Loading...
HomeMy WebLinkAbout2014 CIP Field Survey, NW Construction, Inc. ED J 14, 4 2014 c"UHSTRUCTIR .......... CffY OF BOZEMAN ENGNEERING DEPARTMENT 014 CAPITAL IMPROV E[M, ENff PROJECTS FIELD SURVEY EA-'L-[E G li-F-1 090 AL F0R� Nw CO STRuC TTOK Mc. COPY I JULY 3rd9 2014 ® 5m00PM (Close of Business) CUnSRUCiwUH ADC. July 31d, 2014 City of Bozeman Engineering Department 20 East Olive Avenue Bozeman, MT 59711 RE: Request for Proposals—2014 Capital Improvement Projects Field Survey Dear Sir or Madame: NW Construction, Inc. would like to thank you for the opportunity to submit our proposal on the above reference solicitation. Within this proposal and it's attachments, we are confident that the City of Bozeman will find that NW Construction, Inc. (NWC) has the experience, background and capability to complete a multitude of projects planned for this RFP. Specifically, the owners of NWC and the proposed project management team have a combined experience of almost 40 years with surveying, construction staking, civil design, earthwork, pipeline, roadway, water, wastewater, and dam construction projects across the United States. In addition to performing topographic mapping and boundary surveys, as a heavy civil contractor, NWC has performed extensive as-built surveys for numerous water and sewer utility projects for delivery to engineers after construction. As-built surveys are typically used to locate (horizontally and vertically) elements of a construction project to determine final conditions for pipes, valves, manholes, etc. The performance scope of this RFP is identical to these types of surveys. Our proposal is formatted to follow the outline provided within the RFP and we have provided the required five (5) separate copies. Please find the attached documents relating to the RFP — 2014 Capital Improvement Projects Field Survey. We are confident that not only are we experienced but that we are uniquely qualified with some of the most extensive heavy civil and surveying experience in the industry over the last 20 years in the United States. This experience along with our technical capabilities including, two in-house licensed P.E.'s and a P.L.S., allow us to efficiently execute a project and resolve challenges as they arise. We look forward to the opportunity to work with you. Please do not hesitate to call me at(406)587-1907, or email me at erik.kirsch anwconstruction.us with any additional questions or clarifications. Sincerely, Erik Kirsch, P.E., P.L.S. Director of Engineering Operations '12645 I(RIX CANYON I10AD BONIVIAN,MONTANA 511715 tb rtiow(4116)51/174407 rjv FAX:(4116)58'/4151 tit t4�►Aft+tt.l��t4►cu��srtttrr.rum+.us 2014 Capital Improvements Project Field Survey: 1. Project Management Chart See attached (Attachment B) NW Construction Project Management Chart for this RFP. 2. Schedule of Activities We anticipate the project to have a duration of approximately 30 days utilizing (1)survey crew and (1) drafter. If there are schedule constraints that require accelerated delivery, NW Construction, Inc. would be able to produce final delivery of required documents sooner with the addition of another survey crew. NWC personnel will be available at the City of Bozeman's convenience to perform the project starting immediately. Using the estimated duration of 30 days, if the project were to commence on August 111, 2014, estimated delivery of completed documents would be September 111, 2014. Upon notice to proceed, survey and drafting operations will be continuous through completion of project. 3. Project Team Members—Current and Projected Workloads NW Construction Staff: All work for this project will be performed by Erik Kirsch, P.E., P.L.S. with assistance from surveying/drafting technicians under his direct supervision (see attached Project Management Chart). NW Construction staff assigned to the project will work continuous through the duration of the project. Current Workloads: NW Construction, Inc. is currently working on the Wolf Creek Wastewater System in Wolf Creek, MT. NW Construction is the general contractor for the project and also performing construction staking for the project. Personnel assigned to the City of Bozeman Capital Improvements Survey may overlap some with this project during the month of July 2014, however our schedule is flexible to accommodate a quick start on your project if desired. Projected Workloads: Projected workloads for Survey and Drafting personnel include construction projects in the bidding and proposal phase as well as miscellaneous survey projects. No projects exist that conflict with this RFP for the year 2014. Survey crews for as needed construction staking will be made available with prior notice. The 2014 Capital Improvement Projects Field Survey project does not conflict with current or projected workloads for NW Construction team members. 4. NW Construction Inc.—Qualifications NW Construction Inc. is a Bozeman based Heavy Civil Contractor and Design/Survey Firm. What makes NW Construction, Inc. unique as a design/survey firm is our experience in as a general contractor in the heavy civil industry. This experience allows NW Construction to provide cost effective design to our clients as well as cost estimating for design projects. Please find attached (Attachment C — Company Resumes and Projects) some of NW Construction's past projects for reference. The Engineering and Survey Department is managed by Erik Kirsch, P.E., P.L.S. Mr. Kirsch has 18 years combined experience in the fields of Heavy Civil Construction, Civil Design, ConstructionBoundary Surveying, Land Development, Estimating, and Construction Management on Projects located throughout the United States, Mr. Kirsch has provided Consulting Services and Training in these disciplines to several Civil Design Organizations and Heavy Civil Construction Firms and continues as an Instructor at the University Level. As Director of Engineering Operations, Mr. Kirsch's responsibilities include training and oversight of Company design standards in the areas of Computer Aided Drafting (CAD), Field Survey Techniques and Building Information Modeling (BIM) implementation. He provides project-based training to staff engineers in the areas of Construction Layout, GPS/Conventional Survey/Machine Control Instrumentation, Topographic Surveys, Quantity Measurement, 3-D Structure/Terrain Modeling, Alignment Design, Quality Control, and As-built Preparation. Mr. Kirsch also assists with Estimating, Marketing Proposals,and Field Project Management operations. Surveying/Engineering Related Experience: The following projects Performed and Managed by Erik Kirsch represent similar project elements to the RFP: Musselshell Wind Project and Musselshell Wind Project. Shawmut, Montana. Value Confidential at Owner's request. Performed a topographic survey, a geotechnical evaluation of surface conditions, watershed analysis and culvert sizing, as well as determined the alignments for the projects' access roads. This information was used to design roughly 18,000 LF of turbine access road for the two projects. The Company then constructed over 6,100 LF of subgrade for the roads on the two projects. The combined projects are expected to generate 20 MW from 8 to 10 wind turbines. Bridger Vista Development. Bozeman, Montana. Commercial development of two-acre parcel into three commercial units. Responsibilities included design of municipal water and sewer main extensions, submittal of preliminary design review documents to city authority, architectural drafting of commercial structures, and topographic mapping and site survey. Silverbrook Estates. Kalispell, Montana. Development of approximately 300 acres of agricultural land into 466 residential, 120 town homes, and 12 commercial lots. Services included design and oversight of project from preliminary plat approval through final design and construction administration. St. Luke's Community Hospital. Ronan, Montana.Water,sewer, and storm drainage redesign as part of a hospital addition. Responsibilities included lead design for civil infrastructure, engineer surveys, construction oversight/inspection, budget review, scheduling, and subcontractor management. Computer Aided Drafting (CAD) Related Experience: The following projects Performed and Managed by Erik Kirsch represent similar project elements to the RFP: Montana State