BEFORE THE BOZEMAN CITY COMMISSIONER
CITY OF BOZEMAN, MONTANA
IN THE MATTER OF THE APPLICATION OF ADVANCE FINDINGS OF FACT
TECHNOLOGY, INC., FOR PRELIMINARY SUBDIVISION AND ORDER
PLA T REVIEW OF A ONE-LOT MINOR SUBDIVISION
AND A REMAINING PARCEL OF LAND LOCATED IN
THE NORTHEAST ONE-QUARTER OF SECTION 14,
TOWNSHIP 2 SOUTH, RANGE 5 EAST, M..P.M., CITY OF
BOZEMAN, GALLA TIN COUNTY, MONTANA
PURSUANT to the Montana Subdivision and Platting Act, Section 76-3-101 through 76-3-
614, Montana Codes Annotated, and
FURTHER PURSUANT to Chapter 16 of the Bozeman Area Subdivision Regulations, the
Bozeman City Commission reviewed the proposed Preliminary Subdivision Plat for a one-lot minor
subdivision of Advance Technology Park Subdivision, Phase III, to create a 3. 19-acre business
park/commercial lot and a remaining parcel of land for further subdivision as submitted by the
applicant, together with the required supplementary plans and information, to determine if the
information submitted meets the requirements of the Bozeman Area Subdivision Regulations and the
Montana Subdivision and Platting Act.
It appeared to the City Commission that all parties wishing to appear and comment were given
the opportunity to do so, and as the City Commission was fully advised of all matters having come
before it regarding this application, makes the following Findings of Fact, as required:
FINDINGS OF FACT
I.
The application for preliminary plat review to create a one-lot 3. 19-acre parcel on land
located in the northeast one-quarter of Section 14, T2S, RSE, M.P.M., City of Bozeman, Gallatin
County, Montana, was made on July 30, 1999. An extension to the 3S-day review period was
requested by the applicant's representative, Morrison-Maierle, Inc., in order to schedule the
Preliminary Plat application before the City Commission at the earliest time possible.
II.
The subdivision, as proposed, will create one 3. 19-acre business park/commercial lot and a
remaining 57. 71-acre parcel ofland for further development. City standard streets with curb, gutter
and sidewalk will be constructed within sixty (60) foot wide dedicated public right-of-way currently
iij~.i~~'f<<bfud6ipidKlij]fuM#)..Mijiij~M:JI'i~t~nijQHjtt 1
.
exist along the east boundary of said one-lot minor subdivision. The proposed minor subdivision will
have future frontage on West Garfield Street and Technology Boulevard South with the next phase
of the subdivision.
There are no significant physical or topographical features, water courses or mature
vegetation existing on the property with exception of the watercourse that bisects the remaining
57. 71-acre parcel ofland to the west of the one-lot minor subdivision. No floodplain boundaries have
been identified on the subdivision. No dedication of park land is required with this minor subdivision.
111.
Finding that the subdivision was a second or subsequent minor subdivision created from a
tract of record as outlined in Section 16.12.030.C of the Bozeman Area Subdivision Regulations, an
informational meeting was scheduled before the City of Bozeman Planning Board and a public hearing
scheduled before the Bozeman City Commission.
The City of Bozeman Planning Office caused the subdivision submittal to be reviewed by the
Development Review Committee, and other applicable agencies and departments for review and
comment, per Section 16.12.040.B of the Subdivision Regulations. Those comments, along with
those of the City of Bozeman Planning Staff, were then incorporated into a preliminary Staff Report
which was forwarded to the City of Bozeman Planning Board for their consideration at their August
17, 1999 regular meeting.
IV.
The matter was considered by the City of Bozeman Planning Board at an informational
meeting on August 17, 1999. No members of the public spoke at the meeting and no written
comment was received. The Planning Board found that the application was properly submitted and
reviewed under the procedures of the Bozeman Area Subdivision Regulations and the Bozeman Area
Zoning Ordinance. The Planning Staff reviewed the report and discussed the master plan for future
development in phase three of the technology park, and the need to extend West Garfield Street and
Technology Boulevard South.
The applicant's representative, Tom Henesh, Morrison- Maierle, Inc., commented that review
by the Development Review Committee went well and was available to answer questions from the
Planning Board. As there was no questions of the applicant's representative, the Planning Board then
asked for public comment. Following three calls for public testimony and receiving no response the
&dt.ii~~,,:liiiijijWgy'.Jiitk~..M'ijij~:#j..*..I.ijijiij~.i.Jtakt..ijiji..Otdij.. z
. .
