Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Chris Kukulski, City Manager
Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Wastewater Fund Capital Improvement Plan (CIP) for
FY15-19.
AGENDA ITEM TYPE: Action
MEETING DATE: December 9, 2013
RECOMMENDATION: Adopt the Wastewater Fund Capital Improvement Plan (CIP)
for FY15-19.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. Staff met in October
and November to develop the attached draft schedules.
The Wastewater Fund CIP tracks the capital equipment replacements and construction projects
for Wastewater Operations (collection system) and the Water Reclamation Facility (WRF).
Items of Note:
• WWIF15 - Flanders Mill – Hidden Valley Trunk Main and Lift Station is included on the
Utility schedule, with no cost for the Utility shown. Total project cost on the Impact Fee CIP
is $13,500,000. This is an impact fee project that will likely need underwriting support from
the Utility. We are uncertain if there are project costs that would need to be paid for by the
109
Utility; ie. Non-capacity expanding project costs. These details will be firmed up once
design of the main and lift station are completed.
• WW29 – Energy Recovery (Methane Co-Generation) Project, has been moved back on the
schedule. It is believed that the project will yield operational savings after a relatively short
pay-back period, but we don’t have any engineering estimates substantiating that at this
point. In the schedule, we won’t have enough cash to pay for construction without
borrowing. At the point we are ready to move forward, a more detailed financing proposal,
including estimated energy savings, will be brought forward.
These levels of capital expenditure are in line with our adopted rate models. However, our
current rate models do not include paying costs or underwriting coverage for the WWIF15 -
Flanders Mill – Hidden Valley Trunk Main and Lift Station project. We will need to track on
these items as we move forward with rates in the coming years.
UNRESOLVED ISSUES: Estimated costs for WW44 – Modify Flotation Thickeners are not
available at this point. We anticipate having those ready for Budget Preparation in January.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY15.
Report compiled on: November 27, 2013
Attached: Draft Wastewater Fund CIP
110
Wastewater Fund Capital Improvement PlanFinancial SummaryCurrent YearFY14FY15FY16 FY17 FY18 FY19UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 1,899,728$ 2,024,582$ 1,750,941$ 1,846,106$ 1,942,462$ 2,295,579$ ‐$ Plus: Wastewater Revenues Dedicated to CIP1,278,504$ 1,316,859$ 1,356,365$ 1,397,056$ 1,438,967$ 1,482,137$ ‐$ Less: Scheduled CIP Project Costs(1,153,650)$ (1,590,500)$ (1,261,200)$ (1,300,700)$ (1,085,850)$ (1,810,050)$ (8,000,000)$ Projected Year‐End Cash Dedicated to CIP2,024,582$ 1,750,941$ 1,846,106$ 1,942,462$ 2,295,579$ 1,967,666$ (8,000,000)$ Assumptions Made for Revenue Estimates:Current YearFY14FY15FY16FY17 FY18 FY19Estimated Annual Wastewater Revenues6,206,330$ 6,392,520$ 6,584,295$ 6,781,824$ 6,985,279$ 7,194,837$ Estimated Annual Increase3.0%3%3%3%3%3%Total Estimated Revenues6,392,520$ 6,584,295$ 6,781,824$ 6,985,279$ 7,194,837$ 7,410,683$ Current Revenues Dedicated to CIP %20.0%20.0% 20.0% 20.0% 20.0% 20.0% Plus: Increase Dedicated to CIP0.0%0.0%0.0%0.0% 0.0%0.0% Total % Dedicated to CIP20.0%20.0% 20.0% 20.0% 20.0% 20.0%TtlEti tdRDdi tdt CIP1 278 504$1 316 859$1 356 365$1 397 056$1 438 967$1 482 137$ProjectedProjectedTotal Estimated Revenues Dedicated to CIP1,278,504$ 1,316,859$ 1,356,365$ 1,397,056$ 1,438,967$ 1,482,137$ 9,000,0008,000,0007,000,0006,000,0005,000,0004,000,0003,000,0002,000,0001,000,0000Wastewater Fund Projects & Equipment 111
