HomeMy WebLinkAboutWater Reclamation Facility Change Order Commission Memorandum REPORT TO: Honorable Mayor and City Commission FROM: Bob Murray, Project Engineer Rick Hixson, City Engineer SUBJECT: Bozeman Water Reclamation Facility, Phase 1 Improvements – Change Order No. 10. MEETING DATE: November 5, 2012 AGENDA ITEM TYPE: Consent RECOMMENDATION: Motion and vote to authorize the City Manager’s signature on the Bozeman Water Reclamation Facility, Phase 1 Improvements – Change Order No. 10. BACKGROUND: Attached is a copy of the summary of change order number ten for the above referenced project. This change order includes seventy items. Eight are credits while the other sixty two are additions. Pages two through ten of the attached document titled “Change Order No. 10 Summary” provides a short description of each of the items involved with this change. Additionally, the remainder of the document contains the detailed backup cost information for each item. This change also includes an extension of contract time of 55 days for substantial completion and final completion. The final recommended increase in cost and time extension for this change is reasonable and commensurate with the work involved. UNRESOLVED ISSUES: None ALTERNATIVES: As suggested by the City Commission. FISCAL EFFECTS: Overall this change order increases the contract amount by $102,586.00 from $36,798,705.90 to $36,901,291.90. This will decrease the contingency on the project from $1,444,071.99 to $1,341,485.99. The contingency is included in the overall budget for the project but not in the construction contract which is why the change order must be processed. Attachments: Change Order No. 10, Resolution No 4416 Report compiled on: 10/15/12 77 1 of 2 COMMISSION RESOLUTION NO. 4416 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF BOZEMAN, MONTANA, APPROVING ALTERATION/MODIFICATION OF CONTRACT WITH WILLIAMS BROTHER CONSTRUCTION, LLC., BILLINGS, MONTANA. WHEREAS, the City Commission did, on the 10th day of November 2008, authorize award of the bid for the Bozeman Water Reclamation Facility Phase I Improvements project, to Williams Brother Construction, LLC., Billings, Montana; and WHEREAS, Section 7-5-4308, Montana Code Annotated, provides that any such alterations or modifications of the specifications and/or plans of the contract be made by resolution; and WHEREAS, it has become necessary in the prosecution of the work to make alterations or modifications to the specifications and/or plans of the contract. NOW, THEREFORE, BE IT RESOLVED by the City Commission of the City of Bozeman, Montana, that the proposed modifications and/or alterations to the contract between the City of Bozeman, a municipal corporation, and Williams Brother Construction, LLC., as contained in Change Order No. 10, attached hereto, be and the same are hereby approved; and the City Manager is hereby authorized and directed to execute the contract change order for and on behalf of the City; and the City Clerk is authorized and directed to attest such signature. 78 Resolution No. 4416, Change Order 10 for WRF 2 of 2 PASSED AND APPROVED by the City Commission of the City of Bozeman, Montana, at a regular session thereof held on the 5th day of November 2012. __________________________________________ SEAN BECKER Mayor ATTEST: ________________________________________ STACY ULMEN, CMC City Clerk APPROVED AS TO FORM: _____________________________________________ GREG SULLIVAN City Attorney 79 80 81 82 83 84 85 86 87 88 89