HomeMy WebLinkAbout12-9-13 Water Fund.pdf
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Chris Kukulski, City Manager
Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Water Fund Capital Improvement Plan (CIP) for
FY15-19.
AGENDA ITEM TYPE: Action
MEETING DATE: December 9, 2013
RECOMMENDATION: Adopt of the Water Fund Capital Improvement Plan (CIP) for
FY15-19.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. Staff met in October
and November to develop the attached draft schedules.
The Water Fund CIP tracks the capital equipment replacements and construction projects for
Water Operations (distribution system) and the Water Treatment Plant.
Items of Note:
• W33 – Water Supply Capital Improvements, $50,000,000 was added to the plan,
unscheduled, to indicate the needs that have been outline in the Integrated Water
Resource Plan (IWRP). It also appears in the Water Impact Fee schedule.
Determinations need to be made on how much of this will rely on the Utility and how
much on the Impact Fee program.
141
• WIF03 – 5.3MG Concrete Water Storage Reservoir is an Impact Fee project that will
likely need, at a minimum, the Water Fund to guarantee the loan necessary for the
project. It is included on the Water Impact Fee schedule.
• W32 – Sourdough Bypass pipe lining has been added to the schedule as a newly effective
solution to our maintenance and repair issues with this critical pipe.
These levels of capital expenditure are in line with our adopted rate models, however current
Water Rates (and Water Impact Fees) only include a relatively small amount for Water Supply
related issues ($200,000/yr for purchase of Water Rights.)
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY15.
Report compiled on: November 27, 2013
Attached: Water Fund CIP
142
Water FundCapital Improvement PlanFinancial Summary Current YearFY14 FY15 FY16 FY17 FY18 FY19UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 2,418,979$ 2,754,716$ 1,934,557$ 2,413,160$ 2,777,478$ 3,012,993$ ‐$ Plus: Water Revenues Dedicated to CIP 1,392,402$ 1,455,061$ 1,520,538$ 1,588,962$ 1,660,466$ 1,726,884$ ‐$ Less: Scheduled CIP Project Costs (1,056,665)$ (2,275,220)$ (1,041,935)$ (1,224,645)$ (1,424,950)$ (861,000)$ (50,000,000)$ Projected Year‐End Cash Dedicated to CIP 2,754,716$ 1,934,557$ 2,413,160$ 2,777,478$ 3,012,993$ 3,878,878$ (50,000,000)$ Assumptions Made for Revenue Estimates: Current YearFY14 FY15 FY16 FY17 FY18 FY19Estimated Annual Water Revenues 6,962,012$ 6,962,012$ 7,275,303$ 7,602,691$ 7,944,812$ 8,302,329$ Estimated Annual Increase 0.0% 4.5% 4.5% 4.5% 4.5% 4.0%Total Estimated Revenues 6,962,012$ 7,275,303$ 7,602,691$ 7,944,812$ 8,302,329$ 8,634,422$ Current Revenues Dedicated to CIP % 20.0% 20.0% 20.0% 20.0% 20.0% 20.0% Plus: Increase Dedicated to CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 20.0% 20.0% 20.0% 20.0% 20.0% 20.0%TtlEti tdRDdi tdtCIP1 392 402$1 455 061$1 520 538$1 588 962$1 660 466$1 726 884$ProjectedProjectedTotal Estimated Revenues Dedicated to CIP1,392,402$ 1,455,061$ 1,520,538$ 1,588,962$ 1,660,466$ 1,726,884$ 50,000,00045,000,00040,000,00035,000,00030,000,00025,000,00020,000,00015,000,00010,000,0005,000,0000Water Fund Projects & Equipment 143
