HomeMy WebLinkAboutpacket 3_16-39_Capital Improvements Plan for FY2008-2012 for Wastewater Fund and Wastewater Impact Fees__ Commission Memorandum REPORT TO: Honorable Mayor and City Commissioners FROM: Anna Rosenberry, Finance Director Chris Kukulski, City Manager SUBJECT: Update of CIP Schedules for FY2008-2012 for: Wastewater Fund Wastewater Impact Fees MEETING DATE: March 26, 2007 BACKGROUND: We continue our update of the FY2008-FY2012 Capital Improvements Plan with review of the Wastewater Fund and Wastewater Impact Fee sections tonight. Developing a Capital Improvements Plan is, first and foremost, a planning process - adopting any CIP does not provide budget appropriation authority. Items must be included in a budget resolution before they are funded. Once adopted, it is our intent that the FY2008 items become the basis for FY2008 budget within each of these funds. Revenue Estimates: For the purpose of this CIP, we begin with the current year revenue as an estimate for future years, inflated by a growth factor of 5% each year. Anticipated changes in Wastewater Rates are outlined on the Revenue sheet in the Financial Summaries for the Wastewater fund, mirroring the “Option 1” HDR rate study proposal that you will have heard earlier in this evening’s agenda. Those recommended increases are as follows: FY08 5% increase, FY09 & FY10 9% annual increases, FY11 & FY12 2% annual increases. 1 126 Other Funding Sources: The Wastewater Fund schedule anticipates bonding of $17,735,000 against future revenues in order to build the Wastewater BNR Plant. The Wastewater Impact Fee schedule anticipates developer contributions of $571,694 for the completion of the non-capacity expanding portions of two scheduled projects. Until the City’s Wastewater Utility finds it necessary to replace these segments, any replacement costs will have to be borne by the outside entity which benefits from the project. Because the wastewater system assets currently installed are operating properly, these projects will only occur if local development requires expansion of the system. Project Cost Estimates: All project and equipment costs are estimates that will not be finalized until the City accepts a qualified bid for that specific project or equipment. We have also estimated the amount of costs that would be eligible for Impact Fees (capacity expansion.) We have used the best information available to us at this time, often based on the City Engineer’s extensive knowledge of recent wastewater construction projects. In addition, HDR has assisted with estimating the costs of the BNR Treatment Plant facility, and the construction phasing of that project. Because of the importance and the cost of the BNR Plant Construction, we chose to list a minimal number of other projects within these CIP. More televising of our existing sewer pipes needs to occur in order to properly prioritize future maintenance projects. Once we get closer to actual bids on the Plant and allocation of costs between Impact Fees and Rate Payers, we will add more projects as funding allows. This will take place in our annual CIP updating process. Advisory Committee: The Impact Fee Advisory Committee reviewed the Wastewater Impact Fee Schedules and Projects Lists on January 11th. They met again on January 25th and recommended that the Commission approve all of the listed projects. There was considerable discussion about the “developer contributions” required on some of the projects, and they continue to be concerned that the costs of all projects be properly allocated between “capacity expansion” and “maintenance of existing capacity” within the Wastewater System. After the Advisory Committee met, and through ongoing work with HDR on the rate study and BNR Plant design, $5 million was moved from Phase II into Phase I of the Plant. These improvements are related to solids handling at the facility. This changed the total estimate for BNR Plant Construction – Phase I to $38.1 Million. Although the Advisory Committee has not been asked to approve this increase in a schedule estimate, they were 2 127 informed at their meeting on January 25th that these estimates would be changing as we got further into the design process. They also understood that the project construction was scheduled for FY09, and would consequently be back before the committee again with the FY09-FY13 CIP Update. RECOMMENDATION: Review the attached information and approve, with any modifications. FISCAL EFFECTS: Approving these schedules does not provide appropriation