Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Chris Kukulski, City Manager
Anna Rosenberry, Administrative Services Director
SUBJECT: Adoption of the Storm Water Fund Capital Improvement Plan (CIP)
for FY15-19.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 9, 2013
RECOMMENDATION: Adopt the Storm Water Fund Capital Improvement Plan (CIP)
for FY15-19.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th.
The Public Works and other city staff met in October and November to develop the attached
Capital Plan for the equipment and capital needs of the Storm Water Fund.
As is noted on the schedule, many capital items are listed as "unscheduled" until our Utility
method for charging customers is refined to be more equitable, anticipated some time in FY15.
Items of Note:
• SWRM14 – Storm Water Rate Study is needed in FY15 to arrive at a more nuanced and
equitable charge method for properties in our system.
81
• STRM15 – Impervious Surface Data Creation is needed in FY15 in order to utilize the
impervious surface method of charging customers.
Neither of these items would be required if we kept a more simplistic approach to assessment,
such as per meter or per lot charges. However, these methods are generally seen as a less-
desirable way to charge customers, as they don’t get at the heart of what impacts the stormwater
system (run off, age of existing infrastructure, etc).
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY15.
Report compiled on: November 27, 2013
Attached: Draft Storm Water Fund CIP
82
Storm Water Utility Capital Improvement PlanFinancial Summary Current YearFY14 FY15 FY16 FY17 FY18 FY19UnscheduledProjected Beginning Reserve Balance Dedicated to CIP‐$ ‐$ (53,188)$ 6,466$ 69,101$ 135,495$ Plus: Storm Water Utility Fees Dedicated to Capital‐$ 56,813$ 59,653$ 62,636$ 66,394$ 70,378$ Less: Scheduled CIP Project Costs‐$ (110,000)$ ‐$ ‐$ ‐$ ‐$ (1,139,300)$ Projected Year‐End Cash Dedicated to CIP‐$ (53,188)$ 6,466$ 69,101$ 135,495$ 205,873$ (1,139,300)$ Assumptions Made for Revenue Estimates: Current YearFY13 FY15 FY16 FY17 FY18 FY19Estimated Annual Storm Water Utility Revenue 225,000$ 225,000$ 227,250$ 238,613$ 250,543$ 265,576$ Estimated Annual Increase ‐ Attributed to Growth 1% 1% 1% 2% 2% Estimated Annual Increase ‐ Rate Increase 4% 4% 4% 4% 4%Total Estimated Revenues 225,000$ 227,250$ 238,613$ 250,543$ 265,576$ 281,510$ Current Revenues Dedicated to CIP % 0.0% 25.0% 25.0% 25.0% 25.0% 25.0% Plus: Increase Dedicated to Capital 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 0.0% 25.0% 25.0% 25.0% 25.0% 25.0%ProjectedProjectedTotal Estimated Revenues Dedicated to CIP‐$ 56,813$ 59,653$ 62,636$ 66,394$ 70,378$ Note: Many Capital Items are listed as "unscheduled" until our Utility method for charging customers is refined to be more equitable for Storm Water customers, anticipated in approx FY15.1,200,0001,000,000800,000600,000400,000200,0000FY15 FY16 FY17 FY18 FY19 UnscheduledStorm Water Projects 83
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY15FY17FY18FY19Storm Water FundSTRM01STORM WATERVALLEY UNIT PARK$80,000STRM02STORM WATERROCKY CREEK STORM WATER IMPROVEMENTS$20,000STRM04STORM WATERANNUAL STORM WATER PIPE REHABILITATION$300,000STRM08STORM WATERROUSE AVENUE STORM DRAIN UPSIZING$186,300STRM09STORM WATERROUSE AVENUE STORM WATER TREATMENT$93,000STRM10STORM WATERSWEEPER$75,000STRM11STORM WATERSERVICE TRUCK$40,000STRM12STORM WATERFLUSHER VAC TRUCK$345,000STRM14STORM WATERSTORM WATER RATE STUDY$35,000STRM15STORM WATERIMPERVIOUS SURFACE DATA CREATION$75,000Summary for Storm Water Fund (10 items)Totals by year:$110,000$1,139,300FY15FY16FY17UnscheduledFY19FY1884
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM01
DEPARTMENT
STORM WATER
PROJECT NAME
Valley Unit Park
FY15 FY16 Unscheduled
$80,000
DESCRIPTION OF PROJECT
Improvements to the detention pond at Valley Unit Park, as described on page 6-5 in the Storm Water Facility Plan. This item is
listed as unscheduled until our Utility method for charging customers is refined to be more equitable for Storm Water customers.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Will reduce flooding along Meagher Avenue and Durston Road
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Storm Water Utility, possible Grants.
New
Replacement
Equipment
Project
FY17 FY18 FY19
85
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM02
DEPARTMENT
STORM WATER
PROJECT NAME
Rocky Creek Storm Water Improvements
FY15 FY16 Unscheduled
$20,000
DESCRIPTION OF PROJECT
Improvements to increase and restore the native vegitation cover and diversity, thereby reducing sedimentation and improving
water quality in Rocky Creek, as described on page 6-7 of the Storm Water Facility Plan. This item is listed as unscheduled until
our Utility method for charging customers is refined to be more equitable for Storm Water customers.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Reduced sedimentation and improved water quality.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Storm Water Fund, possible grants.
