HomeMy WebLinkAboutBuilding Division Report for Quarter ending March 31, 2013Page | 1 ` Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Bob Risk, Chief Building Official Wendy Thomas, Director of Community Development SUBJECT: Building Division 3rd Quarter FY13 Update January 1, 2013 – March 31, 2013 MEETING DATE: May 6, 2013 AGENDA ITEM TYPE: Consent RECOMMENDATION: Accept this report detailing the financial and workload position of the Building Division for the quarter ending March 31, 2013. BACKGROUND: To keep the City Commission and the City Administration informed regarding the Building Division revenues and workloads we committed to make quarterly reports regarding revenues, staffing levels and operating costs within the department. The following sections represent the FY13 3rd Quarter. A. REVENUE: Our total revenue for the 3rd quarter was $282,534. Third Quarter Monthly Revenues October $83,962 November $83,003 December $115,569 Average Monthly Revenues: $94,178 69 Page | 2 B. EXPENDITURES: Our total expenditures for the 3rd Quarter were $200,249. Third Quarter Expenditures October $68,648 November $67,612 December $63,989 Average Monthly Expenditures: $66,749 Building Division Revenue/Expenditure Comparison- FY13/FY12 FY 2013 0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 Revenues Expenditures FY 2012 0 20,000 40,000 60,000 80,000 100,000 120,000 140,000 Revenues Expenditures 70 Page | 3 3rd Quarter Budget Status - 75% of Year Lapsed, 25% Remains Budget Spent Amount Remaining Percent Remaining Personnel $731,428 ($517,302) $214,126 29.3% Operating $155,188 ($133,835) $21,353 13.8% CIP $100,000 - $100,000 - Total 986,616 ($651,137) $335,479 34.0 % C. CASH RESERVE: The Administrative Rules of Montana allow the building division to maintain a “cash reserve fund” derived from building permit fees provided that the reserve amount does not exceed the building division operating costs for a 12 month period. Our unadjusted estimate of the building division operating costs for FY13 was $986,616. At the beginning of the 3rd quarter the Building Inspection Fund Cash Reserve was $1,113,471. At the end of the 3rd quarter our Cash Reserve balance was $1,230,774. D. PERMIT ACTIVITY: Permits for New Construction, Tenant Improvements, Remodels, etc. Permit Type 1st QTR 2nd QTR 3rd QTR 4th QTR Yearly Totals Building 503 345 240 1088 Electrical 230 187 195 612 Plumb/Mech 314 274 282 870 Fire Systems 4 24 14 42 Demolition 12 10 7 29 Total Permits 1063 840 738 2641 E. NEW BUILDING VALUATION - Does Not Include Tenant Improvements, Remodels, etc. Occupancy Type 1st QTR 2nd QTR 3rd QTR 4th QTR Yearly Totals Commercial $19,349,625 $5,807,253 $5,459,075 $25,156,878 Residential $26,589,615 $28,640,461 $27,462,935 $55,230,076 Total $45,939,240 $34,447,714 $32,922,010 $113,308,964 71 Page | 4 F. PLAN REVIEW: Completed Plan Reviews. Permit Type 1st QTR 2nd QTR 3rd QTR 4th QTR Yearly Totals Commercial 184 129 126 439 Residential 251 243 221 715 Total 435 372 347 1154 G. BUILDING INSPECTION: Completed Building Inspections; Average Daily Inspections (per inspector) Standard 15 January 17.32 February 17.11 March 19.01 Average inspections per day for the quarter 17.81 The total number of completed inspections, to date, for FY13 equals 13,795 H. STAFFING: At this time, the Building Division staff consists of the Chief Building Official, 2 Plans Examiners, 5 Building Inspectors, 1 Fire Inspector, 1 Code Compliance Officer, 1 Building Project/Permit Coordinator and 1 Building Permit Technician. UNRESOLVED ISSUES: None. ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: Our monthly revenue for the 3rd Quarter averaged $94,178 per month and totaled $282,534 for the quarter. Our monthly expenditures for the 3rd quarter averaged $66,794 per month and totaled $200,249 for the quarter. The Building Division Reserve Fund balance at the end of the 3rd Quarter was $1,230,774. Attachments: None Report Compiled On: April 9, 2013 72