Loading...
HomeMy WebLinkAbout08- West Winds Phase 5 Subdivision & Planned Unit Development J- 494 Inter-office Original to: City of Bozeman Planning Department 20 East Olive Street SUBDIVISION IMPROVEMENTS AGREEMENT WEST WINDS PHASE 5 SUBDIVSION&PLANNED UNIT DEVELOPMENT THIS AGREEMENT is made and entered into this_t 3 ti-N day of (\Jobe-em e ,200 !r, by and between Cascade Development Inc 1627 West Main Street Suite 223 Bozeman MT 59715, hereinafter called the "Subdividers", and the City of Bozeman, a Municipal Corporation and political subdivision of the State of Montana,with offices at 411 East Main Street,P.O.Box 1230,Bozeman,MT 59771-1230,hereinafter called the "City". WHEREAS, it is the intent and purpose of the Subdivider to meet the conditions of approval of a major subdivision preliminary plat application for West Winds Subdivision Phase 5 to subdivide approximately 59.953 acres into eleven (11) residential single households, three 3) residential multi family households, one (1) park area,and one (1) lot for future subdivision on property located at the northwest comer of the intersection of Davis Lane and Oak Street, and legally described a portion of the NW 1/4, Section 2 T2S R5E PMM City of Bozeman Gallatin County Montana; and WHEREAS, it is the intent of the Subdivider to obtain Final Plat approval; and WHEREAS, it is the intent and purpose of both the Subdivider and the City to hereby enter into an Agreement which will guarantee the full and satisfactory completion of the required improvements on the property hereinafter described;and it is the intent of this Agreement,and of the parties hereto,to satisfy the requirements and guarantee improvements for the conditional approval of said subdivision application. NOW, THEREFORE, in consideration of the mutual covenants and conditions contained herein, it is hereby agreed as follows: 1. Property Description This Agreement pertains to and includes those properties which are designated and identified West Winds PUD Phase 5 Subdivision(#P-08013) Improvements Agreement Page 1 of 7 1:$TT2DL_ 23161296,z00e 12:00 40 PM Fee 15 Charlotte Mills - Gallatin County, MT $ 4.00 11111111IIIt11111111111111111f11s I�HN uu,,,..�,...........I........._... __ MISC as a portion of the NW 1/4, Section 2 T2S R5E PMM City of Bozeman Gallatin County Montana. 2. Improvements &Time for Completion of Improvement This Agreement includes all on- site and off-site subdivision improvements as shown in the Preliminary Plat Application, as conditioned in the Preliminary Plat approval, and as required by the Bozeman Municipal Code. Improvements include those described below and listed in the attached Exhibit A,which is made part of this agreement. The list and cost of said improvements has been estimated by DOWL HKM, 920 Technology Boulevard Suite. A Bozeman MT 59718. The Subdivider hereby agrees that the following improvements must be installed within one(1) year of the date of City Commission final plat approval: water, sewer, stormwater facilities transportation facilities streets street lights,trails sidewalks adjacent to public lands etc. , parks and common open space facilities and landscaping_The Subdivider hereby agrees that sidewalks adiacent toto individual lots must be installed within three (3) years of the City Commission final plat approval, or with Building Permits for individual lots,whichever occurs first.In anyevent,all required improvements shall be completed within the time frame provided herein for the completion of the improvements in order to avoid default on the method of security. 