CONCEPT-LEVEL INFRASTRUCTURE COST ESTIMATES
AT POTENTIAL TOP SPORTS COMPLEX
BOZEMAN, MONTANA
March 2014
CLIENT: City of Bozeman, Montana
ENGINEER: TD&H Engineering
234 E. Babcock Street, Suite 3
Bozeman, MT 59715
Job No. B14-022
TOP SPORTS COMPLEX COST ESTIMATES Introduction
BOZEMAN, MONTANA 1
TABLE OF CONTENTS
1.0 INTRODUCTION ............................................................................................................... 2
1.1 PURPOSE AND SCOPE ................................................................................................. 2
1.2 PROJECT DESCRIPTION .............................................................................................. 2
2.0 MASTER PLANS ................................................................................................................ 3
2.1 STREETS ......................................................................................................................... 3
2.2 SEWER ............................................................................................................................ 4
2.3 WATER ............................................................................................................................ 5
2.4 STREAM AND DITCH RELOCATIONS ...................................................................... 5
3.0 COST ESTIMATES ............................................................................................................ 6
3.1 INTRODUCTION ............................................................................................................ 6
3.2 COST SUMMARY .......................................................................................................... 6
4.0 APPENDIX (ITEMIZED COST ESTIMATES) ................................................................. 8
TOP SPORTS COMPLEX COST ESTIMATES Introduction
BOZEMAN, MONTANA 2
CONCEPT-LEVEL INFRASTRUCTURE COST ESTIMATES AT POTENTIAL TOP
SPORTS COMPLEX
BOZEMAN, MONTANA
1.0 INTRODUCTION
1.1 PURPOSE AND SCOPE
This report presents the results of our concept-level cost estimating for the proposed Trails, Open
space and Parks (TOP) Sports Complex to be located in Bozeman, Montana. The purpose of the
effort is to present the approximate costs of installing required public water, sewer, street, storm
drainage and ditch infrastructure adjacent to and in proximity to the proposed TOP Sports
Complex (hereafter “site”) bounded by Baxter Lane on the north, Oak Street on the south,
Flanders Mill Road on the east and Cottonwood Road on the west. The site, shown in in Figure 1
is also approximately known as the northern 80 acres of Tract 1A, Certificate of Survey 2554A.
This cost estimate is in accordance with the agreement between TD&H Engineering and the City
of Bozeman dated February 24, 2014.
1.2 PROJECT DESCRIPTION
It is our understanding the proposed project consists of development of a sports complex
including play fields, parking lots, buildings, lighting, and other site related features. This cost
estimate does not include any of those “on-site” facilities. Instead, this document includes costs
for the surrounding and adjacent public infrastructure likely to be required during review of any
development on this property. The required infrastructure includes those identified in the various
master plans listed below.
TOP SPORTS COMPLEX COST ESTIMATES Master Plans
BOZEMAN, MONTANA 3
2.0 MASTER PLANS
2.1 STREETS
2.1.1 Transportation Plan
In 2007, the City of Bozeman had RPA complete an update to the Greater Bozeman Area
Transportation Plan. The plan identifies corridors for future improvements such as
arterial and collector streets, to accommodate projected traffic. For our cost estimates, we
used the classification of street identified in the transportation plan update, and the typical
section constructed adjacent to the site. Figure 2 below shows the improvements
anticipated.
On Baxter Lane, the estimate includes widening to the south to create ½ of the required
minor arterial section. The north ½ has already been constructed. Starting from the
centerline, this estimate includes an 11 foot driving lane, 5 foot bike lane, 8 foot parking
lane and curb, gutter and 6 foot sidewalk on the south side only. Lighting is included at
the intersections and along the street. We also included storm drainage, signage and
striping and pedestrian ramps at the intersections.
On Flanders Mill Road, the estimate includes curb and gutter on both sides of this local
street, two paved driving lanes for a total width of 31 feet (back of curb to back of curb),
and a 6 foot sidewalk on the west side only. This section matches the section constructed
along the east side of the new Meadowlark Elementary School. No lighting is included as
this is only a local street. Intersection lighting is included in the estimates for Oak Street
and Baxter Lane. We also included storm drainage, signage and striping and pedestrian
ramps at the intersections.