authority. Once approved by the City Commission, the FY08 projects and equipment will be incorporated into the FY08 City Manager’s Recommended Budget in May, which begins the budget appropriation process. The remaining plan years serve as a work plan to guide staff, and will be reviewed and revised in the coming fall. ALTERNATIVES: As suggested by the Commission. Respectfully submitted, Anna Rosenberry, Finance Director Chris Kukulski, City Manager Report compiled on March 21, 2007 Attachments: Financial Summaries Project Sheets 3 128 WASTEWATER FUNDSUMMARY OF CIP BALANCES, REVENUES AND EXPENDITURESCIP FY2008-2012Current Year ----------------------------------------Projected----------------------------------------FY07 FY08 FY09 FY10 FY11 FY12Projected Beginning CIP Balance 3,000,000$ 1,641,175$ 873,710$ 3,071,721$ 142,817$ 2,613,907$ Add: Revenues Dedicated to CIP 1,681,000 1,840,035 13,523,011 9,093,952 2,606,085 2,780,217 Less: Scheduled CIP Expenditures 3,039,825 2,607,500 11,325,000 12,022,856 134,995 1,013,218 __________ __________ __________ __________ __________ __________Projected Year-End CIP Balance 1,641,175$ 873,710$ 3,071,721$ 142,817$ 2,613,907$ 4,380,906$ 129 WASTEWATER FUNDRATE CHANGES & PROJECTION OF CUSTOMER GROWTHCurrent Year ----------------------------------------Projected----------------------------------------FY07 FY08 FY09 FY10 FY11 FY12Rate Changes/Customer GrowthInflationary Adjustment 4.00 4.00 4.00 - - Increase in Rates Dedicated to CIP 3.00 1.00 5.00 5.00 2.00 2.00 Rate Change Attributable to Operations_____ _____ _____ _____ _____ _____Total Current Year Rate Changes 3.00 5.00 9.00 9.00 2.00 2.00 Customer Growth Rate 4.00 5.00 5.00 5.00 5.00 5.00 _____ _____ _____ _____ _____ _____Total Percentage Increase in Base Year Revenues 7.00 10.00 14.00 14.00 7.00 7.00 Percentage of Rates Dedicated to CIP:From Previous Year(s) 40.00 43.00 44.00 49.00 54.00 56.00 Current Year 3.00 1.00 5.00 5.00 2.00 _____ _____ _____ _____ _____ _____Total Percentage of Rates Dedicated to CIP 43.00 44.00 49.00 54.00 56.00 56.00 130 WASTEWATER FUNDREVENUE PROJECTIONSCurrent Year ----------------------------------------Projected----------------------------------------FY07 FY08 FY09 FY10 FY11 FY12Base Revenues for Projections 3,700,000$ 3,700,000$ 4,070,000$ 4,639,800$ 5,289,372$ 5,659,628 Total Projected Current Year Revenues 3,700,000$ 4,070,000$ 4,639,800$ 5,289,372$ 5,659,628$ 6,055,802 Current Year Revenues Dedicated to CIP 1,681,000$ 1,840,035$ 2,288,011$ 2,593,952$ 2,606,085$ 2,780,217 Add: Grants Bond Issues 11,235,000 6,500,000 INTERCAP OTHER/SRF__________ __________ __________ __________ __________ __________Total Revenues Dedicated to CIP 1,681,000$ 1,840,035$ 13,523,011$ 9,093,952$ 2,606,085$ 2,780,217 131 CITY OF BOZEMANCAPITAL IMPROVEMENTS PROGRAMWASTEWATER FUNDItem -------------------------------Projected Costs by Fiscal Year------------------------------- Not # Project Title Department/Division Category FY08 FY09 FY10 FY11 FY12 Total ScheduledWW01 DUMP TRUCK WW OPERATIONS EQUIPMENT 90,000 90,000 WW02 1 TON TRUCK W/ HOIST WW OPERATIONS EQUIPMENT 44,995 44,995 WW03 3/4 TON 4X4 PICKUP WW OPERATIONS EQUIPMENT 37,856 - 37,856 WW04 66% WWTP BNR CONSTRUCTION WW PLANT EQUIPMENT 11,235,000 11,235,000 22,470,000 PW01 SHOP COMPLEX - PH 1 PUBLIC WORKS PROJECT 1,507,500 1,507,500 WW07 BI-ANNUAL ENGINEERING DESIGN WW OPERATIONS PROJECT 90,000 90,000 180,000 WW08 WASTEWATER BI-ANNUAL UPGRADES WW OPERATIONS PROJECT 750,000 - 750,000 - 750,000 2,250,000 WW17 TELEVISION VAN REPLACEMENT WWOPERATIONS EQUIPMENT 263,218 263,218 WW18 SEMI TRUCKS REPLACEMENT WWPLANT EQUIPMENT 200,000 200,000 WW19 UPGRADE FLOATING DREDGE WWPLANT EQUIPMENT 60,000 60,000 - ________ ________ ________ ________ ________ ________ ________Total2,607,500$ 11,325,000$ 12,022,856$ 134,995$ 1,013,218$ 27,103,569$ -$ 132 Project Name: Shops Complex – Phase I Estimated Cost: $4,995,000 – Total, Phase I Project Number: Public Works – PW01 Date Scheduled: FY08 Purpose: □ New ■ Replacement ■ Facility □ Equipment Project Description: This project consists of building a new Water/Wastewater operations building at the Wastewater Treatment Plant. This will be designed and built to be the start of a new shops complex that will be built in phases. The present shops complex is built in a residential neighborhood and it is estimated to have twice the employees working out of the complex than what it was designed for. The present complex has high traffic loads, and with the public water fill station there and driving