University, Gallatin College, Bozeman, Montana (2013 - Present) SCOPE. Instructor, DDSN245 - Civil Drafting. The course's featured software is Autodesk Civil 3D Design program. This course builds on previous CAD experience and applies those skills towards creating engineering drawings specifically intended for the Civil Engineering/Heavy Civil Construction Industry. Additional instruction relates to Basic Engineering Principles including: survey data, acquisition, contour/break line creation, azimuth/bearing calculations, coordinate systems, and slope/grade calculations. Successful students are able to efficiently create design elements for engineering drawings relating to Survey Figures, Points, TIN Surfaces, Earthwork Grading, Material Calculations, Alignments, Profiles, Corridor Modeling, and Pipe Networks. Construction Staking Related Experience: The following projects Performed and Managed by Erik Kirsch represent similar project elements to the RFP: Shallow Flooding Irrigation Design Build Project. Owens Lake, Owens Valley, California. $74.4 million. Designed, built, and operated an irrigation system to flood the existing dry Owens Lake lakebed. The conceptual design consisted of 850,740 LF of pipe, including: 21,940 LF of 60-inch conveyance pipe with a river and highway crossing;91,600 LF of mainline pipe ranging in size from 6 to 48 inches; 71,350 LF of submain ranging from 12 to 27 inches;463,450 LF of laterals ranging from 6 to 12 inches; 140,700 LF of drain pipe and 61,700 LF of recycling line. In addition to the pipe,constructed 462,250 LF of roads and berms, as well as pump stations and power generators. The contract also included 18-month operation and maintenance period following completion of the construction phase. Casitas Dam Modification. Ventura, California. $22.5 million. Deep foundation dewatering system; 2 million CY embankment; 580,000 CY excavation; 75,000 CY sand filter zone; tunnel reinforcements (shear plates, steel liner, hydraulic line); environmentally sensitive area. Difficult schedule milestones met. 130,000 man-hours with no lost-time accidents. Received a safety award from the Bureau of Reclamation. Sewer Improvements District No. 1. Bullhead City, Arizona. $21 million. Project involved taking 3,350 residences off septic tank services and installing a new gravity sewer system. Installing 235,720 LF of 6-inch through 36-inch PVC sewer mains and 365,000 LF of service laterals. Surface improvements included street restoration and paving and three sewage lift stations. SCOPE: Grading Superintendent, $15 million Endicott Bridge Project, Prudhoe Bay, Alaska. 0.5 million CY grading and 2 structural steel bridges. 5. NW Construction Inc.—Brochure—Please see Attachment C—Company Resumes and Projects. 6. Non-Discrimination Affirmation Form — Please see Attachment A — Signed Non-Discrimination Affirmation Form Project Scope: 1. Topographic Survey—Street Corridor Survey will be performed using a combination of Robotic Total Station and GPS instruments. 2. Survey Control— Horizontal and Vertical Horizontal control will be established as required by the RFP. Methods used to establish Horizontal Control will vary depending upon accuracy required by City of Bozeman. GPS methods may include RTK positioning, OPUS positioning, or a Static Control Network. Utilizing a robotic total station, a closed-loop traverse may be completed. Horizontal coordinate system will be local and can be shifted to City of Bozeman existing systems. Distances will be ground and units will be international foot definition. Vertical Control will be established as required by the RFP utilizing existing City of Bozeman Vertical Datum. Methods used to establish Vertical Control will vary depending upon accuracy required by City of Bozeman personnel. GPS methods may include RTK positioning or OPUS positioning. Alternately, a differential level loop may be run through all vertical benchmarks to obtain higher accuracy. The Method used for setting control will govern project completion schedule. 3. Site Map—Deliverable 11x17, 22x34, or 2436 sheets and .pdf documents will be made available depending on City of Bozeman Requirements 4. Electronic Files—AutoCAD Civil 3D 2013 Electronic Files will be submitted in AutoCAD Civil 3D 2013 format. City of Bozeman object styles will be utilized if provided by Engineering Department. 5. Construction Staking NWC survey for construction activities will be available when requested by City of Bozeman. Survey personnel will be made available with prior notice by City of Bozeman. 6. Exclusions/Qualifications: Invert measurements of existing sewer/storm systems are included in the anticipated Project Schedule. NON-DISCRIMINATION AFFIRMATION FORM NW Construction, Inc. [name of entity submitting]hereby affirms it will not discriminate on the basis of race,color,religion,creed,sex,age,marital status,national origin,or because of actual or perceived sexual orientation, gender identity or disability in the performance of work performed for the city of Bozeman,if a contract is awarded to it,and also recognizes the eventual contract,if awarded,will contain a provision prohibiting discrimination as described above and that this prohibition shall apply to the hiring and treatment of the NW Construction, Inc. [name of entity submitting]employees and to all subcontracts it enters into in performance of the agreement with the city of Bozeman. 7 Signature of Bidder: Person authorized to sign on bchalfofthe bidder Neil W. VanAmburg, CEO Corporate Resolution of: lU'UUMQiUL11 We, the undersigned, being all the directors of this corporation consent and agree that the following corporate resolution was made On May 16, 2013 At 2:05 PM At Bozeman, Montana We do hereby consent to the adoption of the following as if it was adopted at a regularly called meeting of the board of directors of this corporation. In accordance with State law and the bylaws of this corporation, by unanimous consent, the board of directors decided that: Neil W. VanAmburg and Neil A. Worden are granted authority to sign on behalf of NW Construction, Inc. and/or its affiliates. This includes and any all legal and binding documents submitted on behalf of NW Construction. Inc. and/or it's affiliates. Therefore, it is resolved, that the corporation shall: Grant authority to sign to Neil W. VanAmburg and Neil A. Worden on behalf of NW Construction. Inc. and/or its affiliates. This includes and any all legal and binding documents submitted on behalf of NW Construction. Inc. and/or it's affiliates. The officers of this corporation are authorized to perform the acts to carry out this corporate resolution. Neil W. VanAmbura May 16, 2013 Director signature Printed name Date 4 - Neil A. Worden May 16, 2013 Director signature Printed name Date The Secretary of the Corporation, certifies that the above is a true and correct copy of the resolution that was duly adopted at al n�q of the dated meeting of the board of directors. i Z ` /AX _-May 16. 2013 Signature of Secretary = Z =Uate Neil W. VanAmburg SEAL , Printed name of Secretary % °°° •' ��� O N TNt�p'��``�� � i City of Bozeman—2014 Capital Improvements Projects p�rll 6 Rn ���p�l� Field Survey Project Management Organizational Chart b loc. •'' 1883 . � 9?ij••...... 'O NCO. Neil W. VanAmburg, P.E. / Neil A. Worden Chief Executive Officer/ President Corporate Oversight Erik T. Kirsch, P.E., P.L.S. Director of Engineering Operations Executes and Manages Design and Surveying Operations for NW Construction, Inc. Provides oversight and training to staff technicians,assists corporate level with project management and cost estimating. Field Survey Crew One Field Survey Crew Two Assists with field surveying, construction As Needed staking,construction as-built preparation and associated computer aided drafting(CAD) functions for engineering/surveying and construction projects. Drafting Technician Assists with Computer Aided Drafting (CAD) for engineering/surveying and construction projects. Erik T. Kirsch, P.E., P.L.S. Director of Engineering Operations Education UNMOOR Bachelor of Science, Construction Engineering Technology t / • Montana State University, Bozeman, Montana, 1998 K. Licenses & Certifications l`{ `.