HomeMy WebLinkAbout10- MT Department of Commerce for Local Government Infrastructure Grant Funds 1- -..\\T A
Department of Commerce
COMMUNITY DEVELOPMENT DIVISION
P.O.Box 200523 * Helena,Montana 59620-0523
Phone 406-841-2770 * Fax 406-841-2771
F , 17 7i2t
October 6, 2010
Chris Kukulski, City Manager
City of Bozeman
P.O. Box 1230
Bozeman, MT 59771-1230
Re: Grant recipient HB 645 Local Government Infrastructure Grant #STMGF-60-MP-013B
Dear Manager Kukulski:
Enclosed for your signature is the amendment for the contract between the City of Bozeman and
the Montana Department of Commerce for HB 645 Local Government Infrastructure Grant funds.
Please sign and return the amendment to: Kelsey Dalton, Community Development Division,
P.O. Box 200523, Helena, MT 59620.
Once we receive your amendment, we will update your file. You will receive a copy of the signed
contract amendment for your records by return mail.
If you have any questions, please call Kelsey at 841-2866 or you can reach me at 841-2700.
Sincerely,
rl
Kelsey Dalton, Program Specialist
HB 645 Local Government Infrastructure Grant
Enclosure
LOCAL GOVERNMENT INFRASTRUCTURE GRANT PROGRAM
Contract Amendment #STMGF-60-MP-013B
This Contract Amendment is entered into by the City of Bozeman, Bozeman, Montana
(hereinafter the "Grantee"), and the Montana Department of Commerce, Helena,
Montana (the Department).
The Grantee and the Department mutually agree to amend Contract#STMGF-60-MP-
013 (the Contract), signed and executed by them on November 16, 2009 as follows:
1. Exhibit A Project Budget— Amended. Exhibit A as amended, attached hereto
and specifically incorporated herein by this reference, supersedes all previous
versions of Exhibit A.
2. All other provisions of the Contract remain in full force and effect.
GRANTEE
09)11/4)-4
n
By: , DATE: 10—)2—l0
Chris Kukulski, City Manager
City of Bozeman
By: DATE:
Dore Schwinden, Director
Montana Department of Commerce
BOZZ—
,,�car°� % CITY OF BOZEMAN
;.. '��, Bozeman, Montana
;� jai
‘',.t 1;83 4
44
•1
1
.r,H co.t,C3,
September 30, 2010
Ms. Kelsey Dalton, Program Specialist
HB 645 Local Government Infrastructure Grants
Community Development Division, MDOC
PO Box 200523
Helena, MT 59620-0523
RE: Request for Budget Amendment
Dear Ms. Dalton:
The City of Bozeman would like to request a budget amendment to our HB 645 Infrastructure
Project Grant.
The ADA Pedestrian Ramp Improvement Project came in well under budget after two attempts
to solicit bids. We are pleased that we were able to complete more ADA pedestrian ramps than
initially planned, but we still have$16,767.09 remaining in the budget. In addition, we did not
spend $370 from the Bogert Park Tennis/Basketball Court budget. We wish to apply the surplus
balance of$17,137.23 towards the Bogert Park Sidewalk Replacement ($2,372.47) and the City
Vehicle Maintenance Shop ($14,764:76). Both projects have incurred additional eligible
expenses that exceed the amount budgeted in the original grant. We propose the following
revised budget (next page):
Street address: 12I N. Rouse Ave.
Plume:(406) 582-2300
Mailing address: P.O. Box 1230 Pts:(406) 582.2344
Bozeman,Montana 59771-1230 TDD: ( 06)582-2301
,"4.1.-� ®z� ; CITY OF BOZEMAN
;") '�',�1Bozeman, Montana
ar16 . '*
4
;83 +4rio
�rjJVE,„
PROJECT BUDGET FOR HB 645 INFRASTRUCTURE PROJECT- City of Bozeman -
Erect City Vehicle Maintenance Shop,ADA Pedestrian Ramp Improvements, Bogert
Park Tennis/Basketball Courts, Bogert Park Sidewalk Replacement, Depot Park—
Phase 2 Improvements, and North 7th & Oak Street Sidewalk
Revised Budget— Sept 2010
1 f 1- ;
Projects II HR �' -•;,, , Total Project Cost I.
II
City Vehicle Maintenance Shop $292,903.21 $1,073,242.44
ADA Pedestrian Ramp Improvements $73,232.91 $73.232.91
Bogert Park Term's/Basketball Courts $89,629.86 $89,629.86
Bogert Park Sidewalk Replacement $37,372.47 $37,372.47
Depot Park- Phase 2 Improvements $18,600.00 $19,645.00
N 7th & Oak Street Sidewalk
Improvements $110,400.00 $136,263.92
TOTAL PROJECT COSTS $622,138.45 $1,429,386.60
Thank you for your consideration.
Sincerely,
cx),:i4, 6jj --
Chris Kukulski
Bozeman City Manager
Strect addrgs: 121 N. Rouse Ave. Phone:(406582-2300
Mailing address: P.O. BoN 1230 ) '
Fax: (406) 582-2344
Roicmati,Montana 59771-1230
TDD: (406) 582-2301
Exhibit A
Project Budget - Amended
PROJECT BUDGET FOR HB 645 INFRASTRUCTURE PROJECT
City of Bozeman - Erect City Vehicle Maintenance Shop, ADA
Pedestrian Ramp Improvements, Bogert Park Tennis/Basketball
Courts, Bogert Park Sidewalk Replacement, Depot Park — Phase 2
Improvements, and North 7th & Oak Street Sidewalk
Revised Budget— Sept 2010
HB 645 Funds Total Project Cost
Projects
City Vehicle Maintenance Shop $292,903.21 $1,073,242.44
ADA Pedestrian Ramp Improvements $73,232.91 $73,232.91
Bogert Park Tennis/Basketball Courts $89,629.86 $89,629.86
Bogert Park Sidewalk Replacement $37,372.47 $37,372.47
Depot Park- Phase 2 Improvements $18,600.00 $19,645.00
N 7th & Oak Street Sidewalk Improvements $110,400.00 $136,263.92
TOTAL PROJECT COSTS $622,138.45 $1,429,386.60