HomeMy WebLinkAboutE1
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Bob Murray, Project Engineer
Chris Kukulski, City Manager
SUBJECT: Wastewater Facility Plan
MEETING DATE: May 8, 2006
BACKGROUND: The City has undertaken the task of updating its facility plans. The team
of Morrison Maierle/HDR was selected for the Wastewater plan. The draft plan has now been
completed and is ready for review and comment. Attached is a copy of the executive summary
for the document which will be the basis of the presentation to the Commission. This meeting
will be for the Commission to discuss and review the findings of the plan with the consultant. A
subsequent public hearing will be held on the 22nd.
RECOMMENDATION: Listen to presentation; ask questions for clarification, discussion.
FISCAL EFFECTS: N/A
ALTERNATIVES: None
Respectfully submitted,
_________________________________ ____________________________
Robert J. Murray Jr., Project Engineer Chris A. Kukulski, City Manager
Attachments: Easement Documents
Report compiled on 5/3/2006
i
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Bozeman Wastewater Facilities Plan
Chapter 1
Executive Summary
Prepared by:
James Nickelson, MMI
Reviewed by:
Bob Morrison, MMI
Amanda McInnis, HDR
ii
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Table of Contents
1.1 INTRODUCTION............................................................................................................1-1
1.2 BASIS OF PLANNING....................................................................................................1-1
1.3 COLLECTION SYSTEM ANALYSIS ..........................................................................1-2
1.4 WASTEWATER TREATMENT PLANT ANALYSIS..............................................1-3
1.5 RECOMMENDATIONS.................................................................................................1-5
1.5.1 Collection System Recommendations...................................................................1-5
1.5.2 Wastewater Treatment Plant Recommendations................................................1-7
List of Tables
Table 1-1 – Projected Influent Wastewater Flows and Loads ................................................ 1-1
Table 1-2 – Probable Total Capital Cost of Recommended WWTP Alternatives ............... 1-5
Table 1-3 – Collection System – Priority 1 Projects ................................................................. 1-6
Table 1-4 – Bozeman WWTP Phase 1 Improvements – Probable Project Capital Cost ... 1-8
Table 1-5 – Bozeman WWTP Phase 2 Improvements – Probable Project Capital Cost ... 1-9
Table 1-6 – Bozeman WWTP Phase 3 Improvements – Probable Project Capital Cost ... 1-9
1-1
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Recommended
design population
for year 2025 is
92,500
1.1 INTRODUCTION
In 2004 the City of Bozeman undertook the task of planning for the future of their wastewater
infrastructure. The goal of the planning effort was to define the existing infrastructure, estimate
future populations and wastewater quantities, determine improvements needed to meet future
permit requirements and accommodate growth, and develop an improvements plan for the
wastewater system. This executive summary briefly describes the contents of the plan and the
resulting recommendations.
1.2 BASIS OF PLANNING
The starting point for projecting wastewater system needs is to define a study boundary and estimate
future populations and wastewater flows and loads. A study area was
selected that includes approximately 42,400 acres. The estimated growth
rate for the City of Bozeman was approximately 5% per year for the
period 2001 to 2005, and is continuing at an accelerated pace that is
exceeding the 5% annual average. In order to effectively plan for future
growth, a year 2025 population of 92,500 based on a 5% annual growth
rate is utilized for the planning period. The following table summarizes
the design population and resulting projected wastewater flows and loads through the planning
period.
Table 1-1 – PROJECTED INFLUENT WASTEWATER FLOWS AND LOADS
Flow and Load Parameters 2005 2010 2015 2020 2025
DESIGN POPULATION 34,900 44,500 56,800 72,500 92,500
ANNUAL AVERAGE
FLOW, mgd
5.20
6.70
8.50
10.90
13.90
ANNUAL AVERAGE
CARBONACEOUS
BIOCHEMICAL OXYGEN
DEMAND (CBOD) LOAD,
lb/day
9,400
12,000
15,300
19,600
25,000
ANNUAL AVERAGE
TOTAL SUSPENDED
SOLIDS (TSS) LOAD, lb/day
9,800
12,500
15,900
20,300
25,900
1-2
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Nearly 110 miles of sewer lines and 2 lift
stations at a total estimated cost of $70
million will be required to provide service to
the study area.
