HomeMy WebLinkAbout03-25-2013 Minutes, City Commission so
MINUTES OF THE MEETING OF THE CITY COMMISSION
BOZEMAN, MONTANA
March 25, 2013
The Commission met in the City Commission Room, City Hall at 121 North Rouse on.Monday,
March 25, 2013. Present were Mayor Sean Becker, Deputy Mayor Jeff Krauss, Commissioner
Carson Taylor, Commissioner Chris Mehl, City Manager Chris Kukulski, City Attorney Greg
Sullivan, and City Clerk Stacy Ulmen.
*These minutes are not ward far word and should be considered along with the audio recording,
0:07,57 A. Call to Order—6 p.m. —Commission Room, City Hall, 121 North Rouse
Mayor Becker called the regular meeting to order at 6.05 p.m.
0:08:051 . Pledge of Allegiance and a Moment of Silence
0:08:39 C. Changes to the Agenda
Mayor Becker asked City Manager Chris Kukulski if there were any changes to the agenda, Mr.
Kukulski stated that there were no changes to the Agenda.
0:08:48 D. Authorize Absence of Commissioner Andrus
It was moved by Cr. Taylor, seconded by Deputy Major Krauss to approve the absence of
Commissioner Andrus.
Those voting Ave being Cr. Taylor, Dc lE Major Krauss, Cr. Mehl and Mayor Becker.
Those voting No being none.
The motion passed 4-0.
0:09:01 E. Consent
1. Authorize Payment of Accounts Payable Claims (LaMeres)
2. Authorize City Manager to enter into an extension of the current sublease agreement
with Montana Rail Link for the Story Mill Spur Trail (Sullivan)
I Finally Adopt Ordinance No, 1847, establishing an initial zoning designation of RS on
19.42 acres for Ditton,Tract B-1 of Certificate of Survey 23928 as amended by the right-
of-way highway acquisition in conjunction with annexation,Zoning Application Z-12056
(Skelton)
Page 1 of 8
Minutes of the Bozeman City Commission meeting,March 25,2013
0:09:02 Public Comment
Mayor Becker opened public comment on the Consent Agenda,
No person commented.
Mayor Becker closed public comment on the Consent Agenda.
0:09:14 Motion and Vote to approve Consent items E. 1-3 as submitted.
It was moved b
a Deputy Mpaor Krauss, seconded by Cr. Mehl to approve Consent items E.
1-3 as submitted.
Those voting Aye being lie pyty_Mayor Krauss, Crs. Mehl, Tallor and Mayor Becker.
Those voting No being none.
The motion passed 4-0.
0:09:28 F. Public Comment
Mayor Becker opened public comment.
No person commented.
Mayor Becker closed public comment.
0:09:47 G. Special Presentation - Mayor State of the City Address (Mayor Sean Becker)
Mayor Sean Becker gave the State of the City Address. Ile spoke regarding the history and
growth of the City, Montana State University, the construction of Gallatin Field, the historic
districts in the Community, current projects in Bozeman, deferred maintenance, the Community
Climate Action Plan, the recent judgment, the creation of jobs, the Parks and Trails bond
implementation, downtown investment, future water supply, a future Police facility, support of
Gallatin College, and those that take part in the Community. Mayor Becker stated that he will not
be running for Mayor in the next term cycle and thanked everyone for allowing him to serve the
community.
0:44:13 H. Action Items
0:44:14 1. The Knoll at Baxter West Preliminary Plat Application P-12014, located
northeast of the intersection of Baxter Lane and Harper Puckett Road, north of Baxter
Meadows Subdivision, Phase 3B and west of Chief Joseph Middle School (Skelton) (Quasi
Judicial)
0:45:07 Dave Skelton, Sr. Planner
Mr. Skelton gave the Staff presentation regarding The Knoll at Baxter West Preliminary Plat
Application P-12014, located northeast of the intersection of Baxter T,ane and Harper Puckett
Road, north of Baxter Meadows Subdivision, Phase 3B and west of Chief Joseph Middle School,
Page 2 of 8
Minutes of the Bozeman City Commission Meeting,March 25,2013
1-18:59 Commission Questions for Staff
The Commission and Staff discussed the block length requirements, the topography of the area,
the trail in the area, park allotment areas, the roads and streets in the area including intersections
near the school, collector standards, street names, variances and the block standards, alley loaded
lots, deviations, storm water locations,park credits, restricted size lots, driveway areas and
setbacks, accessibility to Park Land, cascading development, waivers of SIDs, park land
requirement deviations and the transportation corridor and the alley loaded lots.