The north side of Oak Street would be constructed to ½ of a principal arterial standard.
This would include curb and gutter on both sides of a 32 foot wide paved street (back of
curb to back of curb) and a 6 foot sidewalk on the north side only. There would be a
median in the ultimate build-out, and a matching section to the south, though those
improvements are not included in this estimate. The section proposed for the north ½ of
Oak Street would mirror that constructed in the Flanders Creek subdivision to the
southwest of the TOP Sports Complex site. Lighting is included at the intersections and
TOP SPORTS COMPLEX COST ESTIMATES Master Plans
BOZEMAN, MONTANA 4
along the street. We also included storm drainage, signage and striping and pedestrian
ramps at the intersections.
The estimate for Cottonwood Road also includes ½ of a principal arterial standard. This
would include curb and gutter on both sides of a 32 foot wide paved street (back of curb
to back of curb) and a 6 foot sidewalk on the east side only. There would be a median in
the ultimate build-out, and a matching section to the west, though those improvements
are not included in this estimate. The section proposed for the east ½ of Cottonwood
Road would mirror that constructed in the Flanders Creek subdivision to the southwest of
the TOP Sports Complex site. Lighting is included at the intersections and along the
street. We also included storm drainage, signage and striping and pedestrian ramps at the
intersections.
2.1.2 Traffic Impact Studies
There have been two recent traffic impact studies (TIS) completed for developments
proposed in the vicinity. Both were completed in November 2013. First, the Flanders Mill
subdivision TIS by Marvin and Associates states that no intersection improvements are
necessary as a result of that subdivision. According to that report, all nearby intersections
will continue to operate at acceptable levels of service after construction of that
subdivision.
Second, a TIS was prepared by Abelin Traffic Services for Bouder Creek/Westbrook
Residential Development. That report concluded a four way stop and west bound turn
lane would be necessary at the intersection of Durston Road and Cottonwood Road. They
recommended widening the west leg of that intersection and striping adjustments, in
order to align and handle the anticipated traffic properly. We have included these
intersection improvements in our cost estimates. Specifically, we included paving, curb
and gutter on the south side, storm drainage, lighting, signage and striping. We did not
include any sidewalk improvements or pedestrian ramps.
2.2 SEWER
For purposes of this cost estimate, we used the sewer improvements recommended in the City of
Bozeman Wastewater Facility Plan. Figure 6-2 in the 2005 plan identifies sewer mains needed to
accommodate projected growth. As shown in Figure 3 below, these include a 24 inch sewer main
in Cottonwood Road, and a 27 inch sewer main in Baxter Lane. We included manholes, but did
TOP SPORTS COMPLEX COST ESTIMATES Master Plans
BOZEMAN, MONTANA 5
not include any individual service lines. We should note that there is no 27 inch sewer main to
connect with downstream at this time. The downstream pipe would need to be constructed, along
with a lift station to serve this area of the City. It is beyond the scope of this report to determine
the timing or financing mechanisms needed to complete the projected sewer improvements.
2.3 WATER
For purposes of this cost estimate, we used the improvements recommended in the City of
Bozeman Water Facility Plan. The “20 Year Water Distribution System” map in the 2005 plan
identifies water mains needed to accommodate projected growth. As shown in Figure 3 below,
these include a 12 inch water main in Baxter Lane, of which the eastern half has already been
completed. We made the assumption that a 10 inch water main would be needed in Oak Street
and an 8 inch main would be needed in Cottonwood Road. These pipes would be consistent with
the piping installed in the Flanders Mill subdivision to the west of the sports complex site, and
would complete the grid. We included the usual appurtenances such as valves, fittings and fire
hydrants, but did not include individual service lines.
