HomeMy WebLinkAboutE- Packet 06-11-2007_Full Contract with CommaQ Architecture for Redesig_12Commission Memorandum
REPORT TO Honorable Mayor and City Commission
FROM James Goehrung Director ofFacility Services
Chris Kukulski City Manager
SUBJECT Architectural Contract for the Conversion ofthe old Library to a new City
Hall
MEETING DATE June 11 2007
BACKGROUND The City Commission has provided staffwith direction to proceed with
the remodel ofthe old Library for a new City Hall The initial project programming on space
needs and department locations is complete The next step is refining the space needs into
design documents that will be used for bidding the project
An outline for the architectural contract is drafted detailing the time line for the project and the
design costs associated with the project The next step is to complete the contract for the project
and direct the Architect to begin the next phase of the design
116
RECOMMENDATION Authorize the City Manager to sign an agreement with Comma Q
Architecture Inc for the next four phases of design Design Development Construction
Documents Bidding and Construction Administration The agreement will include the standard
Architectural contract and a multiple page addendum that better addressed the City s needs and
interests
The current project scope includes the work proposed in the Phase I remodel and the Mechanical
Electrical and Plumbing work identified in Phase II The total estimated project budget for the
remodel is work is 1482 233 The architectural contract is set as a base percentage of 10 on
an hourly basis with a not to exceed ofthe 148 223
FISCAL EFFECTS The project will be funded by 1 the sale ofthe current City Hall
site 2 remaining dollars in the Special Projects fund These sources will cover the estimated
remodeling costs
ALTERNATIVES As suggested by the City Commission The Commission addition
is not included in the proposed Phase I and Phase II scope The initial estimate for the
Commission Room Addition is 200 000 depending on when the work occurs in relation to
other construction associated with the remodel The additional services for this architectural
work are proposed at 24 200
fully submitted
Chris A Kukulski City Manager
Director ofFacility Services
Attachments Proposed Services Agreement
Report compiled on June 1 2007
117
Comma Q Architecture Inc
May 29 2007
James Goehrung Director of Facility Services
City of Bozeman
P O Box 1230
Bozeman MT 59715
Dear James
Thank you for the opportunity to submit this proposal to continue professional design services for the Renovation of the old
library Building into the New Bozeman City Hall facility at 220 E Lamme Street The continuation of the design work will
be based on the Final Space Plans and Site Plan dated 1 May 07 and the noted PHASE Iwork on the Statement of
Probable Construction Cost dated 29 Mar 07 including the Second FloorAtrium Infill Option and the design planning for
the PHASE II Mechanical and Electrical items A separate proposal number for the possible implementation of the 800
1000 sJ Commission Room Addition as shown on the Final Space Plans is also provided per your request at our 18 May07meeting
The scope of services will be divided into four phases Design Phase Construction Document Phase Bid Phase and
Construction Administration Phase
Design Phase approximately 6 weeks
Due to the detailed information gathering and conceptual design decisions that were made during the previousProgrammingandSpacePlanningPhaseswearecombiningthenormalSchematicDesignandDesignDevelopment
Phases into a single Design Phase During this Design Phase we will make all the final Space Plan revisions requested byFinanceandHRDepartmentsrevieweachindividualdepartmentlayoutindetailwiththedepartmentdirectorsreviewthe
space layouts with our engineering consultants for integration and additional design refinements to complete a final designplanThedesignideaswillbedevelopedfurthertorefinerelationstipsandsystemswithourconsultantsMaterials
utilities and structural options will be further researched and applied specifically to the design At the end of Design phase
we anticipate an updated Statement of Probable Construction Cost Project Schedule and a client review meeting with
approval to continue with Construction Document Phase
Construction Document Phase approximately 12 weeks
The project will be developed into a set ofdocuments that will be used for Bidding Phase to assist the construction and jobsiteperformanceThedocumentsgeneratedwillbeasetofworkingdrawingsandaprojectmanualTheworkingdrawingswillincludeaarchitecturalsiteplanselectivedemolitionplansfloorplansinteriorelevationsspecificexterior
elevations at areas of work reflected ceiling plans roof plan details and schedules The working drawings will also include