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY15FY17FY18FY19Wastewater FundWW35PUBLIC WORKSGRANITE XP UPGRADE$18,000WW36PUBLIC WORKSWEB MAPPING SYSTEM INTEGRATION$45,000WW27WRF PLANTWATERSHED STUDY AND STREAM MODELING$60,000$60,000$60,000$60,000$60,000WW28WRF PLANTDESIGN PHASE II ‐ WRF PLANT IMPROVEMENTS$5,230,000WW29WRF PLANTENERGY RECOVERY (METHANE CO‐GENERATION) PROJECT$2,200,000$350,000WW33WRF PLANTINSTALL SECOND SCREW PRESS AND ENCLOSURE$220,000WW35WRF PLANTREPLACE COMMERCIAL MOWER$13,000WW36WRF PLANTUPGRADE TRUCK BARN$36,000WW37WRF PLANTUPGRADE OLD PLC'S AND FIRMWARE$29,000WW38WRF PLANT#3 PERFORATED SCREEN & WASHER COMPACTOR$140,000WW39WRF PLANTSANDLAST & PAINT OLD CLARIFIER DRIVES, BEACHES, BAFFLES & WEIRS (6 TOTAL)$15,000$15,000$15,000WW40WRF PLANTUV BUILDING SHADING MATERIAL$15,000WW41WRF PLANTREPLACE 4" DUCTILE PIPE THROUGH DEWATERING BASEMENT WITH GLASS LINED PIPE$15,000WW42WRF PLANTPRIMARY CLARIFIER COVERS$350,000$350,000$350,000WW43WRF PLANTSEAL MIXER FLANGES ON DIGESTER 1$20,000WW44WRF PLANTMODIFY FLOTATION THICKENERWW45WRF PLANTFINAL CLARIFIER LAUNDER COVERS$40,000$40,000$40,000$40,000WW46WRF PLANTCONCRETE PAD FOR ROLLOFF TRUCK CONTAINERS.$14,000112
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY15FY17FY18FY19PW01WW OPSSHOPS FACILITY EXPANSION PLAN$10,000WW07WW OPSENGINEERING/DESIGN FOR ANNUAL WASTEWATER PIPE REPLACEMENTS$22,500$22,500$22,500$22,500$22,500WW08‐15WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2015$914,000WW08‐16WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2016$952,700WW08‐17WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2017$803,200WW08‐18WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCITON IN 2018.$963,350WW08‐19WW OPSWASTEWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2019$1,027,550WW26WW OPSFLUSHER VAC TRUCK REPLACEMENT$365,000WWIF15WWATER IFFLANDERS MILL ‐ HIDDEN VALLEY TRUNK MAIN AND LIFT STATIONSummary for Wastewater Fund (27 items)Totals by year:$1,590,500 $1,261,200 $1,300,700$8,000,000FY15FY16FY17UnscheduledFY19$1,810,050$1,085,850FY18113
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
PW01
DEPARTMENT
WW OPS
PROJECT NAME
SHOPS FACILITY EXPANSION PLAN
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
The construction of the new Vehicle Maintenance Shop at the Lower Yards on Rouse Avenue in FY10/FY11 was Phase I in
expanding and improving our ability to service equipment, store vehicles, and provide work space for Public Works, Parks, and
Facilitiy services. Questions remain about the long-term plan for construction, location, and expansion for: Streets, Sign & Signal,
Forestry, Water/Sewer Operations, Solid Waste Collection & Recycling, Facilities, and Parks & Cemetery departments. This
project would develop a master plan. In scheduling this project, we are recommending waiting until after the Vehicle Maintenance
Division is relocated to its new shop and the interior improvements are made to the Shop at Rouse and Tamarack Street for the
remaining divisions.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
From related divisions: General Fund 20% ($10,000), Water Fund 20% ($10,000), Wastewater Fund 20% ($10,000), Street
Maintenance Fund 20% ($10,000), Solid Waste Fund 20% ($10,000).
New
Replacement
Equipment
Project
FY17
$10,000
FY18 FY19
114
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW07
DEPARTMENT
WW OPS
PROJECT NAME
ENGINEERING/DESIGN for ANNUAL WASTEWATER PIPE REPLACEMENTS
FY15
$22,500
FY16
$22,500
Unscheduled
DESCRIPTION OF PROJECT
This item provides for design work to be completed every-other year, in anticipation of the Annual System Upgrades. As the
Wastewater Operations Division televises (views) the existing system, maintenance projects become apparent. As annual
televising continues, other more-urgent projects may be identified and designed under this project heading.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for design of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY17
$22,500
FY18
$22,500
FY19
$22,500
115
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-15
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - Construction in 2015
FY15
$914,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S. 3rd Ave: W. Olive St - W. Lincoln St S. 4th Ave: W. Babcock St - W. Olive St S. 4th Ave: W. College St - W.