Planning Board closed the public portion of the informational meeting.
After considering the Planning Staff's staff report and reviewing the application against the
applicable review criteria established by Statute, the Planning Board voted on a motion regarding the
subdivision. The motion, to recommend approval of this subdivision as shown on the submitted
Preliminary Plat, and with the conditions recommended by Staff, passed on a unanimous vote of 4
for and 0 in opposition.
V.
The preliminary plat application was considered by the Bozeman City Commission at their
regular scheduled meeting on September 7, 1999, at which time the recommendation ofthe
Planning Board was considered. The Planning Staff discussed the need for a public hearing for
the second or subsequent minor subdivision of a tract of record and reviewed the six public
interested criteria set forth by state statute.
The applicant's representative, Lowell Springer, Springer Group Architects, made a
presentation in favor of the requested one-lot minor subdivision, stating that they have reviewed
the recommended conditions of approval and concur with the conditions.
The City Commission then opened the hearing to the general public for testimony.
Following three calls for public testimony and receiving no response the City Commission closed
the public hearing.
VI.
The application was considered by the Bozeman City Commission and weighed against the
review criteria established by Statute, and found as follows:
1) EFFECTS ON AGRICULTURE:
The proposed business park/professional office lot is located in the Advanced Technology
Park Subdivision and is situated in phase three of the five-phased master plan for the
business park development. Although zoned and master planned for business park/high
tech development, the subject property has remained in agricultural activity until the
market justifies the installation and construction of infrastructure and transportation
facilities for the area. During the 1989 preliminary plat review of the Advanced
Technology Park Subdivision, Phase 1- Y, the City Commission determined that the
subdivision's proximity to existing urban development and non-agricultural land use
designation in the Comprehensive Plan would not ear-mark the property as an ideal
location for agricultural activity. As a result, the governing body determined that no
adverse effects on agriculture would result from development of the Advanced
Technology Park Subdivision. This determination should also apply to the one-lot minor
subdivision.
i.itiiti'.l'ib~mgyp._~lilt#)2Eiiiji~i$M'itiijdOtdit )
2) EFFECTS ON AGRICULTURAL WATER USER FACILITIES:
A designated stream/ditch bisects the remaining parcel ofland running south to north, but
is not effected by the proposed one-lot minor. The applicant does not propose any
relocation, alterations or construction in the area of the watercourse, and should not
interfere with downstream water user facilities.
(3) EFFECTS ON LOCAL SERVICES:
Emereency Services
As the property located in the corporate limits of the City of Bozeman, police and fire
protection will be available to this site. The Bozeman Fire Department has commented
that the department is capable of adequately protecting the one-lot minor subdivision,
assuming the proper roadways and water supply are installed and maintained. Both the
police department and ambulance service commented during preliminary plat review of the
Advanced Technology Park Subdivision that they would be capable of providing
emergency services to the site.
WaterlSewer
Access to municipal infrastructure is currently available as water and sewer mains, and
service stubs, exist in the adjoining public right-of-way for Research Drive. The D.R.C.
reported that extension of infrastructure is not necessary with development of the
proposed one-lot subdivision. However, further subdivision and development of phase
three will require installation of municipal infrastructure and construction of public streets.
An on-site fire hydrant may be necessary with development of the subject property and
will be determined by the Fire Marshall during site plan review for any specific
development proposal for the site.
Streets
The proposed one-lot minor subdivision currently has street frontage along the existing
public street, Research Drive. As a result, the D.R.C. determined that the need for
additional construction of public streets is not necessary with this subdivision. However,
future subdivision and development of the tech park's phase three will require the
extension of Technology Boulevard and West Garfield Street, and may require the
construction of Professional Drive to complete an interior looped vehicular system within
the subdivision.
Only the north half of the right-of-way, or 32.5 feet, for West Garfield Street will be
dedicated with this subdivision. As a result, no direct access to the one-lot minor from
West Garfield Street will be allowed until such time that the full 65-foot right-of-way
adjacent to the lot is dedicated and the street is fully constructed to a City standard street.
The City Engineer's Office also commented that Technology Boulevard South is not
currently dedicated to the west of Research Drive and should not be depicted as shown on
the final plat.