3, Financial Guarantee It is the Subdivider's intent to file the final subdivision plat prior to the completion of subdivision improvements. Therefore, this Agreement shall be secured by a_financial guarantee valid for at least eighteen (18) months which is one hundred and fifty (150) percent of the estimated cost of said improvements.The financial guarantee is in the form of an irrevocable letter of credit issued by First Interstate Bank, in the amount of$2,083,143.00, Letter No. 6326 dated November 19, 2008; with an expiration date of May 19, 2010. It is the Subdivider's intent to file the final subdivision plat prior to the completion of sidewalks adjacent to individual lots. Therefore, this Agreement shall be secured by a financial guarantee valid for at least forty-two(42)months which is one hundred and fifty(150)percent of the estimated cost of said sidewalks adiacent to individual lots. The financial guarantee is in the form of a irrevocable letter of credit issued by First Interstate Bank,in the amount of$65,034.00 No. 6327 dated November 19, 2008, with an expiration date of May 19, 2012 . West Winds PUD Phase 5 Subdivision(#P-08013) Improvements Agreement Page 2 of 7 4. Inspection Representatives of the City-shall have the right to enter upon the propertyat anyreasonable time in order to inspect it and to determine if the Subdivider is in compliance with this Agreement,and the Subdivider shall permit the City and its representatives to enter upon and inspect the property at any reasonable time. 5. Default Time is of the essence for this Agreement. If the Subdivider shall default in or fail to fully perform any of its obligations in conformance with the time schedule under this Agreement,and such default orfailure shall continue fora period of thirty(30)days afterwritten notice specifying the default is deposited in the United States mail addressed to the subdivider, Cascade Development Inc 1627 West Main Street,Suite 223,Bozeman MT 59715,or such other address as the Subdivider shall provide to the City from time to time, without being completely remedied, satisfied, and discharged, the City may elect to enforce any of the following specified remedies: a. The City may,at its option,declare the financial guarantee to be forfeited and secure the complete construction and inspection of the improvements described herein. The City's representative,contractors,and engineers shall have the right to enter upon the property and perform such work and inspection,and the Subdivider shall permit and secure any additional permission required to enable them to do so. In the event that any funds remain from the financial guarantee upon completion of all improvements,such funds shall be promptly returned to the Subdivider. b. The City may enforce any other remedy provided bylaw. 6. Indemnification The Subdivider shall indemnify,hold harmless,and defend the Cityof Bozeman against anyand all claims, at Subdivider's own expense, arising out of or resulting from the acts or omissions of Subdivider or his/her agents,employees,or contractors,whether negligent or otherwise,in connection with the performance of work described in this agreement.The City shall be responsible for any claims arising from negligence or willful misconduct on the part of the City or its agents or employees,except the Subdivider shall be responsible for those claims of negligence and misconduct arising from the Subdivider, his/her agents, or employees not providing to the Municipality, its agents or employees, information relevant to the subject matter of this agreement.The patties shall cooperate in the defense of Claims and shall fumish records, information, and testimony