Lincoln St S. 5th Ave: W. Olive St - W. Lincoln St W. Babcock St: S. 6th Ave - S. Grand Ave W. Olive St: S. 6th Ave - S. 3rd Ave
Alley N of Koch: S. 5th Ave - E. End. After budget approval July 1, 2014, this project would complete design, bid and begin
construction in the Spring/Summer of 2015, at the end of FY15.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
116
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-16
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - Construction in 2016
FY15 FY16
$952,700
Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: Interstate/walmart: N. Rouse Ave - N. 3rd Ave Pea Cannery Line: N. Rouse Ave - End Juniper Street: N. Rouse
Ave - E. Tamarack St N. Rouse Ave: Humane Society - Bridger Center Dr Bridger Center Main: Bridger Drive - N End of Main
Industrial Dr: Trunk Main - Half way to Griffin. After budget approval July 1, 2015, this project would complete design, bid and
begin construction in the Spring/Summer of 2016, at the end of FY16.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
117
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-17
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - Construction in 2017
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: Alley N of Story: S 5th Ave - E. End Alley N of Dickerson: S 5th Ave - E. End, Alley N of Alderson: S 5th Ave - E.
End W. College St: S 5th Ave - E. End, W. College St: S 4th Ave - S. 3rd Ave Alley N. of Harrison: S. 5th Ave - S. 4th Ave, Alley N.
of Cleveland: S. 5th Ave - S. 4th Ave S. 6th Ave: W. Babcoc St - Alley N. of Olive, S. 6th Ave: W. Story St - W. Grant St S. 7th
Ave: Alley N of Olive - W. Story St, S. 7th Ave: W. Story St - W. Harrison W. Olive St: S. 6th Ave - S. 7th Ave, W. Story St: S. 6th
Ave - S. 7th Ave Alley btwn 7th & 8th: Alley N of Olive - Alley N. of Koch Alley btwn 7th & 8th: Alley N of Dickerson - W.
Harrison St.. After budget approval July 1, 2016, this project would complete design, bid and begin construction in the
Spring/Summer of 2017, at the end of FY17.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY17
$803,200
FY18 FY19
118
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-18
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - Construciton in 2018.
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
Alley N of Babcock: S. 11th Ave-Alley E. of 7th: W Babcock St: S. 11th- S. 10th Ave.: Alley N of Olive: S. 6th Ave-S 7th Ave.: Alley
N Of Olive: S. 11th Ave.- Alley E of 8th: Alley btwn 8th&9th: Alley N of Olive-W. College St: S. 9th St.: W. Main St.-Alley N of
Olive: Alley btwn 9th&10th: Alley N of Olive- W. College St: S. 10th Ave: W. Main St – W. Harrison St: W. Harrison St: S. 6th
Ave – S 10th Ave. After budget approval July 1, 2017, this project would complete design, bid and begin construction in the
Spring/Summer of 2018, at the end of FY18.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
$963,350
FY19
119
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW08-19
DEPARTMENT
WW OPS
PROJECT NAME
WASTEWATER PIPE REPLACEMENT PROGRAM - Construction in 2019
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: Alley W of S 10th Ave: Alley N of Olive- W. Koch St. Alley W of S 10th Ave: N of Dickerson – W. Alderson St.
Alley W of S 10th Ave: N of College- W. College St. W. Curtiss St: S. 10th Ave-Alley W of S. 10th. W. Curtiss St.: Alley W of S.