2-.04:23 Applicant Presentation
Applicant representative Trina Wolf gave the applicant presentation for the Knoll at Baxter West
Preliminary Plat Application P-12014, located northeast of the intersection of Baxter Lane and
Harper Puckett Road, north of Baxter Meadows Subdivision, Phase 3B and west of Chief Joseph
Middle School.
2:14:54 Commission Questions for Applicant
The Commission and Applicant spoke regarding right of ways and streets,the park and phase 3
of the project.
2:18:28 Applicant Presentation continued
Applicant representative Dave Crawford continued the Applicant presentation. He spoke
regarding connectivity, deviations, design of the streets and confusion of names.
2:27:47 Public Comment
Mayor Becker opened public comment.
2:28:04 EJHook, Public Comment
Mr. Hook stated that he lives south of the project and emphasized that infrastructure needs to be
addressed on the front end of this project.
2:31:52 Teresa Pool
Public Comment
Ms. Pool of 2375 Lasso Ave stated that the infrastructure part is not being done well and
encouraged the Commission to look more at infrastructure,
2:35:38 Public Comment closed
Mayor Becker closed public comment.
2:35:44 Applicant rebuttal
The Applicant representative spoke regarding the concerns of developers walking away and
proposed to bond Harper Puckett road. She also spoke regarding the name of the subdivision.
2:37:48 Motion'that having reviewed application materials, considered public comment,
and the staff analysis, I hereby adopt the findings presented in the staff report for
application P-12014 and move to approve the requested variances to the following sections,
of Chapter 38 of the Bozeman Municipal Code: 1) Section 38.23.040.B "Block Length" to
Page 3 of 8
Minutes of the Bozeman City Commission Meeting,March 25,20,13
exceed the maximum block length of 400 feet for Blocks 9, 10, 11, 14 and 18, and 2) Section
38.23.040.0 "Block Width" to allow block widths to be less than 200 feet in width for
Blocks 9, 14, and 18. It was moved by Cr. Mehl , seconded by Cr. Taylor that Having
reviewed application materials, considered public comment, and the staff analysis, I hereby
adopt the findings presented in the staff report for application P-12014 and move to
approve the requested variances to the following sections of Chapter 38 of the Bozeman
Municipal Code: 1) Section 38.23.040.B "'Block Length" to exceed the maximum block
length of 400 feet for Blocks 9, 10, 11, 14 and 18, and 2) Section 38.23.040.0 "Block Width"
to allow block widths to be less than 200 feet in width for Blocks 9, 14, and 18.
2:39.12 Commission Discussion
The Commission discussed the topography and the trail connection,the adjoining property and
design concerns, alleys and the size of lots, hardships and block widths.
2:50:34 Vote on the Motion that having reviewed application materials, considered public
comment, and the staff analysis, I hereby adopt the findings presented in the staff report
for application P-12014 and move to approve the requested variances, to the following
sections of Chapter 38 of the Bozeman Municipal Code: 1) Section 38.23.040.B "Block
Length" to exceed the maximum block length of 400 feet for Blocks 9, 10, 11, 14 and 18,
and 2) Section 38.23.040.0 "Block Width" to allow block widths to be less than 200 feet in
width for Blocks 9, 14, and 18.
Those voting Ale being Crs. Mehl, Taylor, Deputy M;k or Krauss and Mayor Becker.
y
Those voting No being none.
The motion passed.4-0.
2:51:12 Motion'that having reviewed application materials, considered public comment,
and the staff analysis, I hereby adopt the findings presented in the staff report for
application P-12014 and move to approve the preliminary plat application for The Knoll at
Baxter West Subdivision authorizing to subdivide 26.314 acres and create 65 residential,
single household lots and the remaining area as open spaces, trails and streets subject to
the conditions, as listed in Planning Board Resolution P-12014.
It was moved by Cr. Mehl , seconded by Cr. Taylor that Having reviewed application
materials, considered public comment, and the staff analysis, I hereby adopt the findings
resented in the staff report forapplication P-12014 and move to approve the prelimin
plat application for The Knoll at Baxter West Subdivision authorizing to subdivide 26.314
acres and create 65 residential, single household lots and the remainin f! area as open
spaces, trails and streets subject to the conditions, as listed in Planning Board Resolution
P-12014.