and attend proceedings, as may be reasonably necessary. West Winds PUD Phase 4 Subdivision(#P-08013) Improvements Agreement Page 3 of 7 7. Warranty The Subdivider shall warrant against defects of all improvements and that these improvements are made in a good and workman-like manner for a period of two (2) years from the date of their written acceptance by the Governing Body. 8. Governing Law and Venue This Agreement shall be construed according to the laws of the State of Montana.In the event of litigation concerning this Agreement, venue is in the Eighteenth Judicial District Court, Gallatin County, State of Montana. 9. Attorney's Fees In the event it becomes necessary for either party to this Agreement to retain an attorney to enforce any of the terms or conditions of this Agreement,then the prevailing party shall be entitled to reasonable attorney's fees and costs,including fees,salary and costs of in-house counsel including City Attorney. 10. Modifications or Alterations No modifications or amendment of this Agreement shall be valid,unless agreed to in writing by the parties hereto. 11. Invalid Provision The invalidity or unenforceability of any provision of this Agreement shall not affect the other provisions hereof, and this Agreement shall be construed in all respects as if such invalid or unenforceable provision were omitted. 12. No Assignment The responsibilities and benefits of this Agreement to the Subdividers may not be assigned without the express written approval of the City.Such approval may not be withheld unreasonably,but any unapproved assignment is void.There is no prohibition on the right of the City to assign its rights under this Agreement. The City shall release the original Subdividers from their liability under this agreement if it accepts and approves a proper assignment from any developer or lenderwho obtains the property. 13. Successors Except as provided in paragraph 12,this Agreement shall be binding upon,enure to the benefit of,and be enforceable by the parties hereto and their respective heirs, successors and assigns. 14. Filing West Winds PUD Phase 4 Subdivision(#P-08013) Improvements Agreement Page 4 of 7 The Subdivider shall have this Agreement recorded in the Office of the Gallatin County Clerk and Recorder at the same time the Final Plat is filed. CORP TION F J inlap scade Development, Inc. STATE OF MONTANA ) ss. County of Gallatin ) On this� day of N o v--e-rnjge,,- , 200f before me,the undersigned, a Notary Public for the State of Montana,personally appeared John Dunlap,known to me to be 0 kti of.Cascade Development, Inc., the corporation that executed the within instrument, and acknowledged to me that he executed the same for and on behalf of said corporation. IN WITNESS WHEREOF,I have hereunto set myhand and affixed myNotarial Seal the day and year first above written. PM R lit ��., e TAR/,qZ:"' Printed Name VJ�l '6- Notary Public for the State of Monfina ='� • .' * = Residing at L rack t MT . Qela, N�`y' • ��'��SI My Commission xpires: pecc,.,.,be r ! 2 v 1 1F�pFitM,o�a'�P```�� (Use 4 digits for expiration year) West Winds PUD Phase 4 Subdivision(#P-08013) Improvements Agreement Page 5 of 7 THE CITY OF BOZEMAN G Andrew C. Epple Director of Planning &Community Development S TA-M OF MONTANA ) :ss County of Gallatin ) On the day of )1 �`}� �� `C— ,2008,before me,a Notary Public for the State of Montana,personally appeared Andrew C.Epple,known to me to be the person described in and who executed the foregoing instrument as Director of Planning and CommunitvDevelopment of the City of Bozeman,whose name is subscribed to the within instrument and