11th. Chequamegon Village: All internal mains. W. Koch St: Alley W of S. 10th- Alley W of S. 12th. Alley W of S 11th Ave: Alley S
of Alderson – University. W. Villard St: N. 7th Ave- N. 8th Ave. N. 8th Ave: W. Villard – W. Beall St. N. 8th Ave: W. Beall St –
W. Mendenhall St. Alley N of Main St: N. 9th Ave _ N. 7th Ave. Alley W of 8th Ave: W. Durston Rd – W. Villard St. W. Villard St
: Alley W of N 8th – N. 9th Ave. N. 9th Ave: W. Villard St – W. Main St. W. Beall St: N. 8th Ave – N. 9th Ave. Alley W of 9th
Ave: W. Durston Rd – W. Villard St. W. Villard St: Alley W of 9th Ave – N. 10th Ave. N. 10th Ave : W. Villard St- W. Main St.
Alley W. of 10th Ave: W. Durston Rd – W. Mendenhall St. W. Lamme St: N. 9th Ave – N. 11th Ave. After budget approval July 1,
2018, this project would complete design, bid and begin construction in the Spring/Summer of 2019, at the end of FY18.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary sewer system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Utility Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
$1,027,550
120
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW26
DEPARTMENT
WW OPS
PROJECT NAME
FLUSHER VAC TRUCK REPLACEMENT
FY15
$365,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Replacement of the City’s Flusher Vac Truck. This flusher vac truck is used daily to excavate around critical infrastructure i.e. fiber
optics, gas, and electric lines in addition to flushing and vacuuming sewer mains. At time of replacement, this truck will be
approximately 10 years old. The existing truck will be sold at auction.
ALTERNATIVES CONSIDERED
Continue to use older vehicle which will be costly to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff and wastewater operations. This piece of equipment eliminates costly repairs because we
can avoid hitting utilities with a hoe and utilize the vacuum instead.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Operating and repair costs are expected to be lower than the existing vehicle.
FUNDING SOURCES
100% Wastewater utility fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
121
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW27
DEPARTMENT
WRF PLANT
PROJECT NAME
Watershed Study and Stream Modeling
FY15
$60,000
FY16
$60,000
Unscheduled
DESCRIPTION OF PROJECT
Develop a comprehensive, multi-year watershed study and computer model for the East Gallatin River which would enable the
City and DEQ to better determine stream load allocations and develop a more scientifically valid TMDL for the river segment we
discharge to. This will require annual field sample collection, laboratory analytical work and detailed computer modeling using
calibrated data. This multi-year study would consist of $45,000 in consulting and computer modeling fees for at least two fiscal
years (FY14 and FY15) and stream sampling/lab fees of $15,000 each year. Craig recommends we should be prepared to continue
this work beyond FY15 as necessary.
ALTERNATIVES CONSIDERED
Not undertake this work and risk having to accept the TMDL and waste load allocations the DEQ has proposed in their original
draft documents. This decision could greatly limit our ability to appeal future nutrient limitations and could result in non-
compliance.
ADVANTAGES OF APPROVAL
This watershed study will greatly enhance the City’s understand of our impact on the East Gallatin River and enable us to more
successfully negotiate future permit limitations with the DEQ.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None, unless additional stream sampling is desired in subsequent years.
FUNDING SOURCES
100% Wastewater Fund
New
Replacement
Equipment
Project
FY17
$60,000
FY18
$60,000
FY19
$60,000
122
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW28
DEPARTMENT
WRF PLANT
PROJECT NAME
DESIGN PHASE II - WRF PLANT IMPROVEMENTS
FY15 FY16 Unscheduled
$5,230,000
DESCRIPTION OF PROJECT
In January 2006 Morrison & Maierle Consulting Engineers completed a comprehensive Wastewater Facilities Plan. The plan
recommends the City proceed with a 3-phased project schedule that includes the construction of the new Water Reclamation
Facility (WRF), capable of handling our increased flows while also reducing the amount of Total Nitrogen discharged to the East
Gallatin River. Phase two is expected to include one new primary clarifier, more BNR reactor basins, clarifiers, tertiary membrane
filtration, liquid sludge storage tanks, anaerobic digestion, and an effluent re-use pumping station. The capacity expanding (impact
fee eligible) elements are: bioreactor basins, clarifiers, and pumping station. It is possible that this phase of the project could be
further divided into phase 2A and phase 2B, if necessary.
ALTERNATIVES CONSIDERED
A variety of treatment technologies and alternatives are presented in the January 2006 Wastewater Facilities Plan.
