HomeMy WebLinkAbout12-9-13 Impact Fee Wastewater.pdf
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Chris Kukulski, City Manager
Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Wastewater Impact Fee Fund Capital Improvement
Plan (CIP) for FY15-19.
AGENDA ITEM TYPE: Action
MEETING DATE: December 9, 2013
RECOMMENDATION: Adopt the Wastewater Impact Fee Fund Capital Improvement
Plan (CIP) for FY15-19.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. The City’s Impact Fee
Advisory Committee (IFAC) met on November 14th to review and make recommendations for
the planned expenditures of Wastewater Impact Fees. There was not a quorum of the
committee, however, those present made suggestions and asked that the schedules move forward
to the Commission.
1. Revenue estimates for Impact Fee collections should be updated from the amount
budgeted in FY14. The attached schedule revenue estimates for FY15 show the 5-year
average of collections (FY09-13), with a modest amount of annual growth projected in
years 2016-2019.
2. The WWIF15- Flanders Mill – Hidden Valley Trunk Main and Lift Station project to
expand service in the West part of town (from the Huffine Lane area back to the Water
Reclamation Facility.) The early design, and identification and purchase of utility right-
162
of-way could prove to save millions of dollars, if done before more development occurs
in the area. With the recent annexations and subdivisions that have occurred in west area
of town, it is felt that this project will need to move forward within the next two years.
a. While the project is generally seen as entirely capacity expanding, there will not
be cash on hand to construct. The Wastewater Utility will need to borrow money
for the project (a pledge by our rate-payers) with debt payments made by the
Impact Fee Fund each year.
3. WWIF17 - Install the Fourth Digester, has been added as unscheduled. This item was
brought forward by WRF staff, after the IFAC had met. It is expected to be entirely
capacity expanding for the plant, needed as growth continues.
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY15.
Report compiled on: November 27, 2013
Attached: Draft Wastewater Impact Fee Fund CIP
163
Wastewater Impact Fee Capital Improvement PlanFinancial Summary Current YearFY14 FY15 FY16 FY17 FY18 FY19UnscheduledProjected Beginning Reserve Balance Dedicated to CIP‐$ ‐$ 152,083$ 307,207$ (0)$ 269$ ‐$ Plus: Impact Fee Revenues Dedicated to CIP 820,000$ 1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ 1,088,163$ ‐$ Plus: Loan for WWIF15 ‐ Flanders Mill Trunk and Lift Stn. 13,300,000$ Less: Scheduled CIP Project Costs (820,000)$ (853,212)$ (14,170,276)$ (1,353,116)$ (1,066,558)$ (1,085,000)$ (3,862,000)$ Projected Year‐End Cash Dedicated to CIP‐$ 152,083$ 307,207$ (0)$ 269$ 3,432$ Assumptions Made for Revenue Estimates: Current YearFY14 FY15 FY16 FY17 FY18 FY19Estimated Annual Wastewater Impact Fee Revenues 820,000$ 985,583$ 1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ Estimated Annual Increase 0.0% 2% 2% 2% 2% 2%Total Estimated Revenues 820,000$ 1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ 1,088,163$ Current Revenues Dedicated to CIP % 100.0% 100.0% 100.0% 100.0% 100.0% 100.0% Plus: Increase Dedicated to Wastewater Capacity Expansion CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 100.0% 100.0% 100.0% 100.0% 100.0% 100.0%ProjectedProjectedTotal Estimated Revenues Dedicated to CIP 820,000$ 1,005,295$ 1,025,401$ 1,045,909$ 1,066,827$ 1,088,163$ 16,000,00014,000,00012,000,00010,000,0008,000,0006,000,0004,000,0002,000,0000FY15 FY16 FY17 FY18 FY19 UnscheduledWastewater Impact Fee Projects 164
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY15FY17FY18FY19Impact Fees WastewaterWWIF05WWATER IFHOSPITAL TRUNK LINE: HAGGERTY TO KAGY$1,062,000WWIF11WWATER IFREPLACE FRONT STREET: TAMARACK/ROUSE$1,800,000WWIF12WWATER IFGRAF STREET EXTENSION$50,000WWIF14WWATER IFWRF PHASE I DEBT RETIREMENT$653,212$870,276$887,681$896,558$600,000WWIF15WWATER IFFLANDERS MILL ‐ HIDDEN VALLEY TRUNK MAIN AND LIFT STATION$200,000$13,300,000WWIF16WWATER IFFLANDERS MILL ‐ HIDDEN VALLEY TRUNK MAIN DEBT RETIREMENT$465,435$120,000$485,000WWIF17WWATER IFINSTALL FOURTH DIGESTER$1,000,000Summary for Impact Fees Wastewater (7 items)Totals by year:$853,212$14,170,276 $1,353,116$3,862,000FY15FY16FY17UnscheduledFY19$1,085,000$1,066,558FY18165
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF05
DEPARTMENT
WWATER IF
PROJECT NAME
HOSPITAL TRUNK LINE: HAGGERTY TO KAGY
FY15 FY16 Unscheduled
$1,062,000
DESCRIPTION OF PROJECT
Construct ~7,900 LF of 12" and 15" sewer collector from manhole C0507 to 1E22.
ALTERNATIVES CONSIDERED
Limit future development in the area.
