HomeMy WebLinkAboutAdoption of the Water Fund Capital Improvement Pla_13.pdf
Commission Memorandum
REPORT TO: Honorable Mayor and City Commission
FROM: Chris Kukulski, City Manager
Anna Rosenberry, Finance Director
SUBJECT: Adoption of the Water Fund Capital Improvement Plan (CIP) for
FY14-18.
AGENDA ITEM TYPE: Action
MEETING DATE: November 26, 2012
RECOMMENDATION: Adoption of the Water Fund Capital Improvement Plan (CIP)
for FY14-18.
BACKGROUND: Each year, the City Manager is required to prepare a 5 Year Capital
Improvements Plan and submit it to the Commission by December 15th. Staff met in November
to develop the attached draft schedules.
The Water Fund CIP tracks the capital equipment replacements and construction projects for
Water Operations (distribution system) and the Water Treatment Plant. By FY 13 we have
budgeted for the entire Water Plant renovation, so FY14 and years beyond do not contain any
costs associated with that upgrade.
These levels of capital expenditure are in line with our adopted rate models.
UNRESOLVED ISSUES: None.
312
ALTERNATIVES: As suggested by the City Commission. If the Commission is does
not wish to adopt this schedule tonight, it can be scheduled for approval on a later agenda.
FISCAL EFFECTS: This step in the process has no fiscal effect. Once adopted, the
Capital Improvements Plan becomes the basis of the City Manager’s Recommended Budget for
FY14.
Report compiled on: November 19, 2012
Attached: Water Fund CIP
313
Water FundCapital Improvement PlanFinancial Summary Current YearFY13 FY14 FY15 FY16 FY17 FY18UnscheduledProjected Beginning Reserve Balance Dedicated to CIP 3,375,761$ 2,418,979$ 3,002,022$ 3,639,796$ 4,547,666$ 5,373,316$ ‐$ Plus: Water Revenues Dedicated to CIP 1,664,792$ 1,739,708$ 1,817,995$ 1,899,804$ 1,985,296$ 2,064,707$ ‐$ Plus: WTP Loan Proceeds 8,500,000$ Less: Scheduled CIP Project Costs (11,121,574)$ (1,156,665)$ (1,180,220)$ (991,935)$ (1,159,645)$ (974,950)$ ‐$ Projected Year‐End Cash Dedicated to CIP 2,418,979$ 3,002,022$ 3,639,796$ 4,547,666$ 5,373,316$ 6,463,074$ ‐$ Assumptions Made for Revenue Estimates: Current YearFY13 FY14 FY15 FY16 FY17 FY18Estimated Annual Water Revenues 6,372,410$ 6,659,168$ 6,958,831$ 7,271,978$ 7,599,217$ 7,941,182$ Estimated Annual Increase 4.5% 4.5% 4.5% 4.5% 4.5% 4%Total Estimated Revenues 6,659,168$ 6,958,831$ 7,271,978$ 7,599,217$ 7,941,182$ 8,258,830$ Current Revenues Dedicated to CIP % 25.0% 25.0% 25.0% 25.0% 25.0% 25.0% Plus: Increase Dedicated to CIP 0.0% 0.0% 0.0% 0.0% 0.0% 0.0% Total % Dedicated to CIP 25.0% 25.0% 25.0% 25.0% 25.0% 25.0%TtlEti tdRDdi tdtCIP1 664 792$1 739 708$1 817 995$1 899 804$1 985 296$2 064 707$ProjectedProjectedTotal Estimated Revenues Dedicated to CIP1,664,792$ 1,739,708$ 1,817,995$ 1,899,804$ 1,985,296$ 2,064,707$ 1,400,0001,200,0001,000,000800,000600,000400,000200,0000Water Fund Projects & Equipment 314
CIP PROJECT FUNDPROJ.DEPARTMENPROJECT NAMEFY14FY16UnscheduledFY15FY17FY18Water FundPW01WATER OPSSHOPS FACILITY EXPANSION PLAN$10,000W03WATER OPSENGINEERING/DESIGN FOR ANNUAL WATER PIPE REPLACEMENT PROGRAM$22,500$22,500$22,500$22,500$22,500W04‐14WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2014$974,165W04‐15WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2015$1,147,720W04‐16WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2016$969,435W04‐17WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2017$1,097,145W04‐18WATER OPSWATER PIPE REPLACEMENT PROGRAM ‐ CONSTRUCTION IN 2018$952,450W24WATER OPSFIXED BASE METER READ SYSTEM$60,000W26WATER OPSINTERNAL PIPELINE ASSESSMENT OF THE SOURDOUGH 30” CONCRETE CYLINDER TREATED WATER MAIN$50,000W25WATER PLANTREPLACEMENT VEHICLE$40,000W27WATER PLANTRE‐ENGINEERING THE LYMAN TANK LINER$50,000Summary for Water Fund (11 items)Totals by year:$1,156,665 $1,180,220$991,935FY14FY15FY16UnscheduledFY18$974,950$1,159,645FY17315
CIP Project Fund
Water Fund
PROJECT NUMBER
PW01
DEPARTMENT
WATER OPS
PROJECT NAME
SHOPS FACILITY EXPANSION PLAN
FY14 FY15
$10,000
FY16 Unscheduled
DESCRIPTION OF PROJECT
The construction of the new Vehicle Maintenance Shop at the Lower Yards on Rouse Avenue in FY10/FY11 was Phase I in