ADVANTAGES OF APPROVAL
Major capital expansion of the Bozeman WRF will enable the City to meet its estimated demand for wastewater services and still
produce a high quality effluent that is in full compliance with the City’s MPDES discharge permit. Expansion of the Bozeman WRF
is consistent with the City’s long-term need to accommodate rapid growth and economic development in the Gallatin Valley.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: no estimates at this time.
FUNDING SOURCES
Total Design Cost: $5,230,000. We estimate the majority of the project costs are related to regulation and maintenance issues
and would be borne by the Utility Fund. Half are related to capacity expansion, and would be borne by Impact Fees. 50%
Wastewater Fund, 50% Wastewater Impact Fee Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
123
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW29
DEPARTMENT
WRF PLANT
PROJECT NAME
ENERGY RECOVERY (METHANE CO-GENERATION) PROJECT
FY15 FY16 Unscheduled
$2,200,000
DESCRIPTION OF PROJECT
Consistent with the goals of the City’s Climate Action Plan & Sustainability Programs, the Bozeman WRF staff and Public
Works Director recommend we move forward with our proposed investigation and installation of a methane recovery and co-
generation system. This system will produce an average of 175 kW of electricity and 974,000 BTU/hour of thermal output using a
generator powered entirely by WRF digester gas. This project has the potential to save the City at least $180,000 in electricity
costs and substantially lower the carbon footprint of the new Bozeman WRF. This project would be implemented in 3 phases
including (1) a feasibility / cost effectiveness study, (2) project engineering / design and (3) the purchase and installation of
appropriate technology for the co-generation of electricity at the Bozeman WRF. Year 1: Project Feasibility Study. Year 2: Project
Engineering Design - $350,000. Year 3: Equipment Purchase and Installation - $2,200,000.
ALTERNATIVES CONSIDERED
Continue to flare our digester methane gas. Micro-turbines and fuel-cells have been analysed and continue to be possible
alternative energy recovery technologies for this project. Our research to date suggests the most proven technology currently
available to help us accomplish our energy recovery goals is likely to be a GE Jenbacher internal combustion engine and heat
recovery system.
ADVANTAGES OF APPROVAL
Current plant waste gases will be captured and utilized to reduce plant operating costs. The project has an estimated net dollar
savings of $230,000 per year. It supports the City's Municipal Climate Action Plan goals.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Once construction is funded, this project results in an estimated net dollar SAVINGS of $230,000/year.
FUNDING SOURCES
Wastewater Fund, other grants or community partners.
New
Replacement
Equipment
Project
FY17 FY18 FY19
$350,000
124
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW33
DEPARTMENT
WRF PLANT
PROJECT NAME
Install second Screw Press and Enclosure
FY15 FY16 Unscheduled
$220,000
DESCRIPTION OF PROJECT
Engineering study and installation of screw press with or without an enclosure.
ALTERNATIVES CONSIDERED
Increase sludge storage to delay the problem of limited processing capacity.
ADVANTAGES OF APPROVAL
The second screw press would provide needed redundancy if a screw press breaks down. It would provide extra sludge
processing capacity now and for future needs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
If used to increase processing capacity, the extra operating costs would include electricity, polymer use and additional cake hauling.
FUNDING SOURCES
Wastewater Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
125
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW35
DEPARTMENT
WRF PLANT
PROJECT NAME
Replace Commercial Mower
FY15 FY16
$13,000
Unscheduled
DESCRIPTION OF PROJECT
Replacement of 2001 Mower for use on the WRF grounds.
ALTERNATIVES CONSIDERED
Continue replacing parts as needed.
ADVANTAGES OF APPROVAL
Replacement parts will become more difficult to find as the mower ages. The increasing maintenance will mean less time for
groundskeeping.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs. May reduce maintenance costs.
FUNDING SOURCES
Wastewater Funds.
New
Replacement
Equipment
Project
FY17 FY18 FY19
126
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW35
DEPARTMENT
PUBLIC WORKS
PROJECT NAME
GRANITE XP UPGRADE
FY15 FY16
$18,000
Unscheduled
DESCRIPTION OF PROJECT
We currently use a Microsoft Access based solution (GraniteXP) for storing our Sewer/Stormwater CCTV inspection records.
This project will upgrade the database to a Microsoft SQL format.
