Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski, City Manager
SUBJECT: Stormwater Facility Plan, Professional Services Agreement Amendment
MEETING DATE: July 10, 2006
BACKGROUND: Attached is a copy of the partially executed Amendment No. 2 to the Professional
Services Agreement for the above referenced project.
The City has contracted with the team of HDR/Morrison Maierle to complete a new Stormwater Facility
Plan, Amendment 1 added a detailed evaluation of the facilities within the MSU Campus. A separate
agreement has been executed between the City and MSU stipulating reimbursement by MSU of all costs
associated with the work covered by these amendments.
RECOMMENDATION: Authorize the City Manager to sign the amendment.
FISCAL EFFECTS: None, all costs for this work will be paid by MSU
ALTERNATIVES: As suggested by the City Commission.
Respectfully submitted,
on
Robert J. Mu ay Jr., Project Engineer Chris A. Kukulski, City Manager
Attachments: Amendment No. 2
Report compiled on 6/26/2006