expanding and improving our ability to service equipment, store vehicles, and provide work space for Public Works, Parks, and
Facilitiy services. Questions remain about the long-term plan for construction, location, and expansion for: Streets, Sign & Signal,
Forestry, Water/Sewer Operations, Solid Waste Collection & Recycling, Facilities, and Parks & Cemetery departments. This
project would develop a master plan. In scheduling this project, we are recommending waiting until after the Vehicle Maintenance
Division is relocated to its new shop and the interior improvements are made to the Shop at Rouse and Tamarack Street for the
remaining divisions.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
From related divisions: General Fund 20% ($10,000), Water Fund 20% ($10,000), Wastewater Fund 20% ($10,000), Street
Maintenance Fund 20% ($10,000), Solid Waste Fund 20% ($10,000).
New
Replacement
Equipment
Project
FY17 FY18
316
CIP Project Fund
Water Fund
PROJECT NUMBER
W03
DEPARTMENT
WATER OPS
PROJECT NAME
ENGINEERING/DESIGN for ANNUAL WATER PIPE REPLACEMENT PROGRAM
FY14
$22,500
FY15
$22,500
FY16
$22,500
Unscheduled
DESCRIPTION OF PROJECT
This item provides for design work to be completed every year, in anticipation of the Annual System Upgrades. As the Water
Operations Division operates the existing system, maintenance projects become apparent. Given our knowledge of system
conditions today, the following projects are candidates for design funding and were identified in the Facility Plan: 1. South 8th
Avenue , 2. Koch: Lindley to Bozeman, 3. Lindley: Olive to Koch, 4. S. Bozeman: Olive to Story As annual operations occur, other
more-urgent projects may be identified and designed under this project heading.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the design of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17
$22,500
FY18
$22,500
317
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-14
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2014
FY14
$974,165
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: N. Montana Ave: E. Lamme St - E. Peach St N. Montana Ave: E. Tamarack St - S. 34' N. Montana Ave: E. Peach
St - E. Tamarack St. The timing of these projects is based on our need to mill-overlay N. Montana Ave. Dell Place: Alderson Ct -
E. Story St. The water pipe segment of E. Story St: S. Tracy Ave - S. Church Ave will also be completed this year, in combination
with REC04- Story Street Reconstruction ($380,000 of this project total is for the E. Story water pipe). After budget approval
July 1, 2013, these projects would complete design, bid and begin construction in the Spring/Summer of 2014, at the end of FY14.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
318
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-15
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2015
FY14 FY15
$1,147,720
FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S. Grand Ave: W. Garfield St - W. College St S. Grand Ave: W College St - W. Main St. N. Rouse Ave: Bond -
Griffin (needs to be completed prior to MDOT Rouse project.) The timing of this project is critical to our need to mill-overlay S.
Grand Ave. After budget approval July 1, 2014, these projects would complete design, bid and begin construction in the
Spring/Summer of 2015, at the end of FY15.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
319
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-16
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2016
FY14 FY15 FY16
$969,435
Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S. Tracy Ave: W. Garfield St - E. Story St N. Willson Ave: W. Lamme St - W. Short St W. Babcock St: S. 10th
Ave - S. 8th Ave N. Montana Ave: E. Tamarack St - N End of Existing. After budget approval July 1, 2015, this project would
complete design, bid and begin construction in the Spring/Summer of 2016, at the end of FY16.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
320
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-17
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2017
FY14 FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: W Olive St: S. 5th Ave - S. 3rd Ave W. Olive St: S. 6th Ave - S. 5th Ave N. Grand Ave: W. Lamme St - W.