2.4 STREAM AND DITCH RELOCATIONS
As part of the Flanders Mill Road street improvements described above, the channel along the
west side of the road must be relocated outside the right of way to make room for the street. The
northern 1/3 of the channel is a stream, so relocation will include permitting through the
Conservation District, Montana Department of Fish, Wildlife and Parks and the US Army Corps
of Engineers. Costs associated with the permitting are not specifically included here, although
some design costs have been added to all the infrastructure costs. The southern 2/3 of the channel
is a drainage waste channel that carries runoff that bypasses the Maynard Border pipeline. It
should be noted that the Maynard Border pipeline transects the TOP Sports Complex site, but no
costs for relocation have been included in this report. We assumed the sports facilities could be
situated to avoid the pipeline, or the on-site cost estimates prepared by others would incorporate
any required irrigation pipeline relocation.
TOP SPORTS COMPLEX COST ESTIMATES Cost Estimates
BOZEMAN, MONTANA 6
3.0 COST ESTIMATES
3.1 INTRODUCTION
The following concept-level cost estimates are based upon historic bid prices received from local
contractors in recent years for similar projects. In some cases, we had to interpolate or
extrapolate from similar work items. This is a common practice. Keep in mind this kind of cost
estimating is not an exact science. Many factors can impact actual construction costs at the time
a project is bid. These include market forces such as availability of materials, labor, equipment,
fuel and many other factors.
The costs presented here are in 2014 dollars, so adjustments should be made for inflation and
other factors if the work is contemplated in future years. We have added a contingency of 20% to
each work item, due to unknowns typically discovered in the design process. As these
improvements have not yet been surveyed or designed, our confidence level is lower than when
we have completed those steps. We also added 15% for administrative, design and construction
engineering service costs. The total concept-level project costs presented include the estimated
construction cost plus the 20% contingency and the 15% administration, design and construction
costs. Other costs would apply if these projects are performed with financing mechanisms such
as special improvement districts.
3.2 COST SUMMARY
The following table lists the total estimated concept-level project costs for the infrastructure
items identified above.
TOP SPORTS COMPLEX COST ESTIMATES Cost Estimates
BOZEMAN, MONTANA 7
Estimated Concept-Level
Streets Project Cost
Baxter Lane $512,054
Flanders Mill Road $836,724
Oak Street $519,741
Cottonwood Road $988,865
Durston and Cottonwood
Intersection
$87,704
Water
Baxter Lane $83,160
Oak Street $133,650
Cottonwood Road $202,973
Sewer
Baxter Lane $222,176
Cottonwood Road $394,470
Flanders Mill Road Stream and
Ditch Relocations
Stream $318,330
Waste Ditch $28,755
Total $4,328,602
Prepared by:
David J. Crawford, P.E.
TD&H Engineering
PROPOSED
"TOP"
SPORTS
COMPLEX
BAXTER LANE
DAVIS LANEREGIONAL PARK
BAXTER
MEADOWS
SUBDIVISION
CHIEF JOSEPH
SCHOOL
MEADOWLARK
SCHOOL FLANDERS MILLCOTTONWOOD RDBAXTER LANE
OAK ST
DURSTON RDDURSTON RD 27TH AVEPETRA
ACADEMY
TARGET
BOZEMAN,
MONTANAHARPER PUCKETT RDQUALITY CHECK:
DESIGNED BY:
DRAWN BY:
CAD NO.
JOB NO.
DATE:
B14-022 FIG 1 VICINITY
Engineering
tdhengineering.com
BOZEMAN "TOP" SPORTS COMPLEX
BOZEMAN, MONTANA
CONCEPT LEVEL INFRASTRUCTURE IMPROVEMENTS
VICINITY MAP
KLS
KLS
DJC
3/4/14
B14-022
FIGURE
1
VICINITY MAP
PROPOSED
"TOP"
SPORTS
COMPLEX
COTTONWOOD ROADFLANDERS MILL ROADBAXTER LANEHARPER PUCKETTOAK STREET
FLANDERS
CREEK
SUBDIVISION
BAXTER
MEADOWS
SUBDIVISION
PHASE 3A 10 ACRE
PARK
QUALITY CHECK:
DESIGNED BY:
DRAWN BY:
CAD NO.
JOB NO.