1.3 COLLECTION SYSTEM ANALYSIS
The wastewater collection system consists of approximately 150 miles of gravity sewer mains,
approximately 3,300 manholes and six lift stations, and associated forcemains that discharge
wastewater to the wastewater treatment plant. The collection system consists of pipe ranging from
new PVC pipe associated with recent expansions and increasing development, to clay pipe exceeding
100 years old. Few capacity problems were identified at existing flows.
Some condition related problems in the existing system include excessive amounts of root cutting
and clay pipe maintenance, infiltration in areas of high groundwater and suspected sump pump
connections, and a non-quantitative approach to setting existing system rehabilitation priorities. It is
recommended that a more proactive approach be taken to rehabilitate the aging pipe network,
including a specific annual sewer main rehabilitation program. Specific conclusions regarding the
existing collection system are as follows:
• The City has an ongoing Closed-Caption Television (CCTV) program that includes
reviewing new and existing infrastructure, however; due to time and staff constraints, much
of the existing system goes un-reviewed unless a problem occurs. The City should establish
a dedicated program to CCTV and record, preferably to a GIS system, approximately 20-
percent of their existing collection system each year to identify specific problem areas
associated with the aging pipe. This would result in a 5-year turn-around time to inspect the
entire system before the inspection cycle begins again.
¾ The City’s current maintenance protocol includes evaluating CCTV reports and recording
the information to a spreadsheet. There is currently no quantitative scoring system in place.
Additionally, the City’s equipment lacks lateral inspection capabilities. Systems are available
that include CCTV inspection equipment with lateral inspection capabilities and a pipe
reporting software system. The software includes a sewer scoring system for structural and
root defect problems. Scoring should be associated with each manhole and segment of pipe
with a feature identification number, in order to more accurately address system
rehabilitation needs.
¾ Several rehabilitation projects identified in the 1998 City of Bozeman Wastewater Facility
Plan have not yet been completed. Additionally, the City has identified spot repairs
including manhole replacement, manhole lining, pipe lining and pipe replacement projects
that need to be addressed.
The significant increase in wastewater flows
over the planning period will require
substantial improvements and expansions of
the collection system. Chapter 6 provides
recommendations for the City of Bozeman’s
future wastewater collection system
improvements which include major and minor infrastructure replacement and paralleling projects,
an outline of future extensions and lift stations with proposed sizing, and a recommended plan to
reduce infiltration and inflow.
1-3
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
The existing WWTP has reached its
design loadings. Growth and new permit
requirements drive the need for $55 million
in improvements.
In order to serve the study area, over 515,000 feet of new sewer and two lift stations will be
required. In addition, approximately 95,000 feet of existing sewer interceptors and trunk mains are
in need of upsizing or installation of paralleling pipes. Key interceptors that will require upsizing
and/or parallel pipes include the Frontage Road Interceptor, the extension of both the Rouse
Interceptor and Front/Tamarack Interceptors, and the main interceptor into the wastewater
treatment plant. Recommendations for upsizing existing sewer lines listed in Chapter 6 include $14
million in scheduled improvements. If the future interceptors that are needed to provide service
throughout the study area are included, the needed improvements approach $70 million (2005
dollars).
In addition to growth related improvements, it is imperative that aging infrastructure become a high
priority issue to the City of Bozeman. While capacity issues have not been identified in areas of
older pipe, continuing problems with root and structural defects creates potential blockages and
capacity issues that predictive modeling cannot foresee. It is only with diligent effort to quantify
these problems with an effective inspection, scoring, and maintenance program, that infrastructure
degradation can be managed and addressed, thus ensuring the continued integrity of Bozeman’s
collection system.
