REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski, City Manager
SUBJECT: 2007 Lyman Creek Reservoir Improvements Project
MEETING DATE: 12/17/07
RECOMMENDATION: Authorize City Manager to sign.
BACKGROUND: Attached is a copy of the partially executed Agreement with Morrison Maierle,
Inc. for Professional Engineering Services for above referenced project.
This project is the implementation of recommendations of the water facility plan for upgrades at both the
Lyman Creek and Sourdough reservoirs. The improvements will serve to both increase the capacity of
the system and address ongoing maintenance issues at both locations. Attached to the contract is a
detailed scope and budget which provides an itemized breakdown of the tasks to be completed with the
project. The document is in the City’s standard format. The proposed fee of $119,495.00 appears to be
commensurate with the project complexity.
FISCAL EFFECTS: Currently budgeted in the water fund and water impact fee CIP.
ALTERNATIVES: As suggested by the City Commission.
Respectfully submitted,
_________________________________ ____________________________
Robert J. Murray Jr., Project Engineer Chris A. Kukulski, City Manager
Attachments: Professional Services Agreement
Report compiled on 12/11/2007
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112