DATE:
B14-022 FIG 2 STREETS
Engineering
tdhengineering.com
BOZEMAN "TOP" SPORTS COMPLEX
BOZEMAN, MONTANA
CONCEPT LEVEL INFRASTRUCTURE IMPROVEMENTS
STREETS
KLS
KLS
DJC
3/4/14
B14-022
FIGURE
2
PROPOSED STREET IMPROVEMENTS
PROPOSED
"TOP"
SPORTS
COMPLEXCOTTONWOOD ROADFLANDERS MILL ROADBAXTER LANEHARPER PUCKETTFLANDERS
CREEK
SUBDIVISION
BAXTER
MEADOWS
SUBDIVISION
PHASE 3A 10 ACRE
PARK
QUALITY CHECK:
DESIGNED BY:
DRAWN BY:
CAD NO.
JOB NO.
DATE:
B14-022 FIG 3 WATER
Engineering
tdhengineering.com
BOZEMAN "TOP" SPORTS COMPLEX
BOZEMAN, MONTANA
CONCEPT LEVEL INFRASTRUCTURE IMPROVEMENTS
WATER AND SEWER
KLS
KLS
DJC
3/4/14
B14-022
FIGURE
3
PROPOSED WATER AND SEWER IMPROVEMENTS
PROPOSED
"TOP"
SPORTS
COMPLEXCOTTONWOOD ROADFLANDERS MILL ROADBAXTER LANEHARPER PUCKETTOAK STREET
FLANDERS
CREEK
SUBDIVISION
BAXTER
MEADOWS
SUBDIVISION
PHASE 3A 10 ACRE
PARK
QUALITY CHECK:
DESIGNED BY:
DRAWN BY:
CAD NO.
JOB NO.
DATE:
B14-022 FIG 4 STREAMS
Engineering
tdhengineering.com
BOZEMAN "TOP" SPORTS COMPLEX
BOZEMAN, MONTANA
CONCEPT LEVEL INFRASTRUCTURE IMPROVEMENTS
STREAM AND DITCH
KLS
KLS
DJC
3/4/14
B14-022
FIGURE
4
PROPOSED STREAM AND DITCH IMPROVEMENTS
TOP SPORTS COMPLEX COST ESTIMATES Itemized Estimates
BOZEMAN, MONTANA 8
4.0 APPENDIX (ITEMIZED COST ESTIMATES)
Bozeman "TOP" Sports Complex
Concept Level Infrastructure Cost Estimate 4-Mar-14
Flanders Mill Road Stream and Ditch Relocation
Quanity Unit Unit Price Total Price
Stream
Mobilization 1 LS $11,000.00 $11,000
Relocate Stream on North End Flanders Mill Road 1100 LF $200.00 $220,000
Erosion Control 1 LS $3,500.00 $3,500
Traffic Control 1 LS $1,300.00 $1,300
Construction Cost Subtotal $235,800
Construction Cost Contingency (20%)$47,160
Administration, Design and Construction Engineering (15%)$35,370
ESTIMATED TOTAL PROJECT COST $318,330
Ditch
Mobilization 1 LS $1,000.00 $1,000
Waste Ditch Relocation on South End of Property 3500 CY $5.00 $17,500
Erosion Control 1 LS $1,500.00 $1,500
Traffic Control 1 LS $1,300.00 $1,300
Construction Cost Subtotal $21,300
Construction Cost Contingency (20%)$4,260
Administration, Design and Construction Engineering (15%)$3,195
ESTIMATED TOTAL PROJECT COST $28,755
\\tdhbozfs1\JDrive\2014\B14-022 City of Bozeman Sports Complex Cost Estimates\DOCUMENTS\COST ESTIMATES\TOP Sports Complex Concept Level Cost Estimate.xls
TOP Sports Complex Concept Level Cost Estimate.xls 1 of 1 5:55 PM 3/5/2014
Bozeman "TOP" Sports Complex
Concept Level Infrastructure Cost Estimate 4-Mar-14
Water Improvements
Quanity Unit Unit Price Total Price
Baxter Lane
Mobilization 1 LS $3,500.00 $3,500
Connect to Existing Water Main 1 EA $2,500.00 $2,500
12" D.I. Pipe, Class 51 660 LF $55.00 $36,300
Gate Valve 2 EA $1,800.00 $3,600
Fire Hydrant Assembly and Piping 2 EA $5,200.00 $10,400
Fittings (Tees, Crosses, Plugs, Bends, etc.)5 EA $500.00 $2,500