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY15FY17FY18FY19Water FundW33PUBLIC WORKSWATER SUPPLY CAPITAL IMPROVEMENTS$50,000,000W34PUBLIC WORKSWATER COST OF SERVICE AND RATE STUDY$50,000WIF03WATER IF5.3MG CONCRETE WATER STORAGE RESERVOIRPW01WATER OPSSHOPS FACILITY EXPANSION PLAN$10,000W03WATER OPSENGINEERING/DESIGN FOR ANNUAL WATER PIPE REPLACEMENT PROGRAM$22,500$22,500$22,500$22,500$22,500W04‐15WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2015$1,147,720W04‐16WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2016$969,435W04‐17WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2017$1,097,145W04‐18WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2018$952,450W04‐19WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2019$838,500W28WATER OPSCL‐12 WATER TAP MACHINE$20,000W29WATER OPSLEAK CORRELATOR$45,000W32WATER OPSLINE 18" PIPE FROM PLANT TO SOURDOUGH BYPASS$1,000,000W25WATER PLANTREPLACEMENT VEHICLE$45,000W30WATER PLANTGAUGING STATIONS$40,000W31WATER PLANTSOURDOUGH TANK REPAIR$50,000$450,000144
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY15FY17FY18FY19Summary for Water Fund (16 items)Totals by year:$2,275,220 $1,041,935 $1,224,645$50,000,000FY15FY16FY17UnscheduledFY19$861,000$1,424,950FY18145
CIP Project Fund
Water Fund
PROJECT NUMBER
PW01
DEPARTMENT
WATER OPS
PROJECT NAME
SHOPS FACILITY EXPANSION PLAN
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
The construction of the new Vehicle Maintenance Shop at the Lower Yards on Rouse Avenue in FY10/FY11 was Phase I in
expanding and improving our ability to service equipment, store vehicles, and provide work space for Public Works, Parks, and
Facilitiy services. Questions remain about the long-term plan for construction, location, and expansion for: Streets, Sign & Signal,
Forestry, Water/Sewer Operations, Solid Waste Collection & Recycling, Facilities, and Parks & Cemetery departments. This
project would develop a master plan. In scheduling this project, we are recommending waiting until after the Vehicle Maintenance
Division is relocated to its new shop and the interior improvements are made to the Shop at Rouse and Tamarack Street for the
remaining divisions.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
From related divisions: General Fund 20% ($10,000), Water Fund 20% ($10,000), Wastewater Fund 20% ($10,000), Street
Maintenance Fund 20% ($10,000), Solid Waste Fund 20% ($10,000).
New
Replacement
Equipment
Project
FY17
$10,000
FY18 FY19
146
CIP Project Fund
Water Fund
PROJECT NUMBER
W03
DEPARTMENT
WATER OPS
PROJECT NAME
ENGINEERING/DESIGN for ANNUAL WATER PIPE REPLACEMENT PROGRAM
FY15
$22,500
FY16
$22,500
Unscheduled
DESCRIPTION OF PROJECT
This item provides for design work to be completed every year, in anticipation of the Annual System Upgrades. As the Water
Operations Division operates the existing system, maintenance projects become apparent. Given our knowledge of system
conditions today, the following projects are candidates for design funding and were identified in the Facility Plan: 1. Koch: Lindley
to Bozeman, 2. Lindley: Olive to Koch, 3. S. Bozeman: Olive to Story As annual operations occur, other more-urgent projects may
be identified and designed under this project heading.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the design of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17
$22,500
FY18
$22,500
FY19
$22,500
147
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-15
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2015
FY15
$1,147,720
FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S. Grand Ave: W. Garfield St - W. College St S. Grand Ave: W College St - W. Main St. N. Rouse Ave: Bond -
Griffin (needs to be completed prior to MDOT Rouse project.) The timing of this project is critical to our need to mill-overlay S.