floor plans reflected ceiling plans and system details for the Mechanical Plumbing Electrical and Structural work The
project manual will include Front End specification sections typical of City of Bozeman projects product specificationsectionsandassociatedschedulesforworkdocumentedontheworkingdrawingsetWeanticipateanupdatedStatement
of Probable Construction Cost Project schedule and a client review meeting with approval near the end ofConstruction
Document Phase
Bid Phase approximately 5to 8 weeks
We will assist with the public bidding of the project with the completed Construction Documents The documents will be
reproduced distributed and made available to contractors from our office We will provide clarifications answer bidder
questions prepare and distribute addenda conduct a Pre Bid Walkthrough at the site attend the Bid Opening and assist in
Bid Evaluation Selection
109 North RI ie vP WI
BozlImiln MlH1UHld 59711
TEL 406 585 1112
FAX U6 8 18
www commaq com
118
Construction Administration Phase approximately 6 to 8 months
We will provide basic architectural services for the construction phase of the project This will include a Pre Construction
Conference weekly project meetings and site visits submittal review processing pay request approvals I processing
substantial completion walkthrough reports final completion walkthrough I reports and project close out activities In
addition our engineering consultants will provide 3scheduled site visits and a final walkthrough site visit report
We estimate approximately 14 calendar months to complete the professional design services for the four phases This
timeframe is based on current office workload We can begin the Design Phase immediately Our work will be
scheduled at a pace that is consistent with your ability to review and approve each Phase
Fee Summary Renovation
The Statement of Probable Construction Costs for the specific project elements you have requested our design services for
is as follows
Phase Iitems Phase II MEP items 2nd Floor Infill item a Total Project Budget of approximately 1482 233 00
We are proposing a ten flercent 1 O fee ofthe Total Project Budget for our Professional Services which will be completed
on an hourly basis with a not to exceed of 148 223 00 This fee includes our engineering consultants for Mechanical
Plumbing Electrical and Structural services We plan to continue with Three Rivers Engineering for the Mechanical
Plumbing work We aiso plan to work with TO H Engineering for the Structural work We have received a proposal from
MKK Engineers of Billings for the Electrical work but have also requested proposals from two electrical engineers from
Missoula as well before we make a selection
Fee Summary Commission Room Addition
The initial estimate for the Commission Room Addition was approximately 200 000 00 This number is variable based on
construction occurring with other phases of work or as astand alone project and will require future examination
In reviewing the tasks associated with providing Professional Services stated above in the Design Construction Document
and Bid Phases we anticipate the following breakdown in fees
Architectural Design Services
Mech Plumbing Design Services
Electrical Design Services
Structural Desion Services
Total
16 000 00
2 2PO 00
2 000 00
4 000 00
24 200 00
Construction Mministration services will be provided on an hourly basis and performed as requested
Our hourly rates are as follows
Architect II
Architect IInterior Designer
Designer Drafter
110 00
90 00
65 00
55 00
Reimbursable costs such as blueprinting photocopies photographs mileage etc are in addition to the total fee and will be
billed at a rate of one point one five times the cost incurred by Comma Q 15 mark up The Owner shall pay all permitsandregulatoryfeesrequiredfortheproject
119
Invoices will be submitted monthly and are due and payable upon receipt A finance service charge of 1 50 per month
will be assessed on any unpaid cash balance after deduction of current payments credits and allowances that are made
within 10 days of the invoice date This is an Annual Percentage Rate of 18 The minimum finance charge is 5 00 An
invoice outstanding for six months or longer will be forwarded to an agency for collection You agree to reimburse us for
any fees we incur as the result of collection Including but not limited to attorney s fees These rates are subject to change
Please give me a call if you have questions or wish to discuss any portion of this proposal If acceptable please sign below
and using your preferred Contract as a basis we will begin final negotiation of an Agreement for Professional Services
Respectfully Submitted