Erosion Control 1 LS $1,000.00 $1,000
Traffic Control 1 LS $1,800.00 $1,800
Construction Cost Subtotal $61,600
Construction Cost Contingency (20%)$12,320
Administration, Design and Construction Engineering (15%)$9,240
ESTIMATED TOTAL PROJECT COST (WATER)$83,160
Oak Street
Mobilization 1 LS $4,500.00 $4,500
Connect to Existing Water Main 1 EA $2,500.00 $2,500
10" D.I. Pipe, Class 51 1320 LF $50.00 $66,000
Gate Valve 3 EA $1,800.00 $5,400
Fire Hydrant Assembly and Piping 3 EA $5,200.00 $15,600
Fittings (Tees, Crosses, Plugs, Bends, etc.)7 EA $500.00 $3,500
Erosion Control 1 LS $1,000.00 $1,000
Traffic Control 1 LS $500.00 $500
Construction Cost Subtotal $99,000
Construction Cost Contingency (20%)$19,800
Administration, Design and Construction Engineering (15%)$14,850
ESTIMATED TOTAL PROJECT COST (WATER)$133,650
Cottonwood Road
Mobilization 1 LS $7,000.00 $7,000
Connect to Existing Water Main 1 EA $2,500.00 $2,500
8" D.I. Pipe, Class 51 2630 LF $45.00 $118,350
Gate Valve 3 EA $1,800.00 $5,400
Fire Hydrant Assembly and Piping 2 EA $5,200.00 $10,400
Fittings (Tees, Crosses, Plugs, Bends, etc.)10 EA $500.00 $5,000
Erosion Control 1 LS $1,200.00 $1,200
Traffic Control 1 LS $500.00 $500
Construction Cost Subtotal $150,350
Construction Cost Contingency (20%)$30,070
Administration, Design and Construction Engineering (15%)$22,553
ESTIMATED TOTAL PROJECT COST (WATER)$202,973
\\tdhbozfs1\JDrive\2014\B14-022 City of Bozeman Sports Complex Cost Estimates\DOCUMENTS\COST ESTIMATES\TOP Sports Complex Concept Level Cost Estimate.xls
TOP Sports Complex Concept Level Cost Estimate.xls 1 of 1 5:56 PM 3/5/2014
Bozeman "TOP" Sports Complex
Concept Level Infrastructure Cost Estimate 4-Mar-14
Sewer Improvements
Quanity Unit Unit Price Total Price
Baxter Lane
Mobilization 1 LS $7,500.00 $7,500
Connect to Existing Sewer MH 0 EA $2,000.00 $0
27" PVC, F679 1,325 LF $95.00 $125,875
5ft. Dia., 5ft Depth Standard MH 4 EA $4,300.00 $17,200
Additional 5ft. Dia. Manhole Depth 30 VF $350.00 $10,500
Erosion Control 1 LS $1,500.00 $1,500
Traffic Control 1 LS $2,000.00 $2,000
Construction Cost Subtotal $164,575
Construction Cost Contingency (20%)$32,915
Administration, Design and Construction Engineering (15%)$24,686
ESTIMATED TOTAL PROJECT COST (SEWER)$222,176
Cottonwood Road
Mobilization 1 LS $13,500.00 $13,500
Connect to Existing Sewer MH 1 EA $2,000.00 $2,000
24" PVC, F679 2,660 LF $85.00 $226,100
5ft. Dia., 5ft Depth Standard MH 7 EA $4,300.00 $30,100
Additional 5ft. Dia. Manhole Depth 50 VF $350.00 $17,500
Erosion Control 1 LS $2,000.00 $2,000
Traffic Control 1 LS $1,000.00 $1,000
Construction Cost Subtotal $292,200
Construction Cost Contingency (20%)$58,440
Administration, Design and Construction Engineering (15%)$43,830
ESTIMATED TOTAL PROJECT COST (SEWER)$394,470