acknowledged to me that he executed the same for and on behalf of City. IN WITNESS WHEREOF, I have hereunto set my hand and affixed my seal on the day and year first written above. (SEAL) Printed Nam ec Notary Public for State of ontana Residing at: Bozeman Montana NpTARI,qj '�% Commission Expires: c)� • = (Use 4 digits for expiration year) * • SEAT 7k West Winds PUD Phase 4 Subdivision(##P-08013) Improvements Agreement Page 6 of 7 Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17, 2008 Bozeman, MT SUMMARY OF COSTS ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Tschache Lane $74,826 Spring View Court $120,139 Autumn Grove Street $162,787 Winward Avenue $187,307 Winter Park Street $71,039 Breeze Lane $43,372 Off-Site (Lot R) $77 275 Oak Street $13,755 Davis Lane $620,062 Park and Boulevard Landscape $61,555 Total Estimated Cost= $1,432,117 50% Contingency $716,058 Total Bond Amount(see below 2 LOC Required) $2,148,175 Infrastructure LOC 18 -Monthl $2,083,141 Sidewalk LOC 42-monthl $65,034 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17,2008 Bozeman,MT TSCHACHE LANE ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS �mum mo Roadway Improvements 100 Excavation 360 CY $3.00 $1,080 102 Embankment 360 CY $4.00 $1,440 103 Asphalt 139 TON $54.00 $7,506 104 Crushed Gravel 150 CY $18.00 $2,700 105 Base Gravel 230 CY $14.00 $3,220 106 Curb and Gutter 378 LF $12.00 $4,536 109 Curb Standard Fillet 4 EA $1,750.00 $7,000 110 5'Sidewalk 344 LF $12.00 $4,128 111 Double Gutter 620 SF $10.00 $6,200 112 Pedestrian Ramp 4 EA $650.00 $2,600 114 Geotextile Fabric 91 SY $1.50 $137 116 Si na e&Stri in 1 LS $1,045.00 $1,045 Subtotals $41,592 Water Improvements 2TB apped DIP Water Line 323 LF $45.00 $14,535 2alves 3 EA $1,450.00 $43501,2_05 rosses, Tees,&Bends 2 EA $400.00 $800nt Assemblies 1 EA $4,250.00 $4,250Assembly 1 EA $1,850.00 $1,850 Type 2 Pipe Bedding 50 CY $13.00 $650 206 Type A Pipe Backfill 240 CY $13.00 $3,120 208 Connect to Existing Mains-live tap 1 EA $2,000.00 $2.000 209 1 Dewatering 1 1 LS $1,615.00 $1,615 $29,555 Miscellaneous 500 Utility Conduit Crossings I2 EA $750.00 $1,500 Subtotal $1,500 Mobilization&Insurance 600 Mobilization, Bonding& Insurance 1 LS $2,179.40 $2,179 Subtotall $2,179 Total Construction Costs $74,826 Prepared by HKM Preliminary Engineer's Estimate For Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17,2008 Bozeman,MT SPRING VIEW COURT ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Roadwa VMPEoveMents 100 ExcavaUon 400 CY $3.00 $1,200 102 Embankment 400 CY $4.00 $1,600 103 Asphalt 147 TON $54.00 $7,938 104 Crushed Gravel 160 CY $18.00 $2,880 105 Base Gravel 240 CY $14.00 $3,360 106 Curb and Gutter 439 LF $12.00 $5.268 110 5'Sidewalk 466 LF $12.00 $5.592 112 Pedestrian Ramp 4 EA $650.00 $2,600 114 Geotextile Fabric 97 SY $1.50 $146 116 Si na e&Striping 1 LS $1 175.00 $1,175 Subtotals j31,759 Water Improvements 200 8"Poly-wrapped DIP Water Line 293 LF $45.00 $13,185 201 8"Gate Valves 3 EA $1,450.00 $4,350 202 8"Water Crosses,Tees,&Bends 2 EA $400.00 $800 203 Fire Hydrant Assemblies 1 EA $4,250.00 $4,250 204 Blow-off Assembly 1 EA $1,850.00 $1,850 205 Type 2 Pipe Bedding 40 CY $13.00 $520 206 Type A Pipe Backfill 220 CY $13.00 $2.860 207 Service Connections-Single Family 4 EA $800.00 $3,200 209 bewatering 1 LS $t,465.00 $1,465 Subtotals 531,015 Sewer Improvements 300 8 in PVC Sewer Line 255 7EA $35.00 $8,925 301 48 in SS Manholes 1 1,850.00 $1,850 304 Type 2 Pipe Bedding 40 $16.00 $640 305 Type A Pipe Backfill 170 $16.00 $2,720 306 Service Connections-Single Family 4 $650.00 $2,600 307 Dewaterin 1 3 825.00 $3,825 Subtotals $16,735 Storm