HomeMy WebLinkAboutCattail Springs Condominiums Water Pipeline and Access Easements_8 Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Dustin Johnson, Project Engineer Rick Hixson, City Engineer SUBJECT: Cattail Springs Condominiums – Water Pipeline and Access Easements MEETING DATE: June 16 AGENDA ITEM TYPE: Consent Agenda RECOMMENDATION: Authorize City Manager to sign BACKGROUND: Attached is a copy (original to Stacy Ulmen), of the partially executed easement for water pipeline and access for the above referenced project. Engineering staff has reviewed the easement and found it to be acceptable. The easements were included as a condition of approval with the original site plan that was reviewed and approved by the Planning Director. FISCAL EFFECTS: N/A ALTERNATIVES: As suggested by the City Commission. Attachments: Water Pipeline and Access Easement Report compiled on: 6/4/14 83 84 85 86 87 88