Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Anna Rosenberry, Administrative Services Director
SUBJECT: Adopt the Parking Fund Capital Improvement Plan (CIP) for Fiscal
Years 2015-2019.
AGENDA ITEM TYPE: Consent
MEETING DATE: December 9, 2013
RECOMMENDATION: Adopt the Parking Fund Capital Improvement Plan (CIP) for
Fiscal Years 2015-2019.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. Similar to recent years
past, we are bringing the various parts of the plan forward as items on the Consent agenda. We
will be prepared to address questions, if they arise, at the public meeting.
This is the first year we have brought a CIP to the Commission for the Parking Fund. Last year,
we worked with the Parking Commission and Parking Manager to begin development of a plan,
but it wasn’t completed until after all of the other plans had been submitted and approved. This
year, we have the fully developed plan for recommendation and adoption. This plan was
discussed and approved by the Parking Commission at their meeting on November 13th.
Items of Note:
• This process brought to light the need for more annual revenues to be dedicated to capital
items – especially of large lot improvement projects are to be funded.
63
• P016 – Purchase of Additional Surface Lots is listed with an unknown cost. The Parking
Commission wanted it in the CIP, as it is an identified area of need.
UNRESOLVED ISSUES: None.
ALTERNATIVES: As suggested by the City Commission. If the Commission does not
wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY15.
Report compiled on: November 26, 2013
Attached: Draft Parking Fund CIP
64
Parking FundCapital Improvement PlanFinancial Summary Current YearFY14 FY15 FY16 FY17 FY18 FY19UnscheduledProjected Beginning Balance Dedicated to CIP 136,600$ 256,100$ 133,600$ 53,600$ 23,600$ 33,600$ Cash In Lieu of Parking 122,000$ ‐$ ‐$ ‐$ ‐$ ‐$ ‐$ Plus: Parking Revenues Dedicated to Capital 17,500$ 17,500$ 5,000$ 5,000$ 5,000$ ‐$ ‐$ Plus: Downtown TIF Interest Contribution 10,000$ 10,000$ 10,000$ 10,000$ 10,000$ 10,000$ Less: Scheduled CIP Costs (30,000)$ (150,000)$ (95,000)$ (45,000)$ (5,000)$ (40,000)$ (880,000)$ Projected Year‐End Cash Dedicated to CIP 256,100$ 133,600$ 53,600$ 23,600$ 33,600$ 3,600$ Assumptions Made for Revenue Estimates: Current YearFY14 FY15 FY16 FY17 FY18 FY19 Annual Parking Revenues Dedicated to Capital 17,500$ 17,500$ 5,000$ 5,000$ 5,000$ ‐$ Plus: Downtown TIF Interest Contribution 10,000$ 10,000$ 10,000$ 10,000$ 10,000$ 10,000$ Total Estimated Revenues Dedicated to Capital27,500$ 27,500$ 15,000$ 15,000$ 15,000$ 10,000$ ProjectedProjected1,000,000750,000500,000250,0000Parking Fund Capital Projects 65
CIP PROJECT FUPROJ.DEPARTMENTPROJECT NAMEFY16UnscheduledFY15FY17FY18FY19Parking FundP002PARKINGCRACK SEALING$20,000$30,000P003PARKINGLIGHTING REPLACEMENT PROGRAM$15,000$15,000$30,000P004PARKINGPARKING LOT HARDWARE & SOFTWARE SYSTEMS$40,000$40,000$40,000P005PARKINGPORTABLE RADIO REPLACEMENT$5,000$5,000$5,000$5,000P006PARKINGHAND‐HELD TICKET WRITER REPLACEMENTS$40,000P009PARKINGBLACK (CARNEGIE) LOT SIDEWALK & LIGHTING IMPROVEMENTS$50,000P011PARKINGWILLSON LOT$150,000P012PARKINGARMORY LOT IMPROVEMENTS$50,000P013PARKINGBLACK (CARNEGIE) LOT PARKING IMPROVEMENTS.$150,000P014PARKINGPARKING GARAGE DECK PATCH AND REPAIR$5,000$5,000P015PARKINGPARKING GARAGE ROOF PROJECT$150,000P016PARKINGPURCHASE OF ADDITIONAL SURFACE LOTS IN THE DOWNTOWN PARKING DISTRICT.P017PARKINGROUSE PARKING LOT RE‐DESIGN AND IMPROVEMENTS$350,000P020PARKINGPARKING VEHICLE REPLACEMENTS$10,000$5,000Summary for Parking Fund (14 items)Totals by year:$150,000 $95,000 $45,000$880,000FY15FY16FY17UnscheduledFY19$40,000$5,000FY1866
CIP Project Fund
Parking Fund
PROJECT NUMBER
P002
DEPARTMENT
PARKING
PROJECT NAME
Crack Sealing
FY15 FY16
$20,000
Unscheduled
DESCRIPTION OF PROJECT
Recurring Project to seal cracks in the surface parking lots. This routine maintenance should be scheduled very 3 Yrs.