�•I Professional Engineer(P.E.), 2006 Professional Land Surveyor(P.L.S.), 2011 Professional Affiliations National Society of Professional Surveyors(NSPS) Montana Association of Registered Land Surveyors (MARLS) Continuing Education BIM Management Certification 2014-Associated General Contractors of America (AGC) ■ BIM Certification Training Class 101, 201, 301,401 i• Trimble GPS Kinematic Training Trimble GPS Static Network Processing Training �o OSHA Competent Person Training (Excavation), 1998 Work Experience NW Construction, Inc., Bozeman, Montana(May 2014-Present) SCOPE: Director of Engineering Operations, Mr. Kirsch has 18 years combined experience in the fields of Heavy Civil Construction, Civil Design, Construction/Boundary Surveying, Land Development, Estimating, and Construction Management on Projects located throughout the United States. Mr. Kirsch has provided Consulting Services and Training in these disciplines to several Civil Design Organizations and Heavy Civil Construction Firms and continues as an Instructor at the University Level. As Director of Engineering Operations, Mr. Kirsch's responsibilities include training and oversight of Company design c standards in the areas of Computer Aided Drafting (CAD), Field Survey Techniques and Building •2 Information Modeling (BIM) implementation. He provides project-based training to staff engineers in the areas of Construction Layout, GPS/Conventional Survey/Machine Control Instrumentation, Topographic C Surveys, Quantity Measurement, 3-D Structure/Terrain Modeling, Alignment Design, Quality Control, and p, As-built Preparation. Mr. Kirsch also assists with Estimating, Marketing Proposals, and Field Project i Management operations. (May 2014-Present)Wolf Creek Wastewater System,Wolf Creek, Montana. $2.3 million. Project consists ,J of the construction of the new wastewater collection system, along with the construction of a new lift o station and wastewater treatment facility.The collection system work includes installation of o approximately 5,955 feet of 8"gravity sewer main and approximately 20 manholes; it includes installation of numerous new sewer services and individual septic system abandonment. Installation of approximately o 1,478 linear feet of 3" HDPE force main using directional drilling of approximately 518 feet of 6"HDPE — steel casting. Construction of new lift station on the souse side of Wolf Creek as well as complete ui construction of new wastewater treatment plant-including building construction,site piping, mechanical -! piping, HVAC, odor control, electrical, plumbing and site work. a ai (May 2014-June 2014) Broadwater Spillway Rubber Gate Replacement Project, Toston Dam, Montana. d $596,500.00. Installation of 7 new inflatable rubber gates 11.5 feet high and 82 feet long each. Work consisted of removal of existing gates, installation of new gates, installation of new air control piping and L valves, concrete coring, concrete demolition, grouting, bulkhead design and installation, dewatering, Y access and safety improvements to the dam. Project required close coordination with the DNRC on scheduling and removal of gates in a staged approached to allow for continue/uninterrupted operations of L the dam and generating facilities. w 1\1 Integral Civil Services, PLLC, Bozeman,Montana (2008 -Present) SCOPE: Owner/Principal. Formation and Management of an Engineering/Survey Firm focusing on Commercial/Residential Site Developments, Municipal Utility Design, Land Boundary Surveys, Topographic Mapping, Wastewater (Septic) Design, Construction Management, CAD Drafting, 3D Modeling, and Civil Consulting/Training Services. Projects located throughout the State of Montana. Montana State University, Gallatin College, Bozeman, Montana(2013 -Present) SCOPE: Instructor, DDSN245 - Civil Drafting. The course's featured software is Autodesk Civil 3D Design program. This course builds on previous CAD experience and applies those skills towards creating engineering drawings specifically intended for the Civil Engineering/Heavy Civil Construction Industry. Additional instruction relates to Basic Engineering Principles including: survey data, acquisition, contour/break line creation, azimuth/bearing calculations, coordinate systems, and slope/grade calculations. Successful students are able to efficiently create design elements for engineering drawings relating to Survey Figures, Points, TIN Surfaces, Earthwork Grading, Material Calculations, Alignments, Profiles, Corridor Modeling, and Pipe Networks. Previous Work History: Barnard Companies, Bozeman,Montana (1998 -2006 and 2009-April 2014) SCOPE: Survey/CAD Manager, Lead Estimator. Responsible for training, and oversight of company design standards in areas of AutoCAD drafting and field survey techniques. Provided project-based training to staff engineers and coordinated subcontractor activities through duration of concurrent projects across the United States. Provided instruction and training in areas of Construction Layout, GPS Instrumentation, Optical Total Stations, Topographic Surveys, Quantity Measurement, 3-D Terrain Modeling (AutoCAD Land Desktop, AGTEK), Alignment Design, Quality Control, and As-built Preparation. Responsible for quantity take-off/verification of contract drawings. (2011) Musselshell Wind Project and Musselshell Wind Project. Shawmut, Montana. Value Confidential at Owners request. Performed a topographic survey, a geotechnical evaluation of surface conditions, watershed analysis and culvert sizing, as well as determined the alignments for the projects' access c roads.This information was used to design roughly 18,000 LF of turbine access road for the two projects. g The Company then constructed over 6,100 LF of subgrade for the roads on the two projects. The 2 combined projects are expected to generate 20 MW from 8 to 10 wind turbines. n O (2006-2008) EAA Reservoir(A-1). South of South Bay, Florida. Construction Management @ Risk, not to a' exceed $400 million. Completed three contracts as part of state and federal effort to restore the W Everglades. GMPs 1 through 3 included constructability and design review, clearing and grubbing, 5 million cy of muck removal, dewatering, drilling and blasting, excavation for a 15-mile seepage control canal, various embankment test sections, and construction and operation of an complex, large-scale w aggregate production plant. Barnard self-performed 75 percent of the contracts while also conducting a ° very successful subcontracting and local hiring program, which included an onsite training program for 2 operators. a i5 (2006) C-43 West Storage Reservoir Test Cell Pilot Project. Hendry County, Florida. $10.25 million. Constructed two separate test cells using primarily onsite materials. Groundwater elevation is two feet below surface. Accelerated schedule. Cleared and grubbed 267 acres of orange grove, cell stripping 8- a inch — 113,000 CY; zoned embankment 555,000 CY; filter blanket and chimney 36,000 CY; canal ua excavation 325,000 CY;soil bentonite cutoff wall 96,000 SF; soil cement 2,500 CY; piezometers—133 a each; electrical and instrumentation; installed temporary pumping and piping systems. u Y H Y L W 11 Ali (2005-2006) Owens Lake Phase V. Keeler, California. $99.7 million. Very tough soil conditions; somewhat hostile work environment. Dust Control Measures: traditional shallow flooding, approximately four square miles, extensive pipeline distribution network, berms; deep-water shallow flood, approximately seven square miles, berms, extensive riprap protection; gravel cover, approximately .2 square miles. Operations and maintenance facilities: permanent home for Los Angeles Department of Water and Power lakebed operations, approximately 32,000 square feet of building space. (2002-2005) Saluda Dam Remediation Project. Columbia, South Carolina. $188 million. Barnard was selected under an alternative procurement process that included significant value engineering. Reconstruction of an earthen embankment dam constructed in 1930 as part of a 206-Mw hydroelectric facility. 1.3 million CY of RCC; 4.1 million CY of Rockfill; 4.5 million CY of drilled and shot quarry excavation; sequenced toe excavation; zoned earthfill dam embankment; demolition and reconfiguration of large-diameter water lines; 4 million CY overburden removal and replacement; 30,000 CY mass concrete; extensive dewatering system; 34,080 SF beam and lag tieback walls; 14,300 SF cement- bentonite slurry tieback walls, managed OCIP and Safety Program. (2002-2005) Tampa Bay Regional Reservoir. Tampa, Florida. $84.2 million. 