HomeMy WebLinkAbout13- Change Order No. 11 Williams Brother Construction for Bozeman WRF Phase 1 Improvements CHANGE ORDER
pit r,istt ,`w�
No. „....._. 11
LATE OF ISSUANCE EFFECTIVE DATE
OWNER City of Bozeman Williams Brother Construction, LLC
Contract: Bozen art WRF"Phase 1 Improveinegts
Project: Bozeman Water Reclamation F'acili j�= OWNER`s Contract No. SRF C303105-01
n__.... ENGINEER°s Contract No _ , .._..n0..60746
You are directed to make the following changes in the Contract Documents.:
Description: Reconcile unit price items and changes as described in the Change Order No. I 1 Summary..
Reason for Change Order: Reconcile contract amount..
Attachments: Change Order No, I I Summary with referenced attachments.
CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES:
Original Contract Price Original Contract Times:
36.362,233.00 Substantial Completion: October 5,2011
_ Ready for final payment: January 8,*2012
(days or dates
Net Increase(Decrease)from previous Change Net change from previous Change Orders No._0 to
Orders No. 0 to 10 No. 10
5;9,061.90 Substantial Completion: 233 ____.. _
—_ _ Ready for final payment: 233 _
da s
Contract Price prior to this Change Order: Contract Times prior to this Change Order:
Substantial Completion: _May 2S 2Q1.2
$36, 901,291.90 Ready for final payment: August 28,2012. -
da's or dates .
Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order:.
Substantial Completion:. 0
$,(232,241.00) � � _ Ready for final payment: 0
(days)
Contract Price with all approved Change Orders., Contract Times with all approved Change Orders:
$ 36,669,050.90 Substantial Completion: May Z5,2012
Ready for final paytnoit: Ati_:.gust282012
(days or dates)
Contractor certifies and agrees that there are no additional costs or claims for extra work,additional time, delays or
omitted items,of any nature whatsoever,associated with the subject change order items,except as identified and set
forth herein and unless expressly stated otherwise in the Change Order. And further,that the price agreed-upon herein
represents the cost and value for the subject work performed and the materials supplied under the terms of the
Contract an a h worl�quantities and value were properly determined and are correct.
TOR(Authorized Signature) Date
RECOMMENDED BY., A OVER
GINEER-Signature) Date C3W NER(Authorized Signature) Date
E.ICDC 1910-8-B (1996 Edition
Prepared by the Engineers Joint Contract Docunsents Committee and endorsed by'rhe Associated General Contractors of America and the
Construction Specifications Institute.
Change Order No. 11 Summary
Bozeman Water Reclamation Facility, Phase 1 Improvements
Summary
This change order balances the unit price pay items and previous change orders in order to
make the final contract amount match the final pay amount. The total amount of the change
results in a deduction of$232,241,00.
1. Asphalt Pay Item
This item was a unit price item in the original contract. The actual quantity of asphalt
increased from 19,717 square yards to 21,355 square yards. Based on the contract
price of$12.50 per square yard this increase the contract amount by$20,475,00,
2, Change Order No, 4
Change Order No, 4 included an estimated amount for increased wages due to a
change in wage rate requirements dictated by the funding agency. The amount of the
original change order was $300,000 and the actual amount spent was $47,284. This
results in a decrease in the contract amount of$252,716.
End
N:210540541Construction Docs\Chan9e Orders=11\Change Order 11 Summary,dom