ADVANTAGES OF APPROVAL
If constructed to the line sizes master planned in the City’s Wastewater Facilities plan, capacity will be provided for anticipating
the long-term future growth in this area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater
utility will pay for these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $743,400 30% Developer Contribution = $318,600
New
Replacement
Equipment
Project
FY17 FY18 FY19
166
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF11
DEPARTMENT
WWATER IF
PROJECT NAME
REPLACE FRONT STREET: TAMARACK/ROUSE
FY15 FY16 Unscheduled
$1,800,000
DESCRIPTION OF PROJECT
This project consists of construction of ~11,000 LF 18", 21" & 24" sewer pipe from manhole F0330 to C0507. The lower
portion of the existing sewer is at capacity. Additional capacity is needed to serve the future Bozeman Deaconess Hospital
development and lands to the south. It is estimated that 70% of this project costs will be due to capacity expansion and will be
eligible for Wastewater Impact Fees. The remaining 30% of the project costs will need to be provided by a developer
contribution or other source. At this time, the City’s Wastewater Utility does not have a need to replace the existing facility; as
such, no utility dollars are scheduled to be spent.
ALTERNATIVES CONSIDERED
Limit development to only that capacity of the existing sewer.
ADVANTAGES OF APPROVAL
This project will significantly increase the service area and capacity of the trunk sewer.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating and Maintenance Costs: Impact fees can not fund operating and maintenance costs. The city’s wastewater
utility will pay for these costs, which are estimated to be a small increment of the city’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees = $1,260,000 30% Developer Contribution = $540,000
New
Replacement
Equipment
Project
FY17 FY18 FY19
167
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF12
DEPARTMENT
WWATER IF
PROJECT NAME
GRAF STREET EXTENSION
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
This project is to extend Wastewater Mains below Graf Street approximately ¼ mile in order to connect infrastructure east from
19th Avenue. This is an important connection for public safety purposes – allowing fire service to meet their response time
requirements in areas where they currently cannot. The Wastewater infrastructure should be installed at the same time the
street connection is made.
ALTERNATIVES CONSIDERED
Do nothing and wait for development to connect the infrastructure.
ADVANTAGES OF APPROVAL
Improved traffic flow and better emergency response to the local area.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Wastewater Impact Fee – to be recovered by developer payback.
New
Replacement
Equipment
Project
FY17 FY18
$50,000
FY19
168
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF14
DEPARTMENT
WWATER IF
PROJECT NAME
WRF PHASE I DEBT RETIREMENT
FY15
$653,212
FY16
$870,276
Unscheduled
DESCRIPTION OF PROJECT
Total adjusted project price for the Water Reclamation Facility (WRF) construction of phase one is estimated at $53.8 Million.
Of that amount, $17.9 Million is for capacity expanding costs of construction. The impact fee account will not have enough cash
on hand to pay the costs of construction when the facility is built. As such, impact fee revenues will be dedicated to pay the
outstanding debt in future years, as fee revenues are collected. At this point, approximately $4.87 Million of impact fee eligible
costs will be paid with a long-term loan (20 years, 3.75%) through the State’s Revolving Loan Fund. A debt schedule will be
updated semi-annually with the amount of impact fee dollars that have been dedicated to debt payments until the full amount
owed is paid.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Major capital expansion of the Bozeman WRF will enable the City to meet its ever growing demand for wastewater services and
still produce a high quality effluent that is in full compliance with the City’s MPDES discharge permit. Expansion of the Bozeman
WRF is consistent with the City’s long-term need to accommodate rapid growth and economic development in the Gallatin Valley.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
*We anticipate having a minimum of $13.1 Million available from Impact Fees through the end of the construction period.
Impact fee collections during the construction period will be dedicated to the project. The remainder of eligible construction
costs would be dedicated to debt service on the Utility Revenue Bonds, as it is collected in the Impact Fee Fund.
New
Replacement
Equipment
Project
FY17
$887,681
FY18
$896,558
FY19
$600,000
169
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF15
DEPARTMENT
WWATER IF
PROJECT NAME
FLANDERS MILL - HIDDEN VALLEY TRUNK MAIN AND LIFT STATION
FY15
$200,000
FY16
$13,300,000
Unscheduled
DESCRIPTION OF PROJECT
This project consists of the installation of large diameter sewer from Huffine Lane to the City Water Reclamation Facility along
the Cottonwood-Flanders Mill- Hidden Valley alignment as identified in the Wastewater Facility Plan. It also includes a Regional
Lift Station located at the north of the alignment and the installation of the force-main necessary to complete the project.
$200,000 in design costs and $13,300,000 in construction costs
ALTERNATIVES CONSIDERED
Limit development in the area served by this trunk sewer to that which can currently be served.
ADVANTAGES OF APPROVAL
This project will significantly increase the area which can be served by the City’s wastewater treatment infrastructure making
development in this corridor possible.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs. Impact fees may not be used to finance those costs. The City’s wastewater utility will pay
for these costs which are estimated to be a small increment of the City’s system as a whole.
FUNDING SOURCES
70% Wastewater Impact Fees (est.) = $9.3M 30% Development contribution =$4M
New
Replacement
Equipment
Project
FY17 FY18 FY19
170
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF16
DEPARTMENT
WWATER IF
PROJECT NAME
FLANDERS MILL - HIDDEN VALLEY TRUNK MAIN DEBT RETIREMENT
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
This items reflects the amount of Impact Fee dollars that are estimated to be available for retirement on the debt used to
financine the Flanders Mill - Hidden Valley sewer trunk main and lift station.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY17
$465,435
FY18
$120,000
FY19
$485,000
171
CIP Project Fund
Impact Fees Wastewater
PROJECT NUMBER
WWIF17
DEPARTMENT
WWATER IF
PROJECT NAME
Install Fourth Digester
FY15 FY16 Unscheduled
$1,000,000
DESCRIPTION OF PROJECT
Fund the design and construction of a fourth anaerobic digester.
ALTERNATIVES CONSIDERED
Do nothing.
ADVANTAGES OF APPROVAL
Additional Capacity for wastewater treatment.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Not known at this time.
FUNDING SOURCES
Wastewater Impact Fee Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
172