2013 WATER RENIOVATIONS PROJECT
CITY OF BOZEMAN
131D OPENING: APRIL 9,2013, 2:00 P.M.
ADDENDUM No. 1 APRIL 2, 2013
TO: All Planholders of Record
Please note the following modifications to the above referenced bid documents:
Plans Sheet W3, — Station 16+20; Sheet W7, — Station 36+50•, Sheet W9— Station 45+52:
In the profile at each location noted above, replace the existing note that reads,
"Where 18" of vertical separation cannot be obtained, provide flowable fill,min. 3' each side of
existing san. sewer main or storm drain main and full width of utility trench to mid height of 8"
water line."
With a new note that reads:
"Where 18" of vertical separation cannot be obtained, provide flowable fill, min. 10' each side of
existing san. sewer main or storm drain main and full width of utility trench to mid height of 8"
water line."
Plans Sheet W5 — Station 26.+50:
The sewer service at this location that is shown going to the north from sewer main is not correct.
The service line extends south from the existing sewer main.
City of Bozeman Modifications to Montana Public Works Standard Specifications Sixth Edition:
Section 2.10, FIRE HYDRANTS, D. Delete the last sentence of this section. Defender Security
Devises will not be required.
Specification Section—SPECIAL PROVISIONS, 44. SCHEDULING AND SEQUENCING OF
WORK:
Add the following additional restriction to the first paragraph of this section:
Unless otherwise allowed by the Engineer, the work shall be complete in Zones 2 and 3 prior to
commencing with work in Zone 1. Installation of the temporary water system in Zone I will be
HOME OF MONTANA STATE UNIVERSITY
GATEWAY TO YELLOWSTONE PARK
exempt from this requirement.
Response to Bidder Question:
The City will perform all striping after completion of the project,
ACKNOWLEDGEMENT
Bidder shall acknowledge receipt and acceptance of this Addendum No. I on the Bid Form to
validate their bid.