ALTERNATIVES CONSIDERED
Keep using Microsoft Access.
ADVANTAGES OF APPROVAL
Microsoft SQL provides a more stable database platform for long-term storage of CCTV data. This also provides the ability to
integrate with other systems as well as improved reporting capabilities.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Potential for increased annual software maintenance costs.
FUNDING SOURCES
General Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
127
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW36
DEPARTMENT
PUBLIC WORKS
PROJECT NAME
WEB MAPPING SYSTEM INTEGRATION
FY15
$45,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Database system integration throughout the organization will provide users with (read-only) access to the most current and
reliable information specific to their needs within one browser. This project will integrate the following databases through
customized GIS (web) views for each Department: Sungard, Cityworks, MicroPAVER, Laserfiche, Firehouse, DOR ORION, etc.
ALTERNATIVES CONSIDERED
Keep database systems isolated.
ADVANTAGES OF APPROVAL
This project will provide access to a variety of information, thus leveraging the power of individual systems in one easy-to-use
format.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Maintenance (first year included) = $7,000
FUNDING SOURCES
There are numerous funding sources, including the Utility Funds, General Fund, Street Assessment Fund. At budget time, the full
project costs will be split among the group.
New
Replacement
Equipment
Project
FY17 FY18 FY19
128
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW36
DEPARTMENT
WRF PLANT
PROJECT NAME
Upgrade Truck Barn
FY15
$36,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Upgrade truck barn to provide storage for rolloffs; frame, insulate, sheetrock and heat 1/2 of truck barn for rolloff storage during
winter months.
ALTERNATIVES CONSIDERED
Build a heated storage building to house rolloffs during winter months.
ADVANTAGES OF APPROVAL
No additional storage area would have to be built saving the structure construction costs.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional costs.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
129
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW37
DEPARTMENT
WRF PLANT
PROJECT NAME
Upgrade Old PLC's and Firmware
FY15
$29,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
THREE PLC'S WILL HAVE THEIR PROCESSORS UPGRADED AND ALL PLC'S WILL HAVE THEIR FIRMWARE UPGRADED. A
NEWER VERSION OF PROGRAMMING SOFTWARE WILL BE INSTALLED.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
THE CITY WILL BE ABLE TO HAVE A STANDARD VERSION OF FIRMWARE AND SOFTWARE THAT WILL ALLOW
UPGRADING ALL PLC'S AT THE WRF IN THE FUTURE
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No new operating costs.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
130
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW38
DEPARTMENT
WRF PLANT
PROJECT NAME
#3 Perforated Screen & Washer Compactor
FY15 FY16
$140,000
Unscheduled
DESCRIPTION OF PROJECT
Extensive Engineering will be needed to install an additional influent huber screen in head works building because of limited space.
Additional screening capacity is needed because during a storm event this summer the influent flow meter pegged out over 15
mgd.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
THE TWO EXISTING SCREENS ARE RUNNING MOST OF THE YEAR SO IF ONE GOES DOWN THERE IS NO
REDUNDANCY. HAVING A THIRD SCREEN WOULD PREVENT A HIGH FLOW EVENT FROM OVER FLOWING THE
BYPASS CHANNEL INFLUENT GATE. THIS UNSCREENED FLOW CONTAINS MATERIAL THAT CAN PLUS PIPING AND
PUMPS CAUSING DAMAGE & EXTRA MAINTENANCE.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
IF PLACED IN A TWO SCREEN ROTATION, THE ONLY EXTRA COSTS WOULD BE AN ANNUAL INSPECTION WITH
PARTS REPLACEMENT PLUS CLEANING OF THE SCREEN & CAHNEL IT IS IN. IF USED TO INCREASE CAPACITY, EXTRA
ELECTRICITY WOULD BE USED BUT LESS CHANNEL CLEANING WOULD NEED TO BE PERFORMED.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
131
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW39
DEPARTMENT
WRF PLANT
PROJECT NAME
Sandlast & Paint old clarifier drives, beaches, baffles & weirs (6 total)
FY15
$15,000
FY16
$15,000
Unscheduled
DESCRIPTION OF PROJECT
Sandblast and paint old clarifier drives, beaches, baffles weirs.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
Replace lost & chipping paint on old clarifiers to prevent deterioration of existing infrastructure.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No new operating costs.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17
$15,000
FY18 FY19
132
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW40
DEPARTMENT
WRF PLANT
PROJECT NAME
UV Building Shading Material
FY15
$15,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Netting or covering to place over roof and sides of UV Building during the summer to reduce solar radiation heating the building.
