HomeMy WebLinkAbout14- Task Order 9-30-14 Tetra Tech, Inc. CMC Bozeman Heebs East Sidewalk Removal Task Order
September 2014 Task Order for Additional Tasks
CMC Bozeman Heebs East Sidewalk Removal
Bozeman, Montana
September 30, 2014
CLIENT: CONSULTANT:
The City of Bozeman Tetra Tech, Inc.
P.O. Box 1230 851 Bridger Drive, Ste 6
Bozeman, Montana 59711-1230 Bozeman, MT 59715
Attention: Mr. Dustin Johnson, PE Attention: Mr. Kirk A. Miller
INTRODUCTION
We are pleased to submit this Task Order for the above referenced project. Our proposal and
cost estimate are based on the expanded scope of work for soil removal under the sidewalk
near the subject Heebs East Main Grocery property and DEQ's request for revisions to several
documents. The additional documents include the following:
• Amended Voluntary Clean-up Plan,
• Construction Completion Report, and,
• Amendments to the Operations and Management Plan.
SCOPE OF WORK
This Modification is for the following work, which is outside the scope of our previously approved
Task Order. Tetra Tech will conduct the following work tasks to close out the Heebs East
Sidewalk contaminated soil removal project.
• Prepare an Amendment to the 2013 CMC Voluntary Clean-up Plan (VCP) to address the
specifics of the Heebs East Sidewalk soil removal project. We anticipate that this will be
a several page long document that identifies the location of the excavation area and the
unique aspects of the soil removal project.
• Prepare a Construction Completion Report that describes the excavation work that was
conducted and the volume of soil and concrete that was removed and their ultimate
disposal method. The estimated volume of soil that would have needed to be excavated
to remove all contaminated soil within the footprint of the excavation will also be
estimated. A summary of all soil samples collected at the site will be provided.
• Update the Operation and Maintenance Plan for the CMC Bozeman site to address DEQ
comments.
• The soil excavation project required excavation and disposal of more soil than originally
anticipated. Our original scope of work called for removal of the sidewalk and the top six
inches of soil. Contaminated soil was observed at depths up to 4 ft. below ground
surface, resulting in a total of 94.5 cubic yards of soil plus the sidewalk being excavated
and transported to the Valley View landfill for disposal. This resulted in four moblizations
Task Order—September 2014 Additional Tasks
CIVIC Bozeman—Heebs East Sidewalk removal
September 30, 2014
by Tetra Tech and Schroeder Contracting due to asbestos being reported in lab
samples, despite no visual evidence being recorded during field screening.
For costing purposes, we have assumed the following:
• The VCP Amendment will be no more than three pages long.
• The Construction Completion Report (CCR) will be no more than 15 pages long (not
including appendices) and will in large part be pulled from our 2009 CCR.
• Amendment of the O&M Plan will require revision or replacement of several paragraphs.
• DEQ will accept the level of effort outlined above for these documents and only one
round of revisions will be necessary to respond to DEQ comments.
Reporting
Tetra Tech will submit the following documents for City review prior to DEQ submittal.
• VCP Amendment
• Construction Completion Report
• Amended O&M Plan
SCHEDULE
Upon written acceptance of this proposal we propose to initiate work on all three documents
simultaneously. These draft documents will be submitted to the City within three weeks of
receipt of authorization to proceed.
COST ESTIMATE
Tetra Tech estimates that our costs to perform the scope of work outlined above on a time and
materials basis is $45,868. This includes $39,758 of additional soil excavation and disposal
costs. We appreciate the opportunity to provide this proposal and look forward to closing out this
project.
Special Conditions
Execution of this Task Order constitutes acceptance of all terms and conditions contained in Tetra
Tech's Professional Services Agreement with the City of Bozeman, dated May 29t`', 2014.
CLIENT: CONSULTANT:
Citv of Bozeman 4 1 A Tetra
By: By: 40
Its: T cxv,cx (eC Its: Sr. Project Manager
Date: -Z�`- I -1 Date: September 30, 2014
Page 2 of 2
Cost Estimate
Task Order for Additional Tasks
Sidewalk Removal and Asbestos Remedlatlon Heebs East Main Grocery
South Wallace Avenue,Bozeman,Montana
September 30,2014
VCP Amendment RATE QUANTITY COST
Labor
Project Manager 20 30.00
Asbestos Manager $120.00 2.0 S240 00
Staff Scientist $95 00 80 $760.00
CADD $65 00 2.0 3130.00
Clerical $55,00 2.0 1$ 10.00
Subtotal S1,240 00
Task Total $1,240.00
Construction Completion Report RATE QUANTITY COST
Labor
Project Manager $170,00 4.0 $680 00
Asbestos Manager $120-00 20 S240.00
Staff Scientist $95.00 160 S1,520 00
CADD $65 00 40 $260,00
Clerical $55 00 80 $440.60
Subtotal S3,140 00
Other Direct Costs
Photocopies $0.10 2000. S2U00
Vehicle Mileage,per mile $0.60 50 0 3$ 0.00
$50.00
Task Total $3,190.00
Operations R Maintenance Plan Amendment RATE QUANTITY COST
Labor
Project Manager S170.00 20 $340 00
Asbestos Manager S120.00 00 SON
Staff Scientist $95.00 4.0 S380,00
CADD $65.00 20 $130.00
Clerical $55 00 40 2$ 20.00
Subtotal S1,070.00
Other Direct Costs
Lodging and Per Diem,per day $120.00 10 $120.00
Vehicle Mileage,per mile S0.60 250.0 1$ 50.00
$270.00
Task Total $1,340.00
Additional Soil Excavation and Disposal RATE QUANTITY COST
Labor
Project Manager $170,00 10.0 $1,700.00
Asbestos Manager $120.00 6,0 $720.00
Staff Scientist S95.00 50.0 $4,750.00
Staff Scientist $88-00 0.0 $0 00
Asbestos Technician $80.00 40 3$ 20,00
Subtotal $7,490.00
Other Direct Costs
Laboratory analysis,per VCP S250 00 70 $1,750.00
Laboratory analysis of backfill,per VCP $470.00 10 $470 00
Asbestos Monitoring,field S75 00 40 $300.00
Lodging and Per Diem,per day $120.00 6.0 $720.00
Vehicle Mileage,per mile $0.65 4000 $260.00
Asbestos Abatement Subcontractor,lump sum+10% 1.0 $28,768.00
Subtotal $32,268.00
Task Total $39,758.00
TOTAL $46,628.00
Tetra Tech Page 1 of 1