Grand Ave. After budget approval July 1, 2014, these projects would complete design, bid and begin construction in the
Spring/Summer of 2015, at the end of FY15.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
148
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-16
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2016
FY15 FY16
$969,435
Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S. Tracy Ave: W. Garfield St - E. Story St N. Willson Ave: W. Lamme St - W. Short St W. Babcock St: S. 10th
Ave - S. 8th Ave N. Montana Ave: E. Tamarack St - N End of Existing. After budget approval July 1, 2015, this project would
complete design, bid and begin construction in the Spring/Summer of 2016, at the end of FY16.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
149
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-17
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2017
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: W Olive St: S. 5th Ave - S. 3rd Ave W. Olive St: S. 6th Ave - S. 5th Ave N. Grand Ave: W. Lamme St - W. Peach
St N. 5th Ave: W. Aspen St - W. Tamarack St S. 3rd Ave: W. Harrison Ave - W. Curtiss St. After budget approval July 1, 2016,
this project would complete design, bid and begin construction in the Spring/Summer of 2017, at the end of FY17.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17
$1,097,145
FY18 FY19
150
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-18
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2018
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S 6th Ave: W. Harrison Ave- W Olive S: W. Koch St: S Grand Ave.- S. Willson Ave: S. Willson Ave.: W. College
St- W. Koch St. After budget approval July 1, 2017, this project would complete design, bid and begin construction in the
Spring/Summer of 2018, at the end of FY18.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
$952,450
FY19
151
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-19
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2019
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S 7th Ave: W. Harrison Ave-W. Story St: W. Harrison Ave: S.8th Ave- S 7th Ave : W. Harrison Ave. S. 5th
Ave.- S. 4th Ave: W. Harrison Ave. : S. 4th Ave. _ S. 3rd Ave.: S.5th Ave: W. Garfield St- W. College St. After budget approval July
1, 2018, this project would complete design, bid and begin construction in the Spring/Summer of 2019, at the end of FY18.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
$838,500
152
CIP Project Fund
Water Fund
PROJECT NUMBER
W25
DEPARTMENT
WATER PLANT
PROJECT NAME
Replacement Vehicle
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
Replacement 4-wheel Drive ½ Ton pick-up, replaces 1997 ¾ ton pick-up that currently has 99,400 miles
ALTERNATIVES CONSIDERED
Keep existing unit in service
ADVANTAGES OF APPROVAL
More reliable, more fuel efficient vehicle
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
none
FUNDING SOURCES
Water Rates
New
Replacement
Equipment
Project
FY17
$45,000
FY18 FY19
153
CIP Project Fund
Water Fund
PROJECT NUMBER
W28
DEPARTMENT
Water Ops
PROJECT NAME
CL-12 Water Tap machine
FY15
$20,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
This machine enables us to make water taps on water mains ranging in size from 4” to 12” in diameter.
ALTERNATIVES CONSIDERED
Have a contractor contract with a contract vendor to do these taps. Currently we do all live taps.
ADVANTAGES OF APPROVAL
This machine is over 40 years old and has been refurbished apox. 7 years ago. It has made hundreds of taps and recently has
shown signs of failure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Fund. We do charge contractors for this service and expect a 5 to 7 years payback depending on growth.
New
Replacement
Equipment
Project
FY17 FY18 FY19
154
CIP Project Fund
Water Fund
PROJECT NUMBER
W29
DEPARTMENT
Water Ops
PROJECT NAME
Leak Correlator
FY15
$45,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
This correlator would replace the current one that is 7 years old and showing signs of aging. This piece of equipment has proven
to be highly successful in finding leaks and is and will be instrumental in our water conservation program.
ALTERNATIVES CONSIDERED
To continue to use the old unit that has increasing down time due to repairs. Subcontract the leak detection out at a cost of
$1,000.00 a day.
ADVANTAGES OF APPROVAL
To have a unit that will be more reliable than our current unit.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
155
CIP Project Fund
Water Fund
PROJECT NUMBER
W30
DEPARTMENT
WATER PLANT
PROJECT NAME
Gauging Stations
FY15
$40,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Per the adopted Integrated Water Resources Plan recommendation, install a new stream gauge on Sourdough Creek and replace
existing gauging equipment on Lyman Creek. A suitable location stream gauge location must be identified for Sourdough Creek
above the City’s intake diversion and a monitoring protocol developed. An existing gauge site exists on Lyman Creek but the
equipment to operate the gauge is no longer functional and must be replaced.
ALTERNATIVES CONSIDERED
Do not install stream gauges.
ADVANTAGES OF APPROVAL
Provides monitoring data on all of City’s water sources. Data is important to monitor drought conditions and seasonal variability
in supply as well as facilitate future updates to reliable yield hydrology.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs. Gauge monitoring to become standard operating procedure for water treatment plant personnel.
FUNDING SOURCES
Water Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
156
CIP Project Fund
Water Fund
PROJECT NUMBER
W31
DEPARTMENT
WATER PLANT
PROJECT NAME
Sourdough Tank Repair
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
The Sourdough Tank leaks. It has a large crack, the dome is deteriorating. The drain and overflow pipes need replacement.
ALTERNATIVES CONSIDERED
Do nothing or build a new tank.