ALTERNATIVES CONSIDERED
Installing a larger cooling system in the PLC compartment.
ADVANTAGES OF APPROVAL
LESS POWER WOULD BE USED BY THE VENTILATION SYSTEM AND THE PLC COOLING SYSTEM. KEEPING THE PLC
CABINET COOLER WILL PREVENT THE UPS FROM FAULTING. THIS UPS POWER THE PLC AND THE TROJAN UV
CONTROL SYSTEM. WHEN THE UV SYSTEM LOOSES POWER IT FAULTS TO A CONDITION OF ALL CHANNELS OPEN
AND ALL LAMPS ON. THIS CONDITIONS IS NOT NEEDED TO REDUCE E-COLI BACTERIA AND WASTES POWER.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Man hours needed to place the shading on in the spring and take the shading off in the fall.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
133
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW41
DEPARTMENT
WRF PLANT
PROJECT NAME
Replace 4" Ductile Pipe Through Dewatering Basement with Glass Lined Pipe
FY15
$15,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Replace 4; Cement Lined Ductile Pipe with Glass Lined pipe in the basement of sludge de-watering building.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
THIS PIPE IS INSTALLED IN THE CEILING OF THE SLUDGE DE-WATERING BUILDING BASEMENT WITH NUMEROUS
ELBOWS WHICH DOES NOT ALLOW ACCESS TO FLUSHING FOR REMOVAL OF STRUVITE OR BLOCKAGES.
INSTALLING GLASS LINED PIPE & FITTINGS WILL REDUCE THE POSSIBILITY OF NEEDING TO FLUSH THE PIPE.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional costs.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
134
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW42
DEPARTMENT
WRF PLANT
PROJECT NAME
Primary Clarifier Covers
FY15 FY16 Unscheduled
$350,000
DESCRIPTION OF PROJECT
INSTALLING A GEODESIC DOME COVER WITH 8 FOOT SIDE WALLS ON A PRIMARY CLARIFIER. THE INSTALLATION
WOULD INCLUDE A DOOR, TWO SKYLIGHTS AND A VENT TUBE. ALSO CLARIFIER DRIVE MOTOR AND CONTROLS
WOULD HAVE TO BE EXPLOSION PROOF.
ALTERNATIVES CONSIDERED
Do nothing
ADVANTAGES OF APPROVAL
COVERING THE PRIMARY CLARIFIERS WILL ALLOW ODOR CONTROL & ELIMINATE CLEANING & PAINTING.
CLEANING & PAINTING OF ALL RAILINGS AND CATWALKS IS AN ON-GOING MAINTENANCE ISSUE TO REMOVE
GREASE & DROPPINGS DEPOSITED BY BIRDS. COVERS ON PRIMARY CLARIFIERS WOULD ALLOW SOME CLARIFIERS
NOT TO BE USED DURING THE WINTER ALLOWING MORE NEEDED CARBON TO ENTER THE BIO-TRAINS.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Only maintenance of odor control would be additional.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17
$350,000
FY18 FY19
$350,000
135
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW43
DEPARTMENT
WRF PLANT
PROJECT NAME
Seal Mixer Flanges on Digester 1
FY15
$20,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
This project replaces the concrete that has been eaten away by H2S on the mixer flanges of Digester 1, extending its useful life
and improving operator safety. The mixers would have to be pulled and the concrete sealing surface under the mixer flanges
rebuilt.
ALTERNATIVES CONSIDERED
Inject epoxy into flange area to seal flange.
ADVANTAGES OF APPROVAL
REPLACE CONCRETE THAT HAS BEEN EATEN AWAY BY H2S TO INSURE STRUCTURAL INTEGRITY OF THE MIXER
SUPPORT AREA AND PROVIDE A TIGHT SEAL. PREVENT H2S AND METHANE GAS LEAKAGE FOR OPERATOR SAFETY.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional operating costs.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
136
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW44
DEPARTMENT
WRF PLANT
PROJECT NAME
Modify Flotation Thickener
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
Modify the existing flotation thickener to improve WRF processes.
