HomeMy WebLinkAboutat a glance NSURB for commission Feb 2010NSURB @ a Glance
Blight announced: August 2005
TIF designated: November 2006
Board first met: May 2008
Members are: Andrew Cetraro, Jeff Krauss, Carl Solvie, Kevin Cook, Michelle
Wolfe, Mike Hope, Scott Hedglin, Susan Riggs, Taylor Lonsdale,
Susan Fraser
City Planning staff: Keri Thorpe
Current project: complete sidewalk on east side of North 7th between Oak and
Peach, along with sidewalk at the northwest corner of the Oak
Intersection (stimulus dollars project – must be completed
September 2010) DCP: The Design and Connectivity Plan, also known as the Winter Plan,
was produced as the first step in the remedy of the blight. It is the
guiding document for the actual layout of sidewalks, lighting,
everything along North 7th. It is available at:
http://www.bozeman.net/bozeman/government/commission/citizen%20advisory%20boards/NSURB/NSURB.pdf
Agendas, minutes available at: http://www.bozeman.net/bozeman/government/commission/citizen%20advisory%20boards/NSURB/NSURB.pdf
2010 Expenditure Plan
TIF Other
2010
Expenditure
Plan
Balance 07/01/09 93,316 93,316
Interest 1,000 1,000
TIF allocation for FY10 272,000 272,000
Big Box Funds 232,000 232,000
Community block grant1 16,100 16,100
Stimulus dollars project 110,400 110,400
Total Revenue Available 366,316 358,500 724,816
Engineering plan, professional contract with
Allied 50,000 100,000 150,000
N7Rehab – Redevelopment Incentive Program2
Façade/Site Improvements Fund 33,329 33,329
Streetscape Enhance Fund 10.829 10,829
Demolition fund 22,500 22,500
Part time staff and other professional services 10,829 10,829
Construction – Lights, Curb and Gutter,
Sidewalk, Landscaping and Irrigation 238,829 258,500 497,329
Total Expenditures 366,316 358,500 724,816
Ending Balance 0 0 0
1community block grant – actuality of dollars yet to be determined
2Pending Commission approval of forthcoming Resolution for N7Rehab Program