12 million CY reservoir embankment; 2 million CY waste clay (slime) removal and disposal; 820,000 SF soil bentonite cutoff wall; 100-foot water tower control structure and bridge; drilled concrete caissons; 10,028 LF of 84-inch and 72- inch diameter steel pipe; 600 LF of 42- inch steel pipe; over 1 million SY geomembrane and geotextile fabric; 350,000 CY soil cement; construction of two reservoir access roads; treatment facilities area with chemical and compressor buildings and chemical containment storage area; 30,094 LF of 8-foot chain link fence; 800 acres and 1 million CY grading for three new wetland mitigation areas. Work was performed in extreme weather conditions: wettest December(2002) in recorded Florida history and three hurricanes(2004). Heavily monitored by the Department of Environmental Protection. SCOPE: Project Engineer. Performed a wide range of engineering/management functions, including planning, estimating, quality control, cost control, progress reporting, surveying, quantity tracking, purchasing, and subcontractor coordination. Responsible for obtaining, reviewing, and forwarding product submittals. (2000-2001) Shallow Flooding Irrigation Design Build Project. Owens Lake, Owens Valley, California. g $74.4 million. Designed, built, and operated an irrigation system to flood the existing dry Owens Lake lakebed. The conceptual design consisted of 850,740 LF of pipe, including: 21,940 LF of 60-inch a conveyance pipe with a river and highway crossing; 91,600 LF of mainline pipe ranging in size from 6 to 0 48 inches; 71,350 LF of submain ranging from 12 to 27 inches; 463,450 LF of laterals ranging from 6 to 0' 12 inches; 140,700 LF of drain pipe and 61,700 LF of recycling line. In addition to the pipe, constructed 462,250 LF of roads and berms, as well as pump stations and power generators. The contract also C: included 18-month operation and maintenance period following completion of the construction phase. C: w (1999-2000) Casitas Dam Modification. Ventura, California. $22.5 million. Deep foundation dewatering ° system; 2 million CY embankment; 580,000 CY excavation; 75,000 CY sand filter zone; tunnel ° reinforcements (shear plates, steel liner, hydraulic line); environmentally sensitive area. Difficult schedule milestones met. 130,000 man-hours with no lost-time accidents. Received a safety award from the o Bureau of Reclamation. vi J (1998-1999) Sewer Improvements District No. 1. Bullhead City, Arizona. $21 million. Project involved n: taking 3,350 residences off septic tank services and installing a new gravity sewer system. Installing W 235,720 LF of 6-inch through 36-inch PVC sewer mains and 365,000 LF of service laterals. Surface a improvements included street restoration and paving and three sewage lift stations. SCOPE: Grading E Superintendent, $15 million Endicott Bridge Project, Prudhoe Bay,Alaska. 0.5 million CY grading and 2 i structural steel bridges. Y H Y L W Schlauch Bottcher Construction, Bozeman, Montana (Sept. 2007-Jan.2009) SCOPE: Construction Manager, Civil Engineer. Responsible for project management and design of various residential/commercial structures and residential/commercial developments. Responsibilities included: civil design, surveying, drafting, scheduling, subcontractor management and estimating. (2007-2009) Ameya Preserve Development. Livingston, Montana. Development of approximately 9,000 acres into a high-end residential community. Project focused on sustainable design and construction practices. Responsibilities included acting as owner's representative for initial infrastructure construction, subcontractor management, project scheduling, and cash flow analysis through phase-one build-out. (2007-2008) Bridger Vista Development, Bozeman, Montana. Commercial development of two-acre parcel into three commercial units. Responsibilities included design of municipal water and sewer main extensions, submittal of preliminary design review documents to city authority, architectural drafting of commercial structures, and topographic mapping and site survey. CTA, Inc., Bozeman, Montana (Oct. 2006-Sept.2007) SCOPE: Project Manager, Construction Manager, Civil Engineer. Responsible for project management and civil design on various commercial ad residential development projects. Responsibilities included: construction oversight and subcontractor management, scheduling, civil design, and internal project coordination. (2006-2007) Amsterdam Village Subdivision. Churchill, Montana. Development of approximately 350 acres of agricultural land into 312 residential, 60 town homes, and 16 commercial lots. Responsibilities included project management for engineering and architectural design teams, development of subdivision design guidelines and covenants, marketing, and construction administration. (2006-2007) Silverbrook Estates. Kalispell, Montana. Development of approximately 300 acres of agricultural land into 466 residential, 120 town homes, and 12 commercial lots. Services included design and oversight of project from preliminary plat approval through final design and construction administration. U) (2006) St. Luke's Community Hospital. Ronan, Montana. Water, sewer, and storm drainage redesign as o part of a hospital addition. Responsibilities included lead design for civil infrastructure, construction 2 oversight/inspection, budget review, scheduling, and subcontractor management. o O c N C_ m C w w O U Ui J a ui a X Y Y 'C W lip, ; Neil W. VanAmburg, P.E. Chief Executive Officer, Co-Owner Colin inucliun Education 4- Bachelor of Science, Construction Engineering Technology ME. Montana State University, Bozeman, Montana, 1995 ,E .• Professional Engineer(P.E.),2002 Awards and Accomplishments Wanapum Dam Future Unit Infill Project- Earned Oregon Daily Journal of Commerce's Top Projects Award-3rd Place, 2011 Public Works/ Infrastructure/Transportation Barnard, HDR Engineering, Inc. and Puget Sound Energy-Received the ASCE Region 8 Minor Project Honorable Mention for design of the Snoqualmie Falls Long-Term Construction Cofferdams,2011 •3 2006 U.S. Society on Dams Award of Excellence in the Constructed Project — Saluda Dam ❖ 2006 AON Build America Award: New Municipal and Utilities—Saluda Dam 2006 American Society of Civil Engineers'Opal Award—Saluda Dam ❖ 2000 Bureau of Reclamation Safety Award—Casitas Dam Professional Affiliations AIC Member USSD Member—Co-authored paper on techniques used in dam construction. Certified Nuclear Gauge Operator •3 Certified ACI Concrete Field Testing Technician-Grade I Montana Contractor Association Scholarship Recipient Licenses& Certifications Contracting License Qualifier in: • Florida, 2008 • South Carolina, 2010 ■ Virginia, 2010 • Oregon,2011 ■ North Carolina,2011 ■ Utah, 2011 p • Arizona, 2011 • California,2012 ■ Alabama,2012 ` ■ Montana, 2012 a O a� Continuing Education v 30-hour Occupational Safety and Health Training Course, 2013 _ Primavera P6 Professional Fundamentals,2013 US Army Corps of Engineers, Construction Quality Management for Contractors, Course #784, Wa 2013 ar Florida Continuing Education-General Contractor, 2012 Engineering Symbology, Prints and Drawings, 2010 S• Primavera Project Management: Planning&Controlling Projects, 2007 E Q "Transportation Engineering"course, 2005 RCC Seminar, 2004 > U.S.Society on Dams, 2003 Breakthrough Project Leadership, an Institute for Project Leaders, 2000 d First Aid/Adult CPR Certification, 1999, 2003, 2009 Z li Continuing Education (continued) ee 10-hour Occupational Safety and Health Training Course, 1998 Primavera Project Planner, Managing Project Data, 1998 Primavera Project Planner, Resource and Cost Analysis, 1998 .