and walking in the complex is dangerous at high traffic periods. Constructing a new complex in phases, with phase one being a new facility for water and wastewater, will give additional space for the other divisions until the final phase can be constructed in FY 10. This phase of the complex will provide office, classroom, and locker facilities, as well as shop and garage area large enough to place the majority of the divisions’ equipment under roof. Alternatives Considered: Build a smaller satellite facility for high traffic volume operations; leave low traffic operations at existing facility. Advantages of Approving this Project: It has been determined there is adequate room at the WWTP for a shop complex, not within the entryway overlay corridor. This will allow all land at the Mandeville Farm to be utilized for an industrial subdivision. Constructing the complex in phases will allow additional time to secure funding for the final phase, eliminate a majority of traffic at the current site, eliminate the public water fill station (will be located at the new site), and free up space in the current complex to alleviate crowding for other divisions. With utilizing the WWTP for the Shops Complex selection of proper site, this move will eliminate using residential streets for day-to-day high volume traffic. This will give more space at the existing complex and make it much safer. Possibly build a new water fill station with it. Estimated New Recurring Costs: Annual Operating & Maintenance Costs: Unknown at this point. Pre-design work is being done in FY07 that should give us a good basis for an estimate of annual operating and maintenance costs for this facility. Funding Sources: Phase I Total = $4,995,000 30% Water Utility Fund = $1,507,500 30% Wastewater Utility Fund = $1,507,500 20% Water Impact Fees = $990,000 20% Wastewater Impact Fees = $990,000 City of Bozeman Capital Improvements Plan FY08-12 133 Photo #1 #1 – Existing Shops Complex - Located at 814 N Bozeman Avenue. Photo #2 #2 – Proposed Future Site on Wastewater Treatment Plant Property - Located at 255 Moss Bridge Road. Exact location of the Shop on this site would be determined so that we get the best use as both BNR Treatment Plant and Shop Location. City of Bozeman Capital Improvements Plan FY08-12 134 Project Name: Dump Truck Estimated Cost: $90,000 Project Number: Wastewater Operations – WW01 Date Scheduled: FY08 Purpose: ■ New □ Replacement □ Facility ■ Equipment Project Description: 4 yard dump truck to haul dirt, gravel, blacktop, etc. to facilitate daily operations in maintenance and repair or our waste water collection system. This will allow us, with our spare hoe, to have three digging crews working simultaneously. Many dig jobs require both of our dump trucks and this doesn’t allow us to dig a second or third hole if there is not a dump truck available. It will also make available an additional dump truck in the winter to the street department for hauling snow. Alternatives Considered: Post pone jobs, borrow dump trucks from Street Dept. if available Advantages of Approving this Project: This truck will allow us to do more work on our distribution and collection systems and prevent more breakdowns in the system. Preventing breakdowns reduces operating costs for overtime and materials. Estimated New Future Recurring Costs: Annual Operating Costs: Annual Maintenance Costs: Other Non-Capital Costs: none. Total: Funding Sources: 100% Wastewater Utility Revenue City of Bozeman Capital Improvements Plan FY08-12 135 Project Name: 1 Ton Flex Fuel Truck with Hoist Estimated Cost: $44,995 Project Number: Wastewater Operations – WW02 Date Scheduled: FY11 Purpose: □ New ■ Replacement □ Facility ■ Equipment Project Description: This request replaces a 2000 1-ton truck with a hoist. At the time of replacement, this truck will be 11 years old with 60,000 miles. This truck is used daily in both water and sewer operations to transport personnel and equipment. The existing truck will not be traded in; it will be utilized as a back-up vehicle when needed. Alternatives Considered: Keep the truck and spend maintenance dollars to have truck serviceable. Advantages of Approving this Project: Advantages to the City for approving this request include savings on fuel and emissions. The new vehicles will improve safety of crews, there would be lower repair costs and it would help maintain current operations levels. Estimated New Future Recurring Costs: Annual Operating Costs: Annual Maintenance Costs: Other Non-Capital Costs: none. Total: Funding Sources: 100% Wastewater Utility Revenue City of Bozeman Capital Improvements Plan FY08-12 136 Project Name: ¾ Ton Flex Fuel Pickup Truck Estimated Cost: $37,856 Project Number: Wastewater Operations – WW03 Date Scheduled: FY10 Purpose: □ New ■ Replacement □ Facility ■ Equipment Project Description: This is to replace asset # 2916 which is a 2001 Dodge Dakota ½ ton pickup which has 40,812 miles. At the time replaced, this vehicle will be 9 years old and have approx 73,000 miles. This truck is used to transport operations crews performing one call locates. Crews respond to over 5,000 calls a year for locate requests. The existing vehicle will be traded in, to reduce the total purchase price. Alternatives Considered: Continue to use older vehicle which is extremely small for the average water department employee. Advantages of Approving this Project: Advantages to the City for approving this request include continued reliability in water operations. Repair and maintenance costs will be minimized with replacement Estimated New Future Recurring Costs: Annual Operating Costs: Annual Maintenance Costs: Other Non-Capital Costs: none. Total: Funding Sources: 100% Wastewater Utility Revenue City of Bozeman Capital Improvements Plan FY08-12 137 Project Name: BNR Plant Construction Estimated Cost: $38.1 Million – Total, Phase I Project Number: Wastewater Plant – WW04 Date Scheduled: FY07 – FY10 Purpose: □ New ■ Replacement ■ Facility □ Equipment Project Description: The Bozeman WWTP is nearing its original design capacity of 5.8 MGD. The current organic loading to the facility (lbs of BOD) has now started to exceed the plant’s original design capacity on a daily basis. These critical loading parameters clearly point to the need for major facility expansion. The facility will soon reach its DEQ imposed non-degradation limit for Total Nitrogen. The existing facility is not designed to remove Total Nitrogen. Once this non-degradation limit of 1010 lbs/day of Total Nitrogen is exceeded, the City of Bozeman will be out of compliance with its MPDES permit and may be subject to substantial fines or a “no growth” moratorium. In January 2006 Morrison & Maierle Consulting Engineers completed a comprehensive Wastewater Facilities Plan. The plan recommends the City proceed with a 3-phased project schedule that includes the construction of a new Biological Nutrient Reduction (BNR) facility that is capable of handling our increased flows while also reducing the amount of Total Nitrogen discharged to the East Gallatin River. The design contract is being written to include LEEDS design features and a Sterling Generator for 100% efficient use of the methane gas produced by the plant. These features may add substantially to the construction cost, but would reduce operating costs over the life of the plan. Alternatives Considered: A variety of treatment technologies and alternatives are presented in the January 2006 Wastewater Facilities Plan. Advantages of Approving this Project: Major capital expansion of the Bozeman WWTP will enable the City to meet its ever growing demand for wastewater services and still produce a high quality effluent that is in full compliance with the City’s MPDES discharge permit. Expansion of the Bozeman WWTP is consistent with the City’s long-term need to accommodate rapid growth and economic development in the Gallatin Valley. Estimated Future Recurring Costs: Annual Operating & Maintenance Costs: Similar to existing plant operations costs. The Facilities Plan estimates a total of $1,439,360 annually including all labor, power, chemicals, equipment maintenance, and equipment replacement. We currently spend $1,574,764 (FY07) on operations and maintenance of the existing wastewater treatment plant. Funding Sources: FY07 Design: Total $3.9 Million 67% Wastewater Utility Cash = $2.33 Million 33% Wastewater Impact Fee Cash = $1.17 Million FY09 & FY10 Construction: Total $34.2 Million 67% Wastewater Utility Bonds = $22.8 Million 33% Wastewater Impact Fee Cash = $11.4 Million City of Bozeman Capital Improvements Plan FY08-12 138 Photo #1 #1 – Existing Wastewater Treatment Plant – Located at 255 Moss Bridge Road. City of Bozeman Capital Improvements Plan FY08-12 139 Project Name: Bi-Annual Engineering Design Estimated Cost: $90,000 per year Project Number: Wastewater Operations – WW07 Date Scheduled: FY09 & FY11 Purpose: □ New ■ Replacement ■ Facility □ Equipment Project Description: This item provides for design work to be completed every-other year, in