Page 4 of 8
Minutes of the Bozeman City Commission Meeting,March 25,2013
2:52:28 Amendment to the Motion to add a condition of subdivision approval that the
developer, bond their share of construction costs of Harper Puckett road with the added
Clarification to the condition that the construction of Harper Puckett be bonded prior to final
plot of the firstphase (instead of last phase) or when the road be built ( 'it is build early).
It was moved by Deputy M# or Krauss, seconded by Cr Mehl to add a condition of
subdivision approval that the developer, bond their share of construction costs-of.Harper
Puckett road with the added clan f -e construction of Harper
(cation that the condition that th
Puckett be bonded prior to final Plat of the Cirrst hale instead oL last hase) or when the road
--E
be built Cif it is build early),
2:52.51 Discussion on the Main Motion as amended.
The Commission discussed the roads and the developer's willingness to step forward,protecting
the public interest and access, to schools.
3:00:53 Vote on the Amendment to the Motion to add a condition of subdivision approval
that the developer, bond their share of construction costs of Harper Puckett road with the
added clarification that the condition that the construction of Harper Puckett be bonded prior
to final plat of the first phase (instead of last phase) or when the road be built(if it is build
early).
Those voting Ave being lie lK Mayor Kraus_sCrs. Mehl, TgIlor and Mayor Becker.
Those votime No being none.
The motion passed 4-0.
3:01:13 Continued Commission discussion
The Commission discussed the alley loaded lots,
3:07:12 Vote on the Main Motion as amended to that having reviewed application
materials, considered public comment, and the staff analysis, I hereby adopt the findings
presented in the staff report for application P-12014 and move to approve the preliminary
plat application for The Knoll at Baxter West Subdivision authorizing to subdivide 26.314
acres and create 65 residential, single household lots and the remaining area as open
spaces, trails and streets subject to the conditions, as listed in Planning Board Resolution
P-12014.
Those voting Aye beinyCrs. Mehl, Taylor, Deputy Mayor Krauss and Major Becker.
Those voting No being,none.
The motion passed 4-0�.
3:07:53 Break
Mayor Becker declared a break.
Page 5 of 8
Minutes of the Bozeman City Commission Meeting,March 25,2013
3:26:51 Meeting called back to order.
Mayor Becker called the meeting back to order.
3:27:012. The Crossing at Baxter Meadows, Phase 4B-41 Preliminary Plat Application
P-12017, located southwest of the intersection of Baxter Lane and Davis Lane, north of Fire
Substation 3 and east of the Gallatin County Regional Park (Skelton) (Quasi Judicial)
3:27:25 Dave Skelton, Sr. Planner
Mr. Skelton gave the staff presentation regarding The Crossing at Baxter Meadows, Phase 413-41
Preliminary Plat Application P-12017, located southwest of the intersection of Baxter Lane and
Davis Lane, north of Fire Substation 3 and east of the Gallatin County Regional Park,
3:38:05 Commission questions for Staff
The Commission and Staff discussed the different phases of the subdivision, credits, green space,
block width, parking, maintenance and upkeep of the subdivision parks and open space corridors.
3.54.51 Applicant Presentation
Applicant representative Susan Riggs of Intrensik Architecture gave the staff presentation
regarding The Crossing at Baxter Meadows, Phase 4B-41 Preliminary Plat Application P-1201'7,
located southwest of the intersection of Baxter Lane and Davis Lane, north of Fire Substation 3
and cast of the Gallatin County Regional Park.
3:58:20 Questions for applicant
The Commission and applicant discussed waiving requirements, the neighborhood center, the
block length concerns along Davis,
4:01:21 Public Comment
Mayor Becker opened public comment.
No person commented.
Mayor Becker closed public comment.