1.4 WASTEWATER TREATMENT PLANT ANALYSIS
The Bozeman Wastewater Treatment Plant (WWTP) is a secondary treatment facility utilizing the
activated sludge process. The Bozeman WWTP was originally constructed in 1970, and has been
expanded or modified five times. The original plant was a very basic secondary treatment facility.
In 1982, the WWTP was expanded and modified to a more advanced activated sludge treatment
plant. In 1983, the plant added final effluent polishing and sludge storage facilities. In 1998, the two
digested sludge storage lagoons were converted to a single larger lagoon and another sludge storage
lagoon was added. In 2002 and 2003, the City expanded and modified the plant again adding a
primary clarifier and improving the anaerobic digesters. Finally, the City has recently completed
construction of a project that included adding
a secondary clarifier, improvements to the
headworks and aeration facilities and a new
computer based supervisory control and data
acquisition system.
The following summarizes the most relevant
findings relative to the existing conditions at the wastewater treatment plant:
1. Flows to the Bozeman WWTP have not increased significantly over the last decade even though
the population has increased significantly. This is an indication that the City’s infiltration and
inflow (I/I) removal program is working by reducing the volume of groundwater and/or rainfall
that reaches the wastewater collection system. Lower than average precipitation over the past
several years may have some impact on recorded flows. Average annual wastewater flows from
2001 to 2005 have been just below 5 mgd. (Design flow of the existing facility is 5.8 mgd.)
2. Wastewater strength parameters (CBOD, TSS, and ammonia) have increased significantly over
the last decade. These parameters are higher than normally expected for Bozeman’s population,
1-4
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
indicating that commuter/day users are exerting more of a demand on the wastewater system
than in the past.
3. The Bozeman WWTP consistently meets or exceeds its discharge permit requirements.
4. The WWTP was originally designed to provide an annual average treatment capacity of 5.80
mgd. Design annual average CBOD and TSS loadings were 8,580 and 7,220 lb/day,
respectively. Current (2001 to 2005) annual average flows to the plant are about 4.9 mgd, or
about 85 to 90 percent of the rated capacity. However, current CBOD and TSS loads have
exceeded the design values by 4 to 16 percent. This necessitates that the WWTP unit process
design capacities be re-evaluated with current wastewater flow and strength characteristics.
5. For the most part, the plant’s current hydraulic conveyance system (pipes, channels, etc.) can
handle the design peak hourly flow without submerging weirs or overtopping walls. However,
the headworks at the influent end of the plant and the effluent end of the plant from the
secondary clarifiers to the outfall to the East Gallatin River does have some hydraulic
bottlenecks that should be addressed.
6. The City’s activated sludge aeration system, and the bio-solids treatment and disposal system
have capacity limitations. The aeration blower system, anaerobic digestion system and sludge
storage system need expanding. In addition, the City will need more farmland for final disposal
of the sludge than it currently has available. Alternate sludge handling and disposal systems
should be investigated and compared to just expanding current processes.
7. The WWTP has a number of equipment items over 20 years old and some over 35 years old.
Much of the existing equipment should be scheduled for replacement or refurbishment over the
next 5 to 10 years.
8. Several upgrades to the existing plant are considered desirable or critical to utilize the existing
plant to its full rated capacity of 5.80 mgd.
In order to provide capacity for the design wastewater flows and loads through the planning period,
the wastewater treatment plant will need to be expanded and additional processes added. The
projected flows and loads at the end of the study period represent an increase of more than 100%
over existing process capacities. In addition, current and anticipated discharge limitations will
require that the wastewater treatment plant be upgraded to a more advanced treatment process.
Solids handling facilities and treatment facilities will also require modifications. Chapter 8 evaluates
multiple alternatives for liquid treatment unit processes and solids handling and treatment
alternatives. The recommended liquid stream process facility for the 20 year planning period is an
advanced biological nutrient removal system with secondary clarification and effluent filtration. It is
recommended that the City continue to stabilize their sludge with anaerobic digestion and to land
apply biosolids; however, it is recommended that screw press dewatering facilities be added.