Storm Water
As there are no storm water runoff facilities in the area of the proposed subdivision, a
storm water master plan for the Advanced Technology Park Subdivision was been
designed by the applicant's consultant that involves the placement of on-site detention
ponds on each individual lot. The storm water plan is designed to remove solids, silt, oils,
grease and other pollutants from the runoff from of private and public streets, as well as all
subdivision lots. The plan also involves storm water discharge from the detention ponds
into the stream/ditch located to the west of the one-lot minor subdivision via a swale along
the future extension of Technology Boulevard. This will require the need for a drainage
easement on the final plat, as well as approval from M.D.E.Q. to discharge the runoff into
$itjijti'fib~i~l,ijtiMdiijt'J~Eii4jijiMjfidijijiitdit 4.
. .
the stream/ditch.
4) EFFECTS ON NATURAL ENVIRONMENT
The proposed subdivision consists of relatively flat pasture lands with no significant out
croppings, topographical or physical features. Thus, the historical use of the property for
agricultural activity has limited the potential for mature vegetation, bushes, or trees on the
site.
5) EFFECTS ON WILDLIFE AND WILDLIFE HABITAT
Because the area in question has historically been used for the cultivating of agricultural
crops and pasture prior to the tech park proposal, and no substantial amounts of mature
vegetation, bushes or trees exist on the property in question, no evidence of wildlife or
wildlife habitant have been identified. Therefore, no effects on wildlife and their habitat
should occur as a result of the proposed subdivision.
6) EFFECTS ON PUBLIC HEALTH AND SAFETY
The Bozeman Development Review Committee and other applicable review agencies
evaluated the preliminary plat application to create the business park lot, and as result did
not identify any significant impacts to the area's public health and safety. The conditions
of Preliminary Plat approval recommended by the Development Review Committee are
provided in this staff report for consideration by the Planning Board and City Commission,
as a means to mitigate any potential impacts to the community that may have been
identified with this minor subdivision and ensure that no effects on public health and safety
will result from development of said property.
76-3-608.3.b.M.C.A.
All subdivision proposals must also be reviewed for the criteria listed in 76-3-608.3.b-d,
M.C.A., 1995 regardless of compliance with master plan status. As a result, the Planning Office
has reviewed this application against the listed criteria and further provides the following summary
review:
(i) - Compliance with survey requirements provided in Part 4 of the Montana
Subdivision and Platting Act.
The proposed minor subdivision appears to have complied with the survey
requirements in Part 4 of the Montana Subdivision and Platting Act and will be
filed in the Gallatin County Clerk & Recorder's Office with Final Plat review and
approval.
(ii) - Compliance with the local subdivision regulations provided for in Part 5 of the
Montana Subdivision and Platting Act.
The proposed minor subdivision is in general compliance with the Bozeman Area
Subdivision Regulations based on the recommended conditions provided by the
Bozeman Development Review Committee.
(iii) - Compliance with the local subdivision review procedures.
The application is in general compliance with the subdivision review procedures
for a minor subdivision established in the Bozeman Subdivision Regulations for a
second or subsequent minor subdivision created from a tract of record. Based on
the recommendation of the D.R.C. and other applicable review agencies, the
Bozeman Planning Board reviewed the proposed minor subdivision on August 17,
1999, and has forwarded a recommendation of conditional approval to the
Bozeman City Commission.
Adjiit~'t~b~Wliitk~lm~~#~%jt~iijbii$ij(i~tijijdnta~j. {;
. .
76-3-608.3.c. M.C.A.
(c) ~ Provision for easements for the location and installation of any planned utilities.
All easements shall be delineated and noted accordingly on the Final Plat and the
appropriate certificate on the plat granting the use of the easements to the
necessary entities. The Development Review Committee recommended a
condition of Preliminary Plat approval that requires the applicant to clearly identify
all applicable easements on the Final Plat. All new utilities (i.e., electricity, gas,
telephone, cable) will be installed underground.
76-3-608.3.d. M.C.A.
(d) - Provisions of legal and physical access to each parcel.
Legal and physical access to this application for Preliminary Plat review will occur
from Research Drive, a City standard public street. The City Engineer's Office has
stipulated that no direct access onto West Garfield Street will occur until a full 65-
foot right-of-way is dedicated and West Garfield Street is constructed to a full City
standard street.
ORDER
The City Commission found that the proposed subdivision complies with the Bozeman Area
Master Plan, Bozeman Area Subdivision Regulations, and the Bozeman Zoning Ordinance, if certain
conditions were imposed.