Water Improvements 400 15 in PVC Storm Main 357 LFL$22 00 $10,710 402 24"x36"Catch Basin 1 EA 00 $1,850 403 Type A Pipe Backfill 80 CY00 $1,040 404 48"Catchbasin 1 EA 00 $2 250 Subtotal Si5,850 Miscellaneous 500 Utility Conduit Crossings 2 EA $750.00 $1,500 507 Gravel Utility Access Road 904 LF $15.00 $13,560 501 Street Li hts 1 EA $4,000.00 $4.000 Subtotal $19,060 Mobilization&Insurance 600 Mobilization,Bonding&Insurance 1 LS $5 720.93 $5,721 Subtotall $5,721 Total Construction Costs $120,139 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17,2008 Bozeman,MT AUTUMN GROVE STEET ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Roadwa f Improvements 100 Excavation 760 CY $3.00 $2,280 102 Embankment 760 CY $4.00 $3,040 103 Asphalt 281 TON $54.00 $15.174 104 Crushed Gravel 310 CY $18.00 $5,580 105 Base Gravel 470 CY $14.00 $6,580 106 Curb and Gutter 905 LF $12.00 $10,860 110 5'Sidewalk 935 LF $12.00 $11,220 112 Pedestrian Ramp 4 SF $650.00 $2,600 114 Geotextile Fabric 186 SY $1.50 $279 116 ISignage&Striping 1 LS $2 242.00 $2 242 Subtotals 559,855 Water Improvements 200 8"Poly-wrapped DIP Water Line 548 LF $45.00 $24,660 201 8"Gate Valves 2 EA $1.450.00 $2,900 202 8"Water Crosses,Tees,&Bends 2 EA $400.00 $800 203 Fire Hydrant Assemblies 1 EA $4,250.00 $4,250 204 Blow-off Assembly 1 EA $1,850.00 $1.850 205 Type 2 Pipe Bedding 80 CY $13.00 $1,040 206 Type A Pipe Backfill 410 CY $13.00 $5,330 207 Service Connections-Single Family 7 EA $800.00 $5,600 207.1 Service Connections-Multi Family 1 EA $1,000.00 $1,000 209 IDewatering LS $2,740.1 $2,740 Subtotals $47.430 Sewer improvements. rovements LO6. 8 in PVC Sewer Line 400 LF $35.00 $14,000 48 in SS Manholes 2 EA $1,850.00 $3,700 Type 2 Pipe Bedding 60 CY $16.00 $960 Type A Pipe Backrui 270 CY $16.00 $4,320 Service Connections-Single Family 7 EA $650.00 $4,550 Service Connections-Multi Family 1 EA $750.00 $750 Dewaterin 1 LS $6,000.00 $6,000 Subtotals 528,280 Storm Water Improvements 400 15 in PVC Storm Main 278 LF $30.00 $8,3-40 402 36"Catch Basins 1 EA $1,850.00 $1,850 403 Type A Pipe Backfill 60 CY $13.00 $780 404 48"Catchbasins 2 EA $2,250.00 $4 500 Subtotal $15,470 Miscellaneous 501 Street Li hts 1 EA $4 000.00 $4,000 Subtotall $4,000 Mobilization&Insurance 600 IMobilization,Bonding&Insurance 1 LS $7,751.751 $7,752 Subtotall $7,752 Total Construction Costs $162,787 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17,2008 Bozeman,MT WINDWARD AVENUE ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS D77- F �r. ,,rnpac.n Ct�-irmq. uf7tt. 1, Prioa I Cot Roadway Improvements 100 Excavation 840 CY $3,00 $2,520 102 Embankment 840 CY $4.00 $3,360 103 Asphalt 309 TON $54.00 $16,686 104 Crushed Gravel 450 CY $18,00 $8,100 105 Base Gravel 620 CY $14.00 $8,680 106 Curb and Gutter 1,003 LF $12.00 $12,036 109 Curb Standard Fillet 6 EA $1,750.00 $10,500 110 5'Sidewalk 913 LF $12.00 $10,956 110.1 6'Sidewalk 47 LF $15.00 $705 111 Double Gutter 950 SF $12.00 $11,400 112 Pedestrian Ramp 1.00 EA $650.00 $650 114 Geotextile Fabric 247 SY $1,50 $371 116 Signage&Striping 1 LS $2,470.001 $2,470 120 1 Fill and Re-grade Temporary Pond 1 LS $7,50&001 $7,500 Subtotalsl $95,934 Water Improvements 200 8"Poly-wrapped DIP Water Line 382 LF $45.00 $17,190 201 8"Gate Valves 2 EA $1,450.00 $2,900 202 8"Water Crosses,Tees,&Bends 2 EA $400.00 $800 204 Blow-off Assembly 1 EA $1,850.00 $1,850 205 Type 2 Pipe Bedding 60 CY $13.00 $780 206 Type A Pipe Backfill 280 CY $13.00 $3,640 209 Dewatenn 1 LS $1,910.00 $1,910 Subtotals[.. $27,160 Storm Water Improvements 400 15 in PVC Storm Main 59 LF $30.00 $1,770 401.3 27 in PVC Storm Main 521 LF $54.00 $28,134 402 