HomeMy WebLinkAboutStory Mill Park Proposed BudgetQuantity Unit Unit Cost Item Cost
City of
Bozeman
Trust for
Public Land
SITE CONSTRUCTION
Site Preparation
Grading and site preparation 350,000 Ea 0.65 227,500 227,500 ‐
Site Demolition 350,000 Ea 0.25 87,500 87,500 ‐
8" Water & Sewer Utilities 1 Ea 107,500 107,500 107,500 ‐
Structure Demolition 1 Ea 160,000 160,000 80,000 80,000
Subtotal 582,500$ 502,500 80,000
Hardscape & Walkways
Concrete walkways 10,000 Sq Ft 6.00 60,000 60,000 ‐
Parking area 90,000 Sq Ft 5.00 450,000 450,000 ‐
Drainage infrastructure 200,000 Sq Ft 1.50 300,000 300,000 ‐
DG walkway 6,500 Linear Ft 6.00 39,000 39,000 ‐
Multi‐use path 2,500 Linear Ft 10.00 25,000 25,000 ‐
Boardwalks 500 Linear Ft 300.00 150,000 150,000 ‐
Subtotal 1,024,000$ 1,024,000 ‐
Landscape
Weed Management Plan 1 Ea 7,405 7,405 ‐ 7,405
Landscape plants and mulch 200,000 Sq Ft 3.00 600,000 ‐ 600,000
Grand lawn 80,000 Sq Ft 0.60 48,000 ‐ 48,000
Reclamation Seeding 100,000 Sq Ft 0.15 15,000 ‐ 15,000
Stream Access Point 1 Ea 15,000 15,000 ‐ 15,000
Boulder placement 50 Ea 400.00 20,000 ‐ 20,000
Irrigation 280,000 Sq Ft 1.00 280,000 ‐ 280,000
Irrigation Wells 10,000 Ea 2.00 20,000 ‐ 20,000
Subtotal 1,005,405$ ‐ 1,005,405
Playground & Sports Field
Playground 1 Ea 400,000 400,000 ‐ 400,000
Sports Fields 100,000 SF 2.50 250,000 ‐ 250,000
Subtotal 650,000$ ‐ 650,000
Other Site Construction
Pedestrian Bridge (Free Span)80 Linear Ft 1,500 120,000 ‐ 120,000
Site Lighting (Dark Sky Friendly)1 Ea 150,000 150,000 ‐ 150,000
Subtotal 270,000$ ‐ 270,000
Site Amenities
Restroom 1 Ea 50,000 50,000 ‐ 50,000
Trash can 10 Ea 2,000 20,000 ‐ 20,000
Benches 15 Ea 2,000 30,000 ‐ 30,000
Off‐leash Dog play area 43,560 Sq Ft 1.50 65,340 ‐ 65,340
Demonstration Gardens 1 Ea 27,000 27,000 ‐ 27,000
Picnic shelters with tables 3 Ea 40,000 120,000 ‐ 120,000
Bike rack 2 Ea 750 1,500 ‐ 1,500
Park monument signs 1 Ea 11,000 11,000 11,000 ‐
Park information signs 5 Ea 1,500 7,500 7,500 ‐
Decorative park fence 100 Linear Ft 250 25,000 ‐ 25,000
Subtotal 357,340$ 18,500 338,840
Contingency (20%)777,000$ 305,000 472,000
SITE CONSTRUCTION SUBTOTAL 4,666,245$ 1,850,000 2,816,245
PLANNING, ADMINISTRATION & STEWARDSHIP
Master Planning, Engineering, and Park Design 450,000 ‐ 450,000
Construction Administration 234,000 ‐ 234,000
Park Stewardship Fund 200,000 ‐ 200,000
PLANNING, ADMIN & STEWARDSHIP SUBTOTAL 884,000$ ‐ 884,000
TOTAL 5,550,245$ 1,850,000 3,700,245
*This is an estimate based on currently available information. A detailed design has not yet been produced and the project has not yet gone out to
bid. As such, the allocations provided above between the City of Bozeman and The Trust for Public Land are for illustrative purposes only.
THE TRUST FOR PUBLIC LAND
Story Mill Community Park Project Budget
Conceptual Park Design and Construction Estimate*