\\tdhbozfs1\JDrive\2014\B14-022 City of Bozeman Sports Complex Cost Estimates\DOCUMENTS\COST ESTIMATES\TOP Sports Complex Concept Level Cost Estimate.xls
TOP Sports Complex Concept Level Cost Estimate.xls 1 of 1 5:57 PM 3/5/2014
Bozeman "TOP" Sports Complex
Concept Level Infrastructure Cost Estimate 4-Mar-14
Street and Drainage Improvements
Quanity Unit Unit Price Total Price
Baxter Lane
Mobilization 1 LS $18,000.00 $18,000
Curb and gutter 1320 LF $15.00 $19,800
Asphalt 1237 TN $72.00 $89,056
Excavation and Embankment 4107 CY $6.00 $24,640
Uncrushed Subbase Gravel 1980 CY $18.00 $35,640
Crushed Base Gravel 660 CY $22.00 $14,520
Geotextile 3960 SY $2.00 $7,920
Concrete Sidewalk 147 CY $290.00 $42,533
Pedestrian Ramps 4 EA $3,000.00 $12,000
Detention Ponds 1 EA $5,000.00 $5,000
Storm Drain Piping 920 LF $32.00 $29,440
Storm Drain Inlets and Manholes 2 EA $2,500.00 $5,750
Street/Stop Signs 0 EA $800.00 $0
Street Lights 6 EA $9,000.00 $54,000
Topsoil and Seeding 1 LS $2,500.00 $2,500
Epoxy Striping 1 LS $13,000.00 $13,000
Erosion Control 1 LS $2,500.00 $2,500
Traffic Control 1 LS $3,000.00 $3,000
Construction Cost Subtotal $379,299
Construction Cost Contingency (20%)$75,860
Administration, Design and Construction Engineering (15%)$56,895
ESTIMATED TOTAL PROJECT COST (STREET AND DRAINAGE)$512,054
Flanders Mill Road
Mobilization 1 LS $27,000.00 $27,000
Curb and gutter 5260 LF $15.00 $78,900
Asphalt 1447 TN $72.00 $104,148
Excavation and Embankment 9936 CY $6.00 $59,613
Uncrushed Subbase Gravel 4749 CY $18.00 $85,475
Crushed Base Gravel 1583 CY $22.00 $34,823
Geotextile 9497 SY $2.00 $18,994
Concrete Sidewalk 292 CY $290.00 $84,744
Pedestrian Ramps 4 EA $3,000.00 $12,000
Detention Ponds 1 EA $5,000.00 $5,000
Storm Drain Piping 2230 LF $32.00 $71,360
Storm Drain Inlets and Manholes 6 EA $2,500.00 $13,938
Street/Stop Signs 1 EA $800.00 $800
Street Lights 0 EA $9,000.00 $0
Topsoil and Seeding 1 LS $5,000.00 $5,000
Striping 1 LS $10,000.00 $10,000
Erosion Control 1 LS $5,000.00 $5,000
Traffic Control 1 LS $3,000.00 $3,000
Construction Cost Subtotal $619,796
Construction Cost Contingency (20%)$123,959
Administration, Design and Construction Engineering (15%)$92,969
ESTIMATED TOTAL PROJECT COST (STREET AND DRAINAGE)$836,724
Oak Street
Mobilization 1 LS $18,000.00 $18,000
Curb and gutter 2640 LF $15.00 $39,600
Asphalt 753 TN $72.00 $54,208
Excavation and Embankment 5133 CY $6.00 $30,800
Uncrushed Subbase Gravel 2457 CY $18.00 $44,220
Crushed Base Gravel 819 CY $22.00 $18,016
Geotextile 4913 SY $2.00 $9,827
Concrete Sidewalk 147 CY $290.00 $42,533
Pedestrian Ramps 4 EA $3,000.00 $12,000
Detention Ponds 1 EA $5,000.00 $5,000
Storm Drain Piping 920 LF $32.00 $29,440
Storm Drain Inlets and Manholes 2 EA $2,500.00 $5,750
Street/Stop Signs 2 EA $800.00 $1,600
Street Lights 6 EA $9,000.00 $54,000
Topsoil and Seeding 1 LS $2,500.00 $2,500