anticipation of the Bi-Annual System Upgrades. We alternate funding of design work and construction work within the CIP. As the Wastewater Operations Division televises (views) the existing system, maintenance projects become apparent. Given our knowledge of system conditions today, the following projects are candidates for design funding and were identified in the Facility Plan: 1. Replace 21” Trunk Line – Rouse to Wal-mart Area. 2. Replace/Line Mendenhall to Tamarack 3. Replace/Line College to Babcock 4. Replace/Line 21” Interstate Crossing near Wal-mart Area. 5. Replace Front Street Collector As annual televising continues, other more-urgent projects may be identified and designed under this project heading. Alternatives Considered: Advantages of Approving this Project: Provides for the design of necessary sewer system maintenance work. Estimated New Future Recurring Costs: None Funding Sources: 100% Wastewater Utility Fund City of Bozeman Capital Improvements Plan FY08-12 140 Project Name: Annual Wastewater Upgrades Estimated Cost: $750,000 per year Project Number: Wastewater Operations – WW08 Date Scheduled: FY08, FY10 & FY12 Purpose: □ New ■ Replacement ■ Facility □ Equipment Project Description: This item provides for construction to be completed every-other year, after the Bi-Annual Engineering Design. We alternate funding of design work and construction work within the CIP. As the Wastewater Operations Division televises (views) the existing system, maintenance projects become apparent. Given our knowledge of system conditions today, the following projects are candidates for construction funding and were identified in the Facility Plan: 1. Replace 21” Trunk Line – Rouse to Wal-mart Area. 2. Replace/Line Mendenhall to Tamarack 3. Replace/Line College to Babcock 4. Replace/Line 21” Interstate Crossing near Wal-mart Area. 5. Replace Front Street Collector As annual televising continues, other more-urgent projects may be identified, designed, and constructed under this project heading. Alternatives Considered: Advantages of Approving this Project: Provides for the construction of necessary sewer system maintenance work. Estimated New Future Recurring Costs: None. Funding Sources: 100% Wastewater Utility Fund City of Bozeman Capital Improvements Plan FY08-12 141 Project Name: Television Van Estimated Cost: $263,218 Project Number: Wastewater Operations – WW17 Date Scheduled: FY12 Purpose: □ New ■ Replacement □ Facility ■ Equipment Project Description: Replacement for the existing Sewer TV Van, routinely replaced every 5 years. Current Van purchased in FY07. This van should be equipped with all modifications to put into service for video inspecting our existing and newly constructed sewage collection infrastructure. The van will allow us to travel out of the sewer main and not only inspect the city’s portion of the service but the homeowner’s side and even into the structure itself. This is critical in identifying infiltration issues and helps identify homes that have sump pumps dumping into our system. This can be done from the street and service workers would not have to enter private residences to televise back out to the main. Alternatives Considered: To attempt to maintain our existing TV van, this is becoming obsolete and outdated with the present and upcoming technology. Advantages of Approving this Project: Provides for the timely replacement of critical maintenance equipment. Estimated New Future Recurring Costs: Annual Operating Costs: Annual Maintenance Costs: Total: Funding Sources: 100% Wastewater Utility Revenues - Approx. 5 year cost recover through TV Line Service Fee, currently 80 cents per foot inspected (FY07 price). City of Bozeman Capital Improvements Plan FY08-12 142 Project Name: Semi Trucks (2 at $100,000 each) Estimated Cost: $200,000 Total Project Number: Wastewater Plant – WW18 Date Scheduled: FY08 Purpose: □ New ■ Replacement □ Facility ■ Equipment Project Description: The current Semi Trucks that operate at the Wastewater Treatment Plant are in need of replacement. Both trucks are nearing 25 years old. With future operations of the BNR Plant, we will continue to be in need of two semi trucks to haul trailers of wastewater liquids and/or solids. The existing trucks will be traded in, reducing the total purchase costs. Alternatives Considered: Lease trucks or contract for a hauler. Advantages of Approving this Project: Provides the city with ownership and control of the assets that are needed to properly dispose of wastewater plant materials. Will