HomeMy WebLinkAboutF3 Amendment 3 PSA
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski, City Manager
SUBJECT: Durston Road, 7th to19th, Professional Services Agreement Amendment
No. 3.
MEETING DATE: July 31, 2005
BACKGROUND: Attached is a copy of the partially executed Amendment No. 3 to the
Professional Services Agreement for the above referenced project. The amendment covers
several items of additional services that were not included in the original scope of work. It also
updates the consultants billing rates as this project went through significant delays due to right of
way issues. This amendment will increase the design phase services from $235,299.00 by
$83,457.65 to a total of $318,756.65, and the construction phase services from $185,319.00 by
$34,422.00 to a total of $219,741.00. A more specific description of the items covered by this
amendment is included in the attached letter from the consultant.
RECOMMENDATION: Authorize the City Manager to sign.
FISCAL EFFECTS: This will be paid for by the project funds.
ALTERNATIVES: As suggested by the City Commission.
Respectfully submitted,
_________________________________ ____________________________
Robert J. Murray Jr., Project Engineer Chris A. Kukulski, City Manager
Attachments: Amendment No. 3
Report compiled on 6/24/06