Epoxy Striping 1 LS $13,000.00 $13,000
Erosion Control 1 LS $2,500.00 $2,500
Traffic Control 1 LS $2,000.00 $2,000
Construction Cost Subtotal $384,994
Construction Cost Contingency (20%)$76,999
Administration, Design and Construction Engineering (15%)$57,749
ESTIMATED TOTAL PROJECT COST (STREET AND DRAINAGE)$519,741
\\tdhbozfs1\JDrive\2014\B14-022 City of Bozeman Sports Complex Cost Estimates\DOCUMENTS\COST ESTIMATES\TOP Sports Complex Concept Level Cost Estimate.xls
TOP Sports Complex Concept Level Cost Estimate.xls 1 of 2 6:12 PM 3/5/2014
Bozeman "TOP" Sports Complex
Concept Level Infrastructure Cost Estimate 4-Mar-14
Street and Drainage Improvements
Cottonwood Road
Mobilization 1 LS $33,000.00 $33,000
Curb and gutter 5260 LF $15.00 $78,900
Asphalt 1500 TN $72.00 $108,005
Excavation and Embankment 10228 CY $6.00 $61,367
Uncrushed Subbase Gravel 4895 CY $18.00 $88,105
Crushed Base Gravel 1632 CY $22.00 $35,895
Geotextile 9789 SY $2.00 $19,579
Concrete Sidewalk 292 CY $290.00 $84,744
Pedestrian Ramps 4 EA $3,000.00 $12,000
Detention Ponds 1 EA $5,000.00 $5,000
Storm Drain Piping 2230 LF $32.00 $71,360
Storm Drain Inlets and Manholes 6 EA $2,500.00 $13,938
Street/Stop Signs 2 EA $800.00 $1,600
Street Lights 9 EA $9,000.00 $81,000
Topsoil and Seeding 1 LS $5,000.00 $5,000
Epoxy Striping 1 LS $26,000.00 $26,000
Erosion Control 1 LS $5,000.00 $5,000
Traffic Control 1 LS $2,000.00 $2,000
Construction Cost Subtotal $732,492
Construction Cost Contingency (20%)$146,498
Administration, Design and Construction Engineering (15%)$109,874
ESTIMATED TOTAL PROJECT COST (STREET AND DRAINAGE)$988,865
Durston and Cottonwood Intersection
Mobilization 1 LS $3,000.00 $3,000
Curb and gutter 200 LF $15.00 $3,000
Asphalt 57 TN $72.00 $4,107
Excavation and Embankment 741 CY $6.00 $4,444
Uncrushed Subbase Gravel 178 CY $18.00 $3,200
Crushed Base Gravel 59 CY $22.00 $1,304
Geotextile 356 SY $2.00 $711
Concrete Sidewalk 0 CY $290.00 $0
Pedestrian Ramps 0 EA $3,000.00 $0
Detention Ponds 0 EA $5,000.00 $0
Storm Drain Piping 0 LF $32.00 $0
Storm Drain Inlets and Manholes 2 EA $2,500.00 $5,000
Street/Stop Signs 4 EA $800.00 $3,200
Street Lights 2 EA $9,000.00 $18,000
Topsoil and Seeding 1 LS $1,000.00 $1,000
Epoxy Striping 1 LS $10,000.00 $10,000
Erosion Control 1 LS $3,000.00 $3,000
Traffic Control 1 LS $5,000.00 $5,000
Construction Cost Subtotal $64,966
Construction Cost Contingency (20%)$12,993
Administration, Design and Construction Engineering (15%)$9,745
ESTIMATED TOTAL PROJECT COST (STREET AND DRAINAGE)$87,704
\\tdhbozfs1\JDrive\2014\B14-022 City of Bozeman Sports Complex Cost Estimates\DOCUMENTS\COST ESTIMATES\TOP Sports Complex Concept Level Cost Estimate.xls
TOP Sports Complex Concept Level Cost Estimate.xls 2 of 2 6:12 PM 3/5/2014
Bozeman "TOP" Sports Complex
Concept Level Infrastructure Cost Estimate 4-Mar-14
