Loading...
HomeMy WebLinkAbout12- Change Order No. 3 with Pall for Bozeman Water Treatment Facility Membrane equipment FDR rv11IRMOm CHANGE ORDER s 1M>; xk No. 3 DATE OF ISSUANCE 4-3-12 EFFECTIVE DATE 4-3-12 BUYER City of Bozeman SELLER Pall Corporation Contract: Project:BOZEMAN WATER TREATMENT FACILITY Membrane Procurement BUYEWs Contract No, ENGINEER HDRIMMI ENGINEER's Contract No. 0000088114 You are directed to make the following changes in the Contract Documents: Description: Change order number 2 included an item#10 to ADD FIT-8204 (12-inch Magmeter).This change order is to DEDUCT FIT-8204 from the scope of supply. Refer to CO#2. There is no change in contract time resulting from this change order. Reason for Change Order: Changes due to detail design and shop drawing review following procurement. Attachments: List documents supporting change) CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Contract Price Original Contract Times: Substantial Completion: NA _$5,558,300.00 Ready for final payment:NA (days or dates Net Increase(Decrease)from previous Change Orders Net change from previous Change Orders No. 0 to No. 2 No. 0 to 2 Substantial Completion: NA $ (44,698-00) Ready for final payment:NA (days) Contract Price prior to this Change Order: Contract Times prior to this Change Order: Substantial Completion: NA $ $ 5,513,602.00 Ready for final payment:NA (days or dates Net increase(decrease)of this Change Order: Net increase(decrease)this Change Order: (12,750.00) Substantial Completion:NA Ready for final payment: NA (days Contract Price with all approved Change Orders: Contract Times with all approved Change Orders: Substantial Completion:NA $ $ 5,500,852.00 Ready for final payment:NA (days or dates) Seller certifies and agrees that there are no additional costs or claims for extra work, additional time, delays or omitted items, of any nature whatsoever, associated with the subject change order items,except as identified and set forth herein and unless expressly stated otherwise in the Change Order. And further, that the price agreed-upon herein represents the full cost and value for the subject work performed and the materials supplied under the terms of the contract and that the work quantit' s and value were properly determined and are correct. 5 --6-r1_q S EMIIYIAuthorized Signature) Date RE E D BY: QVE B j q- NG E R-Signature) ate BUYER(Authorized Signature) Date 0088114 City of Bozeman Hyalite/Sourdough Treatment Plant Membrane Equipment Procurement