Table 1-2 presents the total estimated capital cost of the recommended alternatives. The total cost
of $55 million (2005 dollars) includes the estimated construction cost of the facilities and an
allowance for technical services. The costs are based on year 2025 facilities.
1-5
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Table 1-2
PROBABLE TOTAL CAPITAL COST OF
RECOMMENDED WWTP ALTERNATIVES (a)
Project Component Description Probable Cost
Construction of Liquid Treatment Systems
Construction of Solids Handling/Treatment Systems
Subtotal Construction Cost
$33,570,000
12,300,000
$45,870,000
Engineering, Legal, Administrative and Other Related City Costs at 20% (b) $9,180,000
Total Capital Cost $55,050,000
(a) Cost estimates are prepared in mid-2005 dollars and should be advanced to the mid-point of construction.
(b) Costs for technical services and related City personnel services are based on a percent of total construction for
budgeting purposes only. Final costs for technical services will be negotiated during the final design phase of
the project and may vary depending on actual site conditions, availability of existing data, the final scope of
services, etc.
1.5 RECOMMENDATIONS
The following is a summary of the recommendations for the collection system and wastewater
treatment plant improvements. Additional details are provided in Chapters 4, 6 and 10 regarding the
collection system and Chapters 5, 8 and 10 in regards to the wastewater treatment plant.
1.5.1 Collection System Recommendations
Much of the City’s collection system is old and its condition is unknown. Several changes are
recommended to move to operating in a more pro-active mode where problems are anticipated,
repairs are scheduled, emergencies avoided, rather than in a reactive mode.
• Chapter 4 identifies approximately 4,500 feet of sewer main that should be reviewed in the
field to assess if capacity problems exist at current flows.
• It is recommended that the annual sewer main rehabilitation program receive increased
funding to address system wide problems associated with aging infrastructure.
• City staff indicate that many crawl space sump pumps are connected to the sewer system and
that this has been a practice for over 20 years. There is a City ordinance on record to
prevent crawl space pumps from discharging to the sanitary sewer, but this has not been
enforced. A program should be implemented to address and eliminate such connections to
the collection system.
• The City has an ongoing CCTV program for new and existing sewer lines; however, much of
the existing system goes un-reviewed unless an emergency occurs. The City should establish
a dedicated program to CCTV and record, preferably to GIS, approximately 20-percent of
their existing collection system each year to identify specific problem areas associated with
the aging pipe. This would result in a 5-year turn-around time to inspect the entire system
1-6
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Eight high priority
collection system
projects
recommended
totaling $8 million.
before the inspection cycle begins again. It will require City staff approximately 160 working
days per year with a full-time CCTV staff to collect data on 20-percent of the existing
system.
• The City’s current maintenance protocol includes evaluating CCTV reports and recording
the information to a spreadsheet. There is currently no quantitative scoring system in place.
Additionally, the City’s equipment lacks lateral inspection capability. Systems are available
that include CCTV inspection equipment with lateral inspection capability and a pipe
reporting software system. The software includes a sewer scoring system for structural and
root defect problems. Scoring should be associated with each manhole and segment of pipe
with a feature identification number, in order to more accurately address system
rehabilitation needs.
• With an expanding and aging collection system and
recommendations for additional assessment activities,
additional operations staff will likely be required in the near
term.
• Eight high priority projects based on both capacity and condition are identified in Chapter 6.
The following table describes the projects totaling approximately $8,000,0000 in
improvements in 2005 dollars.