ALTERNATIVES CONSIDERED
Don't seal cracks - this will limit the life of our existing asphalt and base.
ADVANTAGES OF APPROVAL
Proper maintenance of the parking lots will extend their useful life.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None.
FUNDING SOURCES
Parking Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
$30,000
67
CIP Project Fund
Parking Fund
PROJECT NUMBER
P003
DEPARTMENT
PARKING
PROJECT NAME
Lighting Replacement Program
FY15
$15,000
FY16
$15,000
Unscheduled
$30,000
DESCRIPTION OF PROJECT
Replace failing fixtures inside the Garage (not roof level) with LED's.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
100% Parking Fund - Energy Savings will offset many of the costs.
FUNDING SOURCES
New
Replacement
Equipment
Project
FY17 FY18 FY19
68
CIP Project Fund
Parking Fund
PROJECT NUMBER
P004
DEPARTMENT
PARKING
PROJECT NAME
Parking Lot Hardware & Software Systems
FY15
$40,000
FY16
$40,000
Unscheduled
DESCRIPTION OF PROJECT
In the event that Downtown Parking Lots are transitioned to a fee-lot, we will need kiosks for payment that link to the existing
parking management software at the Garage. Each system is estimated to be $40,000, with the necessary curbing and electrical
improvements; one system required for each lot. Potential lots for conversion are thought to be the Black Lot, Armory Lot, and
Willson Lot.
ALTERNATIVES CONSIDERED
Keep lots as they are: permit holders and free transient parking for up to 2 hours.
ADVANTAGES OF APPROVAL
Revenue will be derived from the use of lots by transient, daily parkers.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minor electrical and operational costs.
FUNDING SOURCES
100% Parking Fund
New
Replacement
Equipment
Project
FY17
$40,000
FY18 FY19
69
CIP Project Fund
Parking Fund
PROJECT NUMBER
P005
DEPARTMENT
PARKING
PROJECT NAME
Portable Radio Replacement
FY15
$5,000
FY16
$5,000
Unscheduled
DESCRIPTION OF PROJECT
Replacement of all four department radios, $5,000 ea. Existing radios are old and have seen a lot of wear and tear. These will
need to be replaced as current equipment fails.
ALTERNATIVES CONSIDERED
Hand-me-downs from the Police or Fire Departments as they replace first-responder equipment.
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY17
$5,000
FY18
$5,000
FY19
70
CIP Project Fund
Parking Fund
PROJECT NUMBER
P006
DEPARTMENT
PARKING
PROJECT NAME
Hand-Held Ticket Writer Replacements
FY15
$40,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
Replacement of current group of 8 ticket-writers used by enforcement officers on the street.
ALTERNATIVES CONSIDERED
Approximately $3,500 for refurbished machines, but useful life is likely less.
ADVANTAGES OF APPROVAL
Replacement of critical equipment
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
Parking Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
71
CIP Project Fund
Parking Fund
PROJECT NUMBER
P009
DEPARTMENT
PARKING
PROJECT NAME
Black (Carnegie) Lot Sidewalk & Lighting Improvements
FY15 FY16 Unscheduled
$50,000
DESCRIPTION OF PROJECT
This project extends the Main Street Streetscape north on Black to Mendenhall Street, along the City-own Parking Lot. The
project would coincide with the private property owner project.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
New
Replacement
Equipment
Project
FY17 FY18 FY19
72
CIP Project Fund
Parking Fund
PROJECT NUMBER
P011
DEPARTMENT
PARKING
PROJECT NAME
Willson Lot
FY15 FY16 Unscheduled
$150,000
DESCRIPTION OF PROJECT
Layout, set-backs, landscaping, signage, lighting, storm water requirements.
ALTERNATIVES CONSIDERED
Keep lot as-is.
ADVANTAGES OF APPROVAL
Improved functioning of parking lot.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
Parking Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
73
CIP Project Fund
Parking Fund
PROJECT NUMBER
P012
DEPARTMENT
PARKING
PROJECT NAME
Armory Lot Improvements
FY15
$50,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
This project will be needed after the Etha Hotel construction is completed. Layout, set-backs, landscaping, signage, lighting, storm
water requirements are being considered.
ALTERNATIVES CONSIDERED
Keep the lot as-is.
