agricultural water user facilities, local sernces, the natural
environment, wildlife and the wildlife habitat, and public health and safety.
The property is currently a "highly productive" agricultural field used for hay production.
However, the propeny has been master planned for Residential development. The wban
density development will replace the existing agricultural uses. The subdivider must provide
assurance that no agricultural water user facilities will be impacted by the abandonment of the
ditch.
The annexation agreement reserved capacity for 960 dwelling units. Municipal water, sewer,
roads and emergency services will be provided to the propeny. Sufficient sewer capacity and
traffic impacts will be reviewed further with each phase of the subdivision. The Level of Service
will need to be addressed with each Preliminary Plat submittal.
The applicant has requested a relaxation to the watercourse setback.. Approval of the setback
relaxation could significantly impact the existing wildlife and wildlife habitat associated with
Cattail Creek.. The 50 foot buffer required with a watercourse is essential for continued support
the usual small mammals found in riparian areas. The applicant is aware of the permitting
required for discharging storm water into a stream and will be required to obtain the necessary
pemnts.
B. Compliance with the following:
1. The survey requirements provided for in Part 4 of the Montana Subdivision and
Platting Act.
The subdivision currently complies and will remain in compliance with survey requirements
of the Act.
2. The local subdivision regulations provided forin Part 5 of the Montana Subdivision
and Platting Act.
The final plat shall comply with the standards identified and referenced in the Unified
Development Ordinance unless granted a relaxation through the Planned Unit
Development process. The applicant is advised that unmet code provisions, or code
provisions that are not specifically listed as conditions of approval, does not, in any way,
create a waiver or other relaxation of the lawful requirements of the Bozeman Municipal
Code or state law. The following requirements are standards of the Unified Development
Ordinance and shall be addressed on the final plat:
-3-
I West Winds Major Subdivision Findings of Fact and Order #P-04009 I
. The Restricted Size Lots shall be noted on the Final Plat.
. As recommended by the State Historical Preservation Office (SHPO), a professional
cultural resource inventory of the site shall be conducted by a qualified archeologist.
The results of said survey must be provided to the Planning Department prior to the
submittal of any infrastructure plans and specifications.
. Prior to final plat approval, a Memorandum of Understanding shall be entered into by
the Weed Control District and the subdividerforthe control of county declared noxious
weeds and a copy provided to the Planning Department.
. If approved for Concurrent Construction the property owner shall comply with items 1-
12 of Section 18.7 4.030.D.
. Conditional approval of the preliminary plat shall be in force for not more than three
calendar years, as provided by state statute. Priorto that expiration date, the developer
may submit a letter of request for the extension of the period to the Planning Director
for the City Commission's consideration.
. If it is the developer's intent to me the plat prior to the completion of all required
improvements, an Improvements Agreement shall be entered into with the City of
Bozeman guaranteeing the completion of all improvements in accordance with the
preliminary plat submittal information and conditions of approvaL If the final plat is
filed priorto the installation of all improvements, the developer shall supply the Cityof
Bozeman with an acceptable method of security equal to 150% of the cost of the
remammg 1Illprovements.
. The final plat shall conform to all requirements of the Unified Development Ordinance
and the Uniform Standards for Final Subdivision Plats and shall be accompanied by all
required documents, including certification from the City Engineer that as-built
drawings for public improvements were received, a platting certificate, and all required
certificates. The final plat application shall include four (4) signed reproducible copies
on a stable base polyester film (or equivalent); two (2) digital copies on a double-sided,
high density 3 %-inch floppy disk or compact disk; and five (5) paper prints.
. Storm Water :Master Plan: A Stormwater :Master Plan for the subdivision for a system
designed to remove solids, silt, oils, grease, and other pollutants from the runoff from
the private and public streets and all lots has been provided to the City Engineer. The
applicant is advised that although the general storm drainage and grading concept has
-4-
I West Winds Major Subdivision Findings of Fact and Order #P-04009 I
been reviewed, the submitted data will be subject to further review as part of the
infrastructure plan and specification review process.
. Stormwater generated by the proposed subdivision which discharges to any privately
owned ditch must have the written pennission of the ditch owner.
