HomeMy WebLinkAbout14- Task Order 6-27-14 Tetra Tech, Inc. Bozeman Landfill Resampling Wells, Additional Drilling Time and Mitigation Activities Task Order
June 2014 Task Order for Resampling Wells, Additional Drilling Time and
Additional Mitigation Activities
Bozeman Landfill
Bozeman, Montana
June 27, 2014
CLIENT: CONSULTANT:
The City of Bozeman Tetra Tech, Inc.
P.O. Box 1230 851 Bridger Drive, Ste 6
Bozeman, Montana 59711-1230 Bozeman, MT 59715
Attention: Mr. Rick Hixson. PE Attention: Mr. Kirk A. Miller
INTRODUCTION
This Task Order outlines additional activities requested by the City after the date of our last
Modification, which was submitted on April 4, 2014. These tasks are relative to the vapor
intrusion investigation and mitigation work at the Bozeman Landfill site. The scope of work
expanded for several tasks, including drilling and sampling the new monitoring wells and
installation of a new mitigation system and changes to existing mitigation systems. Since this
work relates to tasks conducted under our original landfill gas investigation project (job number
1140560303A), rather than the new landfill remediation contract (job number 114-560442), we
have submitted this under the previous contract.
SCOPE OF WORK
This Modification is for the following work, which is outside the scope of our previously approved
Task Orders:
Resampling of New Monitoring Wells
The ten new wells installed under the Groundwater Program were sampled in March 2014 and
concentrations of volatile organic compounds above Montana's Groundwater Protection
Standards were reported in an offsite well and several onsite wells. We recommended and the
City concurred that they be resampled. Thirteen samples were collected and submitted for
laboratory analysis. This task includes hours for data validation time, map preparation and data
management.
Longer Drilling Time
During drilling of the ten groundwater-monitoring wells using a hollow stem auger drill rig, we
encountered dense silts and gravels in several borings and a period of warm weather, which
created soft soils and precluded drill rig access to several locations. When the driller's returned
several weeks later we requested they bring an air rotary drill rig to ensure we could reach the
target depths for wells MW-24 and MW-26. This did not affect the driller's costs because we had
them bill by the foot, however, it did take a longer time to drill the wells, thereby increasing our
labor hours for field oversight.
Task Order—June 2014 Modification
Bozeman Landfill, Bozeman, Montana
June 27, 2014
Mitigation System Changes
Several homeowners have requested changes to their mitigation system discharge that are
within the range of typical system installations. The McGovern's requested their fan be
surrounded by a box with insulation since it sits beneath their deck. The Moriarity's requested
their two discharge pipes be carried through a second roof line to get above eaves where frost
build up occurred during cold periods last winter and there have been several smaller
adjustments. We anticipate there will be more requests as the summer progresses and
homeowners spend more time in their yards or with windows open.
• The Olsen's returned to their home after a winter spent out of state and requested a
mitigation system for their home, so a system was installed. The first post mitigation
indoor air sampling of this home will be conducted.
• We are conducting quarterly inspections of the mitigation systems to ensure the system
is running and to check on vacuum levels in the discharge pipe and subslab vacuum
measuring points. We have determined that our original labor estimate for the
inspections was optimistic. We spent almost 20 man hours just tracking down
homeowners to set appointments, rescheduling appointments and waiting for no shows.
In addition, the actual data collection effort took longer than anticipated due to sociable
homeowners and several more events will occur this summer.
• At the last update meeting it was decided to add visual vacuum gauges (i.e.,
manometers) on the mitigation system discharge pipes. After reviewing field notes, we
determined that manometers were installed in many of the systems during construction
(we added this feature part way through the program). Placing visible manometers is a
challenge in some homes because they do not have an easily accessible discharge pipe
or the piping is in a crawl space. We will revisit these homes to see if a practical location
can be found for a manometer. We estimate that approximately eight homes that do not
currently have manometers could be modified to provide a reasonably accessible
manometer.
• We are updating our mitigation system records by taking photographs of key aspects of
each system that are visible. This will allow team members to better understand each
installation without having to travel to the site or disturb homeowners. We are requesting
homeowner permission prior to taking photographs.