replace two very old pieces of critical equipment. Estimated New Future Recurring Costs: Annual Operating Costs: Annual Maintenance Costs: Total: Funding Sources: 100% Wastewater Utility Revenues City of Bozeman Capital Improvements Plan FY08-12 143 Project Name: Upgrade Floating Dredge & Related Piping Estimated Cost: $60,000 Project Number: Wastewater Plant – WW19 Date Scheduled: FY08 Purpose: □ New ■ Replacement □ Facility ■ Equipment Project Description: The current floating dredge and associated piping is in need of repair. This equipment and system is needed for sludge handling at the Wastewater Treatment Plant. Alternatives Considered: Make no improvements. Advantages of Approving this Project: These upgrades will keep the plant compliant with requirements for sludge handling. Estimated New Future Recurring Costs: Annual Operating & Maintenance Costs: minimal. Funding Sources: 100% Wastewater Utility Revenues City of Bozeman Capital Improvements Plan FY08-12 144 WASTEWATER IMPACT FEE FUNDSUMMARY OF CIP BALANCES, REVENUES AND EXPENDITURESCIP Plan FY08-FY12Current Year ----------------------------------------Projected----------------------------------------FY07 FY08 FY09 FY10 FY11 FY12Projected Beginning Restricted Cash Balance 8,600,000$ 10,875,000$ 11,189,000$ 7,799,640$ 4,508,706$ 6,326,486$ Add: Impact Fee Revenue 2,275,000 2,366,000 2,460,640 2,559,066 2,661,428 2,767,885 Other Funding Sources 318,600 - - 253,094 - Less: Scheduled CIP Expenditures 2,052,000 5,850,000 5,850,000 843,648 - __________ __________ __________ __________ __________ __________Projected Year-End Restricted Cash Balance 10,875,000$ 11,189,000$ 7,799,640$ 4,508,706$ 6,326,486$ 9,094,371$ Note: Funding the Construction of the BNR Plant is the #1 Priority for Wastewater Impact Fee spending. Because of the uncertainty of the facility costs and the portion that will be eligible for impact fee spending, a minimal number of projects are scheduled. This may change once the cost and allocation of the BNR Plant is known.145 WASTEWATER IMPACT FEE FUNDREVENUE PROJECTIONSCurrent Year ----------------------------------------Projected----------------------------------------FY07 FY08 FY09 FY10 FY11 FY12Projected Impact Fee Revenues 2,275,000$ 2,275,000$ 2,366,000$ 2,460,640$ 2,559,066$ 2,661,428$ Customer Growth Rate 4% 4% 4% 4% 4%__________ __________ __________ __________ __________ __________Impact Fees Dedicated to CIP 2,275,000$ 2,366,000$ 2,460,640$ 2,559,066$ 2,661,428$ 2,767,885$ Add Other Revenue Sources: Developer Contributions: WWIF05 318,600 Developer Contributions: WWIF07 253,094 __________ __________ __________ __________ __________ __________Total Other Revenue Sources - 318,600 - - 253,094 - __________ __________ __________ __________ __________ __________Total All Revenue Sources 2,275,000$ 2,684,600$ 2,460,640$ 2,559,066$ 2,914,523$ 2,767,885$ Note: Developer Contributions for the above projects cover the non-capacity expanding portion of construction. Until the City's WastewaterUtility finds it necessary to replace these segments, any replacement costs will have to be borne by the outside entity which benefits from the project.146 CITY OF BOZEMANCAPITAL IMPROVEMENTS PROGRAM WASTEWATER IMPACT FEE PROJECTSItem -----------Projected Costs by Fiscal Year----------- Not # Project Title Department Category FY08 FY09 FY10 FY11 FY12 Total ScheduledPW 01 SHOPS COMPLEX - PHASE 1 WW Impact FeesProject 990,000 990,000 WW04 WWTP BNR CONSTRUCTION WW Impact FeesProject 5,850,000 5,850,000 11,700,000 WWIF05 E8 HOSPITAL TRUNK: HAGGERTY TO KAGY WW Impact FeesProject 1,062,000 1,062,000 WWIF07 S15-INSTALL 21" SEWER INTERCEPTOR WW Impact FeesProject 843,648 843,648 WWIF10 A8 SOUTH ROUSE TRUNK: E BABCOCK - KAGY WW Impact FeesProject- 970,000 WWIF11 R3 REPLACE FRONT STREET: TAMARACK/ROUSE WW Impact FeesProject- 1,800,000 ________ ________ ________ ________________ ________ ________Total2,052,000$ 5,850,000$ 5,850,000$ 843,648$ -$ 14,595,648$ 2,770,000$ Note: Projects with external funding sources (ie. Federal Appropriations, grants, urban funds, or developer contributions) indicate "total project costs", with correspondingrevenue sources indicated on the revenue schedule. Projects financed completely with City dollars but out of separate City funds are shown with the respective funding amount in each schedule of the CIP.147 CITY OF BOZEMANCAPITAL IMPROVEMENTS PROGRAMWASTEWATER IMPACT FEE CREDITSItemInitial CreditCredit # Project TitleCreditUsed BalanceCommentImpact Fee Credits:1 NoneTotal -$ -$ -$ 148