. The Developer's engineer has provided a comprehensive Design Report evaluating
existing capacity of water and sewer utilities forthe entire West Wmds P.UD... Detailed
review and approval of the Design Report will be required as part of the infrastructure
plan and specification review and approval process.
. The location of and distinction between existing and proposed sewer and water mains
and all easements shall be clearly and accurately depicted on the plans and specs~ as well
as all nearby fire hydrants and proposed fire hydrants.
. Any easements needed for the water and sewer main extensions shall be a minimum of
30 feet in width. While the final location of the water and sewer mains will be
determined once the final street widths are approved, in no case shall the utility be less
than 10 feet from the edge of the easement All necessary easements shall be provided
prior to final plat approval and shall be shown on the plat. Wherever water and! or
sewer mains are not located under or accessed from improved streets, a 12 foot wide all
weather access drive shall be constructed above the utilities to provide necessary access.
. Plans and Specifications for water and sewer main extensions, prepared and signed bya
Professional Engineer (PE) registered in the State of Montana shall be provided to and
approved by the Gty Engineer. Water and sewer plans shall also be approved by the
Montana Department of Environmental Quality. The applicant shall also provide
Professional Engineering services for Construction Inspection, Post-Construction
Certification, and preparation of mylar Record Drawings. Construction shall not be
initiated on the public infrastructure improvements until the plans and specifications
have been approved and a preconstruction conference has been conducted. No
building pennits shall be issued prior to City acceptance of the required
infrastructure improvements unless approved for concurrent construction.
. Any street rights of way which are within the boundaries of this subdivision and for
which easements were provided with the XL Limited Partnership Armexation
Agreement shall be dedicated to the Gty on the Final Plat for this subdivision.
. A detailed Traffic Study Report for the entire West Wmds Development has been
provided to and reviewed by the City Engineer's office. Additional information is
needed prior to approval of the Phase I improvements. The Traffic Study Report shall
include an analysis of possible warrants at all the proposed intersections with Oak
-5-
I West Winds Major Subdivision Findings of Fact and Order #P-04009
Street. The Traffic Study Repon shall also address pedestrian crossing issues at the
intersection of Oak Street and N 27th Avenue and make recommendations for approval.
The need for any traffic impact analysis updates will be identified at the time of Pre-
Application submittal for each subsequent phase.
. Street names must be approved by the Gty Engineer and county road office.
. Gty standard curb, gutter and sidewalk shall be provided along all streets in the
subdivision. Per O1apter 18.44.080 of the Unified Development Ordinance, sidewalks
will be installed prior to occupancy of any individual lots.
. The applicant is advised that the installation of any traffic cahning devices will be
considered in detail and approved if appropriate during the infrastructure plan and
specification review process.
. All typical street sections, including sidewalk location within the right-of-way and
provisions for bicyclists shall be in conformance with the street standards
recommended in the Grrater Bazemm A rea Transportation Plan, 2001 Update, unless
otherwise approved by the Gty Commission, or by the Gty Engineer through the
plan and specification review and approval process.
. Plans and Specifications for streets and storm drainage facilities, prepared and signed by
a Professional Engineer (PE) registered in the State of Montana shall be provided to and
approved by the Gty Engineer. The applicant shall also provide Professional
Engineering services for Construction Inspection, Post-Construction Cenification, and
preparation of mylar Record Drawings. Construction shall not be initiated on the public
infrastructure improvements until the plans and specifications have been approved and
a preconstruction conference has been conducted. No building pennits shall be
issued prior to City acceptance of the required infrastructure improvements
unless approved for concurrent construction.
. Project phasing shall be clearly defined on the infrastructure plans and specifications
including installation of infrastructure.
. The location of mailboxes shall be coordinated with the Gty Engineering Depanment
prior to their installation.
. The Montana Depanment of Fish, Wildlife and Parks, sa;, Montana Depanment of
Environmental Quality and Army Corps of Engineer's shall be contacted regarding the
proposed project and any required pennits (i.e., 310, 404, Turbidity exemption, ete.)
shall be obtained prior to plan and specification approval.
-6-
I West Winds Major Subdivision Findings of Fact and Order #P-04009
. If construction activities related to the project result in the distwbance of more than 1
acre of natural ground, an erosion! sediment control plan may be required. The
Montana Department of Environmental Quality may need to be contacted by the
Applicant to determine if a Stormwater Discharge Permit is necessary. If a permit is
required by the State, the Developer shall demonstrate to the Gty full permit
compliance.