Special Conditions
Execution of this Task Order constitutes acceptance of all terms and conditions contained in Tetra
Tech's Professional Services Agreement with the City of Bozeman, dated January 3, 1994 and
Amendment Nos. 1, 2, 3, and 4 of the Professional Services Agreement dated July 31, 1995;
January 1, 1996; March 17, 1997; and December 10, 2001, respectively.
CLIENT: CONSULTANT:
City of Bozeman Tetra Tech l By: C /1�/�/'� By: a \k}
Its: C ,Ty avid, ct P( Its: Sr. Proiect Manager
11
Date: . C D 1 1 Date: June 27. 2014
Page 2 of 2
ESTIMATED BUDGET
JUNE 2014 MODIFICATION TO CONTRACT FOR RESAMPLING,DRILLING TIME
AND CHANGES TO MITIGATION SYSTEMS
BOZEMAN LANDFILL
BOZEMAN,MONTANA
Date Submitted:June 27,2014
Resamole of New Groundwater Monitorina Wells
Field Work Units Rate Cost
Project Manager/Senior Hydrogeologist,per hour 4 $170 00 $680 00
Hydrogeologist,per hour(sampling and data analysis) 36 $95 00 $3,420 00
Data validation/management,per hour 6 $95 00 $570 00
CAD,per hour 4 $75 00 $300 00
Staff Field Personnel,per hour 16 $65 00 $1,040 00
Labor Subtotal $6,010.00
DIRECT COSTS
Tetra Tech Vehicle Mileage,per mile 10 $0.60 $6 00
Water Level Meter,per day 2 $25 00 $50.00
YSI Multi-Meter,per week 2 $100.00 $200 00
Sampling Disposables-Filter,each 10 $18 00 $180 00
Sampling Disposables-Bailer,each $4 75 $0 00
Sampling Disposables-Low-flow tip,each 10 $2 50 $25 00
Sampling Disposables-pump tubing,per foot 350 $0 25 $87 50
Sampling Disposables -Miscellaneous,each 10 $3 00 $30 00
Miscellaneous Shipping,estimate 1 $100 00 $100 00
Lab Sample Shipping(overnight to lab),estimate 1 $150.00 $150 00
Lab Analysis(VOCs,Method 8260 Low Level),each 13 $95.00 $1,235 00
Tetra Tech 10%markup on Subcontractors,Equipment,and Materials $206 35
Direct Costs Subtotal $2,263 85
Resample of New Groundwater Monitoring Wells Total $8,273.85
Longer Drilling Time
Project Manager/Senior Hydrogeologist,per hour 1 $170 00 $170.00
Assistant Project Manager/Hydrogeologist,per hour 16 $95 00 $1,520.00
Labor Subtotal $1,690 00
DIRECT COSTS
Vehicle,mileage 5 $0 60 $3.00
Per Diem and Lodging,per person per day $140 00 $0 00
Direct Costs Subtotal $3,00
Longer Drilling Time Total $1,693.00
Changes to Mitigation Systems.Inspections and Manometers
Project Manager/Senior Hydrogeologist,per hour 16 $150 00 $2,400 00
Assistant Project Manager/Hydrogeologist,per hour 60 $95 00 $5,700 00
Project Scientist,per hour(post mitigation sampling and manometer install) 40 $65 00 $2,600 00
Data validation,per hour 4 $95 00 $380 00
Field Technician,per hour(inspections,photos and homeowner scheduling) 60 $65 00 $3,900 00
Administrative Personnel,per hour 12 $55.00 $660 00
Labor Subtotal $15,640 00
DIRECT COSTS
Triple R Mitigation(Olsen's new system and modifications to others) 1 $9,500.00 $9,500 00
Eurofins Air Toxics Lab(Olsen home air sampling costs) 3 $800 00 $2,400 00
Manometers 8 $25 00 $200 00
Direct Costs Subtotal $12,100.00
Additional Mitigation etc.Total $27,740.00
TOTAL OF ALL TASKS $37,706.85
Tetra Tech