New
Replacement
Equipment
Project
FY17 FY18 FY19
86
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM04
DEPARTMENT
STORM WATER
PROJECT NAME
Annual Storm Water Pipe Rehabilitation
FY15 FY16 Unscheduled
$300,000
DESCRIPTION OF PROJECT
General repairs and infrastructure maintenance are estimated to cost $300,000 per year. After mapping and condition
assessments are complete, the utility will begin a systematic program of infrastructure repair and replacement, including
installation of Storm Water Treatment systems. In the future, specific projects and project areas will be defined. Until then, this
item acts as a financial indicator of that work program. When specific projects are scheduled in the CIP, those amounts will
reduce the $300,000 scheduled in this item each year. One year's allocation of this item is listed as unscheduled until our Utility
method for charging customers is refined to be more equitable for Storm Water customers.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Storm Water Fund, grants when available.
New
Replacement
Equipment
Project
FY17 FY18 FY19
87
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM08
DEPARTMENT
STORM WATER
PROJECT NAME
Rouse Avenue Storm Drain Upsizing
FY15 FY16 Unscheduled
$186,300
DESCRIPTION OF PROJECT
This project is in coordination with the MDOT improvements to Rouse Avenue. It entails the upsizing of Stormwater
Infrastructure on Rouse. We will need to be prepared to fund this project in according the construciton timelines established by
MDOT, which are fairly fluid at this point.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Storm Water Utility, TSEP Grant, other grants.
New
Replacement
Equipment
Project
FY17 FY18 FY19
88
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM09
DEPARTMENT
STORM WATER
PROJECT NAME
Rouse Avenue Storm Water Treatment
FY15 FY16 Unscheduled
$93,000
DESCRIPTION OF PROJECT
This project is in coordiantion with the MDOT improvements to Rouse Avenue. It will provide Storm Water treatment facilities
for run-off on Rouse Avenue. We will need to be prepared to fund this project in according the construciton timelines
established by MDOT, which are fairly fluid at this point.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Storm Water Utility, TSEP Grant, other grants.
New
Replacement
Equipment
Project
FY17 FY18 FY19
89
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM10
DEPARTMENT
STORM WATER
PROJECT NAME
Sweeper
FY15 FY16 Unscheduled
$75,000
DESCRIPTION OF PROJECT
Sweeper Lease, for cleaning streets. Keeping streets free from debris keeps the sedimentation and objects out of our storm water
system.
ALTERNATIVES CONSIDERED
Borrow Sweeper from Street Division
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Maintenance Costs
FUNDING SOURCES
Stormwater Utility
New
Replacement
Equipment
Project
FY17 FY18 FY19
90
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM11
DEPARTMENT
STORM WATER
PROJECT NAME
Service Truck
FY15 FY16 Unscheduled
$40,000
DESCRIPTION OF PROJECT
New Vehicle dedicated to use by Storm Water crews.
ALTERNATIVES CONSIDERED
Borrow vehicle from other divisions; purchase used truck.
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal Maintenance Costs
FUNDING SOURCES
Storm Water Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
91
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM12
DEPARTMENT
STORM WATER
PROJECT NAME
Flusher Vac Truck
FY15 FY16 Unscheduled
$345,000
DESCRIPTION OF PROJECT
Replacement of 20 year old vac truck handed down from the sewer division. This truck is used to flush vacuum storm sewer
mains.
ALTERNATIVES CONSIDERED
Continue using current truck and pay increased costs to maintain.
ADVANTAGES OF APPROVAL
Increased reliability and safety for staff and stormwater operations.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual operating and maintenance costs (expected to be lower than existing vehicle)
FUNDING SOURCES
Storm Water Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
92
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM14
DEPARTMENT
STORM WATER
PROJECT NAME
Storm Water Rate Study
FY15
$35,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
The City will hire a contractor to perform a rate study to analyze different rate structures and methods for assessing our
stormwater fees.
ALTERNATIVES CONSIDERED
Continue calculating rates as we currently are or develop another method
ADVANTAGES OF APPROVAL
The City's Stormwater Utility is new and our system hasn't been maintained in the past. A rate study will allow us to determine
how we should be assessing rates so we can ensure that our utility can support itself and we can better maintain and build our
system in the most effective way possible.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Storm Water Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
93
CIP Project Fund
Storm Water Fund
PROJECT NUMBER
STRM15
DEPARTMENT
STORM WATER
PROJECT NAME
Impervious Surface Data Creation
FY15
$75,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Create polygon data to represent the extent of impervious surface area for all properties - so that the Storm Water Utility can
base its charges on the impervious surface on each property.
ALTERNATIVES CONSIDERED
Use existing (partial) Department of Revenue data to supplement known property areas
ADVANTAGES OF APPROVAL
This information will allow for the accurate assessment of the relative impact of stormwater runoff. Industry best practices
recommend that impervious surface is the most defensible and common method used for storm water utility fee calculations.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Recurring costs may be required depending on the level of detail necessary to support overall policy direction (i.e., residential vs
commercial vs tiered structure, etc). Interdepartmental workflow will also be necessary to coordinate and update/maintain
construction information on a persistent basis
FUNDING SOURCES
Storm Water Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
94