Table 1-3 Collection System - Priority 1 Projects
Project Name
Current
Diameter
(inches)
Future
Diameter
(inches)
Replacement
or Parallel
Approx. Length
of Pipe (LF)
S. Rouse Trunk: E Babcock to Kagy 8 24/21 Replacement 8,420
Kagy from 3rd Ave S to 7th Ave S 8 21 Replacement 1,400
Mendenhall to Tamarack from Grand to Rouse 6 to 18 6 to 18
Lining/
Replacement
12,275 (6, 8)
5,150 (10, 15, 18)
Front Street: Tamarack/Rouse to Haggerty Various 24/21/18 Replacement 8,330
College to Babcock from 5th Avenue to 11th
Avenue Various N/A Lining/
Replacement
15,750 (line)
6,575 (repl)
21-inch Interstate Crossing/Wal-Mart 21 21 Lining/
Replacement 2,400
Front Street Collector 8 12 Replacement 410
Babcock between Hunters Way and Silver
Maple 8 12 Replacement 200
It is important that the City continue to monitor the impacts that expansion of the service area has
on the existing collection system and ensure that needed capacity improvements are realized with the
1-7
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Three phase approach to WWTP
Improvements Recommended.
expansion of the service area. This plan provides the framework to allow for the service area to be
expanded; however, scheduling of the improvements is dependent on the need to provide sewer
service to specific areas. Twenty-five specific projects have been identified to provide additional
capacity within the existing collection system area in addition to forty projects that provide
extensions into the expanded service area. The timing of such projects are dependent on the
location of future development projects and their impact on the collection system capacity.
1.5.2 Wastewater Treatment Plant Recommendations
Based on the priority of the needed improvements and the desire of the City to spread out the
capital outlays necessary to construct the required facilities, it is recommended that the treatment
plant improvements be implemented in three phases as summarized below. The project cost
estimates summarized below are advanced forward to the estimated mid-point of construction for
purposes of planning financing. Average inflation rates of 5 percent per year from mid-2005 to
2008, 4.5 percent per year from mid-2005 to 2014, and 4 percent per year from mid-2005 to 2020
were used to estimate future costs. An allowance of 20 percent of the probable construction cost is
also included to account for future preliminary and final engineering, bid phase services,
construction administration, grant administration (if applicable), legal, and City administration staff
services.
Recommended Phase 1 improvements to the Bozeman advanced WWTP include the following:
• New Headworks Building.
• New Primary Effluent Lift Station.
• New BNR bioreactor basins.
• Modify the existing aeration basins to plug flow
arrangement and add aeration system capacity including a new blower building.
• Two new 85-foot diameter secondary clarifiers and a new RAS/WAS pump station.
• New low lift pump station with provisions for connection to a future effluent filtration
system.
• New UV disinfection structure.
• New liquid chlorine storage/feed system for odor control, RAS bulking control, and standby
disinfection.
• New 750 KW emergency power engine generator.
• Construct a parallel 36-inch outfall pipeline.
• New anaerobic digester and a new digester control building.
The Phase 1 projects are critical to the City because they address hydraulic and organic load capacity
issues (the existing plant is rapidly approaching or is already at its design capacity), future treatment
requirements for nitrogen and phosphorous, unsafe and difficult to meet permit requirements with
the existing chlorination and de-chlorination systems, and biosolids treatment capacity issues. Table
1-4 summarizes the total project capital cost for the Bozeman advanced WWTP Phase 1
improvements.
1-8
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Table 1-4
BOZEMAN WWTP PHASE 1 IMPROVEMENTS
PROBABLE PROJECT CAPITAL COST
Project Component Probable Cost(a)
Liquid Treatment Improvements
Solids Handling and Treatment Improvements
$23,900,000
$3,900,000
Subtotal Probable Construction Cost $27,800,000
Engineering, Legal, Administrative
And Other Related City Costs at 20%(b) $5,600,000
Total Capital Cost $33,400,000
(a) Cost estimates have been advanced from mid-2005 dollars to mid-2008 dollars (the estimated Phase 1 mid-point
of construction) assuming an inflation rate of 5 percent per year.
(b) Costs for technical services and related City personnel services are based on a percent of total construction for
budgeting purposes only. Final costs for technical services will be negotiated during the final design phase of the
project and may vary depending on actual site conditions, availability of existing data, the final scope of services,
etc.