• Karrass Effective Negotiating, 1997 Work Experience NW Construction, Inc., Bozeman, Montana(2013-Present) SCOPE: Co-Owner/Chief Executive Officer. In 2013 Mr. VanAmburg and Mr. Neil Worden formed NW Construction, Inc. The company is a general contracting company focused on heavy-civil construction, including but not limited to Dams, Hydroelectric, RCC (roller compacted concrete), Concrete, Large and Small Diameter Piping, Sheet Piling, Site Work, Utilities, Slurry Walls, Demolition, Marine, Drill and Shoot, and Aggregate Processing. Mr. VanAmburg and Mr. Worden have over 40 years of combined experience in heavy-civil construction located throughout the United States and Canada. As CEO, Mr. VanAmburg oversees all operations for NWC, Inc. and is involved in all of the organizations executive decisions. Mr. VanAmburg is also responsible for Company Safety and Quality, Human Resources, Administration, Business Management (accounting, insurance/bonding and tax management), Estimating, Project Management, Marketing, and Technological Enhancements. (May 2014-Present)Wolf Creek Wastewater System,Wolf Creek, Montana. $2.3 million. Project consists of the construction of the new wastewater collection system, along with the construction of a new lift station and wastewater treatment facility. The collection system work includes installation of approximately 5,955 feet of 8"gravity sewer main and approximately 20 manholes; it includes installation of numerous new sewer services and individual septic system abandonment. Installation of approximately 1,478 linear feet of 3" HDPE force main using directional drilling of approximately 518 feet of 6"HDPE steel casting. Construction of new lift station on the souse side of Wolf Creek as well as complete construction of new wastewater treatment plant—including building construction, site piping, mechanical piping, HVAC, odor control, electrical, plumbing and site work. (February 2014-June 2014) Broadwater Spillway Rubber Gate Replacement Project, Toston Dam, Montana. $596,500.00. Installation of 7 new inflatable rubber gates 11.5 feet high and 82 feet long each. Work consisted of removal of existing gates, installation of new gates, installation of new air control piping and valves, concrete coring, concrete demolition, grouting, bulkhead design and installation, dewatering, access and safety improvements to the dam. Project required close coordination with the DNRC on scheduling and removal of gates in a staged approached to allow for continue/uninterrupted operations of the dam and generating facilities. V_ (July 2013-October 2013) South Jetty Dune Stabilization. Fort Stevens State Park, Hammond, Oregon. a, $1.7 million. This project consisted of constructing a dynamic revetment to an elevation from elevation S� 9.00 to elevation 22.00 along the shoreline. Work consisted of approximately 20,000 CY of excavation a and 50,000 CY of zoned embankment with imported aggregates ranging in size up to 8" diameter. This project had a critical schedule that had to be completed prior to winter season. Located on a beach within a state park,the South Jetty Dune Stabilization project was completed successfully with no environmental r or public impacts. The project was completed within budget,on time with no safety violations. U Barnard Companies, Bozeman,Montana(1996-2013) ui SCOPE: Operations ManagerNice President. Overall project responsibility at the Vice President level. a Responsible for and oversaw physical construction efforts on over $300 million in value on completed projects. Overall responsibility of estimates reaching $600 million in size per project. Project Managers and General Superintendents report to the Operations Manager. Regularly visits project sites, E corresponds daily with site management, and institutes all training, safety and quality control programs. C Responsible for estimates and projects from conception through completion. The Operations Managers > reported to the President of the company. Mr.VanAmburg was promoted in 2008. z (2012-2013) Blue Lake Dam Expansion Project. Sitka, Alaska. $88.38 million. This remote project encompassed raising a concrete arch dam 83 feet and constructing a replacement powerhouse to generate more hydroelectric power for the local community. The scope also included a 900 LF new intake tunnel and concrete intake structure; modifications to an existing tunnel; a 360 VF, 10-ft.-dia. Surge shaft; a new penstock section; installation of three 5.3 MW horizontal Francis turbine generators; and the addition of two 69 kV transformers in the associated switchyard upgrade. (2012) Owens Lake Dust Mitigation Project, Phase 8. Lone Pine, California. $53.5 million. Barnard's seventh dust mitigation project on Owens Lake for the Los Angeles Department of Water and Power. Phase 8 addresses a 2-square-mile section of the 30-square-mile dry Iakebed prone to dust storms. The project encompasses crushing, hauling and placing 600,000 CY of gravel, placing 7 million SY of geotextile fabric, and constructing 6,000 LF of 30-inch HDPE pipe within the project site. Challenging conditions include soft subgrade and remote, high desert jobsite. (2011-2012) Los Vaqueros Reservoir Expansion Project, Dam Enlargement. Contra Costa County, California. $35.35 million. Expanding the Los Vaqueros Reservoir's capacity by 60,000 acre-feet involves raising the dam by 34 feet. Barnard will first excavate 47 feet off the existing dam and then add 81 feet to the dam. The project requires 40,000 CY of RCC, 1 million CY of zoned embankment, 525,000 CY of blasting, 100,000 CY of crushing, construction of a 40,000 SF MSE wall, and 100-foot-deep, two-row grout curtain as well as installation of instrumentation and controls, construction of mechanical, electrical and dam facilities structures, and road restoration.Accelerated schedule involving double shifts. (2010-2012) Elwha and Glines Canyon Dam Removal. Port Angeles, Washington. $26.94 million. To restore the Elwha River ecosystem, Barnard will deconstruct the 108-foot-tall Elwha Dam and 210-foot- tall Glines Canyon Dam in a controlled fashion. This involves: demolition (drilling and blasting) and removal of 3,900 CY of concrete from two powerhouses; demolition and removal of 27,000 CY of concrete; work within cofferdams; removal of five hydro-turbine generators; removal of five steel penstocks; demolition and removal of two steel surge towers; removal of 200,000 CY of sediment, rock, gunite and trees; removal of 8 miles of overhead high-voltage transmission lines; removal of concrete intakes and spillways; removal of gate structures; and significant site restoration. (2010-2012) Snoqualmie Falls Hydroelectric Redevelopment Project— Construction Phase. Snoqualmie, Washington. $140.0 million. The project initially involved Design-Assist / Value Engineering services working with the Owner and Engineer to develop plans for the rehabilitation of two, 100-year-old power plants as well as expansion of a diversion dam. Barnard completed the design phase. Our construction scope, which began in 2010, includes: tunnel and shaft work, underground powerhouse (cavern) work, hydro turbine generators, in-river work behind cofferdams, large hydraulic concrete structures, drilling and o blasting, and large-diameter steel pipe work on a very steep hill. The Project is located at an a, environmentally sensitive tourist destination. (2009-2010) Wanapum Dam Future Unit Infill. Beverly, Washington. $29.73 million. Project required C stabilizing five bays in a 1960s dam with mass and structural concrete. The project entailed design and 0 installation of 585 prefabricated concrete stop logs with fish brushes. Stop log installation required diving t to depths of up to 120 feet. Barnard preceded bay-by-bay with dewatering, fish removal, demolition of U existing bulkhead and concrete ceiling and placement of 36,000 CY of structural and mass concrete. — Year-round project on the Columbia River; worked around fish migration. The project was completed two uj years ahead of the owner's original schedule. a ai (2008-2011) Pit River Dams 3, 4, and 5 License Implementation Project. Burney, California. Value n confidential at owner's request. This project included installation of 8-foot-diameter pipes and E appurtenances through Pit River Dams 3, 4 and 5 to increase the river's flow as part of a relicensing c agreement with the Federal Energy Regulatory Commission. Penetration of each dam involved > cofferdamming, core drilling, and demolition, as well as structural analysis of the penetration itself. Installing the 30-foot-tall structural steel intakes and custom-made knife gate valves required work on the — water and diver assistance to depths up to 100 feet deep. Starting with valve house foundation Z excavation, the project required soil nails and rock bolts, drilling 30 to 70 feet into the hillside. We then installed #10 ksi bar with double corrosion protection and followed this with load-testing. The project also