Peach St N. 5th Ave: W. Aspen St - W. Tamarack St S. 3rd Ave: W. Harrison Ave - W. Curtiss St. After budget approval July 1,
2016, this project would complete design, bid and begin construction in the Spring/Summer of 2017, at the end of FY17.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Annual Operating & Maintenance Costs: Incremental increases in general maintenance costs. Current cost estimate of $12,500
per water-main mile maintained annually.
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17
$1,097,145
FY18
321
CIP Project Fund
Water Fund
PROJECT NUMBER
W04-18
DEPARTMENT
WATER OPS
PROJECT NAME
WATER PIPE REPLACEMENT PROGRAM - Construction in 2018
FY14 FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
PROJECT AREA: S 6th Ave: W. Harrison Ave- W Olive S: W. Koch St: S Grand Ave.- S. Willson Ave: S. Willson Ave.: W.
College St- W. Koch St. After budget approval July 1, 2017, this project would complete design, bid and begin construction in
the Spring/Summer of 2018, at the end of FY18.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Provides for the construction of necessary water system maintenance work.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
$952,450
322
CIP Project Fund
Water Fund
PROJECT NUMBER
W24
DEPARTMENT
WATER OPS
PROJECT NAME
Fixed Base Meter Read System
FY14
$60,000
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
This system will consist of fixed radio reMivers that are placed on city structures throughout town. The meters that are currently
in place constantly transmit meter read data, instead of driving once a month around the city collecting reads, the receivers will
automatically collect the data daily and transmit that either through the intranet or cell phone modems to finance and the city
shops. We plan on deploying the receivers starting in FY 13, with completion in FY14. Radio studies have the number of
receivers at 14 but our vendor states with a new model of receiver coming out next year that number should go below 10.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Allows daily readings of the water meters and will allow staff to quickly respond to potential water leaks, meter tampering and
backflow events. Will eliminate driving in the areas that are being read by the fixed base units. This will allow us to contact
customers at the start of a leak event and save both money and water.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
323
CIP Project Fund
Water Fund
PROJECT NUMBER
W25
DEPARTMENT
WATER PLANT
PROJECT NAME
Replacement Vehicle
FY14 FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
Replacement 4-wheel Drive ½ Ton pick-up, replaces 1997 ¾ ton pick-up that currently has 97,400 miles
ALTERNATIVES CONSIDERED
Keep existing unit in service
ADVANTAGES OF APPROVAL
More reliable, more fuel efficient vehicle
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
none
FUNDING SOURCES
Water Rates
New
Replacement
Equipment
Project
FY17
$40,000
FY18
324
CIP Project Fund
Water Fund
PROJECT NUMBER
W26
DEPARTMENT
WATER OPS
PROJECT NAME
Internal pipeline assessment of the Sourdough 30” concrete cylinder treated water main
FY14
$50,000
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
This project will involve insertion of electronic sensors that will evaluate the condition of the pipe internally. Installed primarily in
1983, this is the only treated water feed from the Sourdough Plant, so it important to know the condition of the pipe. This pipe
has failed once before causing voluntary rationing of water, in November 2003.
ALTERNATIVES CONSIDERED
ADVANTAGES OF APPROVAL
Advantages to the City include giving us assessment data of the integrity of the pipe from the inside.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
FUNDING SOURCES
100% Water Utility Fund
New
Replacement
Equipment
Project
FY17 FY18
325
CIP Project Fund
Water Fund
PROJECT NUMBER
W27
DEPARTMENT
WATER PLANT
PROJECT NAME
RE-ENGINEERING THE LYMAN TANK LINER
FY14
$50,000
FY15 FY16 Unscheduled
DESCRIPTION OF PROJECT
This project would fund the engineering work to make improvements to the Lyman Water Tank liner.
ALTERNATIVES CONSIDERED
Keep existing liner as-is.
ADVANTAGES OF APPROVAL
It is anticipated that engineering could assist in making improvements to this liner.
ADDITIONAL OPERATING COSTS IN THE FUTURE, IF FUNDED
Not known.
FUNDING SOURCES
100% Water Fund
New
Replacement
Equipment
Project
FY17 FY18
326