Recommended Phase 2 improvements to the Bozeman advanced WWTP would extend the capacity
of the plant and further improve effluent quality and solids handling flexibility. These
improvements are summarized below:
• Add a third grinder/screen unit to the Headworks.
• One new primary clarifier with a primary sludge pump station.
• Replace the clarifier mechanisms on two existing clarifiers.
• Replace the existing primary sludge and scum pumps in the gravity thickener pump station
and replace existing sludge/scum piping with glass-lined piping.
• Add new primary effluent pump(s).
• Construct second half of the new BNR bioreactor basins.
• New phosphorous removal chemical feed system and primary sludge fermentation system.
• Add new blower(s) to Blower Building.
• One new 85-foot diameter secondary clarifier and add new RAS and WAS pumps to
RAS/WAS pump station.
• New effluent filtration structure with at least four cloth media filter units.
• New liquid sludge storage tank and new screw press dewatering building with one screw
press and odor control facilities.
• New dewatered sludge storage facility.
• Purchase new biosolids haul and application equipment.
• New Administration/Laboratory Building.
The Phase 2 project components address increasingly stringent effluent quality requirements and
critical solids handling system’s flexibility and performance. Table 1-5 summarizes the estimated
total project capital cost for the Phase 2 improvements.
1-9
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
Table 1-5
BOZEMAN WWTP PHASE 2 IMPROVEMENTS
PROBABLE PROJECT CAPITAL COST
Project Component Probable Cost(a)
Liquid Treatment Improvements
Solids Handling and Treatment Improvements
$17,400,000
$10,900,000
Subtotal Probable Construction Cost $28,300,000
Engineering, Legal, Administrative
And Other Related City Costs at 20%(b) $5,700,000
Total Capital Cost $34,000,000
(a) Cost estimates have been advanced from mid-2005 dollars to early 2014 dollars (the estimated Phase 2 mid-point
of construction) assuming an inflation rate of 4.5 percent per year.
(b) Costs for technical services and related City personnel services are based on a percent of total construction for
budgeting purposes only. Final costs for technical services will be negotiated during the final design phase of the
project and may vary depending on actual site conditions, availability of existing data, the final scope of services,
etc.
The recommended Phase 3 improvements to the Bozeman advanced WWTP would extend the
plant capacity to the projected year 2025 conditions. These improvements are summarized below:
• Construct the fifth primary clarifier.
• Add new primary sludge pumps(s) and piping at the newer primary sludge pump station.
• Construct the eighth secondary clarifier.
• Add two new cloth media filter units to the final effluent filtration structure.
• One new anaerobic digester.
• Add one screw press dewatering unit.
Table 1-6 presents the estimated total project capital cost of the recommended Phase 3
improvements.
Table 1-6
BOZEMAN WWTP PHASE 3 IMPROVEMENTS
PROBABLE PROJECT CAPITAL COST
Project Component Probable Cost(a)
Liquid Treatment Improvements
Solids Handling and Treatment Improvements
$4,800,000
$2,700,000
Subtotal Probable Construction Cost $7,500,000
Engineering, Legal, Administrative
And Other Related City Costs at 20%(b) $1,500,000
Total Capital Cost $9,000,000
(a) Cost estimates have been advanced from mid-2005 dollars to early 2020 dollars (the estimated Phase 3 mid-point of
construction) assuming an inflation rate of 4 percent per year.
(b) Costs for technical services and related City personnel services are based on a percent of total construction for
budgeting purposes only. Final costs for technical services will be negotiated during the final design phase of the
project and may vary depending on actual site conditions, availability of existing data, the final scope of services,
etc.
1-10
H:\0417\048\DOCS\Second Draft\Chapter 1.doc
$33 million Phase 1 WWTP project
should be under taken now.
It is our opinion that the recommended alternatives and three project phases is the best approach to
meet the City’s growth and regulatory requirement
demands, minimize WWTP operational difficulties and
eliminate current problem areas, and minimize the cost
impacts that would result from excessive phasing.
It is recommended that the City proceed with the Phase 1 Project at this time in order to be able to
commence construction in 2007.