3. The local subdivision review procedure provided for in Part 6 of the Montana
Subdivision and Platting Act.
The Planning Board and Gty Commission hearings have been properlynouced, as required
in the Unified Development Ordinance.
C. The provision of easements forthe location and installation of any planned utilities.
All utilities and necessary utility easements will be provided and depicted on the final plat.
D. The provision oflegal and physical access to each pan:el within the subdivision and the
required notation of that access on the applicable plat and any instrument of t:r.1nsfer
concerning the pan:el
A11lots within the subdivision will have direct access to the dedicated public streets.
ORDER
After considering all matters of record presented at the public hearing, the Bozeman Gty
Commission found that the proposed subdivision would comply with the Gty of Bozeman Growth
Policy and the requirements of the Gtyof Bozeman Unified Development Ordinance and the Montana
Subdivision and Platting Act, if certain conditions were imposed. The evidence, as stated or referenced
in the Findings of Fact, justifies the imposition of the conditions ordered herein to ensure that the final
plat complies with all applicable regulations and all required criteria.
TI-IEREFORE, IT IS HEREBY ORDERED that the Preliminary Subdivision Plat of the West
Wmds Subdivision for the property owner, Quest West LLC, be approved, subject to the following
conditions:
-7-
I West Winds Major Subdivision Findings of Fad and Order #P-04009 I
1. Phase 1A and 1B of the West Wmds Subdivision shall comply with the approved Planned Unit
Development.
2. The final plat shall include a notation that due to high ground water conditions full or partial
basements are not recommended.
3. Cash-in-lieu of Water Rights, as calculated by the Director of Public Service, shall be paid at the
time the Final Plat is submitted.
4. The propeny owner has proposed that Lot 7 of Phase 1A will be developed with an affordable
housing project in order to meet the Perfonnance Points for a Planned Unit Development. The
final plat shall note that Lot 7 is reserved for affordable housing. The plat shall also note that in
the event the lot does not get developed with affordable housing that the propeny owner shall
provide an alternative means to meet the Planned Unit Perfonnance standards.
5. The final plat shall contain a note prohibiting direct access from single family or duplex lots to
Oak Street and N. 27th Avenue.
6. The west half of N 27th Avenue, from Oak Street to Breeze Lane, and the nonh half of Oak
Street, from N 27th Avenue to Hunters Way must be constructed and accepted by the Cityprior
to filing the Final Plat for Phase lA The west half of N 27th Avenue, from Tschache Lane to
Breeze Lane must be constructed and accepted by the City prior to filing the Final Plat for
Phase lB. The overall design of Oak Street shall include a detailed assessment of traffic needs
and design solutions for the phasing. The timing of the development of Harvest Oeek shall be
taken into account as well. The Phase 1A infrastructure improvements shall include
improvements to the intersection of Oak Street and N 27th Avenue to provide a transition
between the existing and the future roadway. Design of the intersection is also to accommodate
the existing overhead power lines. The intersection design will be reviewed and approved by the
City Engineering Office as a part of the infrastructure improvements review process.
7. There is a discrepancy between Traffic Impact Studies provided for the North 19th Avenue and
Durston Road intersection regarding the Level of Service. If it is confirmed the intersection
operates below Level of Service D, then the Final Plat for Phase 1 may not be filed until the
improvements necessary to raise the Level of Service at the intersection of North 19th Avenue
and Durston Road to Level of Service C are installed and accepted by the City of Bozeman.
This City Commission order may be appealed by bringing an action in the Eighteenth District
Court of Gallatin County, within 30 days after the adoption of these Findings by the City Commission,
by following the procedures of Section 76-3-625, MeA The preliminary approval of this subdivision
-8-
I West Winds Major Subdivision Findings of Fact and Order #P-04009 I
shall be effective forthree years from the date of adoption of these Findings by the City Commission.
At the end of this period the City Commission may, at the written request of the subdivider, extend its
approval as provided for in the City of Bozeman Unified Development Ordinance.
DATED this 9th day of August ,2004.