required construction of shotcrete support walls. In addition, the project added 38 turnouts to the existing River Road, replacement of two bridges, drainage system upgrade, and recreation improvements throughout the Pit River watershed. All of this work took place in a highly sensitive environment, which required critical permitting and received close scrutiny by regulatory agencies. SCOPE: Project Manager. (1997-2008) Responsibilities included safety management, quality control, purchasing, scheduling, cost-tracking and cost controls, subcontract administration and contract negotiations.Also assists in preparing bids ranging from $1 million to $600 million involving underground utility work, earthwork, concrete structures, dam rehabilitation, soil-cement and roller-compacted concrete. (2006-2008) EAA Reservoir(A-1). South of South Bay, Florida. Construction Management @ Risk, not to exceed $400 million. Completed three contracts as part of state and federal effort to restore the Everglades. GMPs 1 through 3 included constructability and design review, clearing and grubbing, 5 million cy of muck removal, dewatering, drilling and blasting, excavation for a 15-mile seepage control canal, various embankment test sections, and construction and operation of an complex, large-scale aggregate production plant. Barnard self-performed 75 percent of the contracts while also conducting a very successful subcontracting and local hiring program, which included an onsite training program for operators. (2002-2005) Saluda Dam Remediation Project. Columbia, South Carolina. $188 million. Barnard was selected under an alternative procurement process that included significant value engineering. Reconstruction of an earthen embankment dam constructed in 1930 as part of a 206-Mw hydroelectric facility. 1.3 million CY of RCC; 4.1 million CY of Rockfill; 4.5 million CY of drilled and shot quarry excavation; sequenced toe excavation; zoned earthfill dam embankment; demolition and reconfiguration of large-diameter water lines; 4 million CY overburden removal and replacement; 30,000 CY mass concrete; extensive dewatering system; 34,080 SF beam and lag tieback walls; 14,300 SF cement- bentonite slurry tieback walls, managed OCIP and Safety Program. (2001-2002) Saluda Dam Phase III RCC Test Section. Columbia, South Carolina. $4.5 million. Test section work for larger dam project. 478,000 CY of overburden removal; drill, shoot and process 92,000 CY aggregate for rockfll and RCC test sections; 3,500 CY RCC. (1999-2000) Casitas Dam Modification. Ventura, California. $22.5 million. Deep foundation dewatering system; 2 million CY embankment; 580,000 CY excavation; 75,000 CY sand filter zone; tunnel reinforcements (shear plates, steel liner, hydraulic line); environmentally sensitive area. Difficult schedule a, milestones met. 130,000 man-hours with no lost-time accidents. Received a safety award from the w Bureau of Reclamation. E 0 a (1997) Dulce Lake Dam and Lower Mundo Lake Dam. Dulce, New Mexico. $7.4 million. 350,000 CY O excavation and embankment. 36,000 SF cement-bentonite slurry wall. 5,700 CY RCC overtopping 2) protection. Deep foundation dewatering system. Outlet works and irrigation supply control structure. U Reinforced concrete box overflow spillway. Temporary cofferdams. uw SCOPE: Project Engineer. (1996-1997) Performs a wide range of engineering/ management functions, a: including planning, estimating, quality control, cost control, progress reporting, surveying, quantity tracking, purchasing, and subcontractor coordination. Responsible for obtaining, reviewing, and a' forwarding product submittals. E Q c (1996) Wirtz Dam - Soil Cement/RCC Overtopping Protection. Marble Falls, Texas. $8.5 million. Project > involved 175,000 CY RCC/soil-cement placement; 130,000 SF RCC/soil-cement vertical steps; 440,000 CY general excavation; 46,000 CY rock excavation; 280,000 CY dam embankment; 1,850 LF exploratory — iiz � 1 r holes;20,000 SY surface preparation of rock foundation; 820 each rock anchors; 950 LF duct bank; 2,700 CY structural concrete; and 1,460 CY grout for riprap. (1996) Bonneau Dam Outlet Works. Rocky Boy Indian Reservation, Montana. $3.45 million. Project involved: breech and reconstruction of existing dam and installation of new outlet works; 101,900 CY of excavation; 108,250 CY of zoned embankment; 1,656 CY of concrete, including 105 ft. high intake tower; 550 LF of 36-inch cast-in-place conduit to regulate discharge; bridge piers and energy dissipater; curtain grouting; 150 CFS cofferdam and dewatering system; an access bridge;and instrumentation. Martin K Eby Construction Co.,Austin, Texas (Dec. 1995-May 1996) SCOPE:Field Engineer. Responsible for surveying and layout for concrete crews on elevated segmented bridge job. Quantity tracking and quality control. Martin K Eby Construction Co.,Austin,Texas (Summer 1995) SCOPE: Internship. Worked as field engineer on segmented bridge. Generated spreadsheets for scheduling, quantities and equipment costs. Surveying, level work,tracking of quantities. Campbell &Associates, Cody,Wyoming (Summer 1994) SCOPE:Surveyor. Surveyed subdivision, ran grade lines, ran section lines, located and set comers. a� U_ O C .� N Q. O v- N L U LLJ d II1 L 3 .B E Q C t4 Z Z it Neil A. Worden President, Co-Owner Education U n ■ E` Northeast Wyoming Community College, Torrington,Wyoming Areas of Expertise •3 Operator of all heavy equipment ❖ Waterline, ductile RCP 2-to 48-inch PVC, Enron Poly welding &fusing Sewer—RCP, clay, poly, PVC,4-to 60-inch Piling—sheet, pipe, cofferdam Foundations, sidewalks, bridge construction, placement Pour concrete, rebar placement,tying, bending Dewatering ❖ Slurry trenching Installation of geomembrane .• Demolition s Microtunneling Marine Awards and Accomplishments Wanapum Dam Future Unit Infill Project- Earned Oregon Daily Journal of Commerce's Top Projects Award-3rd Place, 2011 Public Works/ Infrastructure/Transportation 2011 AON Build America Award: Environmental New Construction—Round Butte Best of 2010 Award, Northwest Construction--Round Butte 2010 Edison Award, electric utility industry's highest honor—Round Butte 2007 U.S. Bureau of Reclamation Construction Safety Award—San Xavier Farm Rehab Project s• 2006 U.S. Society on Dams Award of Excellence in the Constructed Project — Saluda Dam 2006 AON Build America Award: New Municipal and Utilities—Saluda Dam 2005 U.S.Army Corps of Engineers Civil Contractor of the Year- Northwestern Division, Fern Ridge Dam 2001 Marvin M. Black Excellence in Partnering Award—Lake Source Cooling Project d• 2001 Barnard Safety Award,44,000 man-hours with no lost-time accidents Trade Experience Superintendent, 13 years Foreman,4 years Heavy Equipment Operator,21 years Laborer, Pipelayer, 1 year N d L Continuing Education a. 30-hour Occupational Safety and Health Training Course, 2013 c 8• US Army Corps of Engineers, Construction Quality Management for Contractors, Course #784, -a 2013 0 First Aid/CPR Training 24-Hour New Miner MSHA Training Q Breakthrough Project Leadership, an Institute for Project Leaders ❖ Breakthrough Production Management Workshop z I Work Experience NW Construction,Inc., Bozeman, Montana (2013-Present) SCOPE: Co-Owner/President. In 2013 Mr. Worden and Mr. Neil VanAmburg formed NW Construction, Inc. The company is a general contracting company focused on heavy-civil construction, including but not limited to Dams, Hydroelectric, RCC (roller compacted concrete), Concrete, Large and Small Diameter Piping, Sheet Piling, Site Work, Utilities, Slurry Walls, Demolition, Marine, Drill and Shoot, and Aggregate Processing. Mr. VanAmburg and Mr. Worden have over 40 years of combined experience in heavy-civil construction located throughout the United States and Canada. As President, Mr. Worden oversees all operations for NWC, Inc. and is involved in all of the organizations executive decisions. Mr. Worden is also responsible for Company Safety and Quality, Estimating, Scheduling, Job Selection, Project Superintendence and Equipment Management. (May 2014-Present)Wolf Creek Wastewater System,Wolf Creek, Montana. $2.3 million. Project consists of the construction of the new wastewater collection system, along with the construction of a new lift station and wastewater treatment facility. The collection system work includes installation of approximately 5,955 feet of 