HomeMy WebLinkAboutMeeting_105-113_Adopt Resolution 3994 Durston Road 7th to 19th Change Order Number 2
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski, City Manager
SUBJECT: Durston Road 7th to 19th Project
MEETING DATE: 1/29/2007
BACKGROUND: Attached is a copy, of change order number 2 for the above referenced project.
The change order is for delays caused by utility conflicts and relocations along
the corridor; and for weather days when specification work could not proceed.
The change order increases the contract time by 25 days. There is no change in
the contract price with this change order. The final recommended time extension
for this change is reasonable and commensurate with the work involved.
RECOMMENDATION: Motion and vote to approve and authorize City Manager to sign the change
order.
FISCAL EFFECTS: None
ALTERNATIVES: Disapprove
Respectfully submitted,
_________________________________ ____________________________
Robert J. Murray Jr., Project Engineer Chris A. Kukulski, City Manager
Attachments: Change Order 2 &
Resolution 3994
Report compiled on 1/16/07
105
COMMISSION RESOLUTION NO. 3994
A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF
BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF
CONTRACT WITH JTL GROUP, INC., BELGRADE, MONTANA.
WHEREAS, the City Commission did, on the 31st day of May 2006, authorize award of the bid
for the Durston Road 7th to 19th project, to JTL Group, Inc., Belgrade, Montana; and
WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or
modifications of the specifications and/or plans of the contract be made by resolution; and
WHEREAS, it has become necessary in the prosecution of the work to make alterations or
modifications to the specifications and/or plans of the contract.
NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman,
Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a
municipal corporation, and JTL Group, Inc., as contained in Change Order No. 2, attached hereto, be and the
same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract
change order for and on behalf of the City; and the Clerk of the Commission is authorized and directed to
attest such signature.
PASSED AND ADOPTED by the City Commission of the City of Bozeman, Montana, at a
regular session thereof held on the 29th day of January 2007.
__________________________________________
JEFFREY K. KRAUSS, Mayor
ATTEST:
________________________________________
BRIT FONTENOT, City Clerk
APPROVED AS TO FORM:
_____________________________________
PAUL J. LUWE, City Attorney