HomeMy WebLinkAboutF7 Durston Road 7th to 19th Change Order No. 1 Co.
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski,City Manager
SUBJECT: Durston Road 7`'to 19"' Project
MEETING DATE: 10/2/2006
BACKGROUND: Attached is a copy, of change order number 1 for the above referenced project.
The change order is to replace a gate valve at 17'h and Durston that was found to
be leaking and in disrepair during the course of the work.
The change order increases the contract amount from $2,306,869.95 by
$5,535.00 to a total of$2,312,404.95. There is an increase in the contract time of
l day with this change. The final recommended price for this change is
reasonable and commensurate with the work involved.
RECOMMENDATION: Motion and vote to approve and authorize City Manager to sign the change
order
FISCAL EFFECTS: To be paid from the G.O. Bond, and street impact fee funds
ALTERNATIVES: Disapprove
Respectfully submitted,
Robert J. MiAy Jr., Project en weer Chris A. Kukulski, City Manager
Attachments: Change Order 1
Report compiled on 9/25/06
H:\02\M229129\ConstAdmin\Work Directives&Change Orders\CO-I.doc
CHANGE ORDER
No. I
... .......
DATE OF ISSUANCE 9/5/2006 EFFECTIVE DATE
OWNER City of Bozeman CONTRACTOR JTLQLoup.Inc-B.-Igrade
Contract:
Project: Durston Road Reconstruction—N 7"to N 19'� OWNER's Contract No.
ENGINEER HKM EngineeriLig.Inc. ENGINEER's Contract No. 02M229.129
You are directed to make the following cFznges_in the Contract Documents:
Description:
Replace 10"water valve at intersection of 15"'Ave and Druston Rd, as described in Work Directive#/
Reason for Change Order:
Additional work requested by City of Bozeman Water Dept.
Attachments: (List documents supporting change)
Work Directive#1,JTL letters dated 7114106 and 915106
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
I — I
Original Contract Price Original Contract Times:
Substantial Completion: 120 days
$ 2,306,869.95 Ready for final payment: Calendar Days
(days or dates)
Net Increase(Decrease)from previous Change Net change from previous Change Orders No.—to
Orders No. N/A to N/A No.
Substantial Completion: 0
$ 0.00 Ready for final payment: Per General Conditions
(days)
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: 10/17/2006
$ 2,306,869.95 Ready for final payment: Per General Conditions
(da s or dates)
Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order:
Substantial Completion: I day
$ 5,535.00 Ready for final payment: Per General Conditions
(days)
Contract Price with all approved Change Orders: Contract Times with all approved Change Orders:
$ 2,312,404.95 Substantial Completion: 10/18/2006
Ready for final payment: Per General Conditions
(days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work, additional time, delays
or omitted items, of any nature whatsoever, associated with the subject change order items, except as Identified
and set forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed-
upon herein represents the full cost and value for the subject work performed and the materials supplied under the
terms of the contract and that the work quantities and value were properly determined and are correct.
/t
CONTRACTOR(Authorized Signature) Date
RECOMMENDED BY:HKM Engineering, Inc, APPROVED BY. City of Bozeman
0 PJL— — _2151q,
(ENG E. -Signature) Date'l--I OWNER(Authorized Signature) Date
Page 1
r
HKM Engineering Inc. Work Directive No. 1
WORK CHANGE DIRECTIVE
PROJECT: Durston Road Reconstruction DATE OF ISSUANCE: July-1 8.2006
North 7"Ave.to North 19"Ave _.
OWNER: ATTN:Bob MurrayOWNERS PROJECT NO.
City of Bozeman Engineering Department ENGINEERS PROJECT NO. 02M229.129
20 East Olive ENGINEER: Zach Lowe,P.E.
Bozeman,Mt 59715 CONTRACT FOR: 2 306 869.95
CONTRACTOR:
JTL Gropp Inc.
21730 Frontage Road P.O.Box 9
Belgrade,MT 59714
If
You are directed to proceed promptly with the following change(s):
Replace the existing 10-inch water valve and valve box on a fire hydrant at North 17"'Avenue and Durston.
Approximate stationing 16+45.
Attachments: (List documents supporting changes)
Change requested by the City of Bozeman Water Department
If a claim is made that the above change(s)have affected Contract Price or Contract Time,any claim for a Change Order based thereon
will involve one of the following methods of determining the effect of the change(s).
Method of determining change in Contract Price: Method of determining change in Contract Time:
®Time and materials ❑Contractor's records
❑Unit Price ❑Engineer's records
❑Cost plus fixed fee ®Other N/A
®Other
Estimated increase in Contract Price: Estimated increase(decrease)in Contract
$5,535.00(not to exceed amount per JTL letter dated 7/14/06) Time: 0 days. If the change involves an increase,
the estimate time is not to be exceeded without further
authorization.
If the change involves an increase, the estimated amount is not to
be exceeded without further authorization.
RECOMMENDED: AUTHO D:
By:
Engineer Owner
Date 7'l$rob
H:\02\M229129\ConstAdmin\Work Directives\WorkChangeDirective_#1.doc
y
(406)388-6832.21730 FRONTAGE ROAD•P.O.BOX 9•BELGRADE,MONTANA 59714
July 14, 2006
Ralph Gurney P.E.
HKM Engineering Inc.
222 North 32pd Street, Suite 700
Billings, MT 59107
RE: Durston Road Reconstruction
North 70' Avenue to North 19t" Avenue
Ralph,
We have been asked to furnish pricing to replace a10-inch water valve and valve box on a
fire hydrant at North 17`"Avenue and Durston. The old 10-inch valve can be removed
and a new 10-inch gate valve and valve box can be installed using a solid sleeve to make
the connection for$5,535.00.
If you have any questions please call me at 388-6832 extension 19.
Sincerely,
0 /t
1�d�
Steven R. Baeth
JTL Group, Inc.
steve.baeth@itlgroup.com
WE ARE AN EQUAL OPPORTUNITY EMPLOYER
09/05/2006 09:11 FAX 406 388 8347 JTL GROUP ; JJKK WJuuz
s
(406)398-9992.21730 FRONTAGE ROAD-P.O.BOX 9•BELGRADE,MONTANA 59714
September 5, 2006
Zach Lowe P.B. /Ralph Gurney F,E•
HKM Engineering Inc.
222 North 32rd Street, Suite 700
Billings,MT 59107
RE: Durston Road Reconstruction
North 7`h Avenue to North 19`" Avenue
Zach/Ralph,
TL Group,Inc_ is requesting one additional contract day for the installation of the 10-
inch Water Valve and Valve Box at station 16+45.
If you have any questions please call me at 388-6832 extension 19.
Sincerely,
'W.W. k-
dmeff
Steven R.Baeth
JTL Group, Inc.
steve,haeth(alitl.gxoup.cona
aft
40 WE ARE AN EQUAL OPPORTUNITY EMPLOYER