IT IS HEREBY ORDERED that the Preliminary Plat of StoneRidge Planned Unit
Development, Minor Subdivision #2 for Cape/France Enterprises be therefore approved, subject to
the following conditions:
1. That no access to this lot from the partially dedicated (32.5') Garfield Street will be allowed
until the full 65' right-of-way adjacent to this lot is dedicated and the street is fully
constructed. The fu1l6S' right-of-way and construction of Garfield will be required with any
future phases of the Advanced Technology Park. Similarly, no access will be allowed to this
lot from Technology Boulevard South until the right-of-way adjacent to this lot is dedicated
and the street is fully constructed. It is recommended that a statement to this effect be
required on the final plat.
2. Technology Boulevard South is not currently dedicated to the west of Research Drive and
should not be shown as such on the final plat.
3. The location of existing water and sewer mains shall be properly depicted on a supplemental
document attached to plat, not on the Final Plat, for review and approval by the City
Engineer's Office. The plat submitted does not accurately depict the existing mains.
4. The Montana Fish, Wildlife and Parks, SCS, Montana Department of Environmental Quality
and Army Corps of Engineer's shall be contacted regarding the proposed project and any
required permits (i. e., 310, 404, Turbidity exemption, etc.) shall be obtained prior to Final Plat
approval.
5. Easements shall be provided on the lot in accordance with section 16.14.050B. of the
Bozeman Area Subdivision Regulations. Utility easements, a minimum of twenty (20) feet
wide, situated on side and rear property lines for all subdivision lots, shall be depicted on the
&ij~.ijt~.'J'ihfu)i~l:jil~M~ijijt,j+Emdirii,M..~l1iijidJitdit ~
.
. .
Final Plat for review and approval by the Planning Office prior to Final Plat approval, unless
all utility agencies provide written documentation that said utility easements are not
necessary .
6. The drainage master plan for the original Advanced Technology Park called for the discharge
from the storm water detention pond for this lot be directed to the west through an easement
to the ditch. This easement shall be provided with the final plat for this subdivision, and any
subsequent development on the lot will be required to construct a swale to direct the storm
water from the lot to the ditch. Final siting and sizing for the storm drain pond for this lot will
occur with the final site plan for any development on this lot.
7. That the Final Plat shall comply with Section 16.10.030 of the Bozeman Area Subdivision
Regulations, and shall include all appropriate documents, certificates, and be accompanied by
all appropriate documents, including a Platting Certificate. Two mylar and two clothback
copies of the Final Plat must be submitted for Final Plat approval, along with a digital copy
of the Final Plat, on a double sided, high-density 3 1/2" floppy disk.
8. That the applicant obtain Montana Department of Health and Environmental Sciences
approval ofthe subdivision prior to Final Plat approval pursuant to Section 16.16. 101 through
16.16.805. A.R.M.
9. That all wetlands located within the boundaries of said property be identified on the Final Plat
for review and approval by the City Engineer's Office and Army Corps of Engineers prior to
Final Plat approval.
10. That the applicant provide a written narrative stating that the proposed subdivision will not
interfere with any agricultural water user facilities and that no irrigation ditches for
downstream water rights currently exist on said property for review and approval by the
Planning Office prior to Final Plat approval.
11. That the developer shall enter into an Improvements Agreement with the City of Bozeman
guaranteeing the completion of all improvements in accordance with the Preliminary Plat
submittal information and conditions of approval. If the Final Plat is filed prior to installation
of all improvements, the developer shall supply the City of Bozeman with an acceptable
method of security equal to one hundred fifty (150) percent of the cost of the remaining
improvements.
12. That the developer shall have three (3) years from the date of preliminary plat approval to
complete the conditions of Preliminary Plat approval and apply for Final Plat approval.
13. That the applicant submit with the application for Final Plat review a written narrative stating
how each of the above conditions of preliminary plat approval have been satisfactorily
addressed.
DATED this 20th day of December ,1999.
BOZEMAN CITY COMMISSION
By ~;;:)~
Marcia Youngman, Mayor
&ifiittdWi~bi~lly,~ijtk~lmij..#;j+iiidiii$,m,::ii~iid6rtml' .,
.. ..-.---- . ...--...-.-----
.
. . .
ATTEST:
(J~;/ ~
Robin Sullivan
Clerk ofthe Commission