ADVANTAGES OF APPROVAL
Better functioning parking lots.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
Parking Fund - the Etha Hotel Construction Licensing Agreement for use of the lot will bring approx $35,000 to help fund these
improvements.
New
Replacement
Equipment
Project
FY17 FY18 FY19
74
CIP Project Fund
Parking Fund
PROJECT NUMBER
P013
DEPARTMENT
PARKING
PROJECT NAME
Black (Carnegie) Lot Parking Improvements.
FY15 FY16 Unscheduled
$150,000
DESCRIPTION OF PROJECT
Improve the parking lot with layout, set-backs, landscaping, signage, lighting, and sufficient storm water infrastructure.
ALTERNATIVES CONSIDERED
Keep the lot as-is.
ADVANTAGES OF APPROVAL
Better functioning parking lots.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
Parking Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
75
CIP Project Fund
Parking Fund
PROJECT NUMBER
P014
DEPARTMENT
PARKING
PROJECT NAME
Parking Garage Deck Patch and Repair
FY15 FY16
$5,000
Unscheduled
DESCRIPTION OF PROJECT
Routine repairs and patching of concrete parking garage decks.
ALTERNATIVES CONSIDERED
Do not patch (not advised).
ADVANTAGES OF APPROVAL
Will extend the life of the parking garage deck surfaces.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
None
FUNDING SOURCES
Parking Fund
New
Replacement
Equipment
Project
FY17 FY18 FY19
$5,000
76
CIP Project Fund
Parking Fund
PROJECT NUMBER
P015
DEPARTMENT
PARKING
PROJECT NAME
Parking Garage Roof Project
FY15 FY16 Unscheduled
$150,000
DESCRIPTION OF PROJECT
Increased demand for leased space in the Garage has forced the Parking Commission to consider alternatives that would allow
coverage of the upper deck for winter use. Currently, the roof is not used in the winter months because of the difficulties of
snow removal. This option would install a roof on the current top parking deck, making space useable year-round.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Increased useable space in the Parking Garage facility.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
Parking Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
77
CIP Project Fund
Parking Fund
PROJECT NUMBER
P016
DEPARTMENT
PARKING
PROJECT NAME
Purchase of Additional Surface Lots in the Downtown Parking District.
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
The Parking Commission has the sole responsibiltiy for providing public parking spaces in the Downtown district. It is thought
that as Downtown grows we will need additional parking spaces - in the form of Surface Lots. Cost is Unknown. Our current
Black (Carnegie) Parking lot was appraised at $1.5M in 2011.
ALTERNATIVES CONSIDERED
Structured Parking (garaged) - generally thought to be much more expensive than surface lot purchase costs.
ADVANTAGES OF APPROVAL
Additional parking resources, critical to the downtown economy.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Additional lot maintenance each year/season.
FUNDING SOURCES
Parking Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
78
CIP Project Fund
Parking Fund
PROJECT NUMBER
P017
DEPARTMENT
PARKING
PROJECT NAME
Rouse Parking Lot Re-design and Improvements
FY15 FY16 Unscheduled
$350,000
DESCRIPTION OF PROJECT
Rouse Lot Improvements - Layout, set-backs, landscaping, signage, lighting, storm water requirements. Because the lot is ajacent
to Bozeman Creek, this project will require more improvements than any other existing city parking lot.
ALTERNATIVES CONSIDERED
Keep the lot as-is.
ADVANTAGES OF APPROVAL
Better functiong parking lots.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Minimal.
FUNDING SOURCES
Parking Fund, grants for strom water protection, etc.
New
Replacement
Equipment
Project
FY17 FY18 FY19
79
CIP Project Fund
Parking Fund
PROJECT NUMBER
P020
DEPARTMENT
PARKING
PROJECT NAME
Parking Vehicle Replacements
FY15 FY16
$10,000
Unscheduled
DESCRIPTION OF PROJECT
Currently, the Parking Fund uses hand-me-down Police Vehicles that are no longer suitable for first-responder use. The cost to
convert one of these used vehicles to a Parking Vehicle is $5,000 each. The cars are painted and light systems converted.
Currenlty, there are three vehicles used for parking enforcement.
ALTERNATIVES CONSIDERED
Buy brand-new cars.
ADVANTAGES OF APPROVAL
Low cost vehicles that are suitable for the Parking Enforcement function; re-use of police vehicles once they are no longer suitable
for first-responder use.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Additional maintenance is expected to be lower than existing fleet. However, because these are heavily used police vehicles,
annual maintenance is difficult to predict.
FUNDING SOURCES
Parking Fund.
New
Replacement
Equipment
Project
FY17 FY18 FY19
$5,000