8"gravity sewer main and approximately 20 manholes; it includes installation of numerous new sewer services and individual septic system abandonment. Installation of approximately 1,478 linear feet of 3" HDPE force main using directional drilling of approximately 518 feet of 6"HDPE steel casting. Construction of new lift station on the souse side of Wolf Creek as well as complete construction of new wastewater treatment plant—including building construction, site piping, mechanical piping, HVAC, odor control, electrical, plumbing and site work. (February 2014-June 2014) Broadwater Spillway Rubber Gate Replacement Project, Toston Dam, Montana. $596,500.00. Installation of 7 new inflatable rubber gates 11.5 feet high and 82 feet long each. Work consisted of removal of existing gates, installation of new gates, installation of new air control piping and valves, concrete coring, concrete demolition, grouting, bulkhead design and installation, dewatering, access and safety improvements to the dam. Project required close coordination with the DNRC on scheduling and removal of gates in a staged approached to allow for continue/uninterrupted operations of the dam and generating facilities. July 2013-October 2013) South Jetty Dune Stabilization. Fort Stevens State Park, Hammond, Oregon. $1.7 million. This project consisted of constructing a dynamic revetment to an elevation from elevation 9.00 to elevation 22.00 along the shoreline. Work consisted of approximately 20,000 CY of excavation and 50,000 CY of zoned embankment with imported aggregates ranging in size up to 8" diameter. This project had a critical schedule that had to be completed prior to winter season. Located on a beach within a state park, the South Jetty Dune Stabilization project was completed successfully with no environmental or public impacts. The project was completed within budget, on time with no safety violations. Barnard Companies, Bozeman, Montana (1997-2013) SCOPE: Project Superintendent. Responsible for supervision of company foremen and crews; scheduling and tracking of subcontractors and suppliers; daily cost controls; acquisition of equipment, material and labor; work with the Owner, the Owner's agents, inspectors, public and private parties, as necessary; supervise implementation of all safety, quality control, environmental, drug testing, or other — project-specific programs. When not assigned to a project, works with the Estimating Team at the Home Office. a d (2012-2013) Blue Lake Dam Expansion Project. Sitka, Alaska. $88.38 million. This remote project a` encompassed raising a concrete arch dam 83 feet and constructing a replacement powerhouse to generate more hydroelectric power for the local community. The scope also included a 900 LF new intake tunnel and concrete intake structure; modifications to an existing tunnel; a 360 VF, 10-ft.-dia. Surge o shaft; a new penstock section; installation of three 5.3 MW horizontal Francis turbine generators; and the 3� addition of two 69 kV transformers in the associated switchyard upgrade. Q W z (2010-2011) Elwha and Glines Canyon Dam Removal. Port Angeles, Washington. $26.94 million. To restore the Elwha River ecosystem, Barnard will deconstruct the 108-foot-tall Elwha Dam and 210-foot- tall Glines Canyon Dam in a controlled fashion. This involves: demolition (drilling and blasting) and removal of 3,900 CY of concrete from two powerhouses; demolition and removal of 27,000 CY of concrete; work within cofferdams; removal of five hydro-turbine generators; removal of five steel penstocks; demolition and removal of two steel surge towers; removal of 200,000 CY of sediment, rock, gunite and trees; removal of 8 miles of overhead high-voltage transmission lines; removal of concrete intakes and spillways; removal of gate structures; and significant site restoration. (2009-2010) Wanapum Dam Future Unit Infill. Beverly, Washington. $29.73 million. Project required stabilizing five bays in a 1960s dam with mass and structural concrete. The project entailed design and installation of 585 prefabricated concrete stop logs with fish brushes. Stop log installation required diving to depths of up to 120 feet. Barnard preceded bay-by-bay with dewatering, fish removal, demolition of existing bulkhead and concrete ceiling and placement of 36,000 CY of structural and mass concrete. Year-round project on the Columbia River; worked around fish migration. The project was completed two years ahead of the owner's original schedule. (2007-2009) Snoqualmie Falls Hydroelectric Redevelopment Project — Design Phase. Snoqualmie, Washington. Value confidential at owner's request. The project consisted of Design-Assist services working with the Owner and Engineer to develop plans for the rehabilitation of two 100-yearold power plants as well as expansion of a diversion dam. Project scope includes: tunnel rehabilitation; rock shaft reconstruction; concrete intake structures; concrete diversion dam; cofferdams; large-diameter penstock; and hydroelectric facilities. (2006-2009) Round Butte Dam Selective Water Withdrawal. Madras, Oregon. Value confidential at owner's request. This project included a one year Design-Assist phase during which Barnard, Owner PGE, and CH2MHill worked to improve the design and cost of the facility. Steel structure fabrication and erection: 700-ton steel bottom structure—68 FT long by 57 FT wide by 67 FT high, submerged 270 FT; 270-ton, 40-FT-diameter steel conduit structure submerged to connect top and bottom; 1,316-ton floating structure — 150 FT long by 90 FT wide by 50 FT high; 287-FT-long access bridge. These large steel structures were assembled over water and attached to the existing powerhouse intake structure. The project also included underwater excavation, drilling, concrete, and structural work at 270 FT deep. (2005) Fern Ridge Dam Emergency Repair. Eugene, Oregon. $16.53 million. Emergency reconstruction of an existing earthen dam; excavated 403,304 CY of embankment; placed 71,992 CY of filter sand and 46,885 CY of filter rock to construct a toe drain collection system; constructed impoundment dikes inside reservoir; embanked 330,064 CY to reconstruct dam. Project was fast-tracked; double shifts were required. Our team received the U.S. Army Corps of Engineers' Civil Contractor of the Year Award — Northwestern Division. (2005-2006) San Xavier Farm Rehabilitation. San Xavier District, Tohono O'odham Nation, Pima County, Arizona. $31 million. Complete rehabilitation of the existing farm including new mainline and lateral — pipeline for irrigation water delivery and construction of embankments and flood channels to protect farm from flash-flooding during rainy season. 446,407 CY flood channel excavation; 81,220 CY compacted 'a embankments; 14,580 CY soil-cement; 32,560 CY gabions and riprap; 3,872 CY conventional concrete; v a` 6,533 CY shotcrete; 68,141 LF PVC piping ranging from 2 to 36 inches; 1,335 LF metal piping ranging from 2 to 36 inches; electrical and telemetry systems. m (2004-2006) Bisbee Wastewater Improvements Project. Bisbee, Arizona.$23.75 million. Replaced 82,700 0 LF of existing sanitary sewer collection systems; installed and replaced 51,600 LF of sanitary sewer 3: interceptors; installed 5,800 LF of force main. Constructed new treatment facility and lift station. a Decommissioned current wastewater treatment plants and lagoons. Techniques used to bury pipe z included direct bury,jack and bore casing and pipe bursting. Conditions encountered ranged from cross- country work to narrow city streets. Slopes ranged up to 20 percent. Pipe inverts ranged from 2 to 20 feet. (2002-2003) Saluda Dam Remediation Project. Columbia, South Carolina. $188 million. Barnard was selected under an alternative procurement process that included significant value engineering. Reconstruction of an earthen embankment dam constructed in 1930 as part of a 206-Mw hydroelectric facility. 