36"Catch Basins 2 EA $1,850.00 $3,700 403 Type A Pipe Backfill 130 CY $13.00 $1,690 413 60"Catchbasin 4 EA $2,250.00 $9,000 Subtotal $44,294 Miscellaneous 500 1 Utility Conduit Crossings 4 EA $750,00 $3,000 505 Lighting 2 EA $4,000.00 $8.000 Subtotall $11,000 Mobilization&Insurance 600 Mobilization, Bonding&Insurance 1 LS $8,919.381 1,8,919 Subtotall $8,919 Total Construction Costs $187,307 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17, 2008 Bozeman, MT WINTER PARK STREET ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Roadway Improvements 100 Excavation 510 CY $3.00 $1,530 102 Embankment 510 CY $4.00 $2,040 103 Asphalt 189 TON $54.00 $10,206 104 Crushed Gravel 210 CY $18.00 $3,780 105 Base Gravel 310 CY $14.00 $4,340 106 Curb and Gutter 615 LF $12.00 $7,380 110 5' Sidewalk 311 LF $12.00 $3,732 110.1 6'Sidewalk 310 LF $15.00 $4,650 114 Geotextile Fabric 126 SY $1.50 $189 116 Si na e &Striping1 LS $1,509.00 $1,509 Subtotals $39,356 Water Improvements 200 8" Poly-wrapped DIP Water Line 412 LF $45.00 $18,540 201 8" Gate Valves 1 EA $1,450.00 $1,450 205 Type 2 Pipe Bedding 60 CY $13.00 $780 206 Type A Pipe Backfill 310 CY $13.00 $4,030 208 Connect to Existing Mains - live tap 1 EA $2,000.00 $2,000 209 Dewaterin 1 LS $2,060.00 $2,060 Subtotals $26,800 Miscellaneous 500 Utility Conduit Crossings 2 EA $750.00 $1,500 Subtotal $1,500 Mobilization & Insurance 600 Mobilization, Bonding & Insurance 1 LS $3,382.801 $3,383 Subtotal $3,383 Total Construction Costs $71,039 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17, 2008 Bozeman, MT BREEZE LANE ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Roadway Improvements 100 1 Excavation 530 CY $3.00 $1,590 102 Embankment 530 CY $4.00 $2,120 103 Asphalt 195 TON $54.00 $10,'530 104 Crushed Gravel 220 CY $18.00 $31960 105 Base Gravel 320 CY $14.00 $4,480 106 Curb and Gutter 637 LF $12.00 $7,644 110 5' Sidewalk 644 LF $12.00 $7,728 114 Geotextile Fabric 130 SY $1,50 $195 116 Si na e &Striping 1 LS $1,560.00 $1,560 Subtotals $39,807 Miscellaneous 500 1 Utility Conduit Crossings 2 EA $750.00 $1,500 Subtotall $1,500 Mobilization & Insurance 600 Mobilization, Bonding & Insurance 1 LS $2,065.351 $2,065 Subtotal $2,065 Total Construction Costs $43,372 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17, 2008 Bozeman, MT OFF-SITE (LOT R) ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Wencrr. Sewer Improvements 300 8 in PVC Sewer Line 973 LF $35.00 $3 ,,055 301 48 in SS Manholes 4 EA $1,850.00 $7,400 303 Connect to Existing Main 1 LS $1,500.00 $1,500 304 Type 2 Pipe Bedding 140 CY $14.00 $1,960 305 Type Pipe Backfill 650 CY $14.00 $9,100 307 Dewaterin 1 LS $4,865.00 $�"' 8 Subtotals Storm Water Improvements 401.2 24 in PVC Storm Main 224 LF $45.00 $5,580 405 Detention Pond w/ Control Structures 1 LS $14,000.00 $144,000 414 Temporary Stormwater Conveyance Ditch 1290 LF $4.00 $5,160 415 Permanent Stormwater Conveyance Ditch 512 LF $7.50 $3,840 416 36 in equivalent concrete arch pipe 212 LF $95.00 $20,140 Subtotal $19,580 Mobilization & Insurance 600 IMobilization, Bonding & Insurance 1 LS $3,679.