Street Data
Cottonwood and
Durston
Item Baxter Cottonwood Oak Flanders Mill Intersection
Excavation Width (ft)28 35 35 34 20
Excavation Depth (ft)3 3 3 3 5
Gravel Width (ft)27 33.5 33.5 32.5 16
Pit Run Thickness (in)18 18 18 18 18
Crushed Gravel Thickness (in)6 6 6 6 6
Asphalt Width (ft)23 28 28 27 14
Asphalt Depth (in)6 3 3 3 3
Sidewalk Width (ft)6 6 6 6
Sidewalk Thickness (in)6 6 6 6
Road Length (ft)1320 2630 1320 2630 200
Curb and Gutter Length (ft)1320 5260 2640 5260 200
Asphaltic Concrete (Ton)1237 1500 753 1447 57
Sidewalk Volume (CY)147 292 147 292
Stop/Street Signs 1 1 1 1 4
Inlets and Manholes 2 6 2 6 2
Geotextile (SY)3960 9789 4913 9497 356
Storm Piping (LF)920 2230 920 2230 0
Pit Run Volume (CY)1980 4895 2457 4749 178
Crushed Gravel Volume (CY)660 1632 819 1583 59
Excavation and Embankment (CY)4107 10228 5133 9936 741
Bozeman "TOP" Sports Complex
Concept Level Infrastructure Cost Estimate 4-Mar-14
Street and Drainage Improvements
Cottonwood Road
Mobilization 1 LS $33,000.00 $33,000
Curb and gutter 5260 LF $15.00 $78,900
Asphalt 1500 TN $72.00 $108,005
Excavation and Embankment 10228 CY $6.00 $61,367
Uncrushed Subbase Gravel 4895 CY $18.00 $88,105
Crushed Base Gravel 1632 CY $22.00 $35,895
Geotextile 9789 SY $2.00 $19,579
Concrete Sidewalk 292 CY $290.00 $84,744
Pedestrian Ramps 4 EA $3,000.00 $12,000
Detention Ponds 1 EA $5,000.00 $5,000
Storm Drain Piping 2230 LF $32.00 $71,360
Storm Drain Inlets and Manholes 6 EA $2,500.00 $13,938
Street/Stop Signs 2 EA $800.00 $1,600
Street Lights 9 EA $9,000.00 $81,000
Topsoil and Seeding 1 LS $5,000.00 $5,000
Epoxy Striping 1 LS $26,000.00 $26,000
Erosion Control 1 LS $5,000.00 $5,000
Traffic Control 1 LS $2,000.00 $2,000
Construction Cost Subtotal $732,492
Construction Cost Contingency (20%)$146,498
Administration, Design and Construction Engineering (15%)$109,874
ESTIMATED TOTAL PROJECT COST (STREET AND DRAINAGE)$988,865
Durston and Cottonwood Intersection
Mobilization 1 LS $3,000.00 $3,000
Curb and gutter 200 LF $15.00 $3,000
Asphalt 57 TN $72.00 $4,107
Excavation and Embankment 741 CY $6.00 $4,444
Uncrushed Subbase Gravel 178 CY $18.00 $3,200
Crushed Base Gravel 59 CY $22.00 $1,304
Geotextile 356 SY $2.00 $711
Concrete Sidewalk 0 CY $290.00 $0
Pedestrian Ramps 0 EA $3,000.00 $0
Detention Ponds 0 EA $5,000.00 $0
Storm Drain Piping 0 LF $32.00 $0
Storm Drain Inlets and Manholes 2 EA $2,500.00 $5,000
Street/Stop Signs 4 EA $800.00 $3,200
Street Lights 2 EA $9,000.00 $18,000
Topsoil and Seeding 1 LS $1,000.00 $1,000
Epoxy Striping 1 LS $10,000.00 $10,000
Erosion Control 1 LS $3,000.00 $3,000
Traffic Control 1 LS $5,000.00 $5,000
Construction Cost Subtotal $64,966
Construction Cost Contingency (20%)$12,993
Administration, Design and Construction Engineering (15%)$9,745
ESTIMATED TOTAL PROJECT COST (STREET AND DRAINAGE)$87,704