ADVANTAGES OF APPROVAL
Repairing the tank will extend the life of the tank and stop the wasting of water from the leak.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Water Fund
New
Replacement
Equipment
Project
FY17
$50,000
FY18
$450,000
FY19
157
CIP Project Fund
Water Fund
PROJECT NUMBER
W32
DEPARTMENT
WATER OPS
PROJECT NAME
Line 18" Pipe from Plant to Sourdough Bypass
FY15
$1,000,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
This project would use a lining procedure to treat the water supply pipe that comes from the Water Treatment Plant into town.
There is difficulty repairing this critical pipe.
ALTERNATIVES CONSIDERED
Leave as is. Pursue other full replacement methods for the aging pipe.
ADVANTAGES OF APPROVAL
This is viewed as one of the lowest cost options to significantly manage the risks of pipe failure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
Water Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
158
CIP Project Fund
Water Fund
PROJECT NUMBER
W33
DEPARTMENT
PUBLIC WORKS
PROJECT NAME
WATER SUPPLY CAPITAL IMPROVEMENTS
FY15 FY16 Unscheduled
$50,000,000
DESCRIPTION OF PROJECT
The Integrated Water Resource Plan (IWRP) calls out the long term need to fund capital improvements related to the City's
water supply. The current rough estimate of cost totals $50 million. While these costs will be impact fee eligible, we are
uncertain how much to add the the Water Impact Fee CIP, as the current Impact Fee was adopted without a calculation for water
supply costs. Actual costs will depend on community growth, conservation success and results of engineering analysis conducted
as part of the water master plan update.
ALTERNATIVES CONSIDERED
The IWRP considers many alternatives for water supply.
ADVANTAGES OF APPROVAL
Improving our water supply capital will allow the City to grow into the future, with adequate water for citizens, businesses, and
visitors.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Until the chosen alternative is known, operating costs can not be determined.
FUNDING SOURCES
Water Fund, including Cash In Lieu of Water; Water Impact Fees
New
Replacement
Equipment
Project
FY17 FY18 FY19
159
CIP Project Fund
Water Fund
PROJECT NUMBER
W34
DEPARTMENT
PUBLIC WORKS
PROJECT NAME
WATER COST OF SERVICE AND RATE STUDY
FY15 FY16
$50,000
Unscheduled
DESCRIPTION OF PROJECT
The Implementation plan for the Integrated Water Resource Plan (IWRP) calls for an updated cost of service and rate study. This
is also a best practice for Utility management, especially after a significant system upgrade, such as the Water Treatment Plant
project. We expect the plan to also offer options for further water conservation pricing programs.
ALTERNATIVES CONSIDERED
Keep the existing rate structure and limited conservation pricing (currently, residential only, inclined block rates)
ADVANTAGES OF APPROVAL
Our user charges will better match the actual cost of service. Hopefully, we will be able to further incentivize water conservation.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
Water Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
160
CIP Project Fund
Water Fund
PROJECT NUMBER
WIF03
DEPARTMENT
WATER IF
PROJECT NAME
5.3MG CONCRETE WATER STORAGE RESERVOIR
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
THIS PROJECT IS PRIMARILY AN IMPACT FEE ELIGIBLE PROJECT. How much of the project costs will be borne by the Utility
is uncertain at this point in time. According to the 2007 Water Facility Plan, a new 5.3MG partially buried concrete water storage
reservoir was to be constructed by 2017. Given the recent slow-down in growth, we anticipate needing the tank some time after
2017. The proposed location of the reservoir is on City property adjacent (to the North) of the proposed new
Hyalite/Sourdough water treatment plant. This reservoir is sized to meet the City’s storage needs up to 2025, assuming a 5%
annual growth rate. Locating the storage reservoir at the recommended site will raise the hydraulic grade line in the City’s water
system, which will increase pressure for the southern part of the City and will allow future development to occur in the south on
a gravity system.
ALTERNATIVES CONSIDERED
The water facility plan reviewed numerous options. This is the preferred alternative of the adopted plan.
ADVANTAGES OF APPROVAL
Increased water storage to meet the needs of our growth community, and the requirement of MDEQ. Increased system water
pressure in the southern part of the City.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Requires minimal operation and maintenance. Checking of valves, level sensors and vents on an annual basis and diver inspection
and vacuuming every five years. Estimated at $4,000 annually.
FUNDING SOURCES
100% Water Impact Fees. Some of this project could potentially be funded with Utility dollars, or a loan for the project
underwritten by the Utility.
New
Replacement
Equipment
Project
FY17 FY18 FY19
161