-751 3,680 Subtotall $3,680 Total Construction Costs $77,275 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 Subdivision November 17, 2008 Bozeman, MT OAK STREET ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Roadway Improvements 110.1 6'Sidewalk 1 340 1 LF 1 $15.001 $5,100 Subtotalsi $5,100 Miscellaneous 501 IStreet Lights 2 EA $4,000.00 $8,000 Subtotal $8,000 Mobilization & Insurance 600 1 Mobilization, Bonding &Insurance 1 LS $655.00 $655 Subtotal $655 Total Construction Costs $13,755 Prepared by HKM Preliminary Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Bozeman,MT November 17,2008 DAVIS LANE ROADWAY AND UTILITY INFRASTRUCTURE IMPROVEMENTS Roadway Improvements 100 Excavation 9,261 9,260 CY $3.00 $27.780 102 Embankment 926 930 CY $4.00 $3,720 103 Asphalt 2,515 2,515 TON $54.00 $135,810 104 Crushed Gravel 1,684 1,680 CY $18.00 $30,240 105 Base Gravel 5,051 5,050 CY $14.00 $70,700 106 Curb and Gutter 5,220 5,220 LF $12.00 $62,640 106.1 Temporary Pin-Down Curb 412 412 LF $8.00 $3,296 110 6'Sidewalk 2,530 2,530 LF $22.00 $55,660 111 Double Gutter 620 620 SF $15.00 $9,300 112 Pedestrian Ramp 20 20 EA $650.00 $13,000 113 Existing Utility Rim Adjustment 1 1 EA $250.00 $250 114 Geotextile Fabric 10,102 10,102 SY $1.50 $15,153 116 Si na e&Striping 1 1 LS 1 $9,017 $9,017 Subtotals $436,566 Storm Water Improvements 400 15 in PVC Storm Main 375 3757LF $165.00 $30.00 $11,250 402 36"Catch Basins 2 2850.00 $3,700 403 Type A Pipe Backfill 83 83 $13.00 $1,079 L414.1 1 Retention Pond w/Riprap Protection 1 1500.00 $6,500 3 48"RCP 159 159 $26,235 .1 48"RCP Flared End Section 4 4 EA $1,050.00 $4,200 4 48"EQ. RCPA 247 247 LF $182.50 $45,078 48"EQ. RCPA Flared End Section 1 1 EA $1,125.001 $1,125 Subtotal $99,167 Miscellaneous 505 Lighting 1 1 LS $47,302.60 $47,303 506 [Traffic Control 1 1 LS $3,000.00 $3,000 Subtotal $54,803 Mobilization&Insurance 600 Mobilization, Bonding& Insurance 1 1 LS $29,526.76 $29,527 Subtotall $29,527 Total Construction Costs $620,062 Engineer's Estimate for Prepared By: West Winds Planned Community HKM Engineering Phase 5 November 17,2008 Park&Landscaping Bozeman,MT WINTER PARK STREET-LEAR PARK(EXHIBIT A) PARK AND LANDSCAPING IMPROVEMENTS ifr'4r vtirdrA, 4,•'ad�trd�d: tJRytfrd- Un}t btet. 90• 1'-Vu-rpuon Qtm 1 F CE UotY Prka. LANDSCAPING IMPROVEMENTS 101 Street Trees JTL 17 1.00 17 17 EA $110.00 $1 870 102 Trees TCA 4 1.00 4 4 EA $115.00 $460 103 Trees ELM 4 1.00 4 4 EA 120.00 $480 104 Trees ASH 2 1.00 2 2 EA $130.00 $260 105 Trees OAK 2 1.00 2 2 EA $130.00 $260 106 Trees EQM 2 1.00 2 2 EA $135.00 $270 107 Trees CRC 3 1.00 3 3 EA $120.00 $360 108 Trees NW 2 1.00 2 2 EA $135 00 $270 109 Trail 700 1.00 700 700 LF $1500 $10,500 110 Seeded Turf 50.100 1.00 50,100 50,100 SF $0.15 $7,515 111 Irrigation Well 1 1.00 1 1 EA $3,000.00 $3,000 112 Irrigation 50100 1.00 50,100 50,100 SF $0.25 $12525 113 L Med Ballards 2 1.00 2 2 EA $2,500.00 $5,000 Subtotals $42,770 OAK STREET BOULIVARD(Exhibit B) PARK AND LANDSCAPING IMPROVEMENTS t nit } LANDSCAPING IMPROVEMENTS 201 Street Trees JTL 10 1 00 1 10 10 1 EA 1 $110.00 $1.100 202 lrngaWn 3,500 1.00 1 3,500 1 3.500 SF $0.25 $875 203 Sod 3,500 1-00 3,500 3,500 1 SF $0.401 $1,400 Subtotals $3,375 IDAVIS LANE BOULIVARD(EXHIBITS C1&C2) PARK AND LANDSCAPING IMPROVEMENTS iW- t>ion ��. �rfit Fca SEGMENT#1-LANDSCAPING IMPROVEMENTS 301 Trees PGA 1U1�00 1 EA $135.00 $135 3Q2 Trees OAK 3 3 EA $130.00 $390 303 Trees EQM 2 2 EA $135.00 $270 304 Trees ELM 3 3 EA $120 00 $360 305 Sod 4,600 4,600 SF306 Irri anon 4,600 4,600 SF $0.25 $1.150 Subtotals 4,145 SEGMENT#2-LANDSCAPING IMPROVEMENTS 401 Trees PGA 2 1.00 2 2 EA $135.00 $270 402 Trees OAK 3 1.00 3 3 EA $130,00 $390 403 Trees EQM 0 1.00 0 0 EA $135.00 $0 404 Trees ELM 0 1.00 0 0 EA $120.00 $0 405 Sod 2,800 1-00 2,800 2.800 SF $0.40 $1,120 406 mi alion 2,800 1.00 2,800 2,800 SF $0.25 $700 Subtotals 2,480 SEGMENT#3-LANDSCAPING IMPROVEMENTS 501 1 Trees PGA M03 2 EA $135.00 $270 502 Trees OAK 3 EA $130.00 $390 503 Trees EQM 2 EA $135.0098,$785 504 Trees ELM 3 EA $120.00505 Trees CBS 5 EA $115.00506 Trees FHL 5 EA $110.00507 Sod 0 9,800 SF $0.40 508 Irri anon W77-9,800 1.00 9,800 9,800 SF $0 25 Subtotals Total Cost $61,555