HomeMy WebLinkAboutF2 Sprinkler System Contract �4
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: James Goehrung, Superintendent of Faciliti
Chris Kukulski, City Manager
SUBJECT: Bogert Pavilion Fire Suppression System
MEETING DATE: September 5, 2006
BACKGROUND: On August 14, I appeared before the City Commission and received
direction to begin rebuilding the Bogert Pavilion. Most of the initial demolition work is
compete. The arched trusses on the north and south end of the building are scheduled to arrive
on site the first week September.
Tied to the reuse of the facility is the code requirement to install a fire suppression sprinkler
system. The requirement is tied to an A Occupancy, or an assembly occupancy, for the public
activities that occur at the pavilion from park reservations and other activities like the Bogert
Market.
Attached is a contract with Sprinkler Technology Design, Inc. for the design, bidding and
construction oversight for a sprinkler system to be installed at the pavilion. The system will be a
dry system and require a 6 foot by 6 foot enclosed, heated building to house the pump and
pneumatic equipment required for this type of system. A large portion of the cost is due to the
fact that the water line will have to be extended from South Church across the parking lot to the
equipment house.
The design and supervision fees for the project are $10,260.00. The estimated construction costs
are $116,526.00; this includes a 10% contingency. Total estimated cost is $126,786.00.
RECOMMENDATION: Staff recommends the award of the design portion of the contract
at this time. Once bids are received and reviewed for the installation of the system, a separate
request for award will be submitted to the Commission for the construction phase of that
contract.
FISCAL EFFECTS: Money for the project will come from general fund reserves. A
formal request for restitution has been submitted to Youth Probation. I did include a request for
the cost of the sprinkler system in the documents submitted to the court. We will not know how
much the City might receive in restitution until the matter winds its way through the court
system.
ALTERNATIVES: As suggested by the City Commission.
Re y submitted,
James Goeh g Chris A. Kukulski, City Manager
Superintendent of Facilities
Attachments: Sprinkler Technology Design Contract
Report compiled on August 28, 2006
y.
ti Gglp N A c Sprinkler Technology Design, Inc.
p gY n,�
a 2011 N. 22°d Avenue, Suite 4 phone 406-582-1936
Bozeman, MT 59718-2781 fax 406-585-8332
info&sprinklertechnologydesign.com
August 22, 2006
City of Bozeman
P.O. Box 1230
Bozeman, MT 59771
Attn: James Goehrung
Ref: Bogart Pavilion
Fire Sprinkler Design
Bozeman, Montana
Fee Proposal
Dear James,
Per your request we are pleased to provide the following proposal for engineering of the
fire sprinkler system for the above referenced project. Our work will include:
1. Layout drawings of the fire sprinkler system including pipe routing; sprinkler head
location; and appropriate device and equipment locations. Preparation of main
level plans for a 25,875 sq. ft. pavilion building. Also included will be one sheet
which will have appropriate legends, notes, sections, details, fire service line, etc.
2. Specifications.
3. Hydraulic calculations based upon anticipated water supply to this location.
4. Engineering of fire service line in accordance with City of Bozeman requirements.
5. Electrical engineering to incorporate fire alarm/reporting requirements from
appropriate sprinkler flow and tamper switches and power requirements for valve
house heat, light and power.
6. The cost of attending meetings at your office for the purpose of coordinating
design.
7. Pre-bid coordination with Contractors.
8. Material and shop drawing submittal.
9. Drawings for bid, submittal and installation.
10.Ongoing office support and advice during installation of fire sprinklers.
"FIRE SPRINKLERS SAVE LIVES"
11.Final on site observation and preparation of"punch list."
12.Verification of punch list completion.
13,Close-out documentation.
We will provide final shop drawings ready for fire sprinkler contractor fabrication, and
installation, including approvals from building officials for the fixed fee of$5,260.00.
We anticipate probable sprinkler construction costs of $45,000.00. We anticipate
probable electrical construction costs of$5,000.00.
We will provide final drawings for a new fire service line including approvals from
building officials and water officials for the fixed fee of$2,250.00.
We anticipate probable fire service line construction costs of$45,000.00.
Attached please find a design proposal in the amount of ($2,500.00) for design of the
new valve house. We will coordinate this design in the bid package for $250.00.
We anticipate probable valve house construction of$10,000.00
Total design $ 10,260.00
Construction $105,000.00 (est)
$115,260.00
10% $ 11,526.00„(contingency)
$126,786.00
This proposal does not include the cost of permits.
This proposal does not include the cost of CADD files obtained from others.
Contractor shall provide one complete "hard" (printed) copy of project plans and
specifications including all alternates and addendums.
This proposal does not include on-site construction administration or observation other
than included above. This work will be provided based upon Sprinkler Technology
Design's standard hourly rates and expenses at cost plus 10% if requested.
If Sprinkler Technology Design, Inc. does not provide on-site observation verifying the
installation is in accordance with plans provided; the contractor shall hold Sprinkler
Technology Design, Inc. harmless from any and all claims resulting due to contractor
deviation from plans provided.
"FIRE SPRINKLERS SAVE LIVES"
Should you find this proposal acceptable, please sign one copy and return it to us.
We look forward to working with your team on this project.
Very Truly Yours,
SPRINKLER TECHNOLOGY DESIGN, INC.
David R. Hughes, Jr., P.E.
Accepted this day of 2006.
By:
Amount:
"FIRE SPRINKLERS SAVE LIVES"