ALTERNATIVES CONSIDERED
INCREASE THE BIO-TRAIN MASS, ADD MG(OH)2 AND MICRO C 2000 TO THE BIO-TRAINS TO TREAT THE INCREASED
AMMONIA LOAD
ADVANTAGES OF APPROVAL
Treating the return side stream will reduce the load on the bio-trains and reduce chemical costs associated with these loads.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Electrical costs for compressor, mixer and pumps.
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
137
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW45
DEPARTMENT
WRF PLANT
PROJECT NAME
Final Clarifier Launder Covers
FY15
$40,000
FY16
$40,000
Unscheduled
DESCRIPTION OF PROJECT
To cover effluent launder of one final clarifier a year (4 total) to eliminate algal growth in the launder. THE BRUSH SYSTEM
REQUIRES CONTINUAL MAINTENANCE. THERE IS RISK OF BRUSHES BREAKING OFF AND FALLING INTO THE
CLARIFIER THAT MAY BLOCK THE WASTING HOPPER
ALTERNATIVES CONSIDERED
CURRENTLY A BRUSH SYSTEM IS USED TO REDUCE THE AMOUNT OF ALGAL GROWTH WHICH REQUIRES
CONTINUAL MAINTENANCE.
ADVANTAGES OF APPROVAL
COVERING THE CLARIFIERS WILL ELIMINATE CURRENT MAINTENANCE AND HELP REDUCE POTENTIAL HAZZARDS.
MAINTENANCE WOULD BE CUT TO TWICE A YEAR ALLOWING OPERATORS TO SPEND TIME ON OTHER DUTIES AT
THE PLANT.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Reduce oeprating costs (time & materials)
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17
$40,000
FY18
$40,000
FY19
138
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WW46
DEPARTMENT
WRF PLANT
PROJECT NAME
Concrete Pad for Rolloff Truck Containers.
FY15
$14,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Pour 20'x40' concrete pad or two tracks to support steel wheels of sludge cake hauling rolloffs in front and behind truck loading
garage.
ALTERNATIVES CONSIDERED
Lay Steel strips anchored on asphalt to support steel wheels
ADVANTAGES OF APPROVAL
STEEL REINFORCED CONCRETE WOULD BE PURED WHERE THE ASPHALT HAS BEEN REMOVED, WITH A STEEL PLATE
ON TOP EVEN WITH THE ASPHALT SURFACE. THIS CONFIGURATION WOULD BE STRONGER AND BE A LEVEL
SURFACE THAT WILL ALLOW EASIER SNOW PLOWING
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
No additional costs
FUNDING SOURCES
Wastewater Funds
New
Replacement
Equipment
Project
FY17 FY18 FY19
139
CIP Project Fund
Wastewater Fund
PROJECT NUMBER
WWIF15
DEPARTMENT
WWATER IF
PROJECT NAME
FLANDERS MILL - HIDDEN VALLEY TRUNK MAIN AND LIFT STATION
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
THIS PROJECT IS PRIMARILY AN IMPACT FEE ELIGIBLE PROJECT. How much of the project costs will be borne by the Utility
is uncertain at this point in time. The project consists of the installation of large diameter sewer from Huffine Lane to the City
Water Reclamation Facility along the Cottonwood-Flanders Mill- Hidden Valley alignment as identified in the Wastewater Facility
Plan. It also includes a Regional Lift Station located at the north of the alignment and the installation of the force-main necessary
to complete the project. $200,000 in design costs and $13,300,000 in construction costs.
ALTERNATIVES CONSIDERED
Limit development in the area served by this trunk sewer to that which can currently be served.
ADVANTAGES OF APPROVAL
This project will significantly increase the area which can be served by the City’s wastewater treatment infrastructure making
development in this corridor possible.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs. Impact fees may not be used to finance those costs. The City’s wastewater utility will pay
for these costs which are estimated to be a small increment of the City’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees (est.) = $9.3M 30% Development contribution =$4M. Some of this project could potentially be
funded with Utility dollars, or a loan for the impact fee portion of the project underwritten by the Utility.
New
Replacement
Equipment
Project
FY17 FY18 FY19
140