SWIM CENTER NATATORIUM HVAC IMPROVEMENTS
PRE-BID CONFERENCE MEETING MINUTES
March 31, 2009
Introduction and Attendees
Project Scope
A. Owner: City of Bozeman. Compliance with State Laws in
Instruction to Bidders.
B. Project Description & Layout: Demo of existing and new work.
Morrison-Maierle described the general layout of the work to be
performed as shown in the contract drawings.
Instruction to Bidders
A. Opening: Monday, April 13, 2009, 2:00 PM local time, at the office
of the City Clerk, City Hall, 121 North Rouse, Bozeman, MT.
B. Instruction To Bidders (Section 00200) items:
Submittal of Bid: Bound Copy
Bozeman Business License required prior to award.
The question was asked if submittals for specified equipment
will be required in the event that the named product is provided.
Submittal requirements will be clarified in Addendum No. 1.
The question was asked about deadline for substitute
equipment submittals. In the meeting, the response was that
substitution requests are required 10 days prior to bid opening.
(However, upon closer inspection of the project specifications it
appears that Article 11 of Section 00200 states that the deadline
for submittals of pre-approved equipment substitutions is 5 days
prior to bid date. Addendum No. 1 revises that language to
correctly indicate 10 days prior to bid date. Therefore, submit
substitute items to Engineer by Friday, April 3, 2009. Bidders
please note that if there are items approved as equal, that there
could be an addendum issued as late as April 8, 2009.)
MPWSS (Fifth Edition, 2003 & 2006 Addendum) & COB Mods
to MPW (2004) apply for sitework to be performed.
Article 31 & 32 provide for payment time frames: 30 days from
submittal & 14 days from approval.
The question was asked by when questions for Addendum need
to be submitted. Article 7 of Section 00200 states that all
questions that are submitted to the Engineer 10 days prior to bid
opening (by Friday, April 3, 2009) will be answered in an
addendum. Questions submitted after this time may not be
answered. However, any additional questions received after
Page 2 of 4
April 3 that have been answered by the Engineer will be
included on the final Addendum.
Bid Form
A. Critical issues
Acknowledge Addenda on bid form and submit signed copy of
Addenda with bid.
Contractor & Subcontractors MT Registration No. required.
Complete, Sign & submit
1. Non-Collusion Affidavit
2. Certification of Non-Segregated Facilities
3. “Information Required of Bidders” must submit w/in 3
working days of Bid Opening.
Bid all Items in Schedule – Single Contract Award only.
No Additive Alternates
10% Bid Bonds
Bid Form: Lump Sum with schedule of values breakdown
following award.
Contract Time:
1. 63 calendar days - Substantial Completion;
2. 74 calendar days - Final Completion
Contract Time is very important due to working around Swim
Center Events schedule; Engineer will work with successful
bidder to provide quick turnaround time on submittal packages
to expedite materials ordering
Liquidated Damages:
1. $500/day - Substantial Completion
2. $500 /day - Final Completion
3. Plus Engineering costs incurred
The question was asked when equipment can be ordered.
Equipment ordering will be authorized when the contractor has
a set of shop drawings approved by the Engineer and a Notice
to Proceed issued by the Owner.
A request for clarification was made on the term “maintenance”
for 2-year warranty as listed in Note 14 on sheet G-1 of the
project drawings. That clarification will be addressed in
Addendum No. 1.
General Conditions & Supplementary Conditions (Sections 00700 &
00810)
Review thoroughly. Note: Insurance requirements
Contractor to apply for commercial building permit and pay for
the permit cost; Owner has submitted plan review and will pay
that fee
Based on the testing indicated in the Supplementary Conditions,
it is not expected that asbestos or other hazardous materials will
be encountered when dealing with existing elements within the
building. If materials suspected of containing hazardous
Page 3 of 4
materials are encountered, do not disturb; immediately notify the
Engineer and Owner. Owner will remove hazardous materials
under a separate contract. See attached Report titled “Asbestos
Report, Bozeman Swim Center Natatorium HVAC System
Improvements.”
Labor Standards
A. State Wage Rates apply
Weekly payrolls
Prime Contractor Responsible
Technical Provisions:
A. Summary of Work (Section 01 1000)
General scheduling issues
Boundaries of Work: See Sheet G-1 for construction activity
limits and site access limits
Maintain site access at all times- FIRE LANE, fire hydrant in
rear.
Parking in Swim Center lot only, keep pedestrian access clear.
Contractor to supply waste dumpster, locate in Swim Center
parking lot.
Underground & aboveground facilities- locates required prior to
any excavation work.
Access to interior of building: May 18, 2009. Existing HVAC
system to remain intact and functional prior to that date.
Staging/pre-fab OK.
Concurrent work:
1. Pool to be drained by Owner starting May 18, may take 3
days to complete. Possible training of Fire Dept. personnel
shall expedite.
2. VGB Federal Mandate: Drain work to be performed
beginning May 18 under a separate contract- see 1.6.B.1 for
work description. The minimum amount of water required to
submerge the newly completed work will need to be
replaced in deep end immediately following that work for
plaster curing.
3. Electrical service upgrade: Northwestern Energy to perform,
Owner to pay costs, Contractor to coordinate and schedule
with his/her work. NWE has project set up and has started
design.
B. Temporary Facilities and Controls (Section 01 5000)
Provide Construction fencing to keep unauthorized personnel
out of staging and construction areas
Use of Swim Center’s toilets acceptable provided they are
cleaned and maintained in a condition acceptable to Owner
Electricity available from Owner’s existing electrical service
Page 4 of 4
C. Closeout Procedures (Section 01 7700)
One year warranty walk-through with Owner required, contractor
responsibility to schedule
Two year warranty on maintenance/repairs to the HVAC system
and related components.
Other Items to Note:
A. School ends June 10. Students will need pedestrian access to the
rear of the high school adjacent to the air handler location.
B. Owner would like recycling of removed equipment wherever
possible and practical as opposed to landfilling significant
equipment.
C. Protect pool deck and pool shell while working on or over these
surfaces. Damage to the pool deck or the pool shell will be repaired
at the Contractor’s expense.
Updated Plan Holders List
Additional Discussion Items:
Questions about paint touchup responsibilities of the Contractor
were brought up during the walk-through. This will be addressed
in Addendum No. 1.
It was asked who installed and services the existing Swim
Center fire alarm system: It was installed and is serviced by Fire
Suppression Systems, 2171 Industrial Drive, Bozeman, MT
59715, 586-9510.
A question was raised as to where recycling proceeds from
removed equipment on the project will be directed: The
proceeds from recycling existing mechanical equipment that is
to be removed shall be kept by the Contractor.
It was asked what the project budget was for this project, to be
used for bonding purposes: The engineer’s estimate of project
cost for bonding purposes is $180,290.
Site Tour:
A walk-through of the site was conducted for interested
contractors to evaluate site conditions and see where work is to
be performed. Other parties interested in an additional walk-
through may contact the Engineer, Morrison-Maierle, Inc., at
406-587-0721.