1.3 million CY of RCC; 4.1 million CY of Rockfill; 4.5 million CY of drilled and shot quarry excavation; sequenced toe excavation; zoned earthfill dam embankment; demolition and reconfiguration of large-diameter water lines; 4 million CY overburden removal and replacement; 30,000 CY mass concrete; extensive dewatering system; 34,080 SF beam and lag tieback walls; 14,300 SF cement- bentonite slurry tieback walls. (2002) Lakewood Raw Water Pipeline Reconstruction, Phase III, Boulder, Colorado. $21.89 million. Installation of 42,000 LF of 27- to 36-inch welded steel pipe; narrow right-of-way; extensive drilling and blasting; dewatering; wetlands crossings; stream crossing; steep slope construction; environmentally sensitive; USFS property for 12,000 LF of pipeline; fiber optic line; 42,000 LF miscellaneous pipeline appurtenances; concrete diversion structure. (2000-2001) DeCordova Bend Dam Spillway Gate and Hoist Improvements, Contract — 2. Granbury, Texas. $8.25 million. Repaired and strengthened 16 spillway gates; cleaned and painted upstream and downstream portions of spillway gates; constructed new concrete hoist platforms; installed electric hoists at 16 spillway gates; installed new electric power to supply to hoists and existing traveling hoist. (1999-2001) Plateau Creek Pipeline Replacement-Phase 2. Grand Junction, Colorado. $44.5 million. Installed 39,197 LF of 48-inch and 36,793 LF of 54-inch cement mortar-lined tape-coated welded-steel water line; constructed 13,260 LF of 10-foot tunnels using Tunnel Boring Machine; 12 river crossings; rock blasting for pipeline excavation and portal construction; concrete vaults and tunnel portals; extensive dewatering. SCOPE: Foreman. Ensures the safety of crews and personnel in work zones. Provides crew with information and necessary tools. Inspects tools and equipment and maintains in good and safe working condition. Supervises crews. Conducts daily safety and tool box meetings. Records daily costs and prepares budget report. Sets good examples for crew as well as others (professional work ethic and manners). Trains employees at work site. Has thorough knowledge of project plans. Maintains quality work, done in an efficient and timely manner. Promotes teamwork. (1999) Many Farms Dam Modification. Many Farms, Arizona. $12.79 million. Phase I: Raised three dikes 10 feet (140,000 CY zoned fill). Constructed 6,200 CY RCC spillway. Relocated two public roads. Constructed canal crossing. Phase ll: Raised dam 10 feet (213,000 CY zoned fill). Constructed cofferdam. Installed new toe drains. Demolished and reconstructed outlet works. Constructed outlet works canal. Placed 49,000 CY riprap on faces of dam and dikes. (1999) Lake Source Cooling Project, Chilled Water Transmission Piping. Ithaca, New York. $19.6 million. — Barnard was selected under an alternative procurement process, based on experience, work plans, value engineering, and personnel. Installed 28,000 LF of 42-inch API steel pipe with welded joints. Installed v controlled density fill around 42-inch chilled water pipeline. Installed new sanitary sewer, new water main, d and new storm sewer. New paving, sidewalks, granite curb, and landscaping along the pipeline route. a` Shored excavations with sheetpile, H-beams, lagging. River crossing with steel pipe suspended under a ' bridge. Worked in residential, public, private and wooded areas. Extensive traffic control. -(D L O (1998) Sewer Improvement District No. 1. Bullhead City, Arizona. $21 million. Project involved taking 3,350 residences off septic tank services and installing a new gravity sewer system. Installing 235,720 LF Q of 6-inch through 36-inch PVC sewer mains and 365,000 LF of service laterals. Surface improvements — included street restoration and paving and three sewage lift stations. Z 1\1 Al (1996-1997) BARCON, INC. Twin Lakes Enlargement Project. Sheridan Wyoming. $11.87 million. Construction of a new earthfill dam, outlet works, and spillway. Excavated 160,000 CY out of dam foundation, excavated 170,000 CY muck, excavated 42,900 CY rock for new spillway. Embanked 600,000 CY zone fill for new dam, concrete tower, concrete and steel pipe outlet works, concrete labyrinth weir for spillway. Caballo Rojo, Inc., Gillette,Wyoming (Oct. 1994-1997) SCOPE:Dragline Groundsman/Oiler/Operator. The Carter Mining Company, Gillette,Wyoming (May 1994-Oct. 1994) SCOPE:Operator. Production and reclamation. Olsten Temporary Service, Gillette,Wyoming (Sept. 1993-May 1994) SCOPE: Operator. Production and reclamation. Fuller Construction Company, Moorcroft,Wyoming (May 1983-Sept. 1993) SCOPE:Step-up Foreman. Production and reclamation.Worked in most mines in basin. r CD V O L a. C G) .a O Q Z i; ly 9 i�1� Wolf Creek Wastewater System n CluRainucilviR A I K. PROJECT DETAILS This project consists of the construction of the new wastewater collection system, along with the construction of a new lift station and wastewater treatment facility. The collection system work includes installation of approximately 20 manholes; it includes installation of numerous new sewer services and individual septic system abandonment. Installation of approximately 1,478 linear feet of 3' HDPE force main using directional drilling of approximately 518 feet of 6" HDPE and steel casing. Construction of new lift station on the south side of Wolf Creek, as well as complete construction of a new wastewater treatment plant— including building construction, site piping, mechanical piping, HVAC, odor control, electrical plumbing and site work. Location: Wolf Creek, Montana Project Highlights: Installation of pre-packaged MBR wastewater Owner: Wolf Creek County Water treatment system and Sewer District ❖ Environmentally sensitive project location ❖ HDD installation under interstate, RR, and Engineer: Robert Peccia & Wolf Creek, Associates Close coordination with MDOT and Northwestern Energy Contract Value: $2.3 million Construction of new WWTP building and site work Contract Type: Fixed Unit Price New services to 40 existing homesites. (competitive bid) Abandonment of existing system ❖ Dewatering Completion Date: December 2014 ❖ Utility relocations ❖ Surveying / Construction Staking ❖ Site Layout ❖ Roadway repairs and pavement. Y Wolf Creek Wastewater system .oer.xr...yss.oubn i. nl;.. Broadwater Spillway Rubber Gate Replacement Project PROJECT DETAILS This project consists of installation of seven new inflatable rubber gates that are 11 and '/z feet high and 82 feet long, each. Work consists of removing the existing gates, installation of the new gates, installation of new air control piping and valves. As well as concrete coring, concrete demolition, grouting, bulkhead design and installation, dewatering and access and safety improvements to the dam. The project required close coordination with the Department of Natural Resources on scheduling and removal of the gates in a staged approach to allow for continued and uninterrupted operations of the same and generating facilities. Project Highlights: Location: Toston Dam, Montana Replacement of 7 rubber gates ❖ Installation of steel bulkheads & Dewatering Owner: Montana Department of ❖ New Air piping and air control systems Natural Resources Safety/access improvements ❖ Concrete coring and demolition Engineer: MWH Global Grouting ❖ Surveying /Construction Staking Contract Value: $625,000 ❖ Site Layout ❖ No Safety violation or incidents Contract Type: Fixed Unit Price Environmentally sensitive project location (competitive bid) Completion Date: June 2014 Wei . ' South Jetty Dune Stabilization Al Culosinnuclilun PROJECT DETAILS NW Construction constructed a dynamic revetment to an elevation from elevation 9.00 to elevation 22.00 along the shoreline. Work consisted of approximately 20,000 CY of excavation and 50,000 CY of zoned embankment with imported aggregates ranging in size up to 8" diameter. This project had a critical schedule that had to be completed prior to winter season. Located on a beach within a state park, the South Jetty Dune Stabilization project was completed successfully with no environmental or public impacts. The project was completed within budget, on time with no safety violations. Location: Fort Stevens State Park, Project Highlights: Hammond, Oregon 15,000 CY excavation ❖ 40,000 CY imported embankments Owner: United States Corps of ❖ Work completed within Fort Stevens State Engineers Park ❖ Access road construction and restoration Engineer: United States Corps of ❖ Replanting of shore pines and site restoration Engineers ❖ No safety violations or incidents ❖ Surveying /Construction Staking Contract Value: $1.7 million •:e Site Layout ❖ Environmentally sensitive project location Contract Type: Fixed Unit Price ❖ Completion ahead of schedule (competitive bid) ❖ Clearing, grubbing and re-vegetation Completion Date: October 2013