Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski, City Manager
SUBJECT: Durston Road N. 7th to N. 19th
MEETING DATE: 5/16/06
BACKGROUND: Attached is a copy, of the Notice of Award for the above referenced project. This project is the
complete reconstruction of Durston Road from North 7th Avenue to North 19th Avenue.
Bids for the above-referenced project were opened on May 9, 2006 with 2 bids being submitted.
The low bid was submitted by JTL Group, Inc in the amount of $2,306,869.95. The Bid
Tabulation for the project is attached.
The total project costs (construction and engineering) are currently estimated to be $2,761,909.95.
This project will be funded through a combination of G.O. Bond and Impact Fees. The G.O.
Bond has a current balance of $1,591,347 which all be utilized on this project, with the remainder
coming from the street impact fee fund.
RECOMMENDATION: Approve and authorize City Manager to sign the Notice of Award.
FISCAL EFFECTS: To be paid from the G.O. Bond and Street Impact Fee
ALTERNATIVES: Disapprove
Respectfully submitted,
_________________________________ ____________________________
Robert J. Murray Jr., Project Engineer Chris A. Kukulski, City Manager
Attachments: Notice of Award
Report compiled on 8/23/05