4:01:38 Motion that having reviewed application materials, considered public comment,
and the staff analysis, I hereby adopt the findings presented in the staff report and move to
approve the requested variances to the following sections of Chapter 38 of the Bozeman
Municipal Code: 1) from Section 38.23.040.B "Block Length" to exceed the maximum
block length of 400 feet for Blocks 2, 4, 6, 7, 8 and Block 10, and 2) from Section
38.23.040.0 "Block Width" to allow block widths less than 200 feet or more than 400 feet
in width for Blocks 2, 8, 9 and 10. '
It was moved by Cr. Taylor seconded by Deputy M21or Krauss that having reviewed
application materials, considered public comment, and the staff analysis,I hereby adopt
the findings presented in the staff report and move to approve the requested variances to
the following sections of Chapter 38 of the Bozeman Municipal Code: 1) from Section
Page 6 of 8
Minutes of the Bozeman City Commission Meeting,March 25,2013
38.23.040.B "'Block Leneth""' to exceed the maximum block length of 400 feet for Blocks 2,
4, 6, 7, 8 and Block 10, and 2) from Section 38.23.040.+C "Block Width"' to allow block
widths less than 200 feet or,more than 400 feet in width for Blocks 2, 8, 9 and 10.
4:02:27 Commission discussion on the Motion
The Commission discussed the block along Davis Lane and pedestrian traffic,
4:02:29 Meeting extended to 10:1.5 p.m.
4:05:23 Vote on the Motion that having reviewed application materials, considered public
comment, .and the staff analysis, I hereby adopt the findings, presented in the staff report
and move to approve the requested variances to the following sections of Chapter 38 of the
Bozeman Municipal Code: 1) from Section 38.23.040.B "Block Length" to exceed the
maximum block length of 400 feet for Blocks 2, 4, 6, 7, 8 and Block 10, and 2) from Section
38.23.040.0 "Block Width" to allow blockwidths less than 200 feet or more than 400 feet
in width for Blocks 2, 8,9 and 10.
Those voting A Cr. Taylor, Denuly Ma or Krauss Becker.
Ae beinZ Cr. Mehl and May
Those voting No being none.
The motion passed 4-0.
4:05:47 Motion'that having reviewed application materials, considered public comment,
and the staff analysis, I hereby adopt the findings presented in the staff report and move to
approve the preliminary plat application for The Crossing at Baxter Meadows Subdivision,
Phase 4B-41 requested in application P-12017 authorizing to subdivide 36.94 acres and
create 95 residential, single household lots, one multi-household lot, and the remaining area
as open spaces, trails and streets subject to the conditions, as listed in Planning Board
Resolution P-12017.
It was moved by Cr. Taylor, seconded by Deputy Mayor Becker that having reviewed
application materials, considered public comment, and the staff analysis, I hereby ado
the findings presented in the staff report and move to approve the preliminary pl at
Application for The Crossing at Baxter Meadows Subdivision,Phase 4B-41 re nested in
application P-12017 authorizing to subdivide 36.94 acres and create 95 residential e sing
, I
household lots, one multi-household lot, and the remaining area as open spaces, trails and
streets subject to the condftions, as listed in Planning Board Resolution P-12017.
4:06:33 Discussion on the Motion
The Commission agreed that the motion incorporates the name change in Condition No. 3. The
Commission discussed the tree plantings and the park.
Page 7 of 8
Minutes of the Bozeman City Commission Meeting,March 25,2013
4:11:50 'Vote on the Motion that having reviewed application materials, considered public
comment, and the staff analysis, I hereby adopt the findings presented in the staff report
and move to approve the preliminary plat application for The Crossing at Baxter Meadows
Subdivision, Phase 413-41 requested in application P-12017 authorizing to subdivide 36.94
acres, and create 95 residential, single household lots, one multi-household lot, and the
remaining area as open spaces, trails and streets subject to the conditions, as listed in
Planning Board Resolution P-12017.
Those voting Aye.being_.Gr..Traylor, Deputy Mayor Krauss, Cr. Mehl and Mayor Becker.
Those voting No being none
The motion passed 4-0.
4:12:02 L FYI/Discussion
1. Meeting with UK Delegates
2. Cost share tree installation program began last week.
3. Summer Program Guide open and online
4. Birthday Cake for Deputy Mayor Krauss.
5. Building permit review explanation
4:21:41 J. Adjournment
Mayor Becker adjourned the meeting at 10:19 p.m.
o -
Sean A. Becker, Mayor
ATTEST.,,,,
Stacy U' -Mrk
/Sean A. Be
P,
PREPARED y,-
MAI
Stacy M
ma-9 C